WangText
1982-06-18 jho/bko
to: shnmo division
att.: mr. paul f. shey, contracting officer
cc.: lt. col. manfred stoltz, camps program manager
fm: christian rovsing a/s, denmark
gert jensen
our ref: cps/101/tlx/0558
subject: remote tare quotation
------------------------------
1.Introduction
--------------
As requested by SHAPE, Christian Rovsing A/S, hereby
submit a Firm Fixed Proposal for 2 equipped Remote Tare
Racks to be placed:
a) 1 remote tare rack at kolsaas tare site 8
b) 1 remote tare rack at reitan tare site 9
The camps system at sonor is already connected to a
tare rack at sonor. the remote tare racks at kolsaas
and reitan connect sonor camps to the kolsaas tare
and the reitan tare.
2.Price Quotation
-----------------
The cost related to the change is a non-recurring cost.
the cost is divided into:
overall requirements dkr 202.339
hardware dkr 162.106
transportation dkr 23.800
site related services dkr 537.756
̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲
the total cost of the proposal is: dkr
926.001
=============
The price breakdown is as follows:
2̲.̲1̲ ̲o̲v̲e̲r̲a̲l̲l̲ ̲r̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
this item covers the cost of
system engineering, fabrication,
integration and test, maintenance
during warranty and documentation dkr.
202.339
--------------
2.2 hardware cost
-----------------
The proposed remote tare racks are designed in accordance
with:
a) CPS/SDS/001 (CAMPS system design spec),section 5.5.5.4
(introduced by ECO 15)
b) CPS/SDS/043 (Remote Tare Hardware Assembly Breakdown/Hardware
Tree)
c) CPS/210/SYS/1001 (CAMPS SRS) section 3.4.1.10.6.
The following equipment is included in the racks for
the two sites:
1 rack per site
unit price = dkr 19.440
2 items = d.kr 38.880
1 V24 BPJF per site
unit price = d.kr 4.792
2 items d.kr 9.584
1 VF BPJF per site
unit price = d.kr 14.406
2 items d.kr 28.812
1 Modem, per site
unit price = d.kr 28.536
2 items d.kr 57.072
1 Mains Switch,( 220V) per site,
unit price = d.kr 8.947
2 items d.kr 17.894
1 Power distr. panel per site
Unit price = d.kr 2.296
2 items d.kr 4.592
1 power inlet box per site
unit price = d.kr 411
2 items d.kr 822
1 V 24 cable per site
unit price = d.kr 505
2 items d.kr 1.010
1 VF cable per site
unit price = d.kr 220
2 items d.kr 440
mechanics per site
unit price = d.kr. 1.500
2 items d.kr 3.000
subtotal, HW d.kr
162.106
-----------------
2.3 transportation
------------------
cost per site dkr 11.900
Sub total, transportation d.kr.
23.800
----------------
2.4 site related services
-------------------------
costs per site: d.kr. 268.878 covering:
site preparation and verification,
site documentation(CWR,ATBB),
site installation, and
on-site testing
total site costs d.kr
537.756
spares are included in the l-o-i on spares.
3.schedule impact
-----------------
The current installation plan (ref: CPS/TCN/026: installation
sequence and site numbering) tells that the remote
tare racks are installed as follows:
a) kolsaas remote site together with sonar/site no
15.
b) reitan remote site together with reitan/site no
9.
This proposal has no impact on the installation schedule
as described above.
4. bidding provisions
---------------------
4.1 validity
------------
the cost and schedule impact stated in 2 and 3 above
are under assumptions that the order is given to cr
no later than 15/7-82.
4.2 delivery
------------
the delivery of documentation, the fabrication and
the installation will take place for Kolsaas together
with sonor camps, site 15, for reitan together with
reitan camps, site 9.
4.3 acceptance criteria
-----------------------
the change has no impact on the present acceptance
base line. it shall be noted that the total current
connectivity has been increased by 8.
4.4 type of proposal
--------------------
firm fixed price proposal
4.5 payment plan
----------------
30 percent at approval of proposal
70 percent of oem equipment by issue of certificate
of conformance
60 percent of cr equipment at factory acceptance
10 percent of cr equipment at site accetpance.
Of the quoted price d.kr 57.072 represent cost incurred
in us dlrs, therefore d.kr 34.243 will be payable in
us dlrs. applying to the exchange rate 8.32.
kind regards
Gert Jensen