DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦1d51eaf91⟧ Wang Wps File

    Length: 29214 (0x721e)
    Types: Wang Wps File
    Notes: XFX/PLN/0003              
    Names: »4370A «

Derivation

└─⟦7c6ce1fba⟧ Bits:30006155 8" Wang WCS floppy, CR 0035A
    └─ ⟦this⟧ »4370A « 

WangText

…16……00……00……00……00…%…0a……00……00…%…0b…%…0d…%…00…$…08…$…0c…$…86…1                                             …02…           …02…   …02…        

    4370A/aml…02…XFX/PLN/0003

…02…NPP/840223…02……02…#
CROSS FOX MPF INSTALLATION PLAN
…02…Issue 1…02…CROSS FOX MPF














                 CROSS FOX MPF INSTALLATION PLAN



                 XFX/PLN/0003













                 Niels Peder Pedersen




                 Knud Benkjer







                 HARRIS Oslo (7), HARRIS Rochester (1), GJ,
                 OWE, KM, PMS, BHB, KNB, KJK, LU















                          Install. mgr.  830223


             1.1



             840223




    4370A/aml…02… XFX/PLN/0003

…02… NPP/840223…02……02…ii
CROSS FOX MPF INSTALLATION PLAN
…02… Issue 1…02…CROSS FOX MPF














    1   831128                  All      First issue of document

  1.1   840223                7,8,9,     Issue 1 of document has
                              10,14,     been updated according
                              18,19      message 11944 and
                                         xfx/101/tlx/0029.




                    T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



     1  SCOPE AND PURPOSE ........................... 2
       
     2  ORGANIZATION ................................ 2
       
       2.1 INSTALLATION SECTION ..................... 2
             
         2.1.1 Site Installation .................... 4
                 
         2.1.2 Transportation ....................... 5
                 

     3  CONTRACTOR/CUSTOMER RESPONSIBILITIES ........ 6
       
         3.1.1 Site Surveys ......................... 6
                 
         3.1.2 Site Preparation Requirements ........ 7
                 
         3.1.3 Equipment Installation Drawings ...... 8
                 
         3.1.4 Site Readiness Verification .......... 8
                 

       3.2 INSTALLATION ............................. 9
             
         3.2.1 MPF facility ......................... 9
                 
         3.2.2 Crypto Room ..........................10
                 
         3.2.3 TARE/TRC Room ........................10
                 

     4  SITE PREPARATION AND INSTALLATION
             ACTIVITIES .............................14
               
       4.1 SITE PREPARATION .........................14
             
         4.1.1 Site Surveys and Site Visits .........14
                 
         4.1.2 Site Preparation Requirements (SPR) ..15
                 
         4.1.3 Equipment Installation Drawings (EID).16
                 

       4.2 SITE VERIFICATION ........................17
             
       4.3 INSTALLATION .............................18
             
         4.3.1 Preparation for Installation .........18
                 
         4.3.2 Shipment of Equipment ................19
                 
         4.3.3 Installation Phase Activities ........20
                 

     5  INVENTORY CHECK .............................23
       
       5.1 INCOMING INVENTORY .......................23
             
       5.2 FINAL INVENTORY CHECK ....................23
             
         5.2.1 Property Inventory List ..............24
                 


                   1  S̲C̲O̲P̲E̲ ̲A̲N̲D̲ ̲P̲U̲R̲P̲O̲S̲E̲

         This plan outlines the various tasks to be accompliched
         concerning site preparation and installation.  It describes
         how CR intends to manage and perform the job and outlines
         the responsibilities of CR, HARRIS and Nodeca.  A description
         of the major installation tasks completes the plan.









                     2  O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



2.1      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲E̲C̲T̲I̲O̲N̲

         The Installation Section is the section within the
         Logistic Department responsible for CROSS FOX MPF site
         preparation and installation.  The Installation Section
         Manager will report directly to the Logistic Department
         Manager.  The Logistic Department Manager will coordinate
         the Installation Section activities with the CR CROSS
         FOX Project Office.

         See Figure 2.1.


















































 Figure 2.1…01…CROSS FOX Installation Organization and Tasks



2.1.1    S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         a)  The site installation subsection is responsible
             for site preparation and installation planning
             and equipment installation.

             The section will perform the following tasks on
             the CROSS FOX MPF program:

             1.  Prepare a Transportation and an Installation
                 plan.

             2.  Perform site surveys and site verifications.

             3.  Prepare site preparation requirements and equipment
                 installation drawings.

             4.  Perform installation and installation checkout
                 at MPF site 101 and 301.

         b)  The installation of the CROSS FOX MPF equipment
             will be performed by one installation team composed
             of two installation technicians.  One of the technicians
             will lead the team and will report to the manager
             of the site installation subsection.  The team
             leader will be capable of working without close
             supervision.

         c)  The team will install a complete site and be organized
             so that each member will be responsible for specific
             tasks, within the installation program.  Both will
             be experienced in the installation of computer
             equipment and will be familiar with the use of
             maintenance and diagnostic software.



2.1.2    T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲

         a)  The Transportation Subsection is responsible for
             shipment of CROSS FOX MPF equipment from CR's factory
             to each of the two MPF sites.

             The subsection will perform the following tasks
             on the CROSS FOX MPF program:

             1.  Planning, coordination and control of shipments

             2.  Preparation of shipping documentation

             3.  Packing and marking

             4.  Notice of shipments

             5.  Insurance of shipments











         3  C̲O̲N̲T̲R̲A̲C̲T̲O̲R̲/̲C̲U̲S̲T̲O̲M̲E̲R̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲ 

         The following outlines the responsibilities of CR,
         HARRIS, Nodeca and THN concerning site preparation
         and installation of the MPF computer equipment delivered
         by CR.  It translates the requirements of the contract
         into specific responsibilities to be performed by each
         organization.



3.1.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         a)  CR shall participate in HARRIS' site survey of
             the two management centers, sites 101 and 301.
              The site survey is to be accomplished at least
             9 months prior to start of installation at each
             site.

         b)  HARRIS will arrange a visit to each site in coordination
             with CR.  The purpose of the site survey is to
             ensure that CR can prepare site preparation requirements
             and equipment installation drawings.

         c)  Nodeca/THN representatives will assist CR to collect
             the relevant information to be used to prepare
             the site for installation of the CROSS FOX MPF
             equipment.  At least one of the Nodeca/THN representatives
             on each site survey team will be authorized to
             make decisions and to sign a survey report on behalf
             of Nodeca/THN.

         d)  Scaled floor plans and civil engineering drawings
             of the equipment rooms are to be used during the
             survey and shall be handed over to CR at start
             of the survey.  Additional data will be supplied
             by Nodeca/THN in accordance with minutes of meetings
             agreed to during the conclusion of the site survey.





3.1.2    S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

         a)  CR shall prepare site preparation requirements
             (SPR) concerning the preparation of each site for
             installation of the CORSS FOX MPF equipment.  The
             SPR will be submitted to Nodeca through HARRIS
             for approval 6 months prior to start of installation
             at each site.

             Nodeca shall issue approval or a list of deficiensies
             within 25 work days of receipt.

             The SPR will be used by Nodeca/THN to prepare the
             CROSS FOX designated space for CR to install the
             MPF equipment.

         b)  CR's planning baseline for preparation of site
             preparation requirements is the site survey.  If
             Nodeca/THN advise CR of site modifications accomplished
             after the site survey, the contractor will incorporate
             these changes into his site preparation requirements,
             provided that he is notified of the changes not
             later than 6 weeks prior to the submission date.

         c)  If available, Nodeca/THN will deliver additional
             site documentation, requested by CR and updates
             to the site documentation supplied during the site
             surveys.  Last submittal of data from Nodeca/THN
             is 3 months prior to CR's submittal of SPR.

         d)  A detailed description of the contents of the SPR
             is contained in chapter 4.





3.1.3    E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  CR will deliver equipment installation drawings
             to Nodeca through HARRIS for approval not later
             than 2 months prior to the installation start date
             for each site.  Nodeca will issue approval or a
             list of deficiencies within 15 work days of receipt.
              The approved drawings will be used for installation
             of the CROSS FOX MPF equipment.

         b)  The approved site preparation requirements and
             the equipment characteristics are the contractor's
             planning baseline for his preparation of equipment
             installation drawings.  Nodeca is responsible of
             ensuring that any site modifications made after
             site preparation requirements approval are identified
             to the contractor for his incorporation into the
             equipment installation drawings.  The contractor
             shall then incorporate these changes in the equipment
             installation drawings provided that the changes
             are identified to him not later than 6 weeks prior
             to the submission date.

         c)  The equipment installation drawings will be marked
             up during installation as necessary to reflect
             the actual as-built installation and a final corrected
             set will be delivered to Nodeca through HARRIS
             one month after site provisional acceptance test
             is completed. The approved drawings will be included
             in the site maintenance handbook.

         d)  A detailed description of the contents of equipment
             installation drawings are contained in chapter
             4.



3.1.4    S̲i̲t̲e̲ ̲R̲e̲a̲d̲i̲n̲e̲s̲s̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         CR shall perform a verification of the two management
         centers readiness for installation.  Nodeca will participate.
          Nodeca will notify CR through HARRIS of the readiness
         of a site and an inspection date should be mutually
         agreed.  The site readiness inspection shall be accomplished
         at least 30 days prior to start of installation.



3.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



3.2.1    M̲P̲F̲ ̲f̲a̲c̲i̲l̲i̲t̲y̲

         a)  CR will provide and install the contractual number
             of computer racks, disc cabinets, operator positions,
             supervisor positions and engineering positions
             in the Message processing room and interconnect
             them with cables.  (Refer to Figure 3.2.1-1 and
             3.2.1-2).

         b)  CR will provide and install a work station with
             a visual display unit and a medium speed printer
             in the Management room and connect the workstation
             equipment with optical fibre cables to the computer
             racks in the Message processing room.

         c)  Nodeca/THN will install all signal cable ducts
             in the Message processing room identified in the
             SPR.

         d)  Nodeca/THN will be responsible for power and ground
             installations.  The SPR will contain CR's requirements
             to these installations.

         e)  CR will connect the above equipment to power outlets
             and ground connection points installed by Nodeca/THN.

         f)  Nodeca/THN will install the cable ducts and CR
             will supply and run the cables from the Message
             processing room to the Crypto room, the Tare room
             and the MCSF room (Refer to Figure 3.2.1-3).

         g)  Nodeca/THN will be responsible for penetrating
             the tempest shields as part of the cable duct work.
             This includes any filtering and connection to filters
             required.



3.2.2    C̲r̲y̲p̲t̲o̲ ̲R̲o̲o̲m̲

         a)  CR will provide and install the contractual number
             of racks with Crypto interfaces and patch panels
             in the Crypto room and make the contractual number
             of signal cable connections to the Crypto equipment
             and black patch panels. (Refer to Figure 3.2.1-3).

         b)  Nodeca/THN will provide and install the Crypto
             equipment and Crypto racks and all interconnecting
             signal cable ducts.

         c)  Nodeca/THN will be responsible for power and ground
             installations.  The SPR will contain CR's requirements
             to these installations.



3.2.3    T̲a̲r̲e̲/̲T̲R̲C̲ ̲R̲o̲o̲m̲

         CR will provide and run the contractual number of signal
         cables from the Message processing room to the Tare
         room and terminate the cables at the Tare connecting
         point.

         Nodeca/THN will be responsible for penetrating the
         tempest shields as part of the cable duct work. This
         includes any filtering and connection to filters required.


















































  Figure 3.2.1-1…01…Site 101, Typical Equipment Room Layout


















































  Figure 3.2.1-2…01…Site 301, Typical Equipment Room Layout


















































       Figure 3.2.1-3…01…Block Diagram MPF Interfaces



     4  S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲

         This section describes CR's activities in connection
         with site preparation and installation.



4.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲

         The site preparation phase can be defined as the time
         span from contract award to completion of site verification.
          During this phase CR's main activities concerning
         site preparation are the development of site preparation
         requirements and equipment installation drawings for
         each site.  During the same phase THN's main activities
         are concentrated on completion of the design and construction
         or reconstruction of each site, and preparing the site
         area for installation.



4.1.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲ ̲a̲n̲d̲ ̲S̲i̲t̲e̲ ̲V̲i̲s̲i̲t̲s̲

         a)  CR will perform site surveys in conjunction with
             HARRIS/THN at each of the two sites.  Refer to
             section 3.1.1 for an identification of responsibilities.

         b)  A site survey report will be prepared by CR and
             agreed to by Nodeca and THN.  This report will
             identify equipment location, equipment entry routes,
             planned power, grounding and air conditioning,
             local facility support etc.  Action items for outstanding
             information will be included.

         c)  The information collected during the site survey
             will form the Data Baseline for that site.  Information
             needed by CR for this Data Baseline but not available
             during the site survey will be identified by CR
             and agreed by HARRIS/THN.  HARRIS/THN will forward
             this information to CR to complete this baseline.
              Information collected as part of the Data Baseline
             that subsequently changes must be forwarded to
             CR at least 6 weeks prior to CR's delivery of SPR
             if it is to be incorporated in this document.


4.1.2    S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲(̲S̲P̲R̲)̲

         a)  CR will provide SPR for each site as identified
             in paragraph 3.1.2.

         b)  The SPR will contain all information needed to
             clearly identify to THN what civil works are required
             to prepare the site for the contractor to install
             his equipment.

         c)  The SPR will be based on the following information:

             1)  THN drawings/documents handed over to CR during
                 the site surveys or submitted to CR as agreed
                 to during the survey meetings.  If available,
                 the drawings/documents should include cable
                 runs outside the MPF room and also show the
                 location of the Crypto equipment and other
                 equipment which has to be connected to CROSS
                 FOX MPF.

             2)  The information gathered during the surveys
                 and contained in the survey report including
                 the proposed site layouts or an amended site
                 layout if received by CR within 3 months of
                 the SPR delivery date.

             3)  Physical, characteristics of the CROSS FOX
                 MPF equipment, concerning power requirements,
                 air conditioning, power and signal and grounding
                 interface, weight, floor load, envelope dimensions
                 etc.

             4)  The AMSG 719 C installation criterias and National
                 regulations.

         d)  The SPR will cover the following:

             1)  Physical layout of major equipment.

             2)  Requirements to cable ducting and conduits
                 in the MPF, Crypto and Tare/TRC rooms and cable
                 runs between these rooms.



             3)  Requirements concerning space and access.

             4)  Requirement to power and grounding systems
                 including number of required power outlets
                 and grounding connection points in conjunction
                 with major equipment.

             5)  Air-conditioning requirements.

             6)  Other civil works requirements, if any.



4.1.3    E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  CR will provide equipment installation drawings
             (EID) for each site as identified in paragraph
             3.1.3.  These drawings will be used for the installation
             of CROSS FOX MPF equipment on each site and will
             be based on the following information:

             1)  The site survey report.

             2)  The equipment configuration and equipment interface
                 data.

             3)  The site preparation requirements.

             4)  The AMSG 719 C installation criterias and National
                 regulations.

         b)  The EID's will be prepared to cover the following:

             1)  A Key list showing all major assemblies and
                 cable interconnections.

             2)  Room layout to scale of the Message processing
                 room and other equipment areas showing major
                 assemblies and related signal and power cable
                 runs.

             3)  Power supply and power and grounding distribution
                 to major assemblies.

             4)  Interface connection points with mating connector
                 details.

             5)  Installation and check-out procedures.





4.2      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         a)  CR will perform a site verification at each site
             in accordance with paragraph 3.1.4.

         b)  The verification shall certify that all requirements
             in the SPR have been accomplished and that the
             site is ready for installation of the CROSS FOX
             MPF equipment.  This verification will consist
             of inspections and tests according to a site verification
             procedure.  The provisions of AMSG 719 C relative
             to site preparation should be verified by Nodeca/THN
             and ACE COMSEC prior to or during the site verification.
              The procedure prepared by CR will include:

             1)  An introduction and description of the verification
                 tasks to be performed.

             2)  A check of the power and grounding (cabling,
                 distribution, outlets) required in the SPR.

             3)  Verification of the access and space required
                 in the SPR.

             4)  Verification of the cable ducting and conduits
                 required in the SPR for the CROSS FOX MPF equipment
                 rooms.

             5)  Verification and update of the site support
                 and logistic data (storage, liason, facilities
                 for the installation team) recorded during
                 the site survey.

         c)  The procedure is to be signed by the participants
             from Nodeca/THN and CR and then issued as a site
             verification report.

         d)  Discrepancies found during the verification will
             be recorded together with corrective actions required
             and completion date of action taken.  The site
             is ready for equipment installation upon successful
             completion of the verification.



4.3      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



4.3.1    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         a)  Upon successful completion of site verification
             CR will start packing of equipment and preparation
             of the coming on site installation effort.

         b)  CR will notify Nodeca through HARRIS - Rochester,
             copy HARRIS - Oslo of arrival time to site of installation
             team and equipment.  This notice will be made at
             least 15 working days prior to arrival at site.
              Nodeca/THN will arrange for access bagdes for
             CR's installation team and vehicles and clear the
             installation area.

             The arrangements and preparations to be made by
             Nodeca/THN will be discussed and agreed to during
             the site surveys.  Final arrangements will be made
             at the verification meetings.

             The site is requested to provide the following
             preparations and support prior to or during CR's
             presence at site:

             1)  Clear the equipment entry route from unloading
                 area to CROSS FOX MPF Equipment room and from
                 unloading area to storage area.  The equipment
                 entry route will be described in the site survey
                 report.

             2)  Provide temorary storage area for the CROSS
                 FOX MPF equipment.  The storage area required
                 will be specified in the site survey report.

             3)  Provide access to commercial telephone and
                 telex allowing for international communication.
                  The use to be reimbursed by CR.

             4)  Provide access to canteens or messes for CR
                 personnel, if available.

             5)  Provide emergency medical aid in case of accidents,
                 if available.



             6   Provide access to reproduction facilities,
                 if available.

             7)  Provide office space and furniture including
                 desks and chairs.  Space and furniture for
                 two persons are required, if available.  Also
                 storage space for tools and test equipment
                 (locked room or cabinets) is requested.

             8)  Provide site truck/trolley/push waggon for
                 transportation in corridors, if available.



4.3.2    S̲h̲i̲p̲m̲e̲n̲t̲ ̲o̲f̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲

         a)  All equipment will be shipped from CR'S plant in
             Copenhagen, Denmark.  CR will contract with a transportation
             company to provide the transportation to the sites.
              The equipment will be shipped from Copenhagen
             to each MPF site by truck.

         b)  CR intends to schedule the shipments so that the
             installation team will be present at the site to
             receive the equipment.

         c)  Access to site for transportation vehicles and
             personnel as well as unloading, unpacking and temporary
             storage of equipment will be discussed and agreed
             to during the site surveys and final arrangements
             will be made at the verification meetings.

             Full identification of the delivery team (transportation
             company) including names and truck license will
             be provided at least 15 working days prior to delivery.

         d)  Details on transportation are described in the
             CROSS FOX MPF Transportation Plan (XFX/PLN/0002).





4.3.3    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲h̲a̲s̲e̲ ̲A̲c̲t̲i̲v̲i̲t̲i̲e̲s̲

         Figure 4.3.3 is a description of the major installation
         tasks to be performed at a site.

         A step by step description of Figure 4.3.3 follows:

         Step 1, 13  The time spent on travelling to and from
                     the site.

         Step 2  The first day on site will be used to contact
                 site officials, make all necessary arrangements,
                 inspect the installation areas and move in.

         Step 3  Before equipment is brought into the CROSS
                 FOX rooms, CR will install all signal cables.
                  Cable ducts will already have been installed
                 by THN.

         Step 4  An incoming inventory is performed before the
                 containers are moved to the installation areas.
                  (Refer to chapter 5).

                 Racks and terminal equipment is unpacked, and
                 moved to the MPF room and the Crypto room.

         Step 5  The signal cables in the MPF room will be terminated
                 and connected.

         Step 6  The MCSF workstation is installed in the Management
                 room and connected to the computer equipment
                 by optical fibre cables.  The cables are terminated
                 and connected to the workstation terminals.
                  Each terminal will be connected to the power
                 and ground outlet installed by the THN.

         Step 7  The signal cables in the Crypto room and Tare/TRC
                 room are terminated and connected.

         Step 8  The equipment in the Crypto room is unpacked
                 and connected to power and an installation
                 check-out test of hardware is started.


                          ^ WEEK 1  ^ WEEK 2  ^ WEEK 3  ^
                                                        WEEK
                                                        4
                                                        
                                                        ^
                          ^ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲^̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲^̲ ̲ ̲ ̲ ̲ ̲ ̲
                          ̲ ̲ ̲^̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲^
                          ^1̲^̲2̲^̲3̲^̲4̲^̲5̲^̲1̲^̲2̲^̲3̲^̲4̲^̲5̲^̲1̲^̲2̲^̲3̲^̲4̲^̲5̲^̲1̲^̲2̲^̲3̲^̲4̲^̲5̲^
                          ^ ̲ ̲ ̲      ^         ^      
                            ^         ^
 1.                       TRAVEL TIME         ^2̲^̲2̲^  
                                                ^    
                                                  ^  
                                                    ^
                                                     
                                              ^
                          ^     ̲    ^         ^      
                            ^         ^
 2.                       ARRIVAL/INTRODUCTION          ^
                                                        
                                                        
                                                        ^2̲^
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                          ^         ^         ^      
                            ^         ^
 3.                       INSTALLATION OF     ^      
                                              ̲ ̲ ̲^̲ ̲   
                                                  ^  
                                                    ^
                                                     
                                              ^
   SIGNAL CABLES          ^     ^2̲^̲2̲^̲2̲^       ^      
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 4.                       UNLOADING/INSTALLATION        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        ̲
                                                        ̲
                                                        ̲
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   OF EQUIPMENT/INVENTORY ^         ^ ^4̲^̲4̲^   ^      
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 5.                       TERMINATION/CONNECTION        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   OF SIGNAL CABLES IN    ^         ^       ̲ ̲ ̲^      
                            ^         ^
   MPF ROOM               ^         ^     ^1̲^̲1̲^      
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 6.                       INSTALLATION OF WORK-         ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ̲
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   STATION IN MPF ROOM    ^         ^     ^1̲^ ^      
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 7.                       TERMINATION/CONNECTION        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   OF SIGNAL CABLES IN    ^         ^         ̲^̲ ̲     
                            ^         ^
   CRYPTO/TARE ROOM       ^         ^       ^1̲^̲1̲^    
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 8.                       MOUNTING OF MODULES,          ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   POWER UP/CHECK OUT AT  ^         ^         ^ ̲     
                            ^         ^
   THE CRYPTO ROOM        ^         ^         ^1̲^    
                            ^         ^
                          ^         ^         ^      
                            ^         ^
 9.                       MOUNTING OF MODULES ^      
                                                ^    
                                                  ^  
                                                    ^
                                                     
                                              ^
   POWER UP/CHECK OUT AT  ^         ^         ^   ̲ ̲ ̲ ̲
                          ̲ ̲ ̲^         ^
   THE MPF ROOM           ^         ^         ^ ^2̲^̲2̲^̲2̲^̲2̲^
                                  ^
                          ^         ^         ^      
                            ^ ̲        ^
10.                       INVENTORY CHECK     ^      
                                                ^    
                                                  ^  
                                                    ^1̲^
                                                    ^
                          ^         ^         ^      
                            ^         ^
11.                       HARDWARE TEST/INSTAL-         ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        ^
   LATION INSPECTION BY   ^         ^         ^      
                            ^   ̲ ̲ ̲    ^
   COMSEC                 ^         ^         ^      
                            ^ ^2̲^̲2̲^   ^
                          ^         ^         ^      
                            ^ ̲        ^
12.                       PACKING   ^         ^      
                                      ^         ^1̲^  
                                        ^
                          ^         ^         ^      
                            ^       ̲ ̲ ̲^
13.                       TRAVEL TIME         ^      
                                                ^    
                                                  ^  
                                                    ^
                                                  ^2̲^̲2̲^

     ̲             
   ^2̲^  MANPOWER REQUIRED            




       Figure 4.3.3…01…Major Installation Tasks



         Step 9  The equipment in the MPF room is connected
                 to power, modules are unpacked and mounted,
                 and an installation check-out test of hardware
                 is started.

         Step 10 A final inventory check is carried out at the
                 completion of installation with representatives
                 from HARRIS, refer to chapter 5.  The inventory
                 check will verify that the equipment is delivered
                 in accordance with the contract.

         Step 11 A nucleus test is performed to verify that
                 all hardware is functioning.  It will be a
                 subset of the factory acceptance test and will
                 verify that the processor units, the channel
                 units, the watchdog units and the adapter units
                 are correctly installed.  Correct installation
                 of terminal connections is also verified. 
                 The test is regarded as an informal test to
                 demonstrate that installation is completed,
                 and that the site is ready to be taken over
                 by CR's test team.  This test team will arrive
                 on site when installation is completed to install
                 the site software and conduct the PSA.

                 In connection with the hardware test, ACE COMSEC
                 will inspect and check-out the equipment for
                 compliance with the Nato radiation standard.

         Step 12 Packing of tools and test equipment.



                    5  I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲



5.1      I̲N̲C̲O̲M̲I̲N̲G̲ ̲I̲N̲V̲E̲N̲T̲O̲R̲Y̲

         a)  CR will perform an incoming inventory of the containers
             according to the accompaning packing lists.

         b)  Before the containers are moved to the installation
             site, the containers will be inspected for any
             visual damage.

         c)  The results of the above mentioned a) and b) will
             be recorded and a copy will be given to the transportation
             company.

         d)  The incoming inventory/inspections of the containers
             are witnessed by the local property custodian.

         e)  A complete set of shipment documents is handed
             over to the property custodian.

         f)  The packing list will form the record of the incoming
             inventory and will be signed by the property custodian
             of the site and given "back" to the transportation
             company or the CR representative.

         g)  A copy of the signed packing list will be retained
             by the property custodin of the site for evidence
             of receipt in relationship to the Nodeca/THN responsibilities
             stated in CROSS FOX MPF program implementation
             plan (DOC XFX/PIP/0001)



5.2      F̲I̲N̲A̲L̲ ̲I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲

         a)  This inventory check shall verify that all equipment
             and documentation related to the actual site has
             been delivered.  The inventory will consist of
             a visual check of all delivered items against an
             inventory list.

         b)  The inventory check will be conducted by a CR representative
             and carried out with a representative from HARRIS.
              The inventory list will be signed by the HARRIS
             representative.


5.2.1    P̲r̲o̲p̲e̲r̲t̲y̲ ̲I̲n̲v̲e̲n̲t̲o̲r̲y̲ ̲L̲i̲s̲t̲

         a)  CR will prepare an inventory list for each MPF
             site.

         b)  The inventory list will be prepared in block form
             and will have the following sections:

             1)  Main Equipment and disk units
                 (Racks, Modules, Cables etc.)

             2)  Terminal Equipment 
                 (VDU and Printers)

             3)  Ancillary Equipment
                 (Cabinets, Tables etc.)

             4)  Tools and Test Equipment for hardware and software

             5)  Installation Material

             6)  Documentation for hardware and software

             7)  Spare Parts

             8)  Verification (signature, comments)

         c)  The inventory list includes the following data
             elements:

             1)  Site Number

             2)  Item Number

             3)  Description

             4)  True Manufacturers Part Number

             5)  Serial Number

             6)  NATO Stock No.

             7)  Remarks

             8)  Delivered Quantity

             9)  Received Quantity