DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦02c7f8764⟧ Wang Wps File

    Length: 5125 (0x1405)
    Types: Wang Wps File
    Notes: KOMMENTARER TIL MTF       
    Names: »0375A «

Derivation

└─⟦1304ed705⟧ Bits:30006073 8" Wang WCS floppy, CR 0030A
    └─ ⟦this⟧ »0375A « 

WangText




…02…

…02…KM/810205…02……02…#
SITE PREPARATION AND INSTALLATION
…02……02…CAMPS








         This attachment contains further specification of the
         documentation/effort requested in the milestone tracking
         form.



         R̲E̲F̲ ̲M̲T̲F̲ ̲P̲T̲1̲ ̲S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲:̲

         a)  Mainsites 1-13 were performed in May-June 1980.
             A survey report has been issued.

         b)  Mainsites Athens, Sonor, NATO and 20 Remote Terminals
             Sites are pending. Preferably these sites should
             be accomplished in Febr. - March 1981. The surveys
             are to be planned in conjunction with SHAPE.



         R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲K̲T̲ ̲P̲H̲Y̲S̲I̲C̲A̲L̲ ̲C̲H̲A̲R̲A̲C̲T̲E̲R̲I̲S̲T̲I̲C̲S̲ ̲A̲N̲D̲ ̲H̲A̲R̲D̲W̲A̲R̲E̲
         ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲

         a)  ILS will need the following details from SD/HW
             for the preparation of civil works requirements
             and as-to-be-built drawings:

             1)  Envelope dimensions, including a plan view
                 as installed

             2)  Clearance dimensions needed for access, service,
                 maintenance, hook-up, operation, disk travel,
                 etc.

             3)  Equipment weight and center of gravity

             4)  Power and signal interface, interface cabling
                 (size, Qantity, type, connector attachment
                 type)
             5)  Signal and power cable entry/exit of racks
                 and pheripherals.

             6)  Ventilation requirements (location, flowrate)
                 

             7)  Power supply requirements:

                 Power consumption, voltage, frequency, phase,
                 power factor, steady state current, maximum
                 transient current at turn on (or fuse size,
                 fuse type required)

             8)  Grounding of equipment

                 (Type of interface, grounding systems of racks
                 and pheripherals)



             9)  Special operation - environment considerations
                 (vibration, temperature, humidity, dust, EMI,
                 etc.)

             10) Interconnecting cabling with reference designators,
                 cable no., cable type, size and signal data
                 (Wire lists)

             11) Cross connection frames and patch panel details
                 (IDF) to be incorporated in the A-T-B-B drawings

         b)  S̲D̲/̲H̲W̲ ̲a̲r̲e̲ ̲R̲e̲q̲u̲e̲s̲t̲e̲d̲ ̲t̲o̲ ̲D̲e̲l̲i̲v̲e̲r̲ ̲I̲n̲p̲u̲t̲ ̲t̲o̲ ̲I̲L̲S̲ ̲i̲n̲
             ̲A̲c̲c̲o̲r̲d̲a̲n̲c̲e̲ ̲w̲i̲t̲h̲ ̲t̲h̲e̲ ̲F̲o̲l̲l̲o̲w̲i̲n̲g̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

             R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲2̲

             Data for a typical site:
             Above para 1-8,                           15/1-1981

             R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲3̲

             Data for site 1 - 6:

             Prelim above para 1-8,                    1/3-1981
             Final above para 1-10,                    1/4-1981

             R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲4̲

             Data for site 7-16:

             Prelim above para 1-10,                   15/6-1981
             Final above para 1-10,                    15/7-1981

         R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲5̲

         Cross connecton frames and patch panel details (IDF)
         are delivered to ILS with l site per month, starting
         with first delivery 15/7.

         R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲6̲

         ILS will do the follow up on this subject i.e. it will
         be put on the agenda for progress meeting and request
         will be submitted to SHAPE.



         R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲7̲

         a)  The following data will be needed from SHAPE for
             preparation of CWR and A-T-B-B (Refer to sRS para.
             3.6.6.2)

             1)  Cable routing from CAMPS room to user terminals
                 (Site 1-13) due date 1/10-1980 was agreed to
                 during the surveys by SHAPE.

             2)  Same as 1.  For site 14-16 due date to be agreed
                 to during the site surveys .



Due Dates
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

3 months prior       3.                                Grounding
                                                       drawings
                                                       and specifications
                                                       
to delivery of                                         concerning
                                                       conductors,
                                                       electrodes
                                                       and
CWR.                 joints of the site grounding system.

3 months prior       4.                                Drawings
                                                       and specifications
                                                       concerning
                                                       
to delivery of                                         power
                                                       distribution
                                                       boards,
                                                       cabling,
                                                       wiring
CWR.                  and distribution, position of filters.

3 months prior       5.                                Modifications
                                                       or changes
                                                       to the
                                                       baseline
to delivery of                                         established
                                                       at the
                                                       site
                                                       survey.
CWR.             

3 months prior       6.                                Updated
                                                       site
                                                       documentation
                                                       with
                                                       CWR 
to install. of                                         incorporated.
each site.

1/10-1980            7.                                Documentation
                                                       requested
                                                       by ILS
                                                       during
                                                       site
                                                       surveys.

1/11-1981            8.                                Recommended
                                                       installation
                                                       material
                                                       (ducts,
                                                       conduits
                                                       etc.)



         b)  SHAPE has not agreed to any due date for the data
             per 3-6 above.



         R̲E̲F̲ ̲M̲T̲F̲,̲ ̲P̲T̲ ̲8̲

         T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲b̲i̲l̲i̲t̲y̲ ̲s̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲ ̲c̲o̲n̲c̲e̲r̲n̲i̲n̲g̲ ̲t̲h̲e̲ ̲C̲R̲8̲0̲
         e̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲a̲r̲e̲ ̲n̲e̲e̲d̲e̲d̲ ̲f̲r̲o̲m̲ ̲E̲D̲ in order to prepare the
         transportation of CAMPS.

         The following data are requested:

         1)  Requirements for special shipping if any.

         2)  Packaging of modules, crates and fans etc. (i.e.
             specification of shipment containers).

         3)  Any test performance or test planning concerning
             transportation and storage.  (test reports or test
             specifications).



         R̲E̲F̲ ̲M̲T̲F̲ ̲P̲T̲ ̲9̲

         Identification by SHAPE of customs document or other
         special shipping documents to accompany each shipment
         have been requested in the transportation plan (CPS/PLN/007).
          No due date are agreed to.



         R̲E̲F̲ ̲M̲T̲F̲ ̲P̲T̲ ̲1̲0̲

         M&D will be used during site installation.  The M&D
         is needed per 1/1-1982 for planning and for training
         of the installation technicians.



         R̲E̲F̲ ̲M̲T̲F̲ ̲P̲T̲ ̲1̲1̲,̲ ̲1̲2̲,̲ ̲1̲3̲,̲ ̲1̲4̲

         The documentation is needed for detailed installation
         planning and preparation of as-built documentation.