⟦021f8b0d4⟧ Wang Wps File

    Length: 70637 (0x113ed)
    Types: Wang Wps File
    Notes: CPS/AUX/073  (SITE 12)    
    Names: »3843A «

Derivation

└─⟦3b876081a⟧ Bits:30006212 8" Wang WCS floppy, CR 0331A
    └─ ⟦this⟧ »3843A « 

WangText



&…09…&…0e…&…86…1
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 …02…
 
 
 
 
 
 
 
 
 
 
 …02…
 
 
 …02…
 
 
 


 
 
 
 
 3843A/ktd
 
 
 
 
 …02…
 CPS/AUX/073

…02…
 SPN/830630…02……02…#
CAMPS
 INSTALLATION
 PROCEDURES
SITE
 12…02……02…
 CAMPS
 








5.9      P̲O̲W̲E̲R̲ ̲U̲P̲ ̲A̲N̲D̲ ̲C̲H̲E̲C̲K̲ ̲O̲U̲T̲

         Before powering up, verify that a̲l̲l̲ ̲s̲w̲i̲t̲c̲h̲e̲s̲ on a̲l̲l̲
         e̲q̲u̲i̲p̲m̲e̲n̲t̲ are i̲n̲ ̲p̲o̲s̲i̲t̲i̲o̲n̲ ̲o̲f̲f̲ or O.



5.9.1    G̲r̲o̲u̲n̲d̲i̲n̲g̲s̲

         a)  Measure with an Ohm-meter that no short circuit
             exists between the safety group (cabinets) and
             the lines of circuit no. 1 through 9 and 1a through
             3a.

         b)  Remount the lids of the power line filters by the
             30 screws.

         c)  Measure with an Ohm-meter if the "Equipment Frame
             Ground" (cabinets) is isolated from the "Signal
             Ground" (5V return).

             The "Signal Ground" (GND) is found on the CCA-panel,
             refer to Figure 5.9.1.

         d)  Start the powering up in the below sequence, starting
             at the CAMPS power distribution board (PDB):



5.9.2    C̲A̲M̲P̲S̲ ̲P̲D̲B̲

         T̲U̲R̲N̲ ̲O̲N̲:    Main circuit breaker

         T̲U̲R̲N̲ ̲O̲N̲:    Miniature circuit breakers

         C̲H̲E̲C̲K̲O̲U̲T̲:   No fuses in the CAMPS PDB blown due to
                     short circuit in the installation.























































         Figure 5.9.1
         Front Layout for CCA


5.9.3    F̲r̲e̲q̲u̲e̲n̲c̲y̲ ̲S̲t̲a̲b̲i̲l̲i̲z̲e̲r̲s̲ ̲a̲n̲d̲ ̲D̲i̲s̲k̲ ̲D̲r̲i̲v̲e̲s̲

         To examine that the 3 disk drives are supplied from
         3 separate phases via the frequency stabilizers proceed
         in the below sequence:

         a)  F̲r̲e̲q̲u̲e̲n̲c̲y̲ ̲S̲t̲a̲b̲i̲l̲i̲z̲e̲r̲ ̲#̲1̲/̲D̲i̲s̲k̲ ̲#̲1̲ ̲(̲M̲M̲D̲)̲ ̲R̲A̲C̲K̲ ̲A̲

             1)  T̲U̲R̲N̲ ̲O̲N̲:    Input power switch on front of
                             the stabilizer (A1A3)(see CAMPS
                             H/W Breakdown page 344).

                             Set the rotary switch on the by-pass
                             panel to position "frequency stabilizer".

             2)  C̲H̲E̲C̲K̲:      Input power and fault lamp lit.
                             Wait 2-3 seconds for fault lamp
                             to extinguish. "Power out" lamp
                             lit.
                 

             3)  T̲U̲R̲N̲ ̲O̲N̲:    Power switch 1 (left hand) on the
                             front of the main switch located
                             in the bottom of rack A.

             4)  C̲H̲E̲C̲K̲:      "Power on" lamp lit on main switch.

             5)  T̲U̲R̲N̲ ̲O̲N̲:̲    Rear power switch disk drive No.
                             1 located in rack A.

             6)  C̲H̲E̲C̲K̲:      Disk running and "ready" lamp in
                             front of disk lit (wait for 
                             30 sec.).

             7)  T̲U̲R̲N̲ OFF:   Miniature circuit breaker (CAMPS
                             PDB) corresponding to power circuit
                             no. 1 for freq. stab. 1 and disk
                             1 (see ATBB drawing 120).

             8)  C̲H̲E̲C̲K̲:      Disk 1 and freq. stab. 1 powered
                             down.

             9)  Leave the miniature circuit breaker in position
                 OFF.



         b)  F̲r̲e̲q̲u̲e̲n̲c̲y̲ ̲S̲t̲a̲b̲i̲l̲i̲z̲e̲r̲ ̲#̲2̲ ̲a̲n̲d̲ ̲D̲i̲s̲k̲ ̲#̲2̲ ̲(̲S̲M̲D̲)̲

             Repeat step 5.9.3a-1 through a-4 for frequency
             stab. #2 (A1A5) and disk drive #2 (rack B).

             5)  T̲U̲R̲N̲ ̲O̲N̲:̲    Rear switches "AC power" and "power
                             supply".

             6)  C̲H̲E̲C̲K̲:̲      Disk running. (No ready lamp if
                             no disk pack mounted).

         Proceed by repeating step 5.9.3a-7 thru a-9 for 
         circuit no. 2.

         c)  F̲r̲e̲q̲u̲e̲n̲c̲y̲ ̲S̲t̲a̲b̲i̲l̲i̲z̲e̲r̲ ̲#̲3̲ ̲a̲n̲d̲ ̲D̲i̲s̲k̲ ̲#̲3̲ ̲(̲M̲M̲D̲)̲

             Repeat step 5.9.3 a-1 through a-9 for frequency
             stab. #3 (A1A7), circuit no. 3, and disk drive
             #3 (rack C).

         d)  Turn on the 3 miniature circuit breakers in the
             CAMPS PDB one by one.

         e)  Check that all frequency stabilizers and disks
             are operating.

         f)  By-pass the freq. stab. by positioning the switches
             on the by-pass switch panel in the right hand position.

             C̲H̲E̲C̲K̲:̲      All disk drives running.

         g)  T̲U̲R̲N̲ ̲O̲F̲F̲:   Miniature circuit breaker in CAMPS
                         PDB for circuit no. 1, 2 and 3.



5.9.4    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲A̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲4̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:    Power switch No. 2 (right hand) on
                         front of the main switch in rack A.

         2)  C̲H̲E̲C̲K̲:      "Power on" lamps lit.

         3)  T̲U̲R̲N̲ ̲O̲N̲:̲    Supply A (right hand) and supply B
                         (left hand) on the rear of the M-fan
                         located in rack A (A1A2).



         4)  C̲H̲E̲C̲K̲:̲      Fan running/green lamp in front lit.

         5)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply A (right hand) and power
                         supply B (left hand) on the rear of
                         the processor crate in rack A (A1A1).

         6)  C̲H̲E̲C̲K̲:̲      Green "power on" lamp above switches
                         lit.

         7)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply A (left hand) and power
                         supply B (right hand) from the front
                         of the processor crate.

         8)  C̲H̲E̲C̲K̲:̲      All 5 power indicator lamps lit on
                         front of the power supplies.
                         (All 10 lamps lit when A o̲r̲ B in 
                         poss. on).

         9)  T̲U̲R̲N̲ ̲O̲N̲:̲    Supply A (right hand) on the rear of
                         the M-fan located in rack B.

         10) C̲H̲E̲C̲K̲:̲      Fan running/corresponding green lamp
                         in front lit.

         11) T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply A (right hand) on the
                         rear of the channel unit crate in rack
                         B (A2A1).

         12) C̲H̲E̲C̲K̲:̲      Green "power on" lamp above switch
                         lit.

         13) T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply A (left hand) from the
                         front of the CU.

         14) C̲H̲E̲C̲K̲:̲      All 5 power indicator lamps lit on
                         front of the power supply.

         15) T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch on adapter power supply,
                         right hand part on the rear of the
                         adapter crate in rack C (A3A5A23).

         16) C̲H̲E̲C̲K̲:̲      "Power on" lamps lit on left hand section
                         of the adapter crate (2 L/L adapters
                         and 2 Opto T/R)

         17) T̲U̲R̲N̲ ̲O̲F̲F̲:̲   Miniature circuit breaker in CAMPS
                         PDB corresponding to power circuit
                         for main switch in rack A. Leave the
                         circuit breaker in position OFF.



5.9.5    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲B̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲5̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:    Right hand power switch on front of
                         the main switch in rack B.

         2)  C̲H̲E̲C̲K̲:      Green "power on" lamp above switch
                         lit.

         3)  T̲U̲R̲N̲ ̲O̲N̲:    Switch on power supply located on the
                         rear of the watchdog crate (A2A4).

         4)  C̲H̲E̲C̲K̲:̲      Green "Power on" lamp above switch
                         lit.

                         Fans running (build-in fans right hand
                         side of the crate).

         5)  T̲U̲R̲N̲ ̲O̲F̲F̲:̲   Miniature circuit breaker in CAMPS
                         PDB corresponding to power circuit
                         for switch 1 in main switch rack B.
                         Leave the miniature circuit breaker
                         in position OFF.



5.9.6    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲B̲ ̲S̲w̲i̲t̲c̲h̲ ̲1̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲2̲

         Left hand power switch on front of the main switch
         in rack B is in position ON. Turn on the mini circuit
         breaker in CAMPS PDB for circuit No. 2.

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Main switch on the rear side of floppy
                         disk station.

         2)  C̲H̲E̲C̲K̲:̲      "Power on" lamp lit and blower inside
                         both floppy disk drives running.
                         (Power on lamp lit behind the PDP).

         3)  T̲U̲R̲N̲ ̲O̲F̲F̲:̲   CAMPS PDB mini circuit breaker circuit
                         No. 2.





5.9.7    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲C̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲6̲

         S-FAN will be in poss. on and starts running.

         Repeat step 5.9.4 item 1 thru 8 for the main switch
         and equipment in rack C (right hand switch).

         9)  T̲U̲R̲N̲ ̲O̲N̲:̲    Supply B (left hand) on the rear of
                         the M-fan in rack B.

         10) C̲H̲E̲C̲K̲:̲      Fan running/green lamp in front of
                         fan lit.

         11) T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply B (left hand) on the rear
                         of the channel unit crate in rack B.

         12) C̲H̲E̲C̲K̲:̲      Green "power on" lamp above switch
                         lit.

         13) T̲U̲R̲N̲ ̲O̲N̲:̲    Power supply B (right hand) from the
                         front of the CU.

         14) C̲H̲E̲C̲K̲:̲      All 5 power indicator lamps lit on
                         front of the power supply.

         15) T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch on adapter power supply,
                         left hand part on the rear of the adapter
                         crate in rack C (A3A5A22).

         16) C̲H̲E̲C̲K̲:̲      "Power on" lamps lit on right hand
                         section of the adapter crate (4 L/L
                         adapters)

         17) T̲U̲R̲N̲ ̲O̲F̲F̲:̲   Miniature circuit breaker in CAMPS
                         PDB corresponding to power circuit
                         for switch 2 in main switch rack C.





5.9.8    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲D̲ ̲S̲w̲i̲t̲c̲h̲ ̲1̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲7̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch No. 1 (left hand) on front
                         of the main switch in rack D.

         2)  C̲H̲E̲C̲K̲:̲      Green "power on" lamp above switch
                         lit.

         3)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch on the rear main power
                         panel of TDX crate assy #1 (2A1A9).
                         

                         Power switch on the front of the main
                         power supply TDX crate assy #1.

         4)  C̲H̲E̲C̲K̲:̲      +/-12V and 5V lamps on main power supply
                         lit.

         5)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch on the rear adapter power
                         supply TDX crate assy #1.

         6)  C̲H̲E̲C̲K̲:̲      Green power lamps on all adapter modules
                         in TDX crate assy #1 lit.

         7)  T̲U̲R̲N̲ ̲O̲N̲:̲    Rear power switch on S-fan located
                         below TDX crate assy #1.

         8)  C̲H̲E̲C̲K̲:̲      Fan running

         9)  Repeat step 5.9.8 item 3 thru 6 for TDX crate assy
             #2 (2A1A7).



5.9.9    M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲E̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲7̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch No. 2 (right hand) on
                         front of the main switch in rack E.

         2)  Repeat step 5.9.8 item 3 through 8 for TDX crate
             assy #7 (2A2A3) and the S-fan (2A2A5).

         3)  Repeat step 5.9.8 item 3 through 6 for TDX crate
             assy #8 (2A2A1).





5.9.10   M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲E̲ ̲S̲w̲i̲t̲c̲h̲ ̲1̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲9̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch No. 1 (left hand) on front
                         of the main switch in rack E.

         2)  Repeat step 5.9.8 item 3 through 8 for TDX crate
             assy #5 (2A2A9) and the S-fan (2A2A11).

         3)  Repeat step 5.9.8 item 3 through 6 for TDX crate
             assy #6 (2A2A7).



5.9.11   M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲G̲ ̲S̲w̲i̲t̲c̲h̲ ̲1̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲9̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power switch No. 1 (left hand) on front
                         of the main switch in rack G.

         2)  Repeat step 5.9.8 item 3 through 8 for TDX crate
             assy #11 (2A4A7) and the S-fan (2A4A11).

         3)  T̲U̲R̲N̲ ̲O̲N̲:    Power switch on adapter power supply
                         right hand part on the rear of the
                         adapter crate in rack G (2A4A9).

         4)  C̲H̲E̲C̲K̲:      "Power On" lamps lit on the 4 CH L/L
                         adapter lefthand section of the adapter
                         crate.

         5)  T̲U̲R̲N̲ ̲O̲N̲:    Remove the front panel of the two stat.
                         mux'es.

                         Turn on the power switch located on
                         the front of the mux to the left.

         6)  C̲H̲E̲C̲K̲:      Fan in mux running.

                         Lamp "AT" on indicator panel lit.

         7)  T̲U̲R̲N̲ ̲O̲F̲F̲:̲   Miniature circuit breaker in CAMPS
                         PDB corresponding to power circuit
                         for PLF line 9.





5.9.12   M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲D̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲8̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power Switch No. 2 (right hand) on
                         the front of the main switch in rack
                         D.

         2)  Repeat step 5.9.8 item 3 through 8 for TDX crate
             assy #3 (2A1A3) and the S-fan (2A1A5).

         3)  Repeat step 5.9.8 item 3 through 6 for TDX crate
             assy #4 (2A1A1).



5.9.13   M̲a̲i̲n̲ ̲S̲w̲i̲t̲c̲h̲ ̲R̲a̲c̲k̲ ̲F̲ ̲S̲w̲i̲t̲c̲h̲ ̲2̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲N̲o̲.̲ ̲8̲

         1)  T̲U̲R̲N̲ ̲O̲N̲:̲    Power Switch No. 2 (right hand) on
                         the front of the main switch in rack
                         F.

         2)  Repeat step 5.9.8 item 3, 4, 7 and 8 for TDX crate
             assy #9 (2A3A3) and the S-fan (2A3A5).


         3)  T̲U̲R̲N̲ ̲O̲F̲F̲:̲   Miniature circuit breaker in CAMPS
                         PDB corresponding to power circuit
                         for PLF line 8.



5.9.14   T̲U̲R̲N̲ ̲O̲N̲:̲    All the miniature circuit breakers in the
                     CAMPS PDB switched off in step 5.9.3, 5.9.4,
                     5.9.5, 5.9.7, 5.9.9, 5.9.11, and 5.9.13.



5.9.15   V̲e̲r̲i̲f̲y̲ ̲S̲u̲p̲p̲l̲y̲ ̲V̲o̲l̲t̲a̲g̲e̲ ̲o̲n̲ ̲P̲U̲ ̲C̲r̲a̲t̲e̲s̲

         All voltages used in the processor units are verified
         by a digital multimeter.



         The measurements are carried out on the front panel
         of the crate configuration adapter (CCA) located on
         the rear side of the PU crates (1A1A23 and 1A3A23),
         refer to Figure 5.9.1. The voltages are checked to
         be within below limits:

           5V =  5.1 -  5.3V
         +12V = 12.1 - 12.3V
         -12V = 12.1 - 12.3V
         +24V = 22.8 - 25.2V
         -24V = 22.8 - 25.2V



5.9.16   V̲e̲r̲i̲f̲y̲ ̲S̲u̲p̲p̲l̲y̲ ̲V̲o̲l̲t̲a̲g̲e̲ ̲o̲n̲ ̲C̲U̲ ̲C̲r̲a̲t̲e̲

         All voltages used in the channel unit are verified
         by a digital multimeter. The measurements are carried
         out on the front panel of the CCA located on the rear
         side of the CU crate (1A2A1A25), refer to Figure 5.9.1.
         The voltages are checked to be within below limits:

         +24V = 22.8 - 25.2V
         +12V = 12.6 - 12.8V
          +5V = 5.68 - 5.72V
         -12V = 12.6 - 12.8V
         -24V = 22.8 - 25.2V



5.10     I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲ ̲O̲F̲ ̲S̲W̲I̲T̲C̲H̲ ̲S̲E̲T̲T̲I̲N̲G̲S̲ ̲A̲N̲D̲ ̲S̲T̲A̲T̲U̲S̲ ̲L̲E̲D̲S̲

         In order to receive a preliminary impression on the
         condition of the system after powering up use the below
         tables for a visual check of the status LEDS.

         If any discrepancies, refer to the CAMPS Site Level
         Maintenance Manual, Doc. No. CPS/TCM/005.





5.10.1   S̲w̲i̲t̲c̲h̲ ̲S̲e̲t̲t̲i̲n̲g̲s̲

         Before checking the status LEDS, all switches must
         be placed in correct positions:

         U̲N̲I̲T̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲S̲W̲I̲T̲C̲H̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲N̲O̲R̲M̲A̲L̲ ̲P̲O̲S̲S̲

         MAP         S2 MAIN/NRM        NRM
                     S3 DIS/EN          EN

         CUCP        CU BUS A           AUTO
                     CU BUS B            -
                     DISK CTRL 1         -
                     DISK CTRL 2         -
                     DISK CTRL 3         -
                     LTU 1-5             -
                     ST.FD. CTLR         -

         CCBA        S1 EN/DIS          EN

         BSM-X       S1 BUS             BUS 2
                     S2 AUTO/MAN/OFF    MAN

         LTUX-S      CH1-CH4            ON

         CCA         RESET              DOWN


         After power up press MC on PROC 1 and 2.



5.10.2   L̲E̲D̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲

         The following table list the normal condition of the
         equipment led indicators.





          UNIT      LED NORM. COND.  NOTE
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

          M̲A̲P̲       POWER            ON                                 
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    P. FAIL          OFF
                    NO CPU           OFF                                BLINKING
                                                                        A
                                                                        FEW
                                                                        SEC.
                                                                        AFTER
                                                                        TEST
                                                                        OFF
                    CB DMA           OFF                                
                    DC DMA           OFF
                    PUDIS            OFF                                ON
                                                                        =
                                                                        SWITCH
                                                                        S3
                                                                        IN
                                                                        POSS.
                                                                        DIS.
                    INH          OFF ON = SWITCH S2
                                     IS OR HAS BEEN
                                     
                                          IN POSS.
                                     MAINT.
                    HALT             OFF                                ON
                                                                        =
                                                                        SWITCH
                                                                        S2
                                                                        IN
                                                                        POSS.
                                                                        MAINT.
                    MAINT            OFF                                ON
                                                                        =
                                                                        SWITCH
                                                                        S2
                                                                        IN
                                                                        POSS.
                                                                        MAINT.

          C̲P̲U̲/̲C̲A̲C̲H̲E̲ POWER            ON
                    CACHE OFF        ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        1
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP

          R̲A̲M̲       POWER            ON

          S̲T̲I̲       POWER            ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    BUSY             OFF
                    HIDMA            OFF
                    P.ERR            OFF
                    C.ERR            OFF
                    M.ERR            OFF
                    RX STAT          OFF

          M̲I̲A̲       POWER        ON
                    ENABLE       ON  OFF = SWITCH S3
                                     ON MAP IN POSS.
                                     DIS.

          T̲I̲A̲       POWER        ON  
                    TEST         ON  (ON FOR A FEW
                                     SEC. AFTER POWER
                                     UP)





            UNIT    LED NORM. COND.  NOTE
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

            C̲C̲A̲     POWER            ON
                    BUSY             OFF

            M̲B̲T̲     POWER            ON

            D̲I̲S̲K̲ ̲C̲T̲R̲L̲   POWER        ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    ABUS             OFF
                    BBUS             OFF
                    BUSY             OFF

            S̲T̲.̲F̲D̲.̲C̲T̲R̲L̲  POWER        ON
                    TEST             ON
                    ABUS             OFF
                    BBUS             OFF
                    BUSY             ON
                    FRONT LED        OFF

            C̲U̲C̲P̲    POWER            ON
                    AUTO CTRL    ON  OFF: ONE OF THE
                                     SWITCHES N̲O̲T̲ 
                                          IN AUTO
                    DIS (A OR B) OFF ON:  SWITCH IN
                                     POSS. DIS.
                    AUTO             ON                                 OFF:
                                                                        SWITCH
                                                                        IN
                                                                        POSS.
                                                                        DIS.
                    BUS A            OFF
                    BUS B            OFF

            L̲T̲U̲     POWER            ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    BUS A            OFF
                    BUS B            OFF
                    BOOTL.           OFF…86…1         …02…
                                       …02…   …02…   …02…     
                                                  
                                                  
                                              


            UNIT    LED NORM. COND.  NOTE
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

            C̲I̲A̲-̲A̲/̲B̲ POWER            ON                                 
                    P.FAIL           OFF

            W̲C̲A̲     POWER            ON
                    ENABLE           ON                                 OFF:
                                                                        SWITCH
                                                                        S1
                                                                        IN
                                                                        POSS.
                                                                        DIS

            D̲C̲A̲     POWER            ON

            B̲S̲M̲-̲X̲   POWER            ON
                    EXT.POWER    ON
                    BUS 1            ON/OFF                             ONLY
                                                                        BUS
                                                                        1
                                                                        O̲R̲
                                                                        BUS
                                                                        2
                                                                        ACTIVE
                    BUS 2            OFF/ON                             
                    AUTO             OFF                                OFF:
                                                                        S2
                                                                        IN
                                                                        POSS.
                                                                        MAN.
                                                                        OR
                                                                        OFF
                    MAN          ON  ON:  S2 IN POSS.
                                     MAN. OR OFF

            C̲T̲X̲.̲C̲O̲N̲T̲    POWER        ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    REC.ST.          OFF
                    TR.ST.           OFF
                    FUSE             OFF

            O̲P̲T̲O̲ ̲T̲/̲R̲    POWER        ON
                    RCVL             ON                                 RED
                                                                        LIGHT
                                                                        (NO
                                                                        TERM.
                                                                        CONN)
                    RTS          ON
                    CTS          OFF
                    SYNC             ON                                 RED
                                                                        LIGHT
                                                                        (NO
                                                                        TERM.
                                                                        CONN)

            L̲/̲L̲ ̲A̲D̲A̲P̲    POWER        ON

            L̲T̲U̲X̲-̲S̲  POWER            ON
                    TEST             OFF                                ON
                                                                        FOR
                                                                        APP.
                                                                        10
                                                                        SEC.
                                                                        AFTER
                                                                        POWER
                                                                        UP
                    TDX.ST           OFF
                    CH 1-4           ON                                 OFF:
                                                                        SWITCH
                                                                        1-4
                                                                        OFF




           UNIT         LED      NORM. COND.   NOTE
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

…02…M̲M̲D̲        START/READY      ON
                        FAULT/CLEAR            OFF
                        WRITE PROT.            OFF                      ON:
                                                                        SWITCH
                                                                        ACTIVATED

           S̲M̲D̲          START                  OFF
                        READY                  ON
                        FAULT                  OFF
                        WRITE PROT.            OFF                      ON:
                                                                        SWITCH
                                                                        ACTIVATED

           W̲D̲ ̲C̲R̲A̲T̲E̲     POWER                  ON                       TERMINATOR
                                                                        BOARD
                                                                        INSIDE
                                                                        CRATE



5.11     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲D̲E̲L̲T̲A̲ ̲V̲D̲U̲

         a)  The terminals are distributed to the installation
             sites according to ATBB drawings 102, 105, and
             110.

         b)  Supervisory and maintenance terminals must be placed
             on CR provided tables. 



5.11.1   P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

         Power plug connections must be exchanged to fit host
         nation provided power outlets.

         P̲O̲W̲E̲R̲ ̲C̲O̲R̲D̲ ̲F̲R̲O̲M̲ ̲D̲E̲L̲T̲A̲       3̲-̲P̲I̲N̲N̲E̲D̲ ̲P̲L̲U̲G̲

             Brown                     Phase
             Blue                      Neutral
             Green/Yellow              Ground



5.11.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             a)  Before terminating the opto cable, a rubber tubing,
                 size 8 x 12 x 250 mm, must be mounted on the cable,
                 see ATBB dwg. 130.

             b)  The opto fibres are to be pulled through the rear
                 waveguide (port 3) into the VDU.
                 (See ATBB dwg. 130).

             c)  The two fibres must be terminated with special
                 opto connectors.

                 For detailed termination procedures refer to para
                 1.3, doc. No. 4.

             d)  In case of opto splicing this will be done by mounting
                 of an adapter between the two male connectors,
                 using the same kind of male connectors as for the
                 terminals.



             e)  Before connecting the two fibres to the optical
                 modem board in the VDU, the black receiver cable
                 with the opto connector must be checked for supplying
                 enough light emission.

                 The transmitter of the opto T/R in the TDX crate
                 is used as source for the opto fibre (black cable
                 connected).

             f)  Connect the black fibre in the VDU end to the 11XE
                 fiber optic power meter and verify that the optical
                 power output is not less than -34.6dBm.

             g)  If the optical power output is less than  -34.6
                 dBm, the cable will be terminated with a new pair
                 of OPTO connectors. If still outside tolerance,
                 the cable will be marked as Bad and a new cable
                 must be installed.

             h)  To get access to the optical modem board located
                 inside the VDU, unlock the two snappers on the
                 rear and lift the terminal access cover of the
                 VDU.

             i)  The white fibre must be connected to the transmitter
                 jack ("out") and the black fibre to the receiver
                 jack ("in") (see ATBB drawing 130).

             j)  The opto cable must be permanently marked with
                 cable No during the termination procedure.



5.11.3       M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲K̲e̲y̲b̲o̲a̲r̲d̲ ̲a̲n̲d̲ ̲K̲e̲y̲s̲

             a)  The keyboard cable is connected to the female cannon
                 plug located on the lower right hand front of the
                 terminal. The connector is secured by the two front
                 screws.

             b)  Remove the two keys placed on the inside of the
                 terminal access cover and insert the keys in the
                 key-lock on front of the terminal.





5.12         I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲R̲A̲C̲O̲R̲ ̲M̲S̲P̲



5.12.1       P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

             Repeat step 5.11.1 for the power plug of the MSP.



5.12.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             Repeat step 4.11.2 item a) thru g).

             h)  To get access to the optical modem board located
                 inside the printer, unlock the two snappers in
                 front of the printer and lift the cover of the
                 printer.

             i)  Install the fibres through the rear connector entry
                 hole, route through the optical cable entry hole
                 and connect the white fibre to the transmitter
                 ("output") and the black fibre to the receiver
                 ("input"). (See ATBB dwg. 130).

             j)  The opto cable must be permanently marked with
                 cable number during the termination procedure.



5.12.3       I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲P̲A̲P̲E̲R̲ ̲A̲N̲D̲ ̲R̲I̲B̲B̲O̲N̲

             Install the paper and the ribbon according to the instructions
             in the operator's manual.



5.12.4       I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲P̲I̲S̲T̲O̲N̲ ̲S̲P̲R̲I̲N̲G̲

             Mount the Piston spring between the bottom and the
             lid of the printer by rotating the piston spring clockwise
             into the screw thread in the bottom of the printer.

                 The piston spring is connected to the lid by the
                 two Philips screws and the hinge mounted in the
                 lid.



5.13         I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲P̲T̲P̲/̲P̲T̲R̲

             a)  The PTP/PTR is installed in the off-line encryption
                 area (ref ATBB drawing 105).

             b)  The 3/4" 45…0e…o…0f… fitting is mounted in the J-box and
                 fastened from inside the J-box by the nut.

             c)  The metallic conduit is mounted to the fitting
                 by means of the hose lock and the lock nut.

             d)  Repeat step b) and c) for mounting of the conduit
                 to the PTP/PTR (see ATBB drawing 131).

             e)  The metallic interface cable coming from the filter
                 box is pulled through the conduit into the PTP/PTR.

                 The cable will be terminated by a cannon plug according
                 to the pin assignment table 5.3.2 page 5.5 in the
                 ATBB Doc.

             f)  The cable is connected according to ATBB drawing
                 131.





5.14     T̲E̲S̲T̲ ̲O̲F̲ ̲S̲U̲P̲/̲U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲



5.14.1   T̲e̲s̲t̲ ̲o̲f̲ ̲D̲e̲l̲t̲a̲ ̲V̲D̲U̲

         a)  Connect the power plug to the wall outlet.

         b)  Turn on the "power on/off" switch located on the
             lower right front of the terminal.

         c)  Operate the keylock switch to the ON position (right
             hand front panel).

         d)  Immediately after power up the terminal executes
             a series of system diagnostics. If all are working
             properly, the power-up menu will be displayed on
             the screen within 10 seconds.

         e)  Adjust the intensity and focus until the characters
             are clear and bright. Do not advance the intensity
             too far or the display area may be highlighted.

         f)  Adjust the audible alarm for the desired sound
             level (control shift and the G key).

         g)  When all the terminals have been switched on and
             locally tested, the transmitter of the optical
             modem board in the VDU, the white opto cable, and
             the opto connection to the TDX crate must be checked
             for supplying enough light emission.

         h)  Connect one by one all the white fibres terminated
             in the opto T/R located in the TDX crates to the
             11XE fibre optic power meter and check that the
             optical power output is not less than -34.6dBm.

         i)  If the optical power output is less than -34.6
             dBm, the cable will be terminated with a new pair
             of OPTO connectors. If still outside tolerance,
             the cable will be marked as Bad and a new cable
             must be installed.




5.14.2   O̲p̲e̲r̲a̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲

         a)  Assure that the required terminal functions and
             characteristics are correctly stored by checking
             the contents of the configuration menu.

             Correct CAMPS application contents to be:

             DEL/BS         = N̲     PRT CR DLY          = O̲
             ECHO           = N̲     PRT LF AFT CR       = N̲
             CR=XOFF        = N̲     PRT PROT DATA       = N̲
             XMT SO SEQ     = N̲     PRT BSY             = N̲
             MEM RELEASED   = Y̲     PRT BUSY=HIGH       = N̲
             BAUDOT         = N     PRT FF              = N̲
                                    PRT BUF (0,1,2,3)   = O̲

             WRU?X̲7̲2̲6̲0̲  WHATRU? CAMPS       MCLK 0̲0̲0̲0̲0̲0̲ 

               I/O          HOST         PTR

             CHAR            7̲            7̲
             PARITY          E̲            E̲
             STOP BITS       C̲            C̲
             BAUD RATE       G̲            G̲

         b)  The terminal is logged on to the system according
             to procedures stated in the Operator's Manual.

         c)  Messages are sent/rec. between the terminal and
             other terminals.



5.14.3   T̲e̲s̲t̲ ̲o̲f̲ ̲T̲r̲a̲c̲o̲r̲ ̲M̲S̲P̲

         a)  Connect the power plug to the wall outlet.

         b)  Turn on the power switch located on the rear right
             hand side.

             Verify that the power lamp on the front panel lights.

         c)  Operate the key-lock switch to the ON position
             (left hand side in front).



         d)  Depress the "line feed" button on the TCM front
             panel and verify that line feed of paper occurs.

         e)  Press the test button for not more than 4 sec.
             Verify that all lamps on the printer lights.

         f)  Press the test button for at least 5 sec. Verify
             that the following is printed:

                             NO ERRORS IN ROM
                             NO ERRORS IN RAM
                             66 LINES BARBERPOLE PATTERN

         g)  Repeat step 5.14.1 item h) and i) for test of transmitter
             and opto connections.



5.14.4   O̲p̲e̲r̲a̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲

         Arrange to have one or more messages sent to the MSP
         and verify message contents with the transmitting station.
         

         Verify during print out that the key-lock switch stops
         the printing and that no part of the message is lost
         when it is turned on again.



5.15     T̲E̲S̲T̲ ̲O̲F̲ ̲P̲T̲P̲/̲P̲T̲R̲

         Testing the PTP/PTR is a part of the PROCESSOR/LINE
         TERMINATION TEST. Ref. 5.16.



5.16     H̲/̲W̲ ̲T̲E̲S̲T̲ ̲P̲R̲O̲C̲E̲S̲S̲O̲R̲/̲L̲I̲N̲E̲ ̲T̲E̲R̲M̲.̲ ̲U̲N̲I̲T̲S̲

         By means of the M&D- and the Test Drive Software, all
         hardware- and interface functions shall be verified.

         The following step by step procedure outlines the major
         tasks of the testing sequence.

         For a detailed description of the test procedure including
         informations of test control, test data, expected test
         results, test execution procedures, see CPS/TRP/001
         FACTORY ACCEPTANCE TEST SPECIFICATIONS AND PROCEDURES.





5.16.1   P̲U̲ ̲#̲1̲/̲C̲U̲/̲T̲D̲X̲ ̲#̲2̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲

         a)  CPU Test
         b)  MAP Test
         c)  RAM Test
         d)  Disk/FD/LTU/TDX



5.16.2   W̲a̲t̲c̲h̲d̲o̲g̲ ̲P̲r̲o̲c̲e̲s̲s̲o̲r̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲

         a)  WDP Test
         b)  WDP V24 Interface Test
         c)  WDP CCBA Interface Test
         d)  PU #1 CCA Test
         e9  PU #2 CCA Test
         f)  CU CCA Test
         g)  TU1-10 BSM-X Test



5.17     I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲

         a)  As a final step of the installation procedure,
             the CR instalation team will conduct an inventory
             check of all delivered CAMPS equipment to verify
             that the equipment is complete.

         b)  This inventory inspection will be witnessed by
             the customer.

         c)  The inventory is performed in accordance with the
             updated inventory list prepared by CR.

         d)  The inventory check will also include delivery
             to site of spare parts, test equipment, and documentation.

         e)  The results are recorded on the inventory list
             and signed by both parties.











       6  I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
                         S̲I̲T̲E̲ ̲1̲2̲A̲



6.1      S̲H̲I̲P̲M̲E̲N̲T̲ ̲O̲F̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲



6.1.1    D̲i̲s̲a̲s̲s̲e̲m̲b̲l̲y̲ ̲a̲n̲d̲ ̲P̲a̲c̲k̲i̲n̲g̲

         The remote terminal equipment, which will be a part
         of the main site shipment, will be shipped to the remote
         terminal site 12A as follows:

         -   Stat. Mux. rack is packed in a wooden container

         -   Terminal equipment (2 VDU and 2 MSP) are shipped
             in their own containers

         -   Auxilliary equipment (power line filter, modules,
             stat. mux. units and cables) are shipped in their
             own containers

         Above packing scheme will result in the shipment composition
         described in Table 6.1. The table lists quantity of
         containers and packed weight and cubage of each container,
         together with the total quantity, cubage, and weight
         of the shipment. The logistic data given is to be used
         by the site for preparation of the receival and for
         providing temporary storage area.




R̲e̲m̲o̲t̲e̲ ̲S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲e̲d̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲




                                                Total       
 Total 
Item            Item  Size of Cont. Container   Packed     Container
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲ ̲ ̲ ̲ ̲ ̲Q̲t̲y̲ ̲ ̲ ̲W̲x̲D̲x̲H̲ ̲(̲c̲m̲)̲ ̲ ̲ ̲ ̲ ̲Q̲t̲y̲ ̲ ̲ ̲ ̲ ̲W̲e̲i̲g̲h̲t̲ ̲(̲k̲g̲)̲ ̲ ̲C̲u̲b̲a̲g̲e̲
 ̲(̲c̲b̲m̲)̲

STAT MUX RACK    1   72x126x192      1        280           1.74  
                                                             X
MSP              2   65x74x39        2         74           0.38  
                                                             X
VDU              2   65x80x55        2         86           0.57  
                                                             X
STAT. MUX.       1   54x32x61        1          5           0.09
PLF/CABLES       1   30x48x32        1          8           0.05
MODULES          1   29x38x35        1̲         ̲ ̲5̲ ̲          ̲0̲.̲0̲4̲

TOTAL                                8̲        4̲5̲8̲           2̲.̲8̲7̲




                            Table 6.1
                   Logistic Data…01…CRT SITE 12A


6.1.2    T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲t̲o̲ ̲S̲i̲t̲e̲

         The CAMPS equipment will be carried to site by truck.
         The equipment will be loaded at CR's plant in Copenhagen
         and transported directly to site without any transshipment.

         CR will use an experienced transportation company for
         the conveyence.

         The truck used will be an aircushion vehicle type with
         the dimensions indicated in Table 6.2.

         Truck and load data include all Main Site equipment
         and equipment for CRT 12A and 12B. 










                                       T̲r̲u̲c̲k̲         T̲r̲u̲c̲k̲ ̲+̲
 ̲l̲o̲a̲d̲ 

         Weight                     9 tons          14.5 tons
         Size (m)              3.75Hx2.50Wx9.75L    
         Axle load, front           2 tons          6.2 tons
         Axle load, rear            5 tons          10.3 tons






                Table 6.2…01…Truck Dimensions


6.1.3    R̲e̲c̲e̲i̲p̲t̲ ̲o̲f̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲a̲t̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲ ̲S̲i̲t̲e̲ ̲1̲2̲A̲

         a)  Depending on the distance between the main site
             and the CRT site the CR installation team will
             perform the receipt of the CRT equipment.

         b)  In case the team is prevented from being present,
             the CRT site will handle the receipt according
             to the instructions given in 6.3.

         c)  All containers are marked with a container number.
             A complete set of packing lists are enclosed in
             container No. 1 and a set is attached to the outside
             of container No. 1.



6.2      P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲T̲ ̲C̲R̲T̲ ̲1̲2̲A̲



6.2.1    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲s̲ ̲B̲y̲ ̲C̲R̲

         a)  Prior to the planned arrival of the installation
             team, the officer in charge of the CRT site is
             informed by telex or phone call.

         b)  Upon arrival, the local CRT officer in charge will
             give a briefing, addressing the following subjects:

             -   Access to site and house rules

             -   Location of applicable areas such as storage
                 area, parking and unloading area, CRT equipment
                 area, etc.

             -   The support requested by contractor, ref. 6.3.

             -   Introduction of the installation team to relevant
                 local personnel.

             -   Information regarding local facilities such
                 as cafeteria, telephones, medical aid, etc.

         c)  The installation team will present the planned
             major steps of the installation efforts. Ref. 6.4
             through 6.18.



6.2.2    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲s̲ ̲b̲y̲ ̲S̲i̲t̲e̲

         a)  The CRT equipment rooms are prepared for installation
             of the equipment according to the civil works requirements.

         b)  Arrangements to be made for CR's presence at site
             are described in section 6.3.



6.3      I̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲S̲ ̲T̲O̲ ̲T̲H̲E̲ ̲C̲R̲T̲ ̲S̲I̲T̲E̲ ̲1̲2̲A̲



         a)  In case the CR installation team is prevented from
             participating in the receipt of the equipment,
             the transportation personnel has been instructed
             to unpack the equipment and move the equipment
             as close as possible to the installation site.

         b)  The site is requested to assist the transportation
             company as follows:

             -   Escort the transportation personnel

             -   Indicate the equipment entry route.

             -   Ensure that the corridors on the entry route
                 are cleared.

             -   Ensure that the installation areas are cleared.

             -   Ensure that all site provided terminal tables
                 are cleared.

             -   Indicate the installation sites (location of
                 rack installation site in the stat. mux. room).

             -   Provide site truck/trolley/pushwaggon as available
                 upon request by the transportation company.

         c)  Above mentioned arrangements will be discussed
             and finalized during the site verification meetings.





6.4      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲S̲ ̲A̲N̲D̲ ̲S̲U̲P̲P̲O̲R̲T̲

         The site is requested to provide the following preparations
         and support prior to or during CR's presence at site.

         1   Clear the CRT installation area.

         2   Provide/clear tables for the user terminals to
             be installed on customer provided tables.

         3   Clear the equipment entry route from unloading
             area to CRT equipment rooms and from unloading
             area to storage area. 

         4    Provide escort of the transportation personnel.

         5   Provide temporary storage area for the equipment
             specified in Table 6.1. 

         6   Provide access to site, access badges to be ready
             at arrival of the installation team. Request for
             access and identification credentials of the team
             members will be forwarded through SHAPE.

         7   Provide access to commercial telephone and telex
             allowing for international communication. The use
             to be reimbursed by CR.

         8   Provide access to canteens or messes for CR personnel
             if available.

         9   Provide emergency medical aid in case of accidents.

         10  Provide access to reproduction facilities, if available.

         11  Provide site truck/trolley/pushwaggon for transportation
             in the corridors, if available and upon request.





6.5      S̲H̲I̲P̲M̲E̲N̲T̲ ̲C̲O̲N̲T̲A̲I̲N̲E̲R̲S̲

         As explained in section 6.1.1, the equipment is shipped
         in different containers; some of these are reusable.
         It is, therefore, recommended that the site stores
         1-2 empty containers for later use.

         The installation team will point out the containers
         which are recommended for later use to the SHAPE/site
         representatives and the remaining containers will be
         discarded by CR.

         In case the CR installation team is prevented from
         participating in the receipt of the equipment, the
         transportation company is instructed to leave containers
         marked with an "X" in table 6.1.



6.6      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲S̲I̲T̲E̲ ̲1̲2̲A̲

         The following step-by-step procedure contains a detailed
         instruction set of how to install the CR delivered
         equipment for the remote terminal site.

         The major tasks of the installation sequence are:

         6.7     UNPACKING
         6.8     TRANSPORTATION TO SITE
         6.9     MOUNTING OF LEVELLERS
         6.10    MOUNTING OF POWER LINE FILTER
         6.11    REMOUNTING OF STAT. MUX.
         6.12    INSTALL. INT. POWER/SIGNAL CABLES
         6.13    INSTALL. EXT. POWER/SIGNAL CABLES
         6.14    MOUNTING OF MODULES
         6.15    INSTALLATION OF DELTA VDU
         6.16    INSTALLATION OF TRACOR MSP
         6.17    POWER UP AND CHECK OUT
         6.18    TESTS OF DELTA VDU
         6.19    TEST OF TRACOR MSP
         6.20    OPERATIONAL TEST OF USER TERMINALS
         6.21    INVENTORY CHECK





6.7      U̲N̲P̲A̲C̲K̲I̲N̲G̲

         a)  The EMI Stat. Mux. rack for the remote terminals
             is packed in its original wooden container.

             The rack should remain packed during site internal
             transportation and only be unpacked close to the
             installation site, but if the space along the access
             route is limited, the rack can be unpacked before
             transportation to the installation site. The racks
             is unpacked as follows:

         b)  Remove the top cover of the wooden container by
             demounting the 3 ea 1/4 x 2.1/2" bolts on each
             side of the continer and the 4 ea 1/2 - 13 x 2"
             bolts, one in each top corner (see Figure 5.2.1).

         c)  The 4 walls of the container are removed by loosening
             the 21 ea 1/4 x 2.1/2" bolts on each short side.

         d)  The rack is bolted to the container bottom in each
             corner by a 1/2 - 13 x 2.1/2" bolt.

         e)  These bolts are removed from under the container
             bottom.



6.8      T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲T̲O̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲I̲T̲E̲

         a)  After unpacking, the front and rear door of the
             rack must be removed. Check that serial number
             in
             the rack correspond to the serial number of the
             doors.

         b)  Be carefull not to damage the gaskets on the door.

         c)  Depending on means of transportation, 4 eyelets
             can be mounted in the top of the rack in the position
             of the removed 4 ea 1/2 - 13 x 2" bolts.





6.9      M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲L̲E̲V̲E̲L̲L̲E̲R̲S̲

         a)  The 4 levellers are mounted from under the racks
             two by two, by tilting the racks (see ATBB drawing
             152).

         b)  The levellers are mounted to a distance of 40 mm
             between the bottom of the rack and the floor.

         c)  The levellers must be adjusted to ensure equal
             distribution of the floor load.
             Ref. 5.2.7, subpara f.


6.10     M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲P̲O̲W̲E̲R̲ ̲L̲I̲N̲E̲ ̲F̲I̲L̲T̲E̲R̲

         a)  Place the power line filter (PLF) under the two
             front/top knockouts in the rack (see ATBB drawing
             152).

             The 2 1/2" male adaptor, welded to the PLF is to
             be inserted through the right-hand knockout seen
             from the front.

         b)  Place the tightening washer from outside the EMI
             rack.

         c)  Insert the 2.1/2" to 1" reducing bushing and the
             outer washer through the knockout into the PLF
             through the left-hand knockout (see ATBB drawing
             152).

         d)  Mount the 1" to 3/4" reducing bushing and the 3/4"
             45…0e…o…0f… fitting into the 2.1/2" to 1" reducing bushing.

         It is very important to the shielding that the fittings
         are fully tightened.





6.11     R̲E̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲S̲T̲A̲T̲.̲ ̲M̲U̲X̲.̲

         The only separately packed unit, the Stat. Mux., is
         unpacked and installed from the front side into the
         stat. mux. housing, see ATBB drawing 155.

         The stat. mux. unit is locked by the left- and right
         hand locking screws.



6.12     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲/̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         All internal signal and power cables are mounted upon
         receipt except for the following cables:

         a)  Due to the removal of the stat. mux. during the
             transportation, the 9 interface cables between
             the stat. mux and the back panels of the adapter
             crate/ filter box must be reconnected:

             W7  to stat. mux. modem   (from filter box J40)
             W8  to stat. mux. terminal  4
             W9  -  -     -    -         3
             W10 -  -     -    -         2
             W11 -  -     -    -         1
             W12 -  -     -    -         7
             W13 -  -     -    -         6
             W14 -  -     -    -         5
             W15 -  -     -    -         8

             The cables are fastened by the 2 fingerscrews in
             the cannon plug.

         b)  The stat. mux. power cable is connected to the
             power distribution panel (J3).

         c)  The mains switch power cable (J1) is connected
             to the power line filter (J1).





6.13     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲E̲X̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲/̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲,̲ 
         A̲N̲D̲ ̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲F̲I̲T̲T̲I̲N̲G̲S̲



6.13.1   L̲e̲f̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲T̲o̲p̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         a)  Place the tightening washer on the 2.1/2" to 1.1/2"
             reducing bushing.

         b)  Insert the reducing bushing from the outside through
             the knock out into the filterbox and tighten it
             from the inside by the inner nut (see ATBB drawing
             152).

         c)  Mount the 1.1/2" steel tube in the reducing bushing.

         d)  Mount the 48 mm metallic  conduit to the steel
             tube and tighten it by the clamps.

         c)  Mount the 1.1/2" steel tube by means of the two
             nuts to the cable duct and connect the metallic
             conduit by clamps (see ATBB drawing 152).



6.13.2   R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲T̲o̲p̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         Repeat step 6.13.1 for the right hand top penetration.



6.13.3   A̲u̲x̲.̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲ ̲a̲n̲d̲ ̲M̲o̲d̲e̲m̲ ̲C̲a̲b̲l̲e̲

         a)  The aux. connections (W38-41) and the modem cable
             (W21) are pulled through the right hand penetration
             and into the filter box (see ATBB drawing 155).

         b)  The modem cable is terminated by a cannon plug
             and connected to J40 in the filter box. For pin
             assignment, see ATBB page 5.4.

         c)  The aux. connections are terminated and connected
             in the filterbox according to ATBB drawing 155.





6.13.4   R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲F̲r̲o̲n̲t̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

             C̲A̲U̲T̲I̲O̲N̲:     Before terminating the external power
                          cable, assure that the switched power
                          outlet is disconnected or in condition
                          OFF.

         a)  Mount the 3/4" 45…0e…o…0f… fitting in the J-box according
             to ATBB drawing 152.

         b)  Connect the 3/4" metallic conduit between the J-box
             and the power line filter.

         c)  The external 220V cable coming from the switched
             power outlet and the seperate insulated ground
             wire are pulled through the conduit into the power
             line filter.

         d)  For access to the PLF, remove the metallic cover
              fastened by 4 screws during transportation. The
             remaining 26 screws are shipped attached to inside
             wall of the PLF. The cables and the ground wire
             are dismantled and terminated with cable shoes.
             For details of the connection to the terminal board
             see ATBB drawing 152.

         e)  Measure with an ohm-meter that no short circuit
             exists between the safety ground (cabinet) and
             the line in the PLF.

         f)  When the cables have been properly connected, the
             metallic lid of the PLF is reinstalled by the 30
             screws.



6.13.5   U̲s̲e̲r̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲/̲L̲e̲f̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         a)  The 4 opto cables (W22-23 and W30-31) are pulled
             through the left hand penetration, through the
             filter box into the rack trays and out to the front
             of the adapter crate through the cable channel
             assembly, see ATBB drawing 155.



         b)  The opto cables are terminated by special opto
             connectors and connected to the opto T/R:

             W22    VDU 2    Opto T/R    A1A7A8
             W23    VDU 3    -           A1A7A7
             W30    MSP 10   -           A1A7A6
             W31    MSP 11   -           A1A7A5

             See ATBB drawing 155.



6.14     M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲M̲O̲D̲U̲L̲E̲S̲

         a)  For correct physical positioning of the separately
             packed modules, refer to the enclosed packing list.
             The packing list states the serial No. of the unit,
             the crate assy No., the slot No. in the crate and
             the address of the physical position in the system.

         b)  The modules are slid into the print guide and when
             the edge connector of the print has entered the
             connector of the motherboard, the modules are fastened
             by the fixing screw on the front of the modules.



6.15     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲D̲E̲L̲T̲A̲ ̲V̲D̲U̲



6.15.1   P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

         Power plug connections must be exchanged to fit host
         nation provided power outlets.

         P̲O̲W̲E̲R̲ ̲C̲O̲R̲D̲ ̲F̲R̲O̲M̲ ̲D̲E̲L̲T̲A̲       3̲-̲P̲I̲N̲N̲E̲D̲ ̲P̲L̲U̲G̲

             Brown                     Phase
             Blue                      Neutral
             Green/Yellow              Ground





6.15.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             a)  Before termination of the opto cable, a rubber
                 tubing, size 8 x 12 x 250mm, must be mounted on
                 the cable, see ATBB drawing 157.

             b)  The opto fibres are to be pulled through the rear
                 waveguide (port 3) into the VDU, see ATBB drawing
                 157.

             c)  The two fibres must be terminated with special
                 opto connectors, refer to para 1.3, doc. no. 4.

             d)  In case of opto splicing this will be done by mounting
                 of an adapter between the two male connectors,
                 using the same kind of male connectors as for the
                 terminals.

             e)  Before connecting the two fibres to the Optical
                 modem board in the VDU, the black receiver cable
                 with the opto connector must be checked for supplying
                 sufficient light emission.

                 The transmitter of the opto T/R in the adapter
                 crate is used as source for the opto fibre (black
                 cable connected to transmitter).

             f)  Connect the black fibre in the VDU-end to the 11XE
                 fiber optic power meter and verify that the optical
                 power output is not less than -34.6dBm.

             g)  If the optical power output is less than - 34.6
                 dBm, the cable will be terminated with a new pair
                 of OPTO connectors. If still outside tolerance,
                 tha cable will be marked as Bad and a new cable
                 must be installed.

             h)  To get access to the optical modem board located
                 inside the VDU, unlock the two snappers on the
                 rear and lift the terminal access cover of the
                 VDU.

             i)  The white fibre must be connected to the transmitter
                 jack ("out") and the black fibre to the receiver
                 jack ("in") (see ATBB drawing 157).

             j)  The opto cable must be permanently marked with
                 cable No during the termination procedure.





6.15.3       M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲K̲e̲y̲b̲o̲a̲r̲d̲ ̲a̲n̲d̲ ̲K̲e̲y̲s̲

             a)  The keyboard cable is connected to the female cannon
                 plug located on the (front view) lower right hand
                 front of the terminal. The connector is secured
                 by the two front screws.

             b)  Remove the two keys placed on the inside of the
                 terminal access cover and insert the keys in the
                 key-lock on front of the terminal.



6.16         I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲R̲A̲C̲O̲R̲ ̲M̲S̲P̲



6.16.1       P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

             Repeat step 6.15.1 for the MSP.



6.16.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             a)  Before termination of the opto cable, a rubber
                 tubing, size 8 x 12 x 250 mm, must be mounted on
                 the cable, see ATBB drawing 157.

             b)  Install the fibres through the rear connector entry
                 hole, route through the optical cable entry hole
                 and connect the while fibre to the transmitter
                 ("output") and the black fibre to the receiver
                 ("input"), see ATBB drawing 157.

             c)  Repeat step 6.15.2, item c) through g).

             d)  To get access to the optical modem board located
                 inside the printer, unlock the two snappers in
                 front of the printer and lift the cover of the
                 printer.

             e)  The opto cable must be permanently marked with
                 cable No. during the termination procedure.





6.16.3       I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲p̲a̲p̲e̲r̲ ̲a̲n̲d̲ ̲r̲i̲b̲b̲o̲n̲

             Install the paper and the ribbon according to the instructions
             in the operator's manual.



6.16.4       I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲p̲i̲s̲t̲o̲n̲ ̲s̲p̲r̲i̲n̲g̲

             Mount the Piston spring between the bottom and the
             lid of the printer by rotating the piston spring clockwise
             into the screw thread in the bottom of the printer.
             The piston spring is connected to the lid by the two
             Philips screw and the hinge mounted in the lid.


6.17         P̲O̲W̲E̲R̲ ̲U̲P̲ ̲A̲N̲D̲ ̲C̲H̲E̲C̲K̲ ̲O̲U̲T̲

             1)  T̲U̲R̲N̲ ̲O̲N̲:̲    The switched power outlet and the right
                             hand mains switch in the bottom of
                             the rack.

                 C̲H̲E̲C̲K̲:      Green "Power ON" lamp above switch
                             is lit.

             2)  T̲U̲R̲N̲ ̲O̲N̲:    Power switch on adapter power supply,
                             left hand part of the rear of the adapter
                             crate.

                 C̲H̲E̲C̲K̲:̲      "Power On" lamps lit on the 4 opto
                             T/R and the L/L adapter.

             3)  T̲U̲R̲N̲ ̲O̲N̲:̲    Remove the front panel of the stat.
                             mux.

                             Turn on the power switch located on
                             front of the stat.mux to the left hand
                             side.

                 C̲H̲E̲C̲K̲:̲      Fan in stat.mux is running. Lamp for
                             fuse not lit. 

                             "At" lamp on indicator panel lit.



6.18         T̲E̲S̲T̲ ̲O̲F̲ ̲D̲E̲L̲T̲A̲ ̲V̲D̲U̲

             a)  Connect the power plug to the wall outlet.

             b)  Turn on the "power on/off" switch located on the
                 lower right front of the terminal.

             c)  Operate the keylock switch to the ON position (right
                 hand front panel).

             d)  Immediately after power up the terminal executes
                 a series of system diagnostics. If all are working
                 properly, the power-up menu will be displayed on
                 the screen within 10 seconds.

             e)  Adjust the intensity and focus until the characters
                 are clear and bright. Do not advance the intensity
                 too far or the display area may be highlighted.

             f)  Adjust the audible alarm for the desired sound
                 level (control shift and the G key).

             g)  When all terminals have been switched on and locally
                 tested, the transmitter of the optical modem board
                 in the VDU, the white opto cable, and the opto
                 connection to the adaptor crate must be checked
                 for supplying sufficient light emission.

             h)  Connect one by one all the white fibres terminated
                 in the opto T/R located in the adaptor crate to
                 the 11XE fibre optic power meter and check that
                 the optical power output is not less than -34.6dBm.

             i)  If the optical power output is less than -34.6
                 dBm, the cable will be terminated with a new pair
                 of OPTO connectors. If still outside tolerance,
                 the cable will be marked as Bad and a new cable
                 must be installed.




6.19         T̲E̲S̲T̲ ̲O̲F̲ ̲T̲R̲A̲C̲O̲R̲ ̲M̲S̲P̲

             a)  Connect the power plug to the wall outlet.

             b)  Turn on the power switch located on the rear right
                 hand side.

                 Verify that the power lamp on the front panel lights.

             c)  Operate the key-lock switch to the ON position
                 (left hand side in front).

             d)  Depress the "line feed" button on the TCM front
                 panel and verify that line feed of paper occurs.

             e)  Press the test button for not more than 4 sec.
                 Verify that all lamps on the printer lights.

             f)  Press the test button for at least 5 sec. Verify
                 that the following is printed:

                     NO ERRORS IN ROM
                     NO ERRORS IN RAM
                     66 LINES BARBERPOLE PATTERN

             g)  Repeat step 6.18 item g) and h) for test of transmitter
                 and opto connections.



6.20         O̲P̲E̲R̲A̲T̲I̲O̲N̲A̲L̲ ̲T̲E̲S̲T̲ ̲O̲F̲ ̲U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲



6.20.1       T̲e̲s̲t̲ ̲o̲f̲ ̲C̲r̲y̲p̲t̲o̲/̲A̲n̲a̲l̲o̲g̲ ̲L̲i̲n̲e̲

             a)  Press the test switch in the stat. mux. on both
                 the main- and the remote site.

             b)  Check that no inbound error is registrated on either
                 stat. mux.





6.20.2       T̲e̲s̲t̲ ̲o̲f̲ ̲V̲D̲U̲

             a)  Assure that the required terminal functions and
                 characteristics are correctly stored by checking
                 the contents of the configuration menu (see sec.
                 5.14.2).

             b)  The terminal is logged on to the system according
                 to procedures stated in the Operator's Manual.

             c)  Messages are sent/rec. between the terminal and
                 the main site.



6.20.3       T̲e̲s̲t̲ ̲o̲f̲ ̲M̲S̲P̲

             Arrange to have one or more messages sent to the MSP
             and verify message contents with the transmitting station.

             Verify during print out that the key-lock switch stops
             the printing and that no part of the message is lost
             when it is turned on again.



6.21         I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲

             a)  As a final step of the installation procedure,
                 the CR installation team will conduct an inventory
                 check of the delivered Remote Terminal equipment
                 to verify that the equipment is complete.

             b)  This inventory inspection will be witnessed by
                 the customer.

             c)  The inventory is performed in accordance with the
                 updated inventory list prepared by CR.

             d)  The results are recorded on the inventory list
                 and signed by both parties.







         7  I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
                           S̲I̲T̲E̲ ̲1̲2̲B̲



7.1          S̲H̲I̲P̲M̲E̲N̲T̲ ̲O̲F̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲



7.1.1        D̲i̲s̲a̲s̲s̲e̲m̲b̲l̲y̲ ̲a̲n̲d̲ ̲P̲a̲c̲k̲i̲n̲g̲

             The remote terminal equipment, which will be a part
             of the main site shipment, will be shipped to the remote
             terminal site 12B as follows:

             -   Stat. Mux. rack is packed in a wooden container

             -   Terminal equipment (2 VDU and 2 MSP) are shipped
                 in their own containers

             -   Auxilliary equipment (power line filter, modules,
                 stat. mux. units and cables) are shipped in their
                 own containers

             Above packing scheme will result in the shipment composition
             described in Table 7.1. The table lists quantity of
             containers and packed weight and cubage of each container,
             together with the total quantity, cubage, and weight
             of the shipment. The logistic data given is to be used
             by the site for preparation of the receival and for
             providing temporary storage area.





R̲e̲m̲o̲t̲e̲ ̲S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲e̲d̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲




                                                Total       
 Total 
Item            Item  Size of Cont. Container   Packed     Container
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲ ̲ ̲ ̲ ̲ ̲Q̲t̲y̲ ̲ ̲ ̲W̲x̲D̲x̲H̲ ̲(̲c̲m̲)̲ ̲ ̲ ̲ ̲ ̲Q̲t̲y̲ ̲ ̲ ̲ ̲ ̲W̲e̲i̲g̲h̲t̲ ̲(̲k̲g̲)̲ ̲ ̲C̲u̲b̲a̲g̲e̲
 ̲(̲c̲b̲m̲)̲

STAT MUX RACK    1   72x126x192      1        280           1.74  
                                                            X
MSP              2   65x74x39        2         74           0.38  
                                                            X
VDU              2   65x80x55        2         86           0.57  
                                                            X
STAT. MUX.       1   54x32x61        1          5           0.09
PLF/CABLES       1   30x48x32        1          8           0.05
MODULES          1   29x38x35        1̲         ̲ ̲5̲ ̲          ̲0̲.̲0̲4̲

TOTAL                                8̲        4̲5̲8̲           2̲.̲8̲7̲




                            Table 7.1
                   Logistic Data…01…CRT SITE 12B


7.1.2    T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲t̲o̲ ̲S̲i̲t̲e̲

         The CAMPS equipment will be carried to site by truck.
         The equipment will be loaded at CR's plant in Copenhagen
         and transported directly to site without any transshipment.

         CR will use an experienced transportation company for
         the conveyence.

         The truck used will be an aircushion vehicle type with
         the dimensions indicated in Table 7.2.

         Truck and load data include all Main Site equipment
         and equipment for CRT 12A and 12B. 












                                       T̲r̲u̲c̲k̲         T̲r̲u̲c̲k̲ ̲+̲
 ̲l̲o̲a̲d̲ 

         Weight                     9 tons          14.5 tons
         Size (m)              3.75Hx2.50Wx9.75L    
         Axle load, front           2 tons           6.2 tons
         Axle load, rear            5 tons          10.3 tons







                Table 7.2…01…Truck Dimensions


7.1.3    R̲e̲c̲e̲i̲p̲t̲ ̲o̲f̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲a̲t̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲ ̲S̲i̲t̲e̲ ̲1̲2̲B̲

         a)  Depending on the distance between the main site
             and the CRT site the CR installation team will
             perform the receipt of the CRT equipment.

         b)  In case the team is prevented from being present,
             the CRT site will handle the receipt according
             to the instructions given in 7.3.

         c)  All containers are marked with a container number.
             A complete set of packing lists are enclosed container
             No. 1 and a set is attached to the outside of container
             No. 1.



7.2      P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲T̲ ̲C̲R̲T̲ ̲1̲2̲B̲



7.2.1    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲s̲ ̲B̲y̲ ̲C̲R̲

         A)  Prior to the planned arrival of the installation
             team, the officer in charge of the CRT site is
             informed by telex or phone call.

         b)  Upon arrival, the local CRT officer in charge will
             give a briefing, addressing the following subjects:

             -   Access to site and house rules

             -   Location of applicable areas such as storage
                 area, parking and unloading area, CRT equipment
                 area, etc.

             -   The support requested by contractor, ref. 7.3.

             -   Introduction of the installation team to relevant
                 local personnel.

             -   Information regarding local facilities such
                 as cafeteria, telephones, medical aid, etc.

         c)  The installation team will present the planned
             major steps of the installation efforts. Ref. 7.4
             through 7.18.



7.2.2    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲s̲ ̲b̲y̲ ̲S̲i̲t̲e̲

         a)  The CRT equipment rooms are prepared for installation
             of the equipment according to the civil works requirements.

         b)  Arrangements to be made for CR's presence at site
             are described in section 7.3.



7.3      I̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲S̲ ̲T̲O̲ ̲T̲H̲E̲ ̲C̲R̲T̲ ̲S̲I̲T̲E̲ ̲1̲2̲B̲



         a)  In case the CR installation team is prevented from
             participating in the receipt of the equipment,
             the transportation personnel has been instructed
             to unpack the equipment and move the equipment
             as close as possible to the installation site.

         b)  The site is requested to assist the transportation
             company as follows:

             -   Escort the transportation personnel

             -   Indicate the equipment entry route.

             -   Ensure that the corridors on the entry route
                 are cleared.

             -   Ensure that the installation areas are cleared.

             -   Ensure that all site provided terminal tables
                 are cleared.

             -   Indicate the installation sites (location of
                 rack installation site in the stat. mux. room).

             -   Provide site truck/trolley/pushwaggon as available
                 upon request by the transportation company.

         c)  Above mentioned arrangements will be discussed
             and finalized during the site verification meetings.





7.4      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲S̲ ̲A̲N̲D̲ ̲S̲U̲P̲P̲O̲R̲T̲

         The site is requested to provide the following preparations
         and support prior to or during CR's presence at site.

         1   Clear the CRT installation area.

         2   Provide/clear tables for the user terminals to
             be installed on customer provided tables.

         3   Clear the equipment entry route from unloading
             area to CRT equipment rooms and from unloading
             area to storage area. 

         4    Provide escort of the transportation personnel.

         5   Provide temporary storage area for the equipment
             specified in section 7.3.2. 

         6   Provide access to site, access badges to be ready
             at arrival of the installation team. Request for
             access and identification credentials of the team
             members will be forwarded through SHAPE.

         7   Provide access to commercial telephone and telex
             allowing for international communication. The use
             to be reimbursed by CR.

         8   Provide access to canteens or messes for CR personnel
             if available.

         9   Provide emergency medical aid in case of accidents.

         10  Provide access to reproduction facilities, if available.

         11  Provide site truck/trolley/pushwaggon for transportation
             in the corridors, if available and upon request.





7.5      S̲H̲I̲P̲M̲E̲N̲T̲ ̲C̲O̲N̲T̲A̲I̲N̲E̲R̲S̲

         As explained in section 7.1.1, the equipment is shipped
         in different containers; some of these are reusable.
         It is, therefore, recommended that the site stores
         1-2 empty containers for later use.

         The installation team will point out the containers
         which are recommended for later use to the SHAPE/site
         representatives and the remaining containers will be
         discarded by CR.

         In case the CR installation team is prevented from
         participating in the receipt of the equipment, the
         transportation company is instructed to leave containers
         marked with an "X" in table 7.1.



7.6      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲S̲I̲T̲E̲ ̲1̲2̲B̲

         The following step-by-step procedure contains a detailed
         instruction set of how to install the CR delivered
         equipment for the remote terminal site.

         The major tasks of the installation sequence are:

         7.7     UNPACKING
         7.8     TRANSPORTATION TO SITE
         7.9     MOUNTING OF LEVELLERS
         7.10    MOUNTING OF POWER LINE FILTER
         7.11    REMOUNTING OF STAT. MUX.
         7.12    INSTALL. INT. POWER/SIGNAL CABLES
         7.13    INSTALL. EXT. POWER/SIGNAL CABLES
         7.14    MOUNTING OF MODULES
         7.15    INSTALLATION OF DELTA VDU
         7.16    INSTALLATION OF TRACOR MSP
         7.17    POWER UP AND CHECK OUT
         7.18    TESTS OF DELTA VDU
         7.19    TEST OF TRACOR MSP
         7.20    OPERATIONAL TEST OF USER TERMINALS
         7.21    INVENTORY CHECK





7.7      U̲N̲P̲A̲C̲K̲I̲N̲G̲

         a)  The EMI Stat. Mux. rack for the remote terminals
             is packed in its original wooden container.

             The rack should remain packed during site internal
             transportation and only be unpacked close to the
             installation site, but if the space along the access
             route is limited, the rack can be unpacked before
             transportation to the installation site. The racks
             is unpacked as follows:

         b)  Remove the top cover of the wooden container by
             demounting the 3 ea 1/4 x 2.1/2" bolts on each
             side of the continer and the 4 ea 1/2 - 13 x 2"
             bolts, one in each top corner (see Figure 5.2.1).

         c)  The 4 walls of the container are removed by loosening
             the 21 ea 1/4 x 2.1/2" bolts on each short side.

         d)  The rack is bolted to the container bottom in each
             corner by a 1/2 - 13 x 2.1/2" bolt.

         e)  These bolts are removed from under the container
             bottom.



7.8      T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲T̲O̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲I̲T̲E̲

         a)  After unpacking, the front and rear door of the
             rack must be removed. Check that serial number
             in
             the rack correspond to the serial number of the
             doors.

         b)  Be carefull not to damage the gaskets on the door.

         c)  Depending on means of transportation, 4 eyelets
             can be mounted in the top of the rack in the position
             of the removed 4 ea 1/2 - 13 x 2" bolts.





7.9      M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲L̲E̲V̲E̲L̲L̲E̲R̲S̲

         a)  The 4 levellers are mounted from under the racks
             two by two, by tilting the racks (see ATBB drawing
             162).

         b)  The levellers are mounted to a distance of 40 mm
             between the bottom of the rack and the floor.

         c)  The levellers must be adjusted to ensure equal
             distribution of the floor load. 
             Ref 5.2.7, subpara f.



7.10     M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲P̲O̲W̲E̲R̲ ̲L̲I̲N̲E̲ ̲F̲I̲L̲T̲E̲R̲

         a)  Place the power line filter (PLF) under the two
             front/top knockouts in the rack (see ATBB drawing
             162).

             The 2 1/2" male adaptor, welded to the PLF is to
             be inserted through the right-hand knockout seen
             from the front.

         b)  Place the tightening washer from outside the EMI
             rack.

         c)  Insert the 2.1/2" to 1" reducing bushing and the
             outer washer through the knockout into the PLF
             through the left-hand knockout (see ATBB drawing
             162).

         d)  Mount the 1" to 3/4" reducing bushing and the 3/4"
             45…0e…o…0f… fitting into the 2.1/2" to 1" reducing bushing.

         It is very important to the shielding that the fittings
         are fully tightened.



7.11     R̲E̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲S̲T̲A̲T̲.̲ ̲M̲U̲X̲.̲

         The only separately packed unit, the Stat. Mux., is
         unpacked and installed from the front side into the
         stat. mux. housing, see ATBB drawing 165.

         The stat. mux. unit is locked by the left- and right
         hand locking screws.





7.12     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲/̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         All internal signal and power cables are mounted upon
         receipt except for the following cables:

         a)  Due to the removal of the stat. mux. during the
             transportation, the 9 interface cables between
             the stat. mux and the back panels of the adapter
             crate/ filter box must be reconnected:

             W7  to stat. mux. modem   (from filter box J40)
             W8  to stat. mux. terminal  4
             W9  -  -     -    -         3
             W10 -  -     -    -         2
             W11 -  -     -    -         1
             W12 -  -     -    -         7
             W13 -  -     -    -         6
             W14 -  -     -    -         5
             W15 -  -     -    -         8

             The cables are fastened by the 2 fingerscrews in
             the cannon plug.

         b)  The stat. mux. power cable is connected to the
             power distribution panel (J3).

         c)  The mains switch power cable (J1) is connected
             to the power line filter (J1).





7.13     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲E̲X̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲/̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲,̲ 
         A̲N̲D̲ ̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲F̲I̲T̲T̲I̲N̲G̲S̲



7.13.1   L̲e̲f̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲T̲o̲p̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         a)  Place the tightening washer on the 2.1/2" to 1.1/2"
             reducing bushing.

         b)  Insert the reducing bushing from the outside through
             the knock out into the filterbox and tighten it
             from the inside by the inner nut (see ATBB drawing
             162).

         c)  Mount the 1.1/2" steel tube in the reducing bushing.

         d)  Mount the 48 mm metallic  conduit to the steel
             tube and tighten it by the clamps.

         c)  Mount the 1.1/2" steel tube by means of the two
             nuts to the cable duct and connect the metallic
             conduit by clamps (see ATBB drawing 162).



7.13.2   R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲T̲o̲p̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         Repeat step 7.13.1 for the right hand top penetration.



7.13.3   A̲u̲x̲.̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲ ̲a̲n̲d̲ ̲M̲o̲d̲e̲m̲ ̲C̲a̲b̲l̲e̲

         a)  The aux. connections (W38-41) and the modem cable
             (W21) are pulled through the right hand penetration
             and into the filter box (see ATBB drawing 165).

         b)  The modem cable is terminated by a cannon plug
             and connected to J40 in the filter box. For pin
             assignment, see ATBB page 6.4.

         c)  The aux. connections are terminated by host nation
             and connected in the filterbox according to ATBB
             drawing 165.





7.13.4   R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲F̲r̲o̲n̲t̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

             C̲A̲U̲T̲I̲O̲N̲:     Before terminating the external power
                          cable, assure that the switched power
                          outlet is disconnected or in condition
                          OFF.

         a)  Mount the 3/4" 45…0e…o…0f… fitting in the J-box according
             to ATBB drawing 162.

         b)  Connect the 3/4" metallic conduit between the J-box
             and the power line filter.

         c)  The external 220V cable coming from the switched
             power outlet and the seperate insulated ground
             wire are pulled through the conduit into the power
             line filter.

         d)  For access to the PLF, remove the metallic cover
              fastened by 4 screws during transportation. The
             remaining 26 screws are shipped attached to inside
             wall of the PLF. The cables and the ground wire
             are dismantled and terminated with cable shoes.
             For details of the connection to the terminal board
             see ATBB drawing 162.

         e)  Measure with an ohm-meter that no short circuit
             exists between the safety ground (cabinet) and
             the line in the PLF.

         f)  When the cables have been properly connected, the
             metallic lid of the PLF is reinstalled by the 30
             screws.



7.13.5   U̲s̲e̲r̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲/̲L̲e̲f̲t̲ ̲H̲a̲n̲d̲ ̲R̲e̲a̲r̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲

         a)  The 4 opto cables (W22-23 and W30-31) are pulled
             through the left hand penetration, through the
             filter box into the rack trays and out to the front
             of the adapter crate through the cable channel
             assembly, see ATBB drawing 165.



         b)  The opto cables are terminated by special opto
             connectors and connected to the opto T/R:

             W22    VDU 2    Opto T/R    A1A7A8
             W23    VDU 3    -           A1A7A7
             W30    MSP 10   -           A1A7A6
             W31    MDP 11   -           A1A7A5

             See ATBB drawing 165.



7.14     M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲M̲O̲D̲U̲L̲E̲S̲

         a)  For correct physical positioning of the separately
             packed modules, refer to the enclosed packing list.
             The packing list states the serial No. of the unit,
             the crate assy No., the slot No. in the crate and
             the address of the physical position in the system.

         b)  The modules are slid into the print guide and when
             the edge connector of the print has entered the
             connector of the motherboard, the modules are fastened
             by the fixing screw on the front of the modules.



7.15     I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲D̲E̲L̲T̲A̲ ̲V̲D̲U̲



7.15.1   P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

         Power plug connections must be exchanged to fit host
         nation provided power outlets.

         P̲O̲W̲E̲R̲ ̲C̲O̲R̲D̲ ̲F̲R̲O̲M̲ ̲D̲E̲L̲T̲A̲       3̲-̲P̲I̲N̲N̲E̲D̲ ̲P̲L̲U̲G̲

             Brown                     Phase
             Blue                      Neutral
             Green/Yellow              Ground





7.15.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             a)  Before termination of the opto cable, a rubber
                 tubing, size 8 x 12 x 250mm, must be mounted on
                 the cable, see ATBB drawing 167.

             b)  The opto fibres are to be pulled through the rear
                 waveguide (port 3) into the VDU, see ATBB drawing
                 167.

             c)  The two fibres must be terminated with special
                 opto connectors, refer to para 1.3,  doc. No. 4.

             d)  In case of opto splicing this will be done by mounting
                 of an adapter between the two male connectors,
                 using the same kind of male connectors as for the
                 terminals.

             e)  Before connecting the two fibres to the Optical
                 modem board in the VDU, the black receiver cable
                 with the opto connector must be checked for supplying
                 sufficient light emission.

                 The transmitter of the opto T/R in the adapter
                 crate is used as source for the opto fibre (black
                 cable connected to transmitter).

             f)  Connect the black fibre in the VDU-end to the 11XE
                 fiber optic power meter and verify that the optical
                 power output is not less than -34.6dBm.

             g)  If the optical power output is less than - 34.6
                 dBm, the cable will be terminated with a new pair
                 of OPTO connectors. If still outside tolerance,
                 the cable will be marked as Bad and a new cable
                 must be installed.

             h)  To get access to the optical modem board located
                 inside the VDU, unlock the two snappers on the
                 rear and lift the terminal access cover of the
                 VDU.

             i)  The white fibre must be connected to the transmitter
                 jack ("out") and the black fibre to the receiver
                 jack ("in") (see ATBB drawing 167).

             j)  The opto cable must be permanently marked with
                 cable No during the termination procedure.





7.15.3       M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲K̲e̲y̲b̲o̲a̲r̲d̲ ̲a̲n̲d̲ ̲K̲e̲y̲s̲

             a)  The keyboard cable is connected to the female cannon
                 plug located on the (front view) lower right hand
                 front of the terminal. The connector is secured
                 by the two front screws.

             b)  Remove the two keys placed on the inside of the
                 terminal access cover and insert the keys in the
                 key-lock on front of the terminal.



7.16         I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲R̲A̲C̲O̲R̲ ̲M̲S̲P̲



7.16.1       P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲

             Repeat step 7.15.1 for the MSP.



7.16.2       T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

             a)  Before termination of the opto cable, a rubber
                 tubing, size 8 x 12 x 250 mm, must be mounted on
                 the cable, see ATBB drawing 167.

             b)  Install the fibres through the rear connector entry
                 hole, route through the optical cable entry hole
                 and connect the while fibre to the transmitter
                 ("output") and the black fibre to the receiver
                 ("input"), see ATBB drawing 167.

             c)  Repeat step 7.15.2, item c) through g).

             d)  To get access to the optical modem board located
                 inside the printer, unlock the two snappers in
                 front of the printer and lift the cover of the
                 printer.

             e)  The opto cable must be permanently marked with
                 cable number during the termination procedure.

7.16.3       I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲p̲a̲p̲e̲r̲ ̲a̲n̲d̲ ̲r̲i̲b̲b̲o̲n̲ ̲ ̲

             Install the paper and the ribbon according to the instructions
             in the operator's manual.




7.16.4       I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲P̲i̲s̲t̲o̲n̲ ̲S̲p̲r̲i̲n̲g̲

             Mount the piston spring between the bottom and the
             lid of the printer by rotating the piston spring clockwise
             into the screw thread in the bottom of the printer.

             The piston spring is connected to the lid by the two
             Philips screws and the hinge mounted in the lid.



7.17         P̲O̲W̲E̲R̲ ̲U̲P̲ ̲A̲N̲D̲ ̲C̲H̲E̲C̲K̲ ̲O̲U̲T̲

             1)  T̲U̲R̲N̲ ̲O̲N̲:̲    The switched power outlet and the right
                             hand mains switch in the bottom of
                             the rack.

                 C̲H̲E̲C̲K̲:      Green "Power ON" lamp above switch
                             is lit.

             2)  T̲U̲R̲N̲ ̲O̲N̲:    Power switch on adapter power supply,
                             left hand part of the rear of the adapter
                             crate.

                 C̲H̲E̲C̲K̲:̲      "Power On" lamps lit on the 4 opto
                             T/R and the L/L adapter.

             3)  T̲U̲R̲N̲ ̲O̲N̲:̲    Remove the front panel of the stat.
                             mux.

                             Turn on the power switch located on
                             front of the stat.mux to the left hand
                             side.

                 C̲H̲E̲C̲K̲:̲      Fan in stat.mux is running. Lamp for
                             fuse not lit.

                             "At" lamp on indicator panel lit.



7.18         T̲E̲S̲T̲ ̲O̲F̲ ̲D̲E̲L̲T̲A̲ ̲V̲D̲U̲

             a)  Connect the power plug to the wall outlet.

             b)  Turn on the "power on/off" switch located on the
                 lower right front of the terminal.

             c)  Operate the keylock switch to the ON position (turn
                 right) (right hand front panel).

             d)  Immediately after power up the terminal executes
                 a series of system diagnostics. If all are working
                 properly, the power-up menu will be displayed on
                 the screen within 10 seconds.

             e)  Adjust the intensity and focus until the characters
                 are clear and bright. Do not advance the intensity
                 too far or the display area may be highlighted.

             f)  Adjust the audible alarm for the desired sound
                 level (control shift and the G key).

             g)  When all terminals have been switched on and locally
                 tested, the transmitter of the optical modem board
                 in the VDU, the white opto cable, and the opto
                 connection to the adaptor crate must be checked
                 for supplying sufficient light emission.

             h)  Connect one by one all the white fibres terminated
                 in the opto T/R located in the adaptor crate to
                 the 11XE fibre optic power meter and check that
                 the optical power output is not less than -34.6dBm.

             i)  If the optical power output is less than - 34.6
                 dBm, the cable will be terminated with a new pair
                 of OPTO connectors. If still outside tolerance,
                 the cable will be marked as Bad and a new cable
                 must be installed. 



7.19         T̲E̲S̲T̲ ̲O̲F̲ ̲T̲R̲A̲C̲O̲R̲ ̲M̲S̲P̲

             a)  Connect the power plug to the wall outlet.

             b)  Turn on the power switch located on the rear right
                 hand side.

                 Verify that the power lamp on the front panel lights.

             c)  Operate the key-lock switch to the ON position
                 (left hand side in front).

             d)  Depress the "line feed" button on the TCM front
                 panel and verify that line feed of paper occurs.

             e)  Press the test button for not more than 4 sec.
                 Verify that all lamps on the printer lights.

             f)  Press the test button for at least 5 sec. Verify
                 that the following is printed:

                     NO ERRORS IN ROM
                     NO ERRORS IN RAM
                     66 LINES BARBERPOLE PATTERN

             g)  Repeat step 7.18 item g) and h) for test of transmitter
                 and opto connections.



7.20         O̲P̲E̲R̲A̲T̲I̲O̲N̲A̲L̲ ̲T̲E̲S̲T̲ ̲O̲F̲ ̲U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲



7.20.1       T̲e̲s̲t̲ ̲o̲f̲ ̲C̲r̲y̲p̲t̲o̲/̲A̲n̲a̲l̲o̲g̲ ̲L̲i̲n̲e̲

             a)  Press the test switch in the stat. mux. on both
                 the main- and the remote site.

             b)  Check that no inbound error is registrated on either
                 stat. mux.





7.20.2       T̲e̲s̲t̲ ̲o̲f̲ ̲V̲D̲U̲

             a)  Assure that the required terminal functions and
                 characteristics are correctly stored by checking
                 the contents of the configuration menu (see sec.
                 5.14.2).

             b)  The terminal is logged on to the system according
                 to procedures stated in the Operator's Manual.

             c)  Messages are sent/rec. between the terminal and
                 the main site.



7.20.3       T̲e̲s̲t̲ ̲o̲f̲ ̲M̲S̲P̲

             Arrange to have one or more messages sent to the MSP
             and verify message contents with the transmitting station.

             Verify during print out that the key-lock switch stops
             the printing and that no part of the message is lost
             when it is turned on again.



7.21         I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲

             a)  As a final step of the installation procedure,
                 the CR installation team will conduct an inventory
                 check of the delivered Remote Terminal equipment
                 to verify that the equipment is complete.

             b)  This inventory inspection will be witnessed by
                 the customer.

             c)  The inventory is performed in accordance with the
                 updated inventory list prepared by CR.

             d)  The results are recorded on the inventory list
                 and signed by both parties.