top - download
⟦0927a434a⟧ Wang Wps File
Length: 20510 (0x501e)
Types: Wang Wps File
Notes: Spelunked
Names: »~ORPHAN07.08«
Derivation
└─⟦f6f93b0e6⟧ Bits:30006245 8" Wang WCS floppy, CR 0245A
└─ ⟦this⟧ »~ORPHAN07.08«
WangText
…02…PC/TPL/001
…02…KPL/820723…02……02…#
PROTOCOL CONVERTER
TEST PLAN…02……02… PC
L̲I̲S̲T̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
P̲A̲G̲E̲ ̲
1 GENERAL ....................................................
1
1.1 PURPOSE AND SCOPE .....................................
1
1.2 APPLICABLE DOCUMENTS ...................................
2
1.3 TERMS AND ABBREVIATIONS ................................
3
2 DEVELOPMENT TEST ACTIVITY ..................................
4
2.1 PRETEST ACTIVITY .......................................
4
2.2 PRETEST ACTIVITY RESULTS ...............................
4
3 TEST PLAN ..................................................
5
3.1 SYSTEM DESCRIPTION ....................................
5
3.2 TEST SCHEDULES .........................................
5
4 TEST SPECIFICATIONS ........................................
8
4.1 FACTORY ACCEPTANCE TESTS ...............................
8
4.1.1 COMSEC VERIFICATION ................................
8
4.1.2 FUNCTIONAL TESTS ...................................
8
4.2 PRELIMINARY SITE ACCEPTANCE TEST .......................
11
4.2.1 FUNCTIONAL TESTS ..................................
11
4.2.2 TEMPEST VALIDATION .................................
12
4.3 PROVISIONAL SITE ACCEPTANCE TESTS ......................
12
4.3.1 FUNCTIONAL TESTS ...................................
12
4.3.1.1 SITE 1 PROVISIONAL ACCEPTANCE TEST .............
12
4.3.1.2 SITE 2 PROVISIONAL ACCEPTANCE TEST .............
13
4.3.1.3 SITE 3 PROVISIONAL ACCEPTANCE TEST .............
13
4.3.2 COMSEC VERIFICATION ...............................
13
5 FINAL ACCEPTANCE ...........................................
14…86…1 …02… …02……02… …02…
1̲ G̲E̲N̲E̲R̲A̲L̲
This Test Plan comprises the baseline for acceptance
test
of the Protocol Converter to be developed under SHNMO
contract 82-9205-INF.
1̲.̲1̲ P̲U̲R̲P̲O̲S̲E̲ A̲N̲D̲ S̲C̲O̲P̲E̲
Test plan objectives are:
(a) To provide guidance and instructions for the
management and technical personnel throughout
the test period.
(b) To provide the user with an orderly schedule
of test events.
(c) To specify the equipmen and organizational
requirements, and the methodology of testing.
A brief description of pretest methods are included
for
completeness.
A comprehensive plan for system evaluation and records
of
test input and expected outputs will be inclded in
a
separate document entitled "TEST PROCEDURES".
For each test (FAT, Prel. AT, and Prov. AT) including
COMSEC verification the TEST PROCEDURES will specify
the following:
- Purpose
- Personnel Requirements
- HW Requirements
- SW Requirments
- Functional Description
- Acceptance Criteria
- Test Schedule
1̲.̲2̲ A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ D̲O̲C̲U̲M̲E̲N̲T̲S̲
1. Protocol Converter contract SHNMO-82-9205-INF.
1982-04-29.
2. System Requirement Specification (SRS).
Appendix G of Reference 1. 1982-04-2.
3. SCARS II System Design Baseline Vol III A
Rev A, B and C 1981-06-30, 1981-07-15, and 1982-04-28.
Burroughs.
or
CPS/ICD/006, 1981-11-10 Christian Rovsing A/S.
4. Functional Description for the SCARS, CAMPS, ACCIS
interface. 1981-02-5. As appendix E to Reference
3.
5. Remote Terminal Supervisor (GRTS).
Honeywell DD40B rev. 0, July 1976.
6. DINDAC CCTC TR-01, 1978-06-30 and
DINDAC-RCI Protocol Notes, 1982-07-27. CRA.
7. ACE Security Directive 70-1.
1979-08-31 withchange 2 dated 1981-02-06.
8. ACE ADP Standards Manual 96-1-1, part no. 007-3
1980-01-14.
9. AMSG 720A. January 1977.
10. AMSG 719B. September 1976.
11. AQAP 1, 13
12. MIL-STD188C. 1969-11-24
13. WWCCS ADP Telecom Standard Engineering Practices,
DCA November 1979.
14. Control wires and functions for WWMCCS-PC link
(delivery by SHAPE on or before 3. May 1982).
15. X25 LAP (CAMPS) Product Specification.
CSS-MIC/0422/SP/1027. 1982-05-28. Chr. Rovsing
A/S.
16. Protocol Converter, Project Implementation Plan,
issue 2, Christian Rovsing A/S, 1982-07-21.
17. Protocol Converter, System Specification, issue
2,
Christian Rovsing A/S, 1982-07-4.
1̲.̲3̲ T̲E̲R̲M̲S̲ A̲N̲D̲ A̲B̲B̲R̲E̲V̲I̲A̲T̲I̲O̲N̲
This section defines the terms and abbreviations to
be used
in this document.
ACE Allied Commands Europe
CAMPS Computer Aided Messag Processing System
CCIS Command and Control Information System
CR Christian Rovsing A/S
CR80 CR80 minicomputer (Christian Rovsing)
DINDAC autoDIN-wwmccs Direct Access Communications
module
DN355 Honeywell front-end processor
EMI Rack Anti)-Electromagnetic Interference Rack.
End Systems CCIS, CAMPS, or SCARSII
EPROM Erasable Programmable Read-only Memory
FAT Factory Acceptance Test
HW Hardware
I/F Interface
OC Operator's Console
PC Protocol Converter
PIP Proect Implementation Plan
Prov.AT Provisional Acceptance Test
Prel.AT Preliminary Acceptance Test
RAM Random Access Memory
RCI Remote Computer Interface (to Honeywell)
SCARS Status & Control Alerting & Reporting System
SHAPE Supreme Headquaters Allied Powers Europe
SRS System Requirement Specification
SW Software
SWELL Software Engineering Low Level Language
TRC Traffic Controller
VDU Visual Display Unit
WWMCCS World Wide Military Command & Control System
2̲ D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲ T̲E̲S̲T̲ A̲C̲T̲I̲V̲I̲T̲Y̲
This chapter describes the informal tests performed
concurrently with the PC software development.
2̲.̲1̲ P̲R̲E̲T̲E̲S̲T̲ A̲C̲T̲I̲V̲I̲T̲Y̲
Software component will be tested currently during
development.
The functions of the individual software components
will be
verified by means of the general CR80 debugging and
special
facilities for inspecting the general registers at
entry
and exit from SWELLprocedures. Register dumps at the
operators console will contain the procedure name together
with the words ENTRY and EXIT. These dumps may be switched
on and off by SWELL conditional compilation of the
statements generating the dumps.
Data sructures may be dumped as well at critical points
for verification of the semantics of the SW component.
Also semaphore protected areas for message headers
and
message information can be dumped for verification
of the
correct use of these buffrs. This feature is eventually
excluded totally to meet the demands for secure handling
of
classified information.
2̲.̲2̲ P̲R̲E̲T̲E̲S̲T̲ A̲C̲T̲I̲V̲I̲T̲Y̲ R̲E̲S̲U̲L̲T̲S̲
The record of results obtained during the development
tests
will be available for each SW compoent tested.
The record will consist of a suitably
commented hardcopy of the test results to support
trouble-shooting during integration of SW into larger
entities.
3̲. T̲E̲S̲T̲ P̲L̲A̲N̲
3̲.̲1̲ S̲Y̲S̲T̲E̲M̲ D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲
The configuration under test is outlined in Figure
3-1.
---------- ---------- ----------
' ' ' ' '
'
' A '----------' PC '----------' B
'
' ' ' ' '
'
---------- ---------- ----------
FIGURE 3-1 GENERAL PC TEST CONFIGURATION
System A is a CAMPS, SCARSII system, or a suitable
system
for simulating the CAMPS/PC interface if CAMPS is not
available. 'A' communicates with PC using the X.25
protocol
with messages in E1 format a described in Reference
3.
System B is a Honeywell 6000 computer equipped with
a DN355
front-end computer. 'B' communicates with PC using
the
RCI/DINDAC protocol described in References 5 & 6.
System B
is often refered to as CCIS. For FAT systm B will have
to
be simulated on PC equipment due to unavailability
of CCIS
for this test.
3̲.̲2̲ T̲E̲S̲T̲ S̲C̲H̲E̲D̲U̲L̲E̲S̲
Acceptance tests will be performed according to the
schedule given in Table 3-1.
-----------------------------------------------------
' TEST ' DATE
'
'---------------------------------------------------'
' '
'
' Factory Acceptance Test, site 1 ' 83-01-30
'
' '
'
' Factory Acceptance Test, site 2 ' 83-02-15
'
'
'
' Factory Acceptance Test, site 3 ' 83-02-28
'
' '
'
' Preliminary Acceptance Test, site 1 ' 83-03-15
'
' '
'
' ProvisionalAcceptance Test, site 1 ' 83-04-15 &'
' ' 83-07-04
'
' Provisional Acceptance Test, site 2 ' 83-05-15
'
' '
'
' Provisional Acceptance Test, site 3 ' 3-06-06
'
-----------------------------------------------------
TABLE 3-1 ACCEPTANCE TEST SCHEDULE
The Provisional Acceptance Test at site 1 will commence
on
83-04-15 with a test of the PC connected to CAMPS and
CCIS.
Provisional Acceptace Test of SCARSII-PC-CCIS will
take
place on 83-07-04. See Reference 1, p 25.
The following Test Reports will be prepared and delivered
to the customer in 6 copies.
-----------------------------------------------------
' TEST ' DELIVERY
'
'---------------------------------------------------'
' '
'
' Factory Acceptance Test, site 1 ' 83-01-30
'
' '
'
' Factory Acceptance Test, site 2 ' 83-02-15
'
' '
'
' Factory Acceptance Test, site 3 ' 83-02-28
'
' '
'
' Provisional Acceptance Test, site 1 ' 83-05-13
'
' '
'
' Provisiona Acceptance Test, site 2 ' 83-05-30
'
' '
'
' Provisional Acceptance Test, site 3 ' 83-06-27
'
' '
'
----------------------------------------------------
TABLE 3-2 TEST REPORT SCHEDULE
4̲ T̲E̲S̲T̲ S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲S̲
This section describes the test configurations and
provides
an overview of test methods to be used during the tests.
Detailed test procedures will b issued separately.
4̲.̲1̲ F̲A̲C̲T̲O̲R̲Y̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲S̲
The FAT's consist of:
a. COMSEC verification for site 1 equipment
b. Functional test of HW and SW within the constraints
given in reference 1, p.24
4̲.̲1̲.̲1̲ C̲O̲M̲S̲E̲C̲ V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲
CMSEC verification of equipment is divided into two
categories:
a. EMI rack assembly including opto-electrical
interfaces
b. Terminal equipment for supervisory and control
As for the CAMPS programme ACE COMSEC is given admission
to te factory integration site in order to perform
TEMPEST
qualification tests on site 1.
Terminals are delivered with a TEMPEST clearance
certification according to AMSG720A, cf. Reference
2, p 61.
4̲.̲1̲.̲2̲ F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ T̲E̲S̲T̲S̲
The general test coniguration is outlined in Figure
3-1.
For the Factory Acceptance Tests system A is a CAMPS
or a
CAMPS simulator if CAMPS is not available.
For FAT, system B in Figure 3-1 is a Protocol Converter
suitably modified for simulating the CCIS side.
PC hardware is tested using the CPU-, RAM-, and LTU-test
options included in the PC 'Maintenance Controller'
SW
package described in Reference 17, section 4.1.2.
For each ite the FAT is conducted according to the
test
procedures.
The test procedures will identify by name and number
the
item under test. Test procedures must contain a general
description of how the system is prepared for the test.
Special requirments for test system preparation will
be
stated along with each test procedure.
--------------------------------------------------------
' DATE : 82-07-25
'
' TEST ITEM : (name of funcion under test)
'
' TEST NO. : FAT 1
'
' REFERENCES : App. 1 of FAT 1 Test Report
'
'------------------------------------------------------'
' ' '
'
' STEP ' ACTIONS & INPUTS ' EXPECTED RESULTS
'
' ' '
'
'-----------------------------------------------------'
' ' '
'
' 1 ' Masterclear system '
'
' ' on CPU/SCM module ' (M) on OC
'
' ' '
'
' 2 ' Type: "INIT" on OC '
'
' ' ' (L) on OC
'
' ' ' (expected contents
of '
' ' ' a data dump+reference)'
' 3 ' Type: "LOGON CCIS '
'
' ' SHAPE PASW CAMPS" ' (0) on OC
'
' ' ' (further results)
'
' ' '
'
' ' '
'
' . ' ................. ' ...................
'
' ' '
'
' ' '
'
' ' '
'
' . ' ................. ' ...................
'
' ' '
'
' ' '
'
' ' '
'
' . ' ................. ' ..................
'
' ' '
'
' ' '
'
' ' '
'
'-----------------------------------------------------'
' COMMENTS: ' TEST WITNESSES:
'
' Example showing lay-out '
'
' of test procedure record ' ......................
'
' '
'
' ' ......................
'
' '
'
' '
'
--------------------------------------------------------
Table 4-1 SAMPLE TEST PROCEDURE RECORD…86…1 …02… …02……02… …02…
Table 4-1 shows the lay-out of test procedure records
to be
specified in the Test Procedures.
Each component test procedure record will typically
contain
one or more refernces to hardcopy dumps. For the
particular example shown in Table 4-1 these dumps could
be
data structures from which it may be verified, that
the SW
function under test has recognized the input parameters
correctly before they are passed on fo execution.
4̲.̲2̲ P̲R̲E̲L̲I̲M̲I̲N̲A̲R̲Y̲ S̲I̲T̲E̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲
This test has a twofold purpose:
a. Functional test of PC when connected to CCIS
b. Security Certification Test is performed at SHAPE's
initiative by TRW
The PREL AT will be perfored on site 1 immediately
following the installation of the PC.
The test configuration is given in Figure 3-1 with
no
connection between system A and PC, and system B equal
to
CCIS.
4̲.̲2̲.̲1 F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ T̲E̲S̲T̲S̲
These tests are performed to veriy the operation of
the
PC-CCIS link.
The tests will be based on prestored PC test messages
and
SHAPE supplied test messages sent from the CCIS system.
Test procedures specifying the CCIS-PC test will be
issued
along with test procedures for AT and Prov.AT.
4̲.̲2̲.̲2̲ T̲E̲M̲P̲E̲S̲T̲ V̲A̲L̲I̲D̲A̲T̲I̲O̲N̲
This test is conducted to ensure that the
equipment and the installation of it is compliant with
the
requirements listed in the System Requiremens
Specification. Cf. Reference 2, section 7.
Inspection and measurements performed during the Security
Test must not delay the CR functional tests. Functional
tests and TEMPEST test are performed simultaneously,
cf.Reference 1, p25.
4̲.̲3̲ P̲R̲O̲V̲I̲I̲O̲N̲A̲L̲ S̲I̲T̲E̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲S̲
The Provisional site Acceptance Tests consists of:
a. Functional Tests
b. On-site COMSEC Verification
4̲.̲3̲.̲1̲ F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ T̲E̲S̲T̲S̲
These tests are conducted in accordance with the Test
Procedures. SHAPE is oblied to provide relevant equipment
and adequate personnel for running the tests.
It is foreseen that the functional tests will require
availability of each applicable combination of end-systems
for 40 hours distributed throughout the test period.
Time for test shall primarily be allocated during prime
working hours.
At the expiry of the test period for each combination
of
end-systems, CR will issue a test report. At the same
time
the purchaser will issue a 'Notice of Defects' or a
'Dscrepancy Note' if applicable.
4̲.̲3̲.̲1̲.̲1̲ S̲I̲T̲E̲ 1̲ P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲
This test is divided into two stages as stated in Table
3-1. The test configuration used in the first test
is shown
in Figure 3-1 with systems A and B equal to CAMPS nd
CCIS,
respectively.
In the second test, system A is SCARSII and B is CCIS
as
before. Prov.AT is scheduled to 83-07-04. SCARSII must
be
available for test no later than 83-07-04. If this
is not
possible PC-SCARSII may optionally be tested starting on
83-08-15, cf. Reference 1, p53.
Duration of the CAMPS-PC-CCIS Prov.AT is estimated
to one
month starting on 83-04-15. Prov.AT of the SCARSII-PC-CCIS
configuration is scheduled to start o 83-06-01 and
last 14
days.
4̲.̲3̲.̲1̲.̲2̲ S̲I̲T̲E̲ 2 P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲
This test assumes the availability of an operational
CAMPS
and CCIS.
Scheduled start of this test is 83-05-15. The estimated
duration is two weeks.
Test procedures re identical to the ones used during
the
first half of the Prov.AT for site 3, i.e. only the
CAMPS-PC-CCIS configuration exists on site 2.
4̲.̲3̲.̲1̲.̲3̲ S̲I̲T̲E̲ 2̲ P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ T̲E̲S̲T̲
This test is scheduled to start on 83-06-06 and last
for
hree weeks.
First week is allocated test of the configuration
CAMPS-PC-CCIS.
The following week is used for testing SCARSII-PC-CCIS.
The
optional use of having the OC connected to either one
of
the configurations while on-line will be tested uring
Prov.AT on site 3.
4̲.̲3̲.̲2̲ C̲O̲M̲S̲E̲C̲ V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲
The COMSEC verification will be performed by ACE COMSEC
personnel a̲f̲t̲e̲r̲ ̲e̲a̲c̲h̲ ̲P̲C̲ ̲h̲a̲s̲ ̲p̲a̲s̲s̲e̲d̲ ̲t̲h̲e̲ ̲f̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲t̲e̲s̲t̲s̲.
COMSEC tests shall verify that the operational system
and
its environment omplies with the security requirements
stated in the SRS, section 7 and related documents
listed
there.
5̲. F̲I̲N̲A̲L̲ A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲
Final Acceptance of the PC is contingent on the acknowledgement
by SHAPE
that each site has been found in compliance with the
requirements, and that C has met its warranty
obligations.
Final Acceptance is scheduled to 84-08-30.