6.3 C̲h̲a̲n̲g̲e̲ ̲C̲o̲n̲t̲r̲o̲l̲ ̲B̲o̲a̲r̲d̲
All change proposals shall be presented to a change control board for decision before
any actual change may take place.
The change control board shal consist of at least one representative from the following:
- Customer (only for external baselines)
- Project Management
- Technical Experts
- Quality Assurance
The Configuration Manager is responsible for arrangement of board meetingsat a frequency
appropriate to cope with the actual change traffic in the project in question.
The Change Control Board shall evaluate all changes for technical, cost, schedule
and management impacts and decide if, how, and when the change shall b implemented.
The CCB decisions must be unanimous. If this is not possible the issue shall be
deferred for decision at higher management levels.
6.4 C̲h̲a̲n̲g̲e̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲R̲e̲l̲e̲a̲s̲e̲
It is the responsibility of the project management to imp