DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦1ec166cd2⟧ Wang Wps File

    Length: 28941 (0x710d)
    Types: Wang Wps File
    Notes: Spelunked
    Names: »~ORPHAN73.00«

Derivation

└─⟦84647c47a⟧ Bits:30005817 8" Wang WCS floppy, CR 0014A
    └─ ⟦this⟧ »~ORPHAN73.00« 

WangText

…00……00……00……00……00…I…02……00……00…I
H…02…H…05…G…0b…G…0c…G…02…G…05……86…1                                             …02…           …02…   …02…          

…02…CPS/PLN/005

…02…19800926…02……02…#
CAMPS INSTALLATION PLAN
…02……02…CAMPS








                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



   1  SCOPE AND PURPOSE  ..........................  5

   2  ORGANIZATION  ..............................  5

     2.1  SITE PREPARATION AND VERIFICATION  ......  5
     2.2  INSTALLATION  ...........................  7
     2.3  SECURITY CLEARANCE OF INSTALLATION
          PERSONNEL  ..............................  8

   3  SITE PREPARATION AND INSTALATION 
      RESPONSIBILITIES  ........................... 10

     3.1  SITE PREPARATION AND VERIFICATION  ...... 10
     3.2  INSTALLATION  ........................... 11
       3.2.1  Main Sites  ......................... 11
       3.2.2  Remote Tares  ...................... 12
       3.2.3  Remote Terminals  ................... 15

   4  SITE IMPLEMENTATION PLAN  ................... 18

   5  SITE PREPARATION AND VERIFICATION  .......... 21

     5.1  SITE PREPARATION  ....................... 21
     5.2  SITE SURVES AND SITE VISITS  ........... 22
     5.3  CIVIL ENGINEERING REQUIREMENTS (CER)  ... 22
     5.4  AS-TO-BE-BUILT DRAWINGS  ................ 24
     5.5  DELIVERY OF SIGNAL CABLES  .............. 24
     5.6  SITE VERIFICATION  ...................... 25

   6  ISTALLATION  ............................... 26

     6.1  PREPARATION OF INSTALLATION  ............ 26
     6.2  INSTALLATION TASK SCHEDULE  ............. 26
     6.3  SHIPMENT OF EQUIPMENT  .................. 26
     6.4  INSTALLATION AT REMOTE LOCATIONS  ...... 27
     6.5  INSTALLATION PHASE ACTIVITIES  .......... 27
     6.6  DOCUMENTATION  .......................... 31




                  L̲I̲S̲T̲ ̲O̲F̲ ̲F̲I̲G̲U̲R̲E̲S̲



     2.1  CAMPS INSTALLATION ORGANIZATION  ........  6
     2.2  CAMPS INSTALLATION TEAM  ................  9
     3.1  TYPICAL CAMPS ROOM LAYOUT  .............. 13
     3.  CABLE CONNECTIONS AT A TYPICAL MAIN SITE. 14
     3.3  TYPICAL COMMUNICATION LINK TO REMOTE
            TERMINALS  ..............................
 17
     4.1  SITE IMPLEMENTATION PLAN  ............... 19
     6.1  INSTALLATION PHASE ACTIVITY AT A
           TYPICAL SITE  ........................... 31


                1̲ ̲ ̲S̲C̲O̲P̲E̲ ̲A̲N̲D̲ ̲P̲U̲R̲P̲O̲S̲E̲



   This plan outlines the various tasks to be accomplished
   concerning site preparation and installation.  It describes
   how CR intends to manage and perform te job and outlines
   the responsibilities of CR and SHAPE/host nation concerning
   installation.  Milestones of the site implementation
   schedule have been identified and an analysis of the
   site installation task is performed.




                  2̲ ̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



   Ste preparation and installation is a functional section
   within the Logistic Department.

   Figure 2.1 shows the installation organization.



2.1  S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

   The Systems Division has contracted with a Norwegian
   company, Ingen]r P.A. Bakkejord A/S (PAB) to perform
   the following tasks on the CAMPS program:

   1.  Site Survey
   2.  Site Civil Engineering Requirements
   3.  As Built Drawings
   4.  Site Verification

   Under supervision by Logistics Department PAB will
   ensure tha SHAPE will provide sufficient and timely
   information to enable delivery to SHAPE of items 2
   and 3 above.  PAB will act as contractor's representative
   in relation to SHAPE in the following areas:

   1.  Obtain necessary information from SHAPE to geneate
       Civil Works Requrements and As Built Drawings.

   2.  Submit Civil Works Requirements and As Built Drawings
       to SHAPE. Update these if necessary.

   3.  Perform Site Verification.…86…1         …02…   …02…   …02…   …02… 
                                                














































                     FIGURE 2.1
          CAMPS INSTALLATION ORGANIZATION.


2.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         The installation of CAMPS will be performed by 2 teams.
          Each team will install a complete site.  The organization
         of the CAMPS installation team is shown on figre 2.2

         Each team will be composed of a teamleader and 2 installation
         technicians. As a back up 2 technicians will be available
         at CR's plant to relieve a team member in case of sickness,
         vacation etc.  The back-up will also be used for the
         instalation of some of the mainsites with more than
         one remote terminals location connected, and for some
         of the remote TARE sites located far away from the
         mainsites.

         The team will be organized so that each member will
         be responsible for specific task, within the installation
         program; but all will be trained in the whole program
         so they are able to substitute each other if necessary.

         The team leader will be responsible for:

         -   day by day organization of the installation tasks.

         -   interface o site and installation arrangement with
             site.

         -   inspection of main site and remote terminal location.

         -   documentation incl. correction of A-T-B-B drawings.

         -   correspondence with CR, Denmark.

         -   accomodation arrangements and transportation (ersonnel
             and equipment).

         -   inventory check.

         -   log book.

         -   site tests (M & D software).

         -   interface to local COMSEC and other authorities.


         The team member A will be responsible for:

         -   power and power connections

         -   rack integration

         -   mechanics

         -   cables and cabling

         The team member B will be responsible for:

-        terminal equipment and interfaces

         -   test of equipment

         -   OPTO-installations



2.3      S̲E̲C̲U̲R̲I̲T̲Y̲ ̲C̲L̲E̲A̲R̲A̲N̲C̲E̲ ̲O̲F̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲E̲R̲S̲O̲N̲N̲E̲L̲

         During the site surveys CR was informed that special
         clearance (other than NATO secret) was required for
         some insallation areas.  (Refer to each site survey
         report).  SHAPE should investigate this and clarify
         the required security clearance for CR personnel at
         each site.…86…1         …02…   …02…   …02…   …02…                     
                              














































                        FIGURE 2.2
                 (CAMPS INSTALLATION TEAM)


  3̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲



         The following outlines CR's and SHAPE's/Host Nations
         responsibilities concerning site preparation and installation.
          An atempt has been made to translate the requirements
         of the contract into specific installation tasks to
         be performed by each organization.

         The remote terminals have not yet been surveyed and
         some installation responsibilities concerning these
         instalations may, therefore, have to be reconsidered
         and clarified during and after the survey.



3.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



3.1.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         CR will perform site surveys in conjunction with SHAPE.
          SHAPE will assist CR in collecting elevant information
         and site documentation during the surveys for the preparation
         of civil engineering requirements (CER) and as-to-be-built
         drawings.



3.1.2    S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲

         CR will deliver CER 12 months prior to installation
         of each site to b used by host nation to prepare the
         CAMPS installation.

         SHAPE will deliver additional site documentation, 
         requested by CR, or updates to the site documentation
         supplied during the site surveys. Last submittal of
         data from SHAPE/Host Nation is 3 onths prior to CR's
         submittal of CER.

         CR will deliver  As-To-Be-Built drawings to SHAPE 9
         months prior to installation for approval.  The approved
         drawings will be used for installation of the CAMPS
         equipment.


         SHAPE will approve the CER and A-T-B-B drawings to
         meet the national regulations and ACE COMSEC requirements.

         CR will deliver signal cables to be run by host nation,
         with the neessary installation documentation 6 months
         prior to start of installation.



3.1.3    S̲i̲t̲e̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         CR will perform a verification of each site's readiness
         for installation.  SHAPE or SHAPE representatives will
         participate.



3.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
         CR will perform installation of the CAMPS equipment
         in accordance with the requirements of the contract
         and CAMPS Requirements Specification.  

         In the following please refer to figure 3.1 and 3.2.



3.2.1    M̲a̲i̲n̲ ̲S̲i̲t̲e̲s̲

         CR will install the compter racks, supervisor positions
         and maintenance position in the room designated as
         the CAMPS equipment room.

         CR will install all signal cables between racks, between
         racks and maintenance position, between racks and supervisor
         positions and betwen racks and I.D.F. if not incorporated
         in the central equipment. Host Nation will install
         all signal cable ducts in the CAMPS Equipment room.

         CR will connect the above equipment to power outlets
         and ground connection points installed by Host Natin.
          The power outlets and ground connection points will
         be located close to each piece of equipment.  The CER
         will specify number of outlets and maximum distance
         from equipment.


         Host Nation will be responsible for all power and ground
         installations.  The CER will contain CR's requirements
         to these installations.

         CR will install the user terminals in therooms specified
         by host nation; connect the signal cables to the terminals
         and connect the terminals to the power outlets and
         ground connection points installed by Host Nation.
          The power outlets and ground connection points will
         be installed closeto the terminals accordingly to the
         CER.

         Host Nation will install the cable ducts and run the
         cables from the CAMPS equipment room to each user terminal.
          CR will deliver the signal cables (OPTO)


         Host nation will install the TRC and/or low sped teleprinters
         and make all connections in the terminal end.  The
         cables from these terminals will be run to the CAMPS
         room and terminated at the IDF by Host Nation.  Host
         Nation will also provide cables and cable ducting.
          CR will deliver and run he cables from the IDF to
         the computer.

         The same principle will be used regarding the CCIS,
         SCARS and collocated tare connections.



3.2.2    R̲e̲m̲o̲t̲e̲ ̲T̲a̲r̲e̲s̲

         At main site CR will install the modem(s) in the crypto
         room and connect it to adjacent equpment (crypto and
         black patch located in the same rack.) The further
         connection to the MDF or similar will be Host Nation
         responsibility. Host Nation will make the connection
         between the crypto-equipment and the IDF in the CAMPS
         room.

         At remote TRE locations CR will install a rack with
         modem and connect it to power and ground installed
         by Host Nation. CR will specify his requirements to
         power and ground. The rack will have available space
         for the  SHAPE furnished crypto. CR will connect th
         modem to the crypto and black patch in the rack. The
         connection between the black patch and the MDF or similar
         will be Host Nation responsibility.…86…1         …02…   …02…  
         …02…   …02…                                           
















































                        Figure 3.1
 Typical CAMPS Room Layout…86…1         …02…   …02…   …02…   …02…                                
           
         Figure 3.2
         Cable Connections at
         a Typical Main Site.



3.2.3    R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

         In the following please refer to figure 3.3 
         At main sites CR will install the red part of the remote
         terminal equipment in the CAMPS room (i.e. rack withmultiplexer(s)
         and red patch).

         The black equipment (modems and black patch) will be
         installed by CR in the crypto-rack provided and installed
         by Host Nation.

         CR will provide the cable(s) to be run by Host Nation
         between the CAMPS room and the cypto-rack in cable
         ducts provided and installed by Host Nation (it is
         assumed that cable ducts already exist or are planned
         as part of the main installations). CR will include
         the cable(s) in the para 3.1 delivery of signal cables.
         CR will perform he cable(s) run in the CAMPS room as
         part of the main installation.

         CR will provide the cables and make the connection
         between crypto and black patch and between modem and
         black patch. Host Nation will provide the cable and
         make the connection beween black patch and MDF.

         At remote locations CR will install the black equipment
         (modems and black patch) in the crypto rack provided
         and installed by Host Nation. CR will provide and make
         the connections between the modem and black patch and
         beween the crypto and black patch. Host Nation will
         provide and make the connection between the MDF and
         black patch.

         CR will install the red equipment (rack with red patch,
         multiplexer and optical MUX/DEMUX) in the room specified
         by Host Nation

         C will provide the cable to be run by Host Nation between
         the crypto and the red patch. Host Nation will provide
         and install the cable duct for this cable.

         CR will install the terminals in the rooms specified
         by Host Nation. CR will provide the opo-cables to be
         run between the red rack and the terminals. Host Nation
         will install the cable ducts and run the opto-cables.


         CR will terminate the opto-cables at the terminal and
         in the red rack. CR will connect the terminal to power
         outlets and ground connection points installed by Host
         Nation. The powr outlets and ground connection points
         will be installed close to each terminal.

         Host Nation will be responsible for all power and ground
         installations. CR will specify equipment power load,
         number of outlets and other civil engineering requiremets
         to be used by Host Nation to prepare the remote terminal
         site. CR will include the cables to be run by Host
         Nation in the para 3.1 delivery.

         At sites which are implemented with optical links between
         the CAMPS room and remote terminals (i.e. Ukir, Afnorth,
         Non and Sonor) the principles outlined for the main
         site user terminals shall apply.…86…1         …02…   …02…   …02…  
         …02…                                           
















































                        Figure 3.3
 Typical Communication Link to Remote Terminals.…86…1         …02…   …02…   …02…   …02…                     
                      
               4̲.̲ ̲S̲I̲T̲E̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲



         Figure 4.1 shows the milestones of the efforts to be
         accomplished during the site preparation phase, related
         to each site.

         The plan is composed o the date for completion of site
         preparation given by Host Nation during the site surveys
         and the schedules of the contract.

         Each milestone is represented by a dot and reference
         number of effort. The referenced efforts are listed
         at the bottom ofthe plan.

         A discussion of each effort follows.



4.1      S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲

         As shown in the plan site No. 1 through 13 have been
         surveyed during May-June 1980.
         Surveys of MEDEAST and SONOR and of remote terminals
         are to be scheduled by SHAPE and perfored.



4.2      H̲/̲N̲ ̲D̲A̲T̲A̲ ̲S̲U̲B̲M̲I̲T̲T̲A̲L̲S̲

         It was agreed during the site surveys by SHAPE/Host
         Nation to provide missing documentation requested by
         CR at the dates shown in the plan.



4.3      C̲I̲V̲I̲L̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲ ̲(̲C̲E̲R̲)̲

         The contractual due date (12 onths prior to start of
         installation of each site) is shown.



4.4      A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲

         The contractual due date (9 months prior to start of
         installation) is shown.


4.5      H̲O̲S̲T̲ ̲N̲A̲T̲I̲O̲N̲ ̲D̲E̲S̲I̲G̲N̲

         Some sites are already under construction (site 1 and
         2) or under reconstruction (site 5 and 6). The related
         design milestones are therefore not marked in he plan.



4.6      D̲E̲L̲I̲V̲E̲R̲Y̲ ̲O̲F̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         The due date for CR delivery of signal cables (6 months
         prior to start of installation) is shown.



4.7      H̲O̲S̲T̲ ̲N̲A̲T̲I̲O̲N̲ ̲C̲O̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲ ̲O̲R̲ ̲R̲E̲C̲O̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲.

         The scheduled date for completion of construction or
         econstruction as obtained from Host Nation during the
         Site Surveys are shown. Please notice that some sites
         (AFSOUTH, AFNORTH and COMNON) have not completed the
         construction or reconstruction at time of installation.
         Since the CAMPS area modificatin (8) are completed
         1 month prior to installation, this seems only to have
         an impact on the user terminal installations. CR would
         like SHAPE to investigate this and clarify the impact
         if any.



4.8      C̲A̲M̲P̲S̲ ̲A̲R̲E̲A̲ ̲M̲O̲D̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         The scheduled date for ompletion of CAMPS area modification
         as obtained from Host Nation during the Site Surveys
         are shown.



4.9      H̲/̲N̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         Host Nations scheduled completion date for signal cable
         installation is shown.




4.10     S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         The Site Verification by CR is to be performed, when
         the preparation works are finished. As shown only one
         month is scheduled between completion of Site Prparation
         works and start of installation.



4.11     S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         The scheduled completion date of site installation
         is shown.









           5̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



5.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲

         The site preparation phase can be defined asthe time
         span from contract award to start of each site installation.

         During this phase CR's main activities concerning installation
         are placed on preparation of Civil Engineering Requirements
         and as-to-be built drawings  for each site.

         During he same phase Host Nation's main activities
         are concentrated on completion of the design and construction
         or reconstruction of each site, and preparation of
         the site area for installation (for schedule see fig.
         4.1).


         During the site surveys early in the preparation phase
         a Data Baseline was created concerning the preparation
         of each site for CAMPS installation.  However, this
         baseline is stillincomplete for a majority of sites,
         and it was agreed at the site survey meetings to complete
         it by submittal of the missing documentation to CR.

         This submittal will enable contractor to start site
         design and to prepare the CER and A-T-B-B drawins.

         Later updates received in time i.e. at least 3 months
         prior to CR's delivery of CER will be incorporated.



5.2      S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲ ̲A̲N̲D̲ ̲S̲I̲T̲E̲ ̲V̲I̲S̲I̲T̲S̲

         CR will perform site surveys at each site as required.
         Site No. 1 through 13 has been surveyed in My and June
         1980.  The survey of the remaining sites (site No.
         14 and 15) plus the remote terminal locations is to
         be planned and performed.

         Visit to some sites during the preparation phase might
         be necessary.  CR will notify SHAPE if such visits
         re needed.



5.3      C̲I̲V̲I̲L̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲ ̲(̲C̲E̲R̲)̲.̲

         CR will provide CER for each site as required in the
         contract.

         The CER will contain the equipment related information
         needed to enable Host Nation to prepare the installation
         for CAMPS.

         he CER will be based on the following information:

         1.  Host nation drawings/documents handed over to CR
             during the site surveys or submitted to CR as agreed
             to during the survey meetings.  The drawings/documents
             include cable runs outside CAMPS-rom and location
             of user terminals and other equipment which has
             to be connected to CAMPS.


         2.  The information gathered during the surveys and
             contained in the survey report including the proposed
             site layouts or an amended site layout if received
             in time from SHAPE/HostNation.

         3.  Physical characteristics of the CAMPS equipment.

         The CER will cover the following:

         1.  Physical layout of major equipment.

         2.  All cable ducts and conduits in the CAMPS room.

         3.  Record of Host Nation/ACE COMSEC cable runs outsidethe
             CAMPS room.

         4.  Requirement to power and grounding systems including
             number of required power outlets and grounding
             connections point in conjunction with major equipment.

         5.  Airconditioning requirements.

         6.  Other civil requirements, if any




5.4      A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲

         CR will provide as-to-be-built drawings for each site
         as required in the contract.

         These drawings will be used for the installation of
         CAMPS equipmet on each site.

         The A-T-B-B drawings will be based on the following
         information:

         1   The site documentation required to prepare the
             CER.

         2.  The equipment configuration and equipment interface
             data.

         3.  The CER.

         The A-T-B-B drawings will be pepared to cover the following:

         1.  Physical layout of major equipment.

         2.  Floor and wall plans showing cable runs of all
             interface cables and interconnecting cables to
             be run inside the CAMPS room. Signal cable runs
             from CAMPS room to user termials.

         3.  Equipment interface to power and grounding systems.

         4.  Airconditioning interface to existing systems,
             if any.

         5.  Cable diagrams and cable details.

         6.  Distribution frames and patch panels details.


5.5      D̲E̲L̲I̲V̲E̲R̲Y̲ ̲O̲F̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         Al signal cables to be run by host nation will be delivered
         at least 6 months prior to installation as agreed during
         the site survey meetings, together with necessary installation
         documentation.

         The correct installation of these cables will be veriied
         during site verification.




5.6      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         CR will perform a verification of each site prior to
         installation.

         The verification shall prove that the site is ready
         for installation of the CAMPS equipent.

         The proving will consist of inspections and tests according
         to a Site Verification Procedure.

         The procedure will be prepared on basis of CR's civil
         engineering requirements as-to-be-built drawings and
         Host Nation civil works drawings.

         Th procedure is to be signed off by the participants
         and issued as a Site Verification Report.

         Discrepancies found during the verification will be
         recorded together with corrective actions to be taken
         and completion date of action taken.

         The siteis first to be considered as handed over to
         contractor upon successfull completion of the verification.



                     6̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



6.1      P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         Final arrangements concerning CR's arrival to site
         are to be made at time of site verification.  The site
         representatives willbe informed about how CR intends
         to accomplish the installation. Also the responsibilities
         of the site personnel will be discussed. The purpose
         of this is to assure that CR can carry out the installation
         in an efficient way without interference of he daily
         operations at the site.



6.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲T̲A̲S̲K̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲

         During the installation phase the team will be working
         in accordance to a detailed task schedule, which will
         itemize work functions at the site for all installation
         personnel and dentify major areas of installation completion.



6.3      S̲H̲I̲P̲M̲E̲N̲T̲ ̲O̲F̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         CR intends to schedule the shipment of CAMPS so that
         the installation team will be present at site to receive
         the equipment.

         In order to take into account any slippage of this
         schedule (delays caused by customs, transportation
         of delay of the installation at the previous site)
         arrangements for each site to handle the receipt of
         the equipment will be made.

         The equipment for remote terminals and remote TARE
         willeither be unloaded at the main site and brought
         to the remote location by the installation team or
         transported directly after main site equipment is unloaded.



6.4      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲T̲ ̲R̲E̲M̲O̲T̲E̲ ̲L̲O̲C̲A̲T̲I̲O̲N̲S̲

         CR will integrate the installation of remote terminals
         and remote tares into the main site installation. 
         This approach will benefit both manower allocation
         and installation schedule.  CR expects that some remote
         site installations will require extra manpower in order
         to accomplish this joint installation within the schedule.



6.5      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲H̲A̲S̲E̲ ̲A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲

         Figure 6.1 is an analyis of the installation effort
         to be carried out at a typical site.  A similar analysis
         will be made for each site, when the site configurations
         are finalized.

         A step by step description of figure 6.1 follows:

         Step 1      One week…08…s buffer between stes seems necessary
                     in regard to the distance between sites
                     and in order to make up for delay in the
                     installation of the previous site or shipment
                     of equipment.  The necessary buffer will
                     be calculated when the final installation
                     sequence is decide. 

         Step 2,3,4  The first 2 days on site will be used to
                     contact site officials, make all necessary
                     arrangements, inspect the installation
                     areas and move in.  A checklist will be
                     prepared for the inspection.

         Step 5      Before any equipment is brough into the
                     CAMPS room the signal cables must be installed.
                      Cable ducts will already have been installed
                     by Host Nation.

         Step 6      The team leader will use one or two days
                     for inspection of remote terminals and
                     remote TARE locations depending of thetravel
                     distance.  A checklist will be prepared
                     for the inspections.


         Step 7      Racks, terminal equipment and furniture
                     is unpacked, and moved to the CAMPS and
                     CRYPTO-room.  Since the access routes on
                     the majority of sites are long and on some
                     part ofthe route extremely narrow it will
                     be impossible to move more than two racks
                     per day.  Assistance from the site will
                     be needed to this job in form of trolleys
                     and manpower.  The availability of assistance
                     has been investigated during the site surves
                     and recorded in the site survey report.

         Step 8      The signal cables is to be terminated and
                     connected.  The quantity of cables for
                     a typical CAMPS site is approx. 100.

         Step 9,10   The user terminals (up to 24) are to be
                     installed in different roos located all
                     over the site.  The cables (optical fibres)
                     are already installed by Host Nation. 
                     The cables are to be terminated and connected
                     to the user terminals.

                     Close to each terminal location a power
                     outlet and a secure ground connectionpoint
                     has been installed by Host Nation.

         Step 11,12  Both the Remote Terminal installations
                     and Remote Tares are considered here.

                     The installation task concerning Remote
                     Terminals will vary from site to site,
                     because of the number of remote trminal
                     locations connected to a main site.  The
                     installation effort of remote terminals
                     is, therefore, to be analyzed site by site
                     in connection with the analysis of each
                     main site.  A typical remote terminal installation
                     consisting of 1 rack plus  terminals has
                     been used for this evaluation.


                     The installation task at a Remote TARE
                     location will consist of the installation
                     of 1 rack plus 1 modem; because of the
                     considerable distance to some of the Remote
                     TARE locatio it might be necessary to use
                     extra manpower for the installation.

                     At both locations equipment is installed
                     and the hardware tested.  Final test can
                     first be performed when the mainsite equipment
                     is functioning.

         step 13, 14 The equipment in he CAMPS room is
         15          connected to power, modules are unpacked
                     and mounted, and the test of hardware is
                     started.
 
         step 16     When the hardware at a mainsite is functioning
                     a final hardware test is performed at the
                     remote location.

         step 17     An inentory check is carried out at the
                     completion of installation with representatives
                     from the site and or SHAPE.  The inventory
                     check shall prove that the equipment is
                     delivered and installed in accordance with
                     the inventory list and the as-to-be-buit
                     drawings.

         step 18     A nucleus test (subset of the factory acceptance
                     test is performed to verify that all hardware
                     is functioning. 

                     A test procedure for this nucleus test
                     will be prepared.  The test is regarded
                     as an informal test to prove hat installation
                     is completed, and that the site is ready
                     to be taken over by CR's test team.  The
                     test results will be recorded in the log
                     book. The test team will arrive to site
                     when installation is completed to perform
                     the site adaptation in sofware and to conduct
                     the site provisional acceptance test (SPA).…86…1
                             …02…   …02…   …02…   …02…                     
                                          















































Fig. 6.1…86…1         …02…   …02…   …02…   …02…                                         
  
6.6      D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲


         The installation team is responsible for installation
         of the equipment in accordance with the As-To-Be-Built
         drawings.  A copy of the A-T-B-B drawings will be arked
         up during the installation to reflect deviations, if
         any.

         A log book will follow the system from start of integration
         at factory throughout the lifetime of the system. 
         All activities during the installation phase will be
         recorded in the lobook with the date of completion.
          The logbook will remain at site after installation
         and the recording will be continued by the test team
         performing site acceptance test.

         Any inspections such as quality assurance inspection,
         ACE COMSEC inspectios should be recorded in the log
         book.

         After site provisional acceptance (PSA) the site will
         be responsible for keeping the logbook.…86…1 …02… …02… …02… …02… …02… …02… …02… …02… …02… …02…
         …02…