DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦05c860015⟧ Wang Wps File

    Length: 4807 (0x12c7)
    Types: Wang Wps File
    Notes: Spelunked
    Names: »~ORPHAN62.00«

Derivation

└─⟦3928290b5⟧ Bits:30006240 8" Wang WCS floppy, CR 0407A
    └─ ⟦this⟧ »~ORPHAN62.00« 

WangText




…02…PC/TRP/0003

…02…BHE/831229…02……02…#
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02……02…   PC











                 PROTOCOL CONVERTER
                 FACTORY ACCEPTANCE TEST
                 REPORT, SITE 3


                 PC/TRP/0003

                 Line Item No. 1.14










                 B]rge Hermansen





                 B[RGE HERMANSEN







                 SHAPE (2), DL.                   
                                                      














                         …0f…                          


         1



         831229                               …86…1            
                                                        …02…   
                              …02…        

                                               PC/TRP/0003

…02…BHE/831229…02…   ii
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02…      …02…   PC 
…0f…












       831229                  All        Initial issue of Document…86…1
                                                           
                        …02…           …02…   …02…   

            …02…PC/TRP/0003

…02…BHE/831229…02…   iii
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02…        …02…    PC 










                    TABLE OF CONTENTS


 1 GENERAL ..........................................
   1 

   1.1 PURPOSE ......................................
         1 
   1.2 APPLICABLE DOCUMENTS ........................
         1 

 2 TEST OVERVIEW ....................................
   1 

   2.1 CONTRACTUAL REFERENCES .......................
         1 
   2.2 TEST BASELINE ................................
         2 

 3 TEST GROUND RULES ...............................
   2 

 4 TEST CONDUCTORS ..................................
   3 


 A̲P̲P̲E̲N̲D̲I̲C̲E̲S̲


 APP. A:     PROTOCOL CONVERTER ACCEPTANCE TEST
             PROCEDURES, SITE 2, (PC/TPR/0001(2.2))
               SEC. 2

 APP. B:     TEST LOG, PC SITE 3                   
               SEC. 3

 APP C:      CONFIGURATION LIST 831224             
               SEC. 4

 APP. D:     FAT-APPLIED MESSAGES                  
               SEC. 5

 APP. E:     RELATED COMPUTER PRINTOUTS G.F.C. 4.5.3
              SEC. 6

 APP. F:     RELATED COMPUTER PRINTOUTS G.F.C. 4.5.4
              SEC. 7…86…1         …02…   …02…   …02…   …02…            
                                           
                    1 G̲E̲N̲E̲R̲A̲L̲



1.1  P̲U̲R̲P̲O̲S̲E̲

 The purpose of this document is to describe the result
 of the SITE 3 Factory Acceptance Test, which took place
 at the Christian Rovsing A/S facilities o 831215 and
 831228.



1.2  A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲

 a)  Protocol Converter Test Plan
   Contract SHNMO-82-9205-INF.
   PC/TPL/001, issue 3.

 b)  Protocol Converter Acceptance Test Procedures
   Contract SHNMO-82-9205-INF.
   PC/TPR/001, issue 2.2.



                  2 T̲S̲T̲ ̲O̲V̲E̲R̲V̲I̲E̲W̲



2.1  C̲O̲N̲T̲R̲A̲C̲T̲U̲A̲L̲ ̲R̲E̲F̲E̲R̲E̲N̲C̲E̲S̲

 On the dates of 15 and 28 of November, 1983, the 
 Site 3 Factory Acceptance Test was completed successfully.

 The test is specified in the Protocol Converter Test
 Plan para's 3.3.2 to 3.3.2.6 and the Prtocol Converter
 Contract Clause 14.3.




2.2      T̲E̲S̲T̲ ̲B̲A̲S̲E̲L̲I̲N̲E̲

         The Factory Acceptance Test Report (this document)
         is divided into 7 sections:

         1.  Protocol Converter Factory Acceptance Test Report,
             Site 3, 
             PC/TRP/0002(1)

         2.  Protocol Converter Acceptance Test Procedures,
             
             Site 3,
             PC/TPR/0001 (2.2)                        App. A.

         3.  Test Log, PC Site 3.                     App. B.

         4.  Configuration List 831215                App. C.

         5.  FAT-APPLIED MESSAGES                    App. D.

         6.  RELATED COMPUTER PRINTOUTS G.F.C. 4.5.3  App. E.

         7.  RELATED COMPUTER PRINTOUTS G.F.C. 4.5.4  App. F.


                   3 T̲E̲S̲T̲ ̲G̲R̲O̲U̲N̲D̲ ̲R̲U̲L̲E̲S̲




         The Site 3 FAT was based on the sequences of tests
         described in the test procedures n the document "Protocol
         Converter Acceptance Test Procedures, Site 3, PC/TPR/0001(2.2).

         During the tests, the results was noted in the test
         procedure and the test log. If any comments were necessary,
         these were noted in the test procedure and tet log
         as well.
         If a problem was encountered during the test, the problem
         was either catagorised as a descrepancy or a defect.
         By a descrepancy is meant a mutually agreed issue showing
         an agreed date for clearance of the issue. By a defect
         is meanta problem which prevented the acceptance of
         the test.


         Also problems encountered during the test were divided
         into two further categories:

         o   Board Failures

         o   System Level Failures.

         Board failures were corrected immediately by relacement
         of the board. System level failures were corrected
         after the first test was completed and a retest was
         performed.



                    4 T̲E̲S̲T̲ ̲C̲O̲N̲D̲U̲C̲T̲O̲R̲S̲



         The following test team conducted the test:

         [strup, Thorvald            SHAPE Representative (GQAR)
         Hermans