⟦033efb691⟧ Wang Wps File

    Length: 24627 (0x6033)
    Types: Wang Wps File
    Notes: PMOM NO. 20               
    Names: »4435A «

Derivation

└─⟦e9ca1be93⟧ Bits:30006183 8" Wang WCS floppy, CR 0382A
    └─ ⟦this⟧ »4435A « 

WangText


…00……00……00……00…6…02…6
5…09……86…1                                             …02…           …02…   …02…        


…02…

…02…KNN/831221…02……02…#
PROGRESS MINUTES OF MEETING NO. 20
…02……02…CAMPS








             SHAPE stated that the final delivery date (September
             84) in the CAMPS contract cannot be waived.

             SHAPE agreed that a contract amendment was necessary
             to exclude site 12 and 14 from the system delivery
             in September 84 as they had to be used for penetration
             test as requested by SHAPE.

             CRs statement:

             CR repeated that a delay in shipment and installation
             of site 12 and 14 requested by SHAPE to accomodate
             the benefits highlighted below can only be supported
             by CR if SHAPE accepts a contract adjustment, which
             adjusts the date of the 16th site to the 15th of
             November 1983.

             a)  Reduced probability for shut-down of the 240
                 hours system (site 12) during 240 hours test.

             b)  Support of the certification process performed
                 by TRW on the same configuration as the 240
                 hours test (i.e. site 12 and CR internal test
                 drive system) in CR's plant.

             Furthermore, CR explained their spirit of good
             will, cooperation and flexibility to adjust the
             sequences of the remaining site installatons, if
             this is to the benefit for the CAMPS program.

             Provided that SHAPE does not accept this proposal
             CR is going to ship site 14 as original scheduled.
             Furthermore, site 12 will be shipped immediately
             after completion of the 240 hours tests, which
             means that TRW will not be able to perform the
             penetration testing within CR's plant.

             CR explained that they are willing to await SHAPE's
             final position: to 10th January 1984.






         
                                        831221   20              CR
                                                                 A/S


                           Progress Minutes of Meeting
                           No. 20 held at Christian
                           Rovsing A/S 21st December
                           1983




         Commodore Elfrink              Gert Jensen
         Ltc Col. Hofmann               Kurt Nybroe-Nielsen
         Mr. Wellekens  Ole Eskedal
         Ms. Michel     Jan Lauridsen
         Mr. Reynolds   Jan Holm
         Mr. Lohisse    Uffe R]nnenkamp Holst




          1   2̲4̲0̲ ̲H̲o̲u̲r̲s̲ ̲T̲e̲s̲t̲ ̲S̲t̲a̲t̲u̲s̲

              CR stated that the 240 hours test would
              not be started before certain criterias
              are met:

              -   All integration test cases are successfully
                  completed

              -   A dry run of the 240 hours test cases
                  is completed successfully

              -   A mean-time-between-failure on a
                  confidence level that is acceptable
                  for the 240 hours criteria (no more
                  than 6 errors in 240 hours)

              CR had investigated the situation. An
              optimistic start date for the 240 hours
              test is the 1st February. A pessimistic
              schedule is the 1st March.

              SHAPE stated that a slippage of the 240
              hours test has to be preferred to an
              unstable system. SHAPE questioned whether
              CR intended to compromise the quality
              of the system in view of the slippage
              and CR said definitely not.

              CR stated that in the area of man-machine
              interface some problems had occurred.
              Delta Data is working on the problems
              and has promised a corrected set of SW
              in the beginning of January.

              In response to CR's announcement of schedule
              delay to the 240 hours test and subsequent
              contract milestones SHAPE stated the
              following. SHAPE does not relieve or
              excuse CR's requirement to meet the contractually
              required Sept 84 completion date for
              the Site Provisional Acceptance (SPA)
              of the sixteenth site and


              SHAPE notifies CR that the delay is unacceptable.
              Further, SHAPE reserves its rights to
              all remedies available under the contract
              including liquidated damages for the
              delay. In addition, in the event that
              SHAPE should agree in the future to a
              contract modification which extends the
              date for completion of the sixteenth
              site SPA and which revises the schedule
              for completion of intermediate contract
              milestones prior to SPA of the sixteenth
              site, appropriate and equitable considerations
              will be required to be provided by CR
              to SHAPE.

          2.  C̲R̲ ̲P̲r̲o̲g̲r̲a̲m̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲

              SHAPE questioned whether any changes
              are foreseen in program management. CR
              responded that there are no such plans
              and added that management will be intensified
              on the project as a result of CR's slippage
              in the start of the 240 hours test.

          3.  O̲C̲R̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲

              The OCR interface is baselined through
              the interface-documentation. The interface
              is tested using a data communication
              tester in the 240 hours test.

              During the Progress Meeting SHAPE forwarded
              to CR a part of the OCR SW Test procedures
              that were performed on the CAMPS-OCR
              prototype, which is now the baseline
              for production of the other OCR systems.

              A copy of the test outputs was also forwarded
              to CR. On this print-out the test procedure
              step has been referenced by pen.

              The third document forwarded was the
              message entered in the OCR. The documents
              were explained by SHAPE.

              In view of eliminating possible discrepancies
              at both sides of the interface SHAPE
              also mentioned the possibility to have
              an OCR system at the CR factory.
          CR  However, CR will first forward comments
              to the forwarded documents.

              If SHAPE provides an OCR, CR agreed to
              make an informal test of an OCR provided
              at CR's plant separated from the 240
              hours test to increase confidence to
              the Systems-interface, before tested
              at the SHAPE site during the functional
              test.



              CR will not share any costs related to
              the above mentioned OCR.

          4.  M̲S̲P̲-̲R̲e̲t̲r̲o̲f̲i̲t̲

              CR provided the following status report
              on the MSPs.

              3 problems were recognized:

              a)  Power Lamp brightness

              b)  Keylock status

              c)  Character lightness

              Tracor had submitted ECOs on item a and
              b. They are still investigating item
              c. When all items are solved, Tracor
              will retrofit all printers at CR plant
              and on site. A tentative schedule is
              January 84 - March 84.

          5.  D̲E̲P̲M̲E̲T̲ ̲S̲t̲a̲t̲u̲s̲ ̲R̲e̲p̲o̲r̲t̲

          SHAPE   SHAPE will investigate how the DEPMET
                  status report should be provided
                  as a separated volume, but declared
                  it satisfactory as of now.

          6.  T̲r̲a̲i̲n̲i̲n̲g̲

              CR agreed to provide the necessary retraining
              on site for the participants on the first
              RST-course as already agreed.

          7.  M̲a̲n̲u̲a̲l̲s̲ ̲a̲n̲d̲ ̲H̲a̲n̲d̲b̲o̲o̲k̲s̲

              On the subject of manuals and handbooks
              CR raised the following issues:

              a)  Comments from SHAPE on the MSP maintenance
                  manual is due.

              b)  The PTR/P and the V11-manuals shall
                  be incorporated in the same folder

              c)  The numbering of the SMD/MMD manual.

              d)  Print quality of the drawings.

              e)  Site maintenace manual approval.



              SHAPE will reappraise the issues and
              return with an answer.

          8.  O̲p̲t̲i̲o̲n̲s̲

              CR requested SHAPE to explain what has
              happend to the option of D.Kr. 7.8 Mill.
              contained in memorandum of understanding
              February 1. 1983.

          SHAPE   SHAPE agreed to examine the quotation
                  of the two open options stated in
                  the Memorandum of Understanding (Appendix
                  C).

          9.  2̲4̲0̲ ̲H̲o̲u̲r̲s̲ ̲T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

              Some disagreements on the 240 hours test
              procedures still exist between CR and
              SHAPE. It was agreed that the 240 hours
              test procedures should be agreed in a
              splinter meeting during this progress
              meeting.

          SHAPE   CR provided and explained their answer
                  to SHAPE tlx. no. 1532. SHAPE will
                  review and comment CRs answer - attached
                  as Appendix A.

          10. C̲h̲a̲n̲g̲e̲ ̲o̲f̲ ̲P̲r̲o̲j̲e̲c̲t̲ ̲M̲i̲l̲e̲s̲t̲o̲n̲e̲s̲

              CR assessed a worse case schedule as
              follows:

              1 March: Start 240 hours test

              1 April: Start functional test

              1 May:                                             Start
                                                                 operational
                                                                 test

              1 July:                                            Completion
                                                                 of
                                                                 the
                                                                 operational
                                                                 test

              However, CR will try to improve the situation
              by up to 2 months.

              To increase confidence in the schedule
              2 months were added to the schedule.
              It means that the SPA for site 1 should
              be 15. July 1984 - and for the last site
              should be 15th November 1984. CR promised
              to provide a
          CR  proposed detailed milestone and installation
              schedule within two weeks.

              CR and SHAPE recognized that the new
              SPA-schedule may conflict with the installation-schedule
              for the TARE system.



              CR will forward a SPA schedule. SHAPE
              will investigate whether this is in conflict
              with the TARE schedule.

              CR and SHAPE recognized that CR will
              continue with the installation of site
              10 and 13 as presently agreed. In the
              event that NATO does not approve the
              proposal of CR in subsequent paragraph
              Installation Schedule, CR will revert
              to the current valid schedule (per Master
              Schedule 830725) and will provide revised
              installation dates for sites 14, 02,
              and 16) within the currently valid schedule.

          11. T̲a̲r̲e̲ ̲R̲a̲c̲k̲s̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲

              SHAPE requested that all TARE racks should
              be delivered to NAMSA.

          12. Q̲u̲o̲t̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲I̲n̲-̲C̲i̲r̲c̲u̲i̲t̲ ̲T̲e̲s̲t̲ ̲P̲r̲o̲g̲r̲a̲m̲s̲

              CR basic quotation is contained in CPS/101/TLX/1064.

              CR is willing to set-up one day demo
              to show an example of what the test programs
              are.

              If SHAPE requests updates of Zehntel
              program this is considered an extra copy.
              CR has earlier in CPS/101/TLX/1027 given
              a price of a copy of one program is D.kr.
              17,462.

              For delivery of Zehntel test programs
              and copies later than 1st March 1984,
              CR will use an escalation of 0,8 per
              cent per month.

              Quotation valid until 31st December l984.

          SHAPE   CR need an answer from SHAPE on this
                  proposal.

          13. 2̲4̲0̲ ̲H̲o̲u̲r̲s̲ ̲T̲e̲s̲t̲ ̲C̲l̲o̲c̲k̲ ̲a̲n̲d̲ ̲L̲o̲g̲s̲

              It was agreed between SHAPE and CR that
              the final period of 48 hours mentioned
              in telex log 1517 is revised to 32 hours.
              The scheme of the 240 hours test clock
              and logs as proposed with above mentioned
              telex (CAMPS log 1517) was agreed by
              CR and SHAPE. CR and
          CR/SHAPE     SHAPE will in detail together
                       elaborate on the agreed scheme
                       with respect to particular examples.



          14. S̲t̲a̲t̲e̲m̲e̲n̲t̲s̲ ̲o̲n̲ ̲S̲e̲c̲u̲r̲i̲t̲y̲

          SHAPE   SHAPE will attempt to obtain a non
                  disclosure statement signed by TRW
                  in which they agree to consider all
                  proprietary information and data
                  submitted from Christian Rovsing
                  A/S as CRAS "proprietary" and handle
                  it accordingly for a period of 3
                  years.

          15. C̲A̲M̲P̲S̲ ̲C̲o̲m̲c̲e̲n̲t̲e̲r̲ ̲B̲a̲c̲k̲-̲U̲p̲

              SHAPE will investigate what the state
              is of the option mentioned in the MOU
              from February 83.

              The option is closed 31st December 1983.

          16. C̲A̲M̲P̲S̲ ̲S̲e̲c̲u̲r̲i̲t̲y̲ ̲C̲e̲r̲t̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

              CR explained that they are supporting
              TRW directly due to the fact that TRW
              cannot get the data necessary from SHAPE
              to proceed the CAMPS certification process.

              SHAPE advised CR that TRW shall obtain
              the documentation from SHAPE and not
              directly from CR.

              CR will based on this statement stop
              direct transmission of any further documentation
              to TRW but will continue to provide all
              contractual documentation to SHAPE for
              transmission to TRW.

              It is CR's point of view that such an
              approach will impose prolongation to
              TRW's certification effort, but be in
              line with the non-interference statement,
              which SHAPE has emphasized very strongly
              in the past.

          17. O̲v̲e̲r̲d̲u̲e̲ ̲P̲a̲y̲m̲e̲n̲t̲s̲

          SHAPE   SHAPE agreed to forward a detailed
                  status of each invoice in telex CPS/101/TLX/1083,
                  dated 83-12-14.

              CR need to know for each invoice when
              and how much has been paid.

          SHAPE   SHAPE agreed to forward a l-o-i for
                  test equipment to be able to authorise
                  advance payment of the item.



              It was recognized that SHAPE, due to
              problems with the acceptance of the deliveries,
              would not accept payment of 

              -   SW packs

              -   Test procedures

              -   Manuals

              SHAPE agreed that for all other invoices
              there should not be any reason for withhelding
              payment and that some of the invoices
              in CPS/101/TLX/1083 have been paid already.

              CR stated that there was no reason for
              withhelding payment for the SW packs.
              Concerning the test procedures, CR referred
              to a meeting on 17th June 1983, where
              SHAPE agreed to pay the test procedures.
              Concerning the manuals CR still stated
              that a preliminary version of all manuals
              have been delivered,
          SHAPE   which the line item calls for. SHAPE
                  will return with an answer.

              Considering the last delivery of software
              source listings in December 1983 and
              CR authorization for SHAPE to copy the
              existing software on magnetic media during
              January 84. SHAPE is now in the position
              to effect all payment of related SW packages
              line item.
          CR  CR agreed to provide an updated magnetic
              disk of the start at the 240 hours test.

          18. I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

              SHAPE stated that due to the utilization
              of site 12 and 14 equipment for in-plant
              testing by TRW and SECAN it might be
              possible to exempt the SPA dates of these
              two sites, from the existing installation
              completion schedule without change to
              the SPA of the sixtenth site. In that
              event SPA for sites 12 and 14 would be
              required not later than 1. October 1984.
              Such change will be considered by SHAPE
              and is subject to NATO approval.

              CR proposed that it would make available
              in-plant during the penetration testing
              by TRW and SECAN at CR's cost the system
              is configured for the 240 hours test
              (site 12 system plus Test Drive System)
              and would maintain and repair the system
              during the penetration


              testing and would permit TRW personnel
              access to operate the system for the
              test and would support TRW with CR engineers
              if required, provided SHAPE will agree
              to revise the contract completion for
              SPA of the sixteenth site from Sept.
              84 to 15. Nov. 84. SHAPE will consider
              the proposal and SHAPE's response is
              subject to NATO approval.

              SHAPE stated its belief that part of
              the consideration for the CR delay should
              include the costs of the delay to the
              TRW contractor as a result of the CR
              delay. CR did not agree to SHAPE proposed
              consideration.

              CR's proposal will be in affect for thirty
              days following its proposal and SHAPE's
              receipt of CR's proposed schedule described
              in "change of project milestones", above
              paragraph no. 10.

          19. S̲e̲c̲u̲r̲i̲t̲y̲ ̲M̲O̲U̲

              CR and SHAPE agreed to the rephasing
              of para 3 of the 6. September 1983 security
              agreement. The original of the agreement
              is in CRAS fields and a copy is attached
              as Appendix B.

          20. A̲c̲t̲i̲o̲n̲ ̲I̲t̲e̲m̲ ̲L̲i̲s̲t̲

          SHAPE   The action item list was updated
                  in a draft version. For the SHAPE
                  action item list SHAPE will forward
                  a telex where the references to the
                  closing telex for each item is provided.

          CR  CR will forward a similar telex for the
              CR action item list.

          21. H̲a̲r̲d̲w̲a̲r̲e̲ ̲P̲r̲o̲b̲l̲e̲m̲s̲ ̲i̲n̲ ̲D̲e̲l̲i̲v̲e̲r̲e̲d̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲

              SHAPE forwarded to CR the following HW
              problems.

              V̲D̲U̲/̲O̲M̲-̲1̲ ̲B̲o̲a̲r̲d̲:̲

              Problem:

              When power is removed and immediately
              re-applied, the fuse blows. During the
              Progress Meeting CR noted that the problem
              was identified early 1983 and that they
              sent a telex to Versitron to investigate
              the problem and if needed to issue an
              engineering change order.



              Versitron replied immediately and indicated
              that the problem probably was due to
              inductive load generating a spike which
              in turn caused the fuse of 1/4 amp to
              blow. Delta Data was informed by Versitron
              accordingly. CR received and installed
              1/2 Amp on all VDU's of all sites since
              then, except on the VDU's of the SHAPE
              site (and some of site 7), which were
              already shipped to SHAPE. CR will take
              action prior to start of the functional
              test.

              Since replacement of the fuses in the
              VDUs, CR has no more encountered the
              mentioned problems.

              M̲S̲P̲

              Problem:

              At SHAPE 3 MSPs out of 11, the audible
              alarm starts when test button is activated.
              The only way to stop is to turn the printer
              off for about an hour.

          SHAPE   The error was unknown to CR and,
                  therefore, CR requested to issue
                  an error report for MSP in question
                  as described in the Site Level Maintenance
                  Manual. 

              Problem:

              Metallic flat cable is twisted over 90…0e…o…0f…
              and outer wire is object to heavy strain.

              During the Progress Meeting the problem
              was demonstrated by SHAPE. CR believes
              it is not possible to re-design the equipment
              and suqqests to fold the flatcable over
              2 x 45 degrees to solve the problem.
          SHAPE   SHAPE to investigate this alternative.

              Problem:

              Capacitor on CPU-board makes contact
              with phd-board.

              It seems that Tracor knows the problem
              because on later shipments the design
              has been changed. The back of the boards
              are now also covered by an insulation
              sheet cover that prevents the contact
              between capacitor on one board and the
              other board. Tracor
          CR  will be requested to bring all MSPs to
              same design level, SHAPE printers included.



              Problem:

              The motor driver board is difficult to
              remove. The metal plate is to be bent
              to take the board out.

              SHAPE tried to investigate the problem
              but the problem does not exist on the
              last delivered printers available at
              CR. However, CR indicated that a redesign
              of the physical layout of the printers
              is not possible.

              4̲ ̲c̲h̲a̲n̲n̲e̲l̲ ̲L̲/̲L̲ ̲A̲d̲a̲p̲t̲o̲r̲:̲

              P̲r̲o̲b̲l̲e̲m̲:̲

              3 failed during COMSEC testing at SHAPE.
              (Reliability problem). CR checked and
              confirmed that the boards are at the
              CR plant now, and there they will investigate
              the failure and report to SHAPE by telex.
              SHAPE
          CR  explained that the problem was certainly
              not due to the removal of the board while
              the power was still on.

              From a principle point of view and to
              ease maintenance CR asked to follow from
              now on the maintenance philosophy from
              the site level Maintenance Manual.

          22. L̲o̲a̲d̲ ̲T̲e̲s̲t̲ ̲D̲e̲m̲o̲n̲s̲t̲r̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲S̲R̲S̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

              SHAPE has requested an explanation of
              how all requirements of the SRS para
              3.4.1 are verified. CR's explanation
              is as follows:

              1)  Para 3.4.1.2 Message Traffic Throughput

                  These requirements will be verified
                  by succesful execution of test group
                  2 in CPS/TPR/007

              2)  Para 3.4.1.3-5 Storage Characteristics

                  These requirements can be verified
                  by review of the data-declarations
                  specified in CAMPS SW Documentation
                  (Source Listings)

              3)  Para 3.4.1.6 Timing Requirements

                  The requirement of para 3.4.1.6.2-3
                  will require a special test set-up
                  for verification. CR will


          CR      issue a Technical Note defining this
                  test setup and test results.

                  The requirements of para 3.4.1.6.4-5
                  can be verified simply by means of
                  a stop-watch. This verification can
                  be performed during execution of
                  test group 1.

              4)  Para 3.4.1.7-10

                  These requirements are verified through:

                  -    DSMT HW Test

                  -    FAT site 1-16

          23. O̲n̲-̲S̲i̲t̲e̲ ̲H̲W̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲M̲i̲s̲s̲i̲n̲g̲ ̲I̲n̲f̲o̲r̲m̲a̲t̲i̲o̲n̲
              ̲a̲n̲d̲ ̲D̲e̲f̲i̲c̲i̲e̲n̲c̲i̲e̲s̲

              By means of examples on the VDU, MSP,
              L/L Adaptor, TDX (LTU, LTU-X) SHAPE stated
              that site documentation should be updated
              for missing information and existing
              deficiencies, according to the HW status.

              Concerning missing information CR stated
              that all information to connect CR supplied
              equipment is contained in the site level
              maintenance manual and documentation
              for SHAPE supplied equipment like OCR
              and LS equipment is not yet included.,
              but it was indicated that the application
              programs will also contain LTU-X set-up
              initialisations.

              SHAPE noted that for instance for the
              OCR, the ICD 008 should allow CR to establish
              interface description. CR agreed and
              will include in section 4.5 of Site Level
              Maintenance Manual the interface description
              between TDX and external equipment (i.e.
              ITA 2/5, half/full duplex, baudrate,
              stop bits, XMT & REC data normal/invert
              parity).

              The other reported SHAPE comments on
              site HW information will be forwarded
              by SHAPE telex as comments to issue 2
              of Site Level Maintenance Manual.

              CR stated that once documents are approved
              additional corrections or additions will
              be included by means of DCNs.















   A P P E N D I X   B…01…***********************















   A P P E N D I X   C…01…***********************







             APENDIX  A…01…**************


In-Plant Software Test Specification and Procedures…01…CPS/TPR/007,
 Issue 2
----------------------------------------------------------------


Ref.: CAMPS Log no. 1532, 831209

CR's answeres to the comments contained in above ref.
 are as follows:

1.     System Functions specified in para 2.1.4 are paragraph
       headings from the SRS. The SRS contains no paragraph
       with the heading: NICS TARE messages. However,
       ACP 127 message traffic via the NICS TARE interface
       is tested in test 1/d/3.

2.     It is intended to repeat the Supervisor scenario
       several times during the test. The change in the
       text reflects this intention.

3.     CR agrees.

4.     Please read para 3.1.3.1, figure 3.1.3.1-1 will
       be updated to reflect acutal configuration.

5.     a)  CR agrees.

  b)   CR agrees.

  c)   Not agreed. A1 containing previously entered data
       is displayed.

  d)   The preformatted messages to be used during this
       test will be no. 1 defined in DAG note dated 7.
       Dec. 1982.

  e)   CR agrees.

  f)   Will be changed to "Select no as release decision
       for msg 102-2".



  g)   CR agrees.

  h)   Please read step 9.4.

  i)   CR does not agree. User deletion only applies
       to msgs. in all stages of preparation ref. ICD/001
       para 3.10. A stored first draft cannot be used
       for further preparation.

  j)   CR agrees.

  k)   CR agrees.

  l)   Please refer to ICD/001 para 3.9.

  m)   CR agrees.

  n)   CR agrees.

  o)   Step 12.5: local distribution to VDU OPA is rejected
       due to removal of the reception capability performed
       in step 12.3. In step 12.3 text will indicate
       romoval of receive capability.

  p)   Will be changed to "terminal OPB".

  r)   CR agrees.

  q)   CR agrees.

  s)   SHAPE withdraws.

  t)   CR agrees.

  u)   "And release it" will be added. A release notification
       is sent to the drafter of the message ref. ICD/001,
       para 4.5.

  v)   CR agrees.

  w)   The classifcation of the related RI is not changed.

  x)   Please refer to answer given to 5,d.

  y)   CR agrees.

  z)   Step 28.4 is executed as specified.



6.     CR agrees.

  a)   That is correct.

  b)   Will be changed to "249 SIGSQN".

  c)   Please refer to ICD/001, Appendix A, p. 143.

  d)   Test messages specified in PTR/007 are not intended
       to be in absolute accordance with ACP 127, but
       rather a readable specification of the message
       parameters.

       However, the actual test message to be used will
       be in accordance with ACP 127.

7.     a-b)  CR agrees.

8.     a)  CR agrees.

  b)   Will be changed to 3.4.1.15.

  c)   Steps 13.5-13.8 will be inserted.

9.     General:

       a)  If the supervisor specifies "Statistics on"
           a daily statistics printout is performed.
           Will be included in text in start of test
           1/c)1).

       b)  Switch of mode (SUPV, MSO, MDCO) is accomplished
           via the high level menu.

  a-e) CR agrees.

  f)   An error response is displayed if queues are not
       empty.

  g-h) CR agrees.

  i)   Prior to start of the 240 hours test SHAPE will
       be provided with a complete set of table printouts
       provided with a complete set of table printouts.
       Steps 15.9 and 15.10 will be added.

  j-k) Verification is done on the report printer.

  l)   CR agrees.

  m)   SHAPE agrees to specification of case 23 provided
       the answer given to i) above.



  n)   CR agrees.

  o)   Result is depending on the test pass.

  p)   SHAPE withdraws.

  q-r) CR agrees.

9.     a)  In test 1/c)2: "18." will be changed to "18.3".

  b-c) These cases are demonstrated for TRC/PTOP by means
       of input from a paper tape via a TTY. Lines longer
       than 132 chars. and messages containing non-printable
       chars. cannot be handled by the Test Drive Systems.

  d-f) CR agrees.

10.    a-b)  See answer givne to 9 b,c.

  c)   CR agrees.

  d)   See answwer given to 6 b,d.

  e)   This is a test of the CAMPS/SCARS interface.

  f)   Precedence prosign FL2 is garbled, therefore,
       it is required that the message is processed as
       with precedence immediate.

11.    a-b)  See answer given to 9 b,c.

  c)   See answer given to 6 b,d

  d)   Format lines 12 b, c and a are garbled.

12.    a)  Mount (and assignment) of offline disk is
           performed in Supervisor scenario case 26.

  b)   The command OFLI has been deleted. Communication
       mode is selected by means of commands PUN1 or
       PUN2.

  c)   CR agrees.

13.    CR agrees.

14.-15.    This item is treated as a separate agenda
           item in Progress Meeting No. 20.