DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦053ad1bc4⟧ Wang Wps File

    Length: 992 (0x3e0)
    Types: Wang Wps File
    Notes: Spelunked
    Names: »~ORPHAN10.12«

Derivation

└─⟦1f76ea5a7⟧ Bits:30006218 8" Wang WCS floppy, CR 0277A
    └─ ⟦this⟧ »~ORPHAN10.12« 

WangText



         C13. Line Item 0009, Terminal Relocation. The Contractor
         will provide terminal relocation services and materials
         which will allow an installed terminal(s) to be relocated
         to anothr room. The Contractor will ensure its operability
         and maintain TEMPEST requirements (NACSIM 5100A) after
         terminal relocation by the following:

         The contractor will make a checkout test of the terminal
         relocation, and contractor will make the termnal relocation
         installation according to the installation criterias
         for the first increment terminals specified in this
         proposal.

         Contractor will begin a relocation at least 30 DMS
         after contractor has received a delivery order.

         The relecation ffort will comprise relocation of a
         terminal and a walloutlet and installation of the associated
         signal cables, connection of the terminal device to
         power and signal and checkout of the terminal.

         It is assumed that a FCC will provide and install