top - download
⟦28da544a0⟧ Wang Wps File
Length: 99824 (0x185f0)
Types: Wang Wps File
Notes: CRT/SDS/001
Names: »1203A «
Derivation
└─⟦d04a935aa⟧ Bits:30006049 8" Wang WCS floppy, CR 0078A
└─ ⟦this⟧ »1203A «
WangText
…11……00……00……00……00…C…0a……00……00…C…0b…C B…0e…B…07…6…0a…6…0e…6…02…/…01…/…06……1e……0c……1e……02……1d……09……1d……0a……1d……0b……1d……0c……1d……0d……1d……0e……1d……0f……1d……00……1d……01……1d……07……1c……0d……1c……02……1c……06……1b……0c……1b……01……1a……08……1a……00……1a……05……19……0b……19……01……19……07……18……0e……18……01……18……05……17……0a……17……0f……17…
…16……09……16……01……16……07……15……0e……15……05……14……0e……14…
…14… …86…1 …02… …02… …02…
…02…CRT/SDS/001
…02…850501…02……02…
CAMPS REMOTE TERMINALS
SYSTEM REQUIREMENT AND DESIGN SPECIFICATION…02…ISSUE 1.1…02…CRT
T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
1 SCOPE .........................................
7
2 APPLICABLE DOCUMENTS ..........................
7
2.1 APPLICABLE DOCUMENTS ......................
7
2.2 REFERENCED DOCUMENTS ......................
8
2.3 TERMS .....................................
8
3 REQUIREMENTS ..................................
9
3.1 SYSTEM DEFINITION .........................
9
3.1.1 General Description ...................
9
3.1.2 Functional Requirements ...............
9
3.1.2.1 Remote Site Connections ...........
11
3.1.2.2 Main Site Connections .............
11
3.1.3 Design Requirements ...................
12
3.2 FUNCTIONAL PRINCIPLE ......................
12
3.2.1 Basic Configuration ...................
12
3.2.1.1 Main Site Configuration ...........
12
3.2.1.2 Remote Site Configuration .........
13
3.2.2 Reconfiguration Possibilities .........
21
3.2.2.1 Option 1 ..........................
21
3.2.2.2 Option 2 ..........................
21
3.2.3 Interface Capability ..................
22
3.2.4 Specific Equipment Characteristics ....
24
3.2.4.1 Crypto/Modem ......................
24
3.2.4.2 Medium Speed Printers .............
24
3.2.4.3 Visual Display Units ..............
24
3.3 PHYSICAL CHARACTERISTICS ..................
25
3.3.1 Power Input ...........................
25
3.3.2 Environmental Conditions ..............
25
3.3.2.1 Temperature and Humidity ..........
26
3.3.2.2 Dust and Fumes ....................
26
3.4 SECURITY ..................................
27
3.4.1 TEMPEST Acceptance ....................
27
3.5 CONSTRUCTION REQUIREMENTS .................
29
3.5.1 General ...............................
29
3.5.1.1 Equipment produced by
Christian Rovsing A/S .............
29
3.5.1.2 Equipment produced by
Subcontractors ....................
29
3.5.1.3 Products from other Suppliers .....
29
3.5.2 Special Requirements for the
CRT System ............................
30
3.5.2.1 Utility Outlet Sockets ............
30
3.5.2.2 Bench Handling ....................
30
3.5.2.3 Wiring ............................
30
3.5.2.4 Ventilation and Cooling ...........
31a
3.5.2.5 Nameplates and Product marking ....
31a
3.5.2.6 Safety ............................
31a
3.5.2.6.1 Regulations ...................
31a
3.5.2.6.2 Personnel Safety ..............
31b
3.5.2.6.3 Equipment Safety ..............
31b
3.5.2.6.4 Grounding .....................
31c
3.6 CRT DOCUMENTATION .........................
31d
3.6.1 Headlines to the CRT Equipment
Handbook ..............................
31d
3.6.2 Contents of the CRT Equipment
Handbook ..............................
32
3.6.2.1 Scope of Manual ...................
32
3.6.2.2 Introduction ......................
32
3.6.2.3 Specifications ....................
33
3.6.2.4 Connections .......................
34
3.6.2.5 Detailed Functional Description ...
34
3.6.2.6 Installation ......................
34
3.6.2.7 Operating Instructions ............
34
3.6.2.8 Maintenance .......................
34
3.6.2.9 Assembly Breakdown ................
35
3.6.2.10 Inventory .........................
35
3.6.2.11 Spare Parts List ..................
35
3.6.2.12 Circuit Boards and Diagrams .......
35
3.6.3 Field Modification Documents ........
35
3.7 LOGISTIC REQUIREMENTS .....................
36
3.7.1 Transportation and Installation .......
36
3.7.1.1 Transportation ....................
36
3.7.1.2 Installation ......................
36
3.7.1.2.1 Equipment installation
at main sites .................
36
3.7.1.2.2 Equipment installation
at remote sites ...............
37
3.7.1.2.3 Standards and Security ........
38
3.7.1.2.4 Power Supply and Power
distribution ..................
38
3.7.1.2.5 Grounding .....................
39
3.7.1.2.6 Space and access ..............
40
3.7.1.2.7 Site Surveys ..................
40
3.7.2 Maintenance and Support ...............
42
3.7.3 Spares and Codification ...............
42
3.7.3.1 Supply of parts ...................
42
3.7.3.2 NATO Codification .................
42
3.7.4 Training ..............................
43
4 SYSTEM VERIFICATION ...........................
44
4.1 TEST AND VERIFICATION METHODS .............
44
4.2 VERIFICATION ..............................
45
4.2.1 Hardware Verification .................
45
4.2.1.1 Production Verification ...........
45
4.2.1.2 Factory Acceptance Test ...........
46
4.2.2 System Verification ...................
46
4.2.2.1 COMSEC on-site verification .......
46
4.2.2.2 Site Functional Test ..............
46
4.3 FACTORY ACCEPTANCE AND SITE FUNCTIONAL
TEST DOCUMENTATION ........................
47
4.3.1 General ...............................
47
4.3.2 Factory Acceptance Test Document ......
47
4.3.3 Site Functional Test Document .........
47
4.3.4 Test Procedures .......................
47
4.3.5 Test Result Forms .....................
48
4.3.6 Approval and Delivery .................
48
5 SYSTEM DESIGN .................................
49
5.1 MAIN SITE EQUIPMENT .......................
49
5.1.1 TDX-Crate Assembly ....................
51
5.1.1.1 CTX-Crate .........................
51
5.1.1.2 BSM-X .............................
58
5.1.1.2.1 BSM-X Panel ...................
58
5.1.1.3 LTUX-S .............................
60
5.1.1.3.1 TDX Bus Interface .............
60
5.1.1.3.2 Mechanical and Electrical
Specification .................
65
5.1.1.3.3 User Interface ................
67
5.1.1.3.4 V24 Back Panel ................
67
5.1.1.3.5 OMDT ..........................
67
5.1.1.3.6 V24 Monitor Panel .............
68
5.1.1.4 TDX Power Supply ..................
68
5.1.1.4.1 Main Power Panel ..............
69
5.1.1.5 Opto Power Supply .................
71
5.1.2 Adaptor Crate Assembly ................
71
5.1.2.1 V28(L/L) Adaptor ..................
73
5.1.2.2 V24 Back Panel ....................
77
5.1.2.3 Adaptor Power Supply ..............
77
5.1.3 Statistical Multiplexer ...............
77
5.1.3.1 Statistical Multiplexer
Transmission ......................
78
5.1.3.2 Error Control .....................
78
5.1.3.3 Buffer Control ....................
78
5.1.3.4 Configuration .....................
79
5.1.3.5 Channel Interface .................
79
5.1.3.6 Mux-Line Interface ................
79
5.1.3.7 Power .............................
80
5.1.4 Synchroneous Multiplexer...............
5.1.5 Resynchronization Module...............
5.1.5.1 Power Consumption..................
5.2 REMOTE SITE EQUIPMENT .....................
80
5.2.1 Statistical Multiplexer ...............
83
5.2.2 Opto Crate Assembly ...................
83
5.2.2.1 Optical Mux/Demux Tranceiver
(OMDT) ............................
85
5.2.2.2 V28 (L/L) Adaptor .................
86
5.2.2.3 V24 Back Panel ....................
86
5.2.2.4 Opto Power Supply .................
86
5.2.2.5 V24 Monitor Panel .................
87
5.3 RACK AND SUB-ASSEMBLIES ...................
88
5.3.1 CR80S Mechanical System ...............
91
5.3.1.1 CTX-Crate .........................
91
5.3.1.2 Cooling of CR80S Crates ...........
94
5.3.1.3 Cable Channel Assembly ............
94
5.3.2 Rack-Mounted Peripherals and
Special Assemblies ....................
97
5.3.2.1 Statistical/Synchroneous Multiplexer
97
5.3.2.2 Power Line Filter .................
97
5.3.2.3 Mains Switch Assembly .............
97
5.3.2.4 Power Distribution Panel ..........
98
5.3.2.5 Filter Box Assembly ...............
98
5.3.3 EMI Shielded Racks ....................
100
5.3.3.1 Stand Alone Racks .................
102
5.3.3.2 Multibay Rack-Assembly ............
102
5.3.3.3 Power, Heat and Weight ............
102
5.3.3.4 Grounding of Racks and Equipment
in Racks ..........................
107
1̲ ̲ ̲S̲C̲O̲P̲E̲
This specification establishes the functional, performance,
physical design, connectivity, testing and verification
requirements for CRT (CAMPS REMOTE TERMINALS).
The document consists of the following five chapters.
Chapter 1, SCOPE, which introduces the document.
Chapter 2, APPLICABLE DOCUMENTS, which contains the
list of documents constituting the requirements baseline.
Chapter 3, REQUIREMENTS, which defines the performance
and design for CRT.
Chapter 4, SYSTEM VERIFICATION, which denotes the responsibility
during verification test and the associated verification
documentation.
Chapter 5, SYSTEM DESIGN, which gives a more detailed
description of the design including specifications
and description of the components used to implement
the design.
2̲ ̲ ̲A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲
2.1 A̲p̲p̲l̲i̲c̲a̲b̲l̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
The following documents are applicable to the CRT system
requirement specification:
a) CPS/TCN/024, issue 4
CRT Design Document, Equipment Breakdown
b) AMSG 719B
c) AMSG 720A
2.2 R̲E̲F̲E̲R̲E̲N̲C̲E̲D̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲
a) CAMPS Maintenance Plan
CPS/PLN/006, sections 3.4 and 3.5
b) CAMPS Transportation Plan
CPS/PLN/007
c) CAMPS Site Design Concept
CPS/TCN/023, issue 2
d) CAMPS Standard Manual
CPS/STM/001
e) CAMPS System Requirement Specification
CPS/210/SYS/0001
f) CCITT Recommendation V24
g) CCITT Recommendation V28
h) MIL-STD-188C, section 7.2.1
2.3 T̲E̲R̲M̲S̲
ANALYSIS See section 4.1b)
BID 1000 Name for cryptographic equipment
BPJF Black Patch Jack Field
bps Bit per second
BSM-X Bus Switch Module for TDX
CAMPS Computer Aided Message Processing
System
CCB Configuration Control Bus
CLK Clock
COMSEC Communications Security
CPU Central Processing Unit
CR Christian Rovsing A/S
CRC Cyclic Redundancy Check
CRT C̲A̲M̲P̲S̲ Remote Terminals
CRYPTO Cryptographic Equipment
CTX CAMPS TDX
CWR Civil Work Requirement
EMI Electro-Magnetic Interference
EXAMINATION See section 4.1 c)
FIFO First In First Out register
HF High Frequency
H/W Hardware
I/O Input/Output
J Joule
LTUX Line Termination Unit for TDX
MAIN SITE A site, having a CAMPS
MDF Main Distribution Frame
MIL-STD-188C See Referenced Document
MODEM Modulator/Demodulator
MOTHERBOARD See section 5.1.1.1
MSP Medium Speed Printer
NRZL Non-Return-to-Zero-Logic
OCR Optical Card Reader
OMDT Optical Mux/Demux Transceiver
ppm Parts Per Million
RED AREA See section 3.4.1 h)
REMOTE SITE Site associated to a CAMPS site
by a communication link.
RF Radio Frequency
RPJF Red Patch Jack Field
SHAPE Supreme Headquarters Allied Power
Europe
SPL-D Split-phase encoded data
S/W Software
TDX Telecommunication Data Exchange
TEST See section 4.1 a)
VDU Visual Display Unit
V.24 See referenced document
V.28 See referenced document
V.28(L) See notes for table 3.2.3-1
V.28(L/L) See notes for table 3.2.3-1
VERIFICATON See section 4.1
X-NET TDX-Bus System
X-NET TERM TDX-Bus Termination Module
3̲ ̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.1 S̲Y̲S̲T̲E̲M̲ ̲D̲E̲F̲I̲N̲I̲T̲I̲O̲N̲
3.1.1 G̲e̲n̲e̲r̲a̲l̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
The CAMPS Remote Terminals (CRT) system supports the
capability of moving some terminal operations from
the main sites to remote locations.
This does not mean that the max. connectivity of each
CAMPS-site as specified in ref. e) has been expanded.
The feature is obtained by means of statistical multiplexers
and customer supplied crypto/modem lines between main
and remote sites.
Thus 8 V24 channels connect each remote site to the
related main site.
The CRT equipment is contained in EMI shielded racks.
At the main sites the CRT rack(s) are bolted to the
main CAMPS Line Termination racks and form a 4 or 5
bay configuration, except Site 10 where a stand alone
rack is used.
3.1.2 F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
The remote terminal concept shall provide the following
possibility:
The transmission shall consist of 8 channels connecting
each remote site with the related main site.
The communication between each remote site and its
main site shall use a single multiplexed link.
3.1.2.1 R̲e̲m̲o̲t̲e̲ ̲S̲i̲t̲e̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲.̲
A single channel is saved for an OCR-option while the
7 channels are used as follows:
a) Primarily the 7 channels are used for transmission
of CAMPS-channels (connection to CAMPS expansion
or CRT LTUX at main site).
At the remote site 4 of these channels are terminated
with OMDTs for opto-cable connection to the terminals,
and 3 are terminated with V28(L/L) adaptors for
connection with electrical cables (auxiliary channels).
b) Secondary (option 1) it shall be possible to implement
a changed configuration, where the 3 auxiliary
channels are disconnected from CAMPS at the main
site and used as separate channels.
3.1.2.2 M̲a̲i̲n̲ ̲S̲i̲t̲e̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲
At the main site the remote terminal equipment shall
include one LTUX per remote site (4 channels).
a) Primarily these 4 channels are connected to the
stat.mux. and used for transmission to the remote
site.
b) Secondary (option 2) it shall be possible to implement
a changed configuration, where the stat. mux. is
disconnected, and the LTUX channels are used for
expanding the number of connected terminals in
the main site. The terminal connection points thus
made available shall have an optical interface.
3.1.3 D̲e̲s̲i̲g̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
a) The system design shall be such that the same hardware
can be used to provide the required capability
at any of the installations.
b) The equipment provided at all installations covered
by this specification shall differ from one another,
if at all, only in the number of hardware units
of any given type in each configuration.
c) An operating CRT link includes both CR delivered
and SHAPE supplied equipment. The division of responsibility
of the equipment is defined by the responsibility
demarkation line, which will be on the feed-through
connectors mounted in the filter box. This applies
both on main sites and remote sites.
3.2 F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲P̲R̲I̲N̲C̲I̲P̲L̲E̲
3.2.1 B̲a̲s̲i̲c̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲
Fig. 3.2.1-1 shows the configuration of a typical CRT-link
between a main site and its related remote site(s).
All CR supplied CRT-equipment are contained in separate
racks at the main site and remote site.
3.2.1.1 M̲a̲i̲n̲ ̲S̲i̲t̲e̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲
a) The connection to main CAMPS is obtained by means
of CTX crates, equipped with TDX-modules, connected
to the TDX-busses of CAMPS.
b) The statistical multiplexer multiplexes 8 V24 channels,
of which normally 4 channels are obtained from
the CRT-LTUX, 3 are auxiliary channels, which
are obtained from CAMPS expansion LTUX, (wherever
possible), and the last is reserved for a future
positioning of an OCR at the remote site.
c) The stat.mux. takes care of:
1) C̲h̲a̲n̲n̲e̲l̲ ̲m̲u̲l̲t̲i̲p̲l̲e̲x̲i̲n̲g̲. Statistical multiplexing
gives an improved modem line utilization compared
to none or conventional time division multiplexing.
2) T̲r̲a̲n̲s̲m̲i̲s̲s̲i̲o̲n̲ ̲e̲r̲r̲o̲r̲ ̲p̲r̲o̲t̲e̲c̲t̲i̲o̲n̲ by means of a
cyclic redundancy check and automatic retransmission
request on errors.
3) T̲r̲a̲f̲f̲i̲c̲ ̲f̲l̲o̲w̲ ̲c̲o̲n̲t̲r̲o̲l̲, which takes care of possible
data peak load effects by controlling the sending
activities of the data terminal equipment.
d) The mux-line of the stat.mux. is connected to a
feed-through connector in the filter box (responsibilities
demarkation line).
e) The mux. line is connected by customer supplied
wiring from the filter box to the red patch jack
field in the crypto room. In the crypto-room customer
supplied equipment takes care of encryption and
modulation of information to be transmitted through
the transmission media to the remote site and the
reverse function for information received from
the remote site.
3.2.1.2 R̲e̲m̲o̲t̲e̲ ̲S̲i̲t̲e̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲
a) Purchaser supplied equipment performs the same
function as described in 3.2.1.1.e) on information
received from/transmitted to the main site, ending
up with the mux line interface in the filter box.
b) The stat.mux demultiplexes the message and the
channels are connected to V28(L/L) adaptors and
Opto Mux/Demux Transceivers (OMDT) respectively.
c) The output of these devices leaves the EMI shielded
rack through the filter box.
d) The opto channels are connected to
1) the CR supplied Delta VDUs and/or
2) the CR supplied TRACOR medium speed printers.
FIGURE 3.2.1.1, (sheet 1 of 8)
C̲R̲T̲ ̲L̲I̲N̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
FIGURE 3.2.1.1 (sheet 2 of 8) DETAIL A
M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
(̲M̲A̲X̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲)̲S̲I̲T̲E̲S̲ ̲2̲,̲ ̲3̲,̲ ̲8̲,̲ ̲9̲,̲ ̲1̲3̲,̲ ̲1̲4̲
FIGURE 3.2.1.1 (sheet 3 of 8) DETAIL A…0e…1…0f…
M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲S̲I̲T̲E̲ ̲1̲0̲
FIGURE 3.2.1.1 (sheet 4 of 8), detail B…01…M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲,̲…01…S̲I̲T̲E̲S̲
̲5̲,̲ ̲6̲,̲ ̲7̲,̲ ̲1̲1̲,̲ ̲1̲2̲,̲ ̲1̲5̲
FIGURE 3.2.1.1 (Sheet 5 of 8), DETAIl D
M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲,̲
S̲I̲T̲E̲ ̲4̲ ̲R̲A̲C̲K̲ ̲G̲,̲ ̲H̲
FIGURE 3.2.1.1 (Sheet 6 of 8)
M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲,̲ ̲S̲I̲T̲E̲ ̲4̲ ̲R̲A̲C̲K̲ ̲I̲,̲ ̲J̲
FIGURE 3.2.1.1 (sheet 7 of 8), detail E…01…R̲E̲M̲O̲T̲E̲ ̲S̲I̲T̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
̲(̲T̲Y̲P̲I̲C̲A̲L̲)̲
FIGURE 3.2.1.1 (Sheet 8 of 8)
R̲E̲M̲O̲T̲E̲ ̲S̲I̲T̲E̲ ̲4̲A̲,̲ ̲4̲C̲,̲ ̲4̲D̲,̲ ̲4̲E̲
(̲M̲A̲X̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲)̲,̲ ̲C̲R̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
3.2.2 R̲e̲c̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲P̲o̲s̲s̲i̲b̲i̲l̲i̲t̲i̲e̲s̲.̲
3.2.2.1 O̲p̲t̲i̲o̲n̲ ̲1̲
a) Purpose: It shall be possible to implement a changed
configuration where the 3 auxiliary channels
are disconnected from CAMPS at the main
site and used for separate channels.
b) Design: The option is implemented by addition of
V28(L/L) adaptor equipment on the main
site.
These added adaptors (and crates etc.)
may be placed in the rack during normal
operation. Thus, a configuration change
is implemented by adding the needed cables.
3.2.2.2 O̲p̲t̲i̲o̲n̲ ̲2̲
a) Purpose: It shall be possible to implement a changed
configuration where the stat.mux is disconnected
and the LTUX channels are used for expanding
the number of connected terminals in the
main site. The terminal connection points
thus made available shall have an optical
interface.
b) Design: The option is implemented by adding opto
power supplies to the CRT TDX-crates assemblies.
The OMDTs can not be placed in the racks
during normal operation, so the option
may be implemented by transferring the
remote site OMDTs to the main site along
with the terminals.
Thus, a configuration change is implemented
by removing the unwanted cables, transferring
the OMDTs and adding the needed opto-cables.
3.2.3 I̲n̲t̲e̲r̲f̲a̲c̲e̲ ̲C̲a̲p̲a̲b̲i̲l̲i̲t̲y̲
Each CRT system shall provide the interface capabilities
tabulated in table 3.2.3-1.
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
CHANNEL BAUD- INTERFACE SYNC/ ALPHABET NOTES
RATE ASYNC
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
VDU 1̲2̲0̲0̲
2400 V24/Opto Async. ITA NO.5 1,
2,
3
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
1200 V24/V28(L/L) Async. ITA NO.5 2,
3
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
MSP 1̲2̲0̲0̲
2400 V24/Opto Async. ITA NO.5 1,
2,
3
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
1200 V24/V28(L/L) Async. ITA NO.5 2,
3
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Auxiliary 1200 V24/V28(L/L) Async. ITA NO.5 2,
3
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
OCR 1200 V24/V28(L/L) Async. ITA NO.5 2,
3
(Optional)
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Crypto/ 2̲4̲0̲0̲
Modem 4800 V24/V28(L) Sync. Stat. Mux. 1,
2,
3
Protocol
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Notes: See next page
T̲A̲B̲L̲E̲ ̲3̲.̲2̲.̲3̲-̲1̲
N̲O̲T̲E̲S̲ ̲F̲O̲R̲ ̲T̲A̲B̲L̲E̲ ̲3̲.̲2̲.̲3̲-̲1̲
1) Baud-rate Underlined baud-rates will be used
during acceptance tests.
2) Interface
a) Opto Transmision at remote site between
the EMI shielded rack and the terminals
will be by an optical transmission
link.
b) V28(L) Transmision between the Stat. Mux.
in the EMI shielded rack and the
Crypto equipment (via the BPJF)
will be by a V28(L) electrical
transmission link. V28(L) is CCITT
V28, constrained by MIL-STD-188C
(standard low level) except for
voltage polarities. Transmission
length is up to 15 meters.
c) V28(L/L) Transmission at remote site between
the EMI shielded rack and the terminals/auxiliary
channels will be by a V28(L/L)
electrical transmission link. V28(L/L)
equals V28(L), but enables transmission
length up to 275 meter.
3) Alphabet
a) ITA No.5 International Telegraph Alphabet,
CCITT recommended, ASCII code.
b) Stat. Mux. Communication between Stat. Muxes
Protocol follows a data protocol unique
to the Stat. Muxes.
3.2.4 S̲p̲e̲c̲i̲f̲i̲c̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲C̲h̲a̲r̲a̲c̲t̲e̲r̲i̲s̲t̲i̲c̲s̲
3.2.4.1 C̲r̲y̲p̲t̲o̲/̲M̲o̲d̲e̲m̲
1) I̲n̲t̲e̲r̲f̲a̲c̲e̲:̲ Synchronous V24 interface with
speed of 2400 or 4800 bps, supporting
the following interchange circuits:
101 Protective Ground
102 Signal Ground
103 Transmitted Data
104 Received Data
105 Request to Send
106 Ready for Sending
109 Carrier Detect
114 Transmitter signal element
timing
115 Receiver Signal element
timing.
3.2.4.2 M̲e̲d̲i̲u̲m̲ ̲S̲p̲e̲e̲d̲ ̲P̲r̲i̲n̲t̲e̲r̲s̲
CR-supplied TRACOR MSPs model 8000 RO. The Medium Speed
Printer has an optical or a V28 interface.
3.2.4.3 V̲i̲s̲u̲a̲l̲ ̲D̲i̲s̲p̲l̲a̲y̲ ̲U̲n̲i̲t̲s̲
CR-supplied Delta Data VDUs model 7260 T. The Visual
Display Unit has an optical or a V28 Interface.
3.3 P̲H̲Y̲S̲I̲C̲A̲L̲ ̲C̲H̲A̲R̲A̲C̲T̲E̲R̲I̲S̲T̲I̲C̲S̲
3.3.1 P̲o̲w̲e̲r̲ ̲I̲n̲p̲u̲t̲
The CRT equipment shall be capable of satisfying the
specified performance requirements when operating with
the following power input:
a) Phases: Single-phase and ground.
b) Voltage: Nominal value: 220 V AC
Tolerances: +10%/-15%
Except UKAIR where nominal value
is 240 V AC.
c) Frequency: Nominal value: 50 Hz
Tolerances: +10/-10%
d) Harmonic
distortion: Max. 5%
e) Transients: Non-repetitive impulsive interference
with a magnitude not to exceed 500
volts, pulse rise and fall times
not faster than 10 microseconds
and a total duration of maximum
1 millisecond. The available impulse
energy at the equipment power inlet
shall not exceed 5J.
3.3.2 E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲C̲o̲n̲d̲i̲t̲i̲o̲n̲s̲
In designing the equipment to meet the specified requirements
no account need be taken of catastrophic events such
as fire, flood, explosion, etc., which are beyond the
control of an equipment manufacturer.
The equipment will normally operate within accomodation
suitable for the operation of equipment produced for
commercial use.
After initial adjustments have been made, the equipment
shall maintain normal operation under all specified
environmental and power supply conditions.
3.3.2.1 T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲ ̲a̲n̲d̲ ̲H̲u̲m̲i̲d̲i̲t̲y̲
The equipment shall continue to function when the humidity
and temperature of its environment are within the ranges
and cycling specified below.
The equipment shall continue to operate in a fully
satisfactory manner even under the worst conditions
specified below.
a) T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲
Range: 10 to 40 deg.C
Rate of Change: max 10 deg. C per hour
b) H̲u̲m̲i̲d̲i̲t̲y̲ ̲(̲R̲e̲l̲a̲t̲i̲v̲e̲ ̲H̲u̲m̲i̲d̲i̲t̲y̲ ̲=̲ ̲R̲H̲)̲
Range: 40 to 90% RH, non-condensing
Rate of Change: max. 6% RH per hour, non-condensing.
c) A̲l̲t̲i̲t̲u̲d̲e̲
Range: Sea level to 2000 meter.
3.3.2.2 D̲u̲s̲t̲,̲ ̲F̲u̲m̲e̲s̲
The equipment shall be able to operate continuously
and with normal scheduled preventive maintenance in
the following air environment:
a) A̲i̲r̲ ̲c̲l̲e̲a̲n̲n̲e̲s̲s̲
Particle size Max. allowable number
(microns) (particles/cubicmeter)
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
greater than 5 4* (10 5)
greater than 1.5 4* (10 6)
greater than 1 4* (10 7)
b) F̲u̲m̲e̲s̲
sulphur dioxide max. 14 ppm.
3.4 S̲E̲C̲U̲R̲I̲T̲Y̲
This section addresses or references all requirements
related to security.
In general: Transfer and transmission within the installation
means transfer and transmission between the components.
3.4.1 T̲E̲M̲P̲E̲S̲T̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲
The CR delivered components of the CRT equipment at
the main sites are contained in a 1- or 2-bay rack
bolted to the CAMPS 3-bay Line Termination Rack Assembly,
except for UKAIR, where the CRT rack is freestanding.
The CR delivered components of the CRT equipment at
the remote sites are contained in an EMI shielded rack,
except the VDUs and MSPs
During short periods of corrective and preventive maintenance
e.g. open back doors, the emanation requirements below
are degraded.
Operational procedures are required to ensure that
the supervisor is currently informed on activities
concerning corrective and preventive maintenance and
thus is able to decide whether it is acceptable to
continue operation or not.
a) The E̲M̲I̲ ̲s̲h̲i̲e̲l̲d̲e̲d̲ ̲r̲a̲c̲k̲s̲ used for CR delivered CRT
equipment are manufactured for the same performance
as the EMI shielded racks used for CAMPS.
b) To meet the i̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲r̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲, the equipment,
including ancillaries and peripherals, must be
installed in accordance with criteria laid down
in AMSG 719B. After installation, a COMSEC Radiation
Survey will be carried out at each location prior
to operational approval being given. Rectification
of equipment shortcomings shall be the responsibility
of the contractor.
c) S̲p̲e̲c̲i̲a̲l̲ ̲e̲a̲r̲t̲h̲i̲n̲g̲ ̲a̲r̲r̲a̲n̲g̲e̲m̲e̲n̲t̲s̲, see section 3.7.1.2.5
a,b,c,d.
d) All e̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲i̲n̲t̲e̲r̲c̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲,̲ connecting equipment
inside to equipment outside the EMI shielded rack,
will be by low level keying systems, V28(L), i.e.
the electrical interface specification shall comply
with the V28 recommendation concerning the data
and control signal voltage polarities, while all
other characteristics (e.g. currents, rise and
fall time, impedance, voltage levels) are governed
by the MIL-STD-188C (Low level) standard digital
interface specification.
e) On send circuits the pulse form shall be measured
at the connectors of the filter box. Limits shall
be met at this r̲e̲f̲e̲r̲e̲n̲c̲e̲ ̲p̲l̲a̲n̲e̲ with the circuits
terminated with loads according to MIL-STD-188C.
f) I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲w̲o̲r̲k̲ will be checked by local COMSEC
staff to ensure that all installation conforms
to COMSEC requirements.
g) The C̲R̲T̲ ̲s̲t̲a̲t̲.̲m̲u̲x̲ ̲l̲i̲n̲e̲ between the mainsites and
the remote sites will be equipped with on-line
synchronous cryptographic equipment to be supplied,
installed and maintained by the customer.
h) The C̲R̲T̲ ̲e̲q̲u̲i̲p̲m̲e̲n̲t̲ will be installed in an area
designated as a R̲e̲d̲ ̲A̲r̲e̲a̲. Within the Red Area classified
information may be handled in plain language; the
transfer of information in an electrical form within
this area shall be subject to and comply with the
criteria laid down in AMSG 719B.
i) The c̲r̲o̲s̲s̲t̲a̲l̲k̲ ̲a̲t̲t̲e̲n̲u̲a̲t̲i̲o̲n̲ between any circuit carrying
classified information and any other circuit within
the installation shall be not less than 100 dB.
j) The p̲o̲w̲e̲r̲ ̲s̲u̲p̲p̲l̲y̲ to all the equipment in the Red
Area will enter via a f̲i̲l̲t̲e̲r̲ or a group of filters
which will be supplied by the customer. The function
of these filters is to ensure that no compromising
signals are able to reach a Black Area via the
power supply leads. The equipment shall function
satisfactorily with these filters present in the
power leads.
3.5 C̲O̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.5.1 G̲e̲n̲e̲r̲a̲l̲
The following section defines the general construction
requirements applicable to CRT.
3.5.1.1 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲P̲r̲o̲d̲u̲c̲e̲d̲ ̲b̲y̲ ̲C̲h̲r̲i̲s̲t̲i̲a̲n̲ ̲R̲o̲v̲s̲i̲n̲g̲ ̲A̲/̲S̲
a) The CR produced equipment is designed and produced
according to CR standard, CPS/STM/001 sections
A-C, A-D and A-E.
b) Maintenance of CR standards are performed under
configuration management and supervised by CRs
Quality Assurance department.
c) All standards and their maintenance may be inspected
by customers Quality Assurance Representative.
3.5.1.2 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲P̲r̲o̲d̲u̲c̲e̲d̲ ̲b̲y̲ ̲S̲u̲b̲c̲o̲n̲t̲r̲a̲c̲t̲o̲r̲s̲
The CR sub-contractor supplying equipment to CAMPS/CRT
may propose the use of other standards, on condition
that adequate documentary evidence is provided to demonstrate
that the alternative standards are at least equivalent
in scope and depth of coverage to this requirement
section.
3.5.1.3 P̲r̲o̲d̲u̲c̲t̲s̲ ̲F̲r̲o̲m̲ ̲O̲t̲h̲e̲r̲ ̲S̲u̲p̲p̲l̲i̲e̲r̲s̲
a) Equipment supplied by OEMs not quoted as sub-contractors
- i.e. standard equipment from stock - is chosen
in accordance with the requirements stated compared
to the specification given by the OEMs.
b) Quality Assurance shall check and ensure that the
quality of such equipment fulfil all requirements
in respect to:
1) performance (in accordance with specifications
given by manufacturer)
2) durability
3) stability under extreme working condition
4) maintainability
3.5.2 S̲p̲e̲c̲i̲a̲l̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲f̲o̲r̲ ̲t̲h̲e̲ ̲C̲R̲T̲ ̲S̲y̲s̲t̲e̲m̲
In this section is mentioned a number of requirements
special for the CRT project.
3.5.2.1 U̲t̲i̲l̲i̲t̲y̲ ̲O̲u̲t̲l̲e̲t̲ ̲S̲o̲c̲k̲e̲t̲s̲
Utility outlet sockets for the operation of test equipment
etc. shall be located in close proximity to all major
racks or cabinets. Installation of utility outlets
will be the responsibility of customer.
3.5.2.2 B̲e̲n̲c̲h̲ ̲H̲a̲n̲d̲l̲i̲n̲g̲
Smaller assemblies and sub-assemblies normally subject
to bench repair shall be capable of withstanding being
dropped onto a hard surface on all faces from a 30…0e…0…0f…
angle, using any one edge of the unit as a pivot, without
any physical, electrical or electronic damage.
3.5.2.3 W̲i̲r̲i̲n̲g̲
Wiring shall be identified by colour coding, numbering,
or by other feasible means such as marking of terminals
at both ends of lead. All wires shall carry corresponding
identification numbers. Colour coding for chassis wiring
shall comform to good engineering practice.
3.5.2.4 V̲e̲n̲t̲i̲l̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲C̲o̲o̲l̲i̲n̲g̲
The distributed cooling systems in the CR produced
equipment may be supplied with air filters of a nominal
thickness of 2.5 cm. The cooling air should preferably
be exhausted to the atmosphere at the top of the cabinet.
3.5.2.5 N̲a̲m̲e̲p̲l̲a̲t̲e̲s̲ ̲a̲n̲d̲ ̲P̲r̲o̲d̲u̲c̲t̲ ̲M̲a̲r̲k̲i̲n̲g̲
a) A nameplate giving the serial number, SHAPE contract
number, date of manufacture, manufacturers name
and address, and principal characteristics where
appropriate, shall be attached in a prominent position
on each major assembly.
b) Cables and wires or similar connectors shall carry
a CR parts number. These numbers shall be the same
numbers as given in the documentation.
3.5.2.6 S̲a̲f̲e̲t̲y̲
All necessary safeguards shall be taken during the
design, development, production and installation of
the equipment to ensure safety of operating and maintenance
personnel from electrical and mechanical hazards.
3.5.2.6.1 R̲e̲g̲u̲l̲a̲t̲i̲o̲n̲s̲
a) The actual site installations in the different
host nations shall be made in accordance with the
appropriate National Safety Regulations of the
country concerned according to installation drawings
as approved by the purchases.
b) The equipment itself and its associated power cabling
shall comply with the National Safety Regulations
of the country of origin for the equipment.
3.5.2.6.2 P̲e̲r̲s̲o̲n̲n̲e̲l̲ ̲S̲a̲f̲e̲t̲y̲
a) Interlocks or key locks shall be incorporated where
appropriate to prevent any major assembly carrying
high tension voltages from being opened by unauthorised
personnel.
b) With the equipment assembled and set up for operation,
personnel shall be protected from contact with
potentials in excess of 30 volts to ground, chassis
or frame, including potentials or charged capacitors.
c) Relevant notice and markings on equipment or documents
are to be provided to draw the attention of operating
and maintenance personnel to points where dangerous
voltages may be encountered.
d) Where a voltage of 50 or more volts is exposed
during the maintenance activities a suitable warning
shall be provided. It should be made according
to the following principles:
1) "DANGER (xxx) VOLTS WHEN COVER REMOVED" (in
aluminium or white lettering l.5 cm high on
a red background) where (xxx) is the nominal
voltage.
2) "DANGER HIGH VOLTAGE (xxx) VOLTS" where (xxx)
is the nominal voltage.
3) "CAUTION (xxx) VOLTS. DISCONNECT POWER BEFORE
REMOVAL OF COVER" where (xxx) is the nominal
voltage.
3.5.2.6.3 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲S̲a̲f̲e̲t̲y̲
a) Circuit breakers or switches which operate to make
or break AC power lines shall make or break all
conductors at the same time. The neutral wire in
three-phase circuits shall not pass through any
fuse.
b) Fuses and circuit breakers shall be provided within
the equipment as required for protection of the
equipment from damage due to overload. Each major
assembly shall be individually protected so that
a fault in one major assembly cannot damage any
other major assembly.
c) All fuses and circuit breakers should be located
such that they are readily accessible. Fuses shall
incorporate a visual system of failure indication.
3.5.2.6.4 G̲r̲o̲u̲n̲d̲i̲n̲g̲
a) The grounding system shall provide effective protection
for personnel and material against insulation defects.
It shall be arranged so that there are four separate
and isolated ground circuits, namely:
1) AC power neutral
2) Equipment frame ground
3) Signalling and control ground
4) Secure ground
b) The AC power neutral shall provide a return for
the primary current so that the equipment frame
ground is used only to establish a safety ground
and is not used as a normal current grounding element.
No place in the equipment or power filters shall
the AC power neutral be connected directly to equipment
frame ground.
c) All panels, drawers and other sub-assemblies, whether
fixed or removable, shall be fastened, or connected
to the associated frame, in a manner that ensures
they are securely grounded.
d) The signalling and control ground is to be routed
via the interconnecting wires and cables as appropriate.
e) The cryptographic ground shall conform to the requirements
of AMSG 719B.
3.6 C̲R̲T̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
The hardware documentation developed by CR under this
contract will be produced in accordance with the requirements
applicable for CAMPS.
This section gives a detailed table of contents for
the CRT Equipment Handbook, which constitutes the CRT
documentation. Each section of the Equipment Handbook
contains a short abstract.
3.6.1 H̲e̲a̲d̲l̲i̲n̲e̲s̲ ̲t̲o̲ ̲t̲h̲e̲ ̲C̲R̲T̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲H̲a̲n̲d̲b̲o̲o̲k̲
The CRT Equipment Handbook contains the main sections
as specified below:
TABLE OF CONTENTS
LIST OF ILLUSTRATIONS
LIST OF TABLES
1 SCOPE OF MANUAL
2 INTRODUCTION
3 SPECIFICATIONS
4 CONNECTIONS
5 DETAILED FUNCTIONAL DESCRIPTION
6 INSTALLATION
7 OPERATING INSTRUCTIONS
8 MAINTENANCE AND SERVICING
9 ASSEMBLY BREAK DOWN
10 INVENTORY
11 SPARE PARTS LIST
12 CIRCUIT BOARDS, MODULES AND DIAGRAMS
3.6.2 C̲o̲n̲t̲e̲n̲t̲s̲ ̲o̲f̲ ̲C̲R̲T̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲H̲a̲n̲d̲b̲o̲o̲k̲
The specifications and descriptions of the handbook
shall be preceded by
a) TABLE OF CONTENTS
b) LIST OF ILLUSTRATIONS
c) LIST OF TABLES
3.6.2.1 S̲c̲o̲p̲e̲ ̲o̲f̲ ̲M̲a̲n̲u̲a̲l̲
This section contains a general overview of the handbook.
3.6.2.2 I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲
1) S̲y̲s̲t̲e̲m̲ ̲o̲v̲e̲r̲v̲i̲e̲w̲
This section gives a general description of the
CRT system.
2) N̲o̲m̲e̲n̲c̲l̲a̲t̲u̲r̲e̲ ̲a̲n̲d̲ ̲a̲b̲b̲r̲e̲v̲i̲a̲t̲i̲o̲n̲s̲
The terms and abbreviations used in the handbook
are explained in this section.
3) D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲R̲e̲f̲e̲r̲e̲n̲c̲e̲
The documents relevant and applicable to the user
of the handbook are referenced.
4) F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲B̲l̲o̲c̲k̲ ̲D̲i̲a̲g̲r̲a̲m̲
This section comprises a functional block diagram
together with a description of the block functions.
It also describes the units and modules used for
the implementation of the CRT.
5) I̲n̲t̲e̲r̲a̲c̲t̲i̲o̲n̲ ̲w̲i̲t̲h̲ ̲s̲u̲r̲r̲o̲u̲n̲d̲i̲n̲g̲s̲
This section gives a general overview of the communication
between CAMPS and Remote Terminals, including the
VDUs, MSPs, auxilliary V28(L/L) connections and
OCR.
6) I̲/̲O̲ ̲M̲o̲d̲e̲s̲ ̲a̲n̲d̲ ̲F̲o̲r̲m̲a̲t̲s̲
This section gives a general overview of the modes
and formats of the data communication of the I/O
connections.
3.6.2.3 S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲
1) O̲p̲e̲r̲a̲t̲i̲o̲n̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲
a) User Safety and Warnings.
The user safety precautions and warnings shall
be explained. These will be placed on the inner
side of the handbook cover.
b) Environmental Requirements/Specifications. The
environmental limits of the equipment are specified
here.
2) S̲y̲s̲t̲e̲m̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲
a) Electrical Specifications
b) Mechanical Specifications
3.6.2.4 C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲
This section includes a drawing, showing the physical
layout and the interconnections between the racks at
the Main Site and between the racks and I/O equipment
at the Remote Site (auxiliary V28(L/L), OCR and opto
to VDUs and MSPs). It also includes a description of
the different I/O connectors including pin designation
and numbering.
3.6.2.5 D̲e̲t̲a̲i̲l̲e̲d̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This section will describe in detail the function of
the different modules including references to the relevant
diagrams and manuals.
3.6.2.6 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
1) Storage, Transport and Unpacking.
This section will include a reference to the applicable
CAMPS procedure concerning storage, transport and
unpacking.
2) Assembly.
This section gives a detailed description of the
configuration and the reconfiguration possibilities.
3.6.2.7 O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲I̲n̲s̲t̲r̲u̲c̲t̲i̲o̲n̲s̲
This section describes the operating procedures and
controls, applicable to the CRT and a reference to
the proper CAMPS Manual.
3.6.2.8 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲
This section references the CAMPS Maintenance instructions.
3.6.2.9 A̲s̲s̲e̲m̲b̲l̲y̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲
This section includes an Assembly Breakdown for the
CRT equipment.
3.6.2.10 I̲n̲v̲e̲n̲t̲o̲r̲y̲
This section incorporates a consumerable and item listing.
3.6.2.11 S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲L̲i̲s̲t̲
This section contains the spare parts list for the
Remote Site equipment, and a reference to the CAMPS
spare parts list for the Main Site equipment.
3.6.2.12 C̲i̲r̲c̲u̲i̲t̲ ̲B̲o̲a̲r̲d̲s̲ ̲a̲n̲d̲ ̲D̲i̲a̲g̲r̲a̲m̲s̲
The Preset adjustments and settings are pointed out
in this section. This section also comprises the diagrams
and photos of the Circuit Boards.
3.6.3 F̲i̲e̲l̲d̲ ̲M̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
All field modification documents generated by CR will
be submitted to SHAPE logistics function for distribution
to the respective main sites. The maintenance at of
the main sites will in turn be responsible for implementation
of the changes to the remote equipment.
3.7 L̲O̲G̲I̲S̲T̲I̲C̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.7.1 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
3.7.1.1 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲
The CAMPS Remote Terminal (CRT) Equipment provided
by CR will be shipped together with CAMPS Main Site
Equipment as specified in the CAMPS Transportation
Plan, CPS/PLN/007.
Packing, marking and shipping documentation will be
as required for Mainsite Equipment and therefore as
described in the Transportation Plan.
3.7.1.2 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
3.7.1.2.1 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲a̲t̲ ̲M̲a̲i̲n̲ ̲S̲i̲t̲e̲s̲
a) At the applicable main sites CR will provide and
install a CRT-rack (at Proto 2 CRT-racks are required)
in the CAMPS room. (refer to fig. 3.2.1.1). The
rack(s) will be bolted to the 3-bay CAMPS line
termination rack assembly (D,E,F) except at UKAIR,
where a stand alone rack will be installed. The
rack(s) will be designated as rack G, (H).
b) SHAPE will provide and install the red patch Jack
field (RPJF), the BID 1000, the black patch Jack
field (BPJF) and the modem.
c) The signal cable and connections from the filter
box of rack F to the RPJF, from the RPJF to the
BID 1000 from the BID 1000 to the BPJF, from the
BPJF to the modem and from the modem to the Main
Distribution Frame (MDF) will be provided and installed
by SHAPE/Host Nation.
Rack G(H) requires a secure ground and pink power
from the CAMPS power distribution board. SHAPE/Host
Nation will provide this power and ground in accordance
with the Civil Works Requirement (CWR) for each
site.
3.7.1.2.2 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲a̲t̲ ̲R̲e̲m̲o̲t̲e̲ ̲L̲o̲c̲a̲t̲i̲o̲n̲s̲
a) At remote locations CR will provide and install
a CRT-rack and the contractual specified number
of user terminals. This equipment will be installed
in rooms designated by SHAPE/Local Commands (Refer
to fig. 3.2.1-1).
b) The signal cable and connections from filter box
of the CRT-rack to the RPJF, from the RPJF to the
BID 1000, from the BID 1000 to the modem and from
the modem to the MDF will be provided and installed
by SHAPE/Host Nation. The connectors to be used
in the Filter box of the CRT-rack will be provided
by CR.
c) The OCR connection and the auxiliary V28(L/L) connections
to the filter box of the CRT-rack will be provided
and installed by SHAPE/Host Nation.
d) SHAPE/Host Nation will run the Opto-cables between
the CRT-rack and the terminals in conduits or ducts
provided and installed by SHAPE/Host Nation. The
Opto-cables will be provided by CR, and terminated
and connected to the CRT-rack and the terminals
by CR.
e) CR will provide a set of space and power requirements
for each remote location which will be incorporated
in the related main site CWR-package.
f) The CRT-rack requires a secure ground and pink
power. SHAPE/Host Nation will provide this power
and ground in accordance with the CWR. The user
terminals will be supplied with power (pink or
black) and ground (secure or safety) from SHAPE/Host
Nation provided 3-pin outlets in accordance with
the CWR.
3.7.1.2.3 S̲t̲a̲n̲d̲a̲r̲d̲s̲ ̲a̲n̲d̲ ̲S̲e̲c̲u̲r̲i̲t̲y̲
a) The equipment shall operate from mains power installations
conforming to national regulations concerning power
and safety.
b) CR will ensure that As-To-Be-Built drawings submitted
to SHAPE will conform to national safety regulation.
c) SHAPE will approve the As-To-Be-Built drawings
for conformance to ACE COMSEC regulations and will
obtain approval of the completed installation from
national authorities.
d) The CRT installations at main and remote sites
shall conform with the relevant requirements for
automatic processing devices contained in the current
issue of AMSG719B. The AMSG719B requirements have
been adapted to CAMPS as described in document
CPS/TCN/023 (CAMPS Site Design Concept)
e) Customers local COMSEC staff shall monitor the
installation works. A final test and inspection
before each installation becomes operative will
be carried out by an ACE-COMSEC team.
3.7.1.2.4 P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲ ̲a̲n̲d̲ ̲P̲o̲w̲e̲r̲ ̲D̲i̲s̲t̲r̲i̲b̲u̲t̲i̲o̲n̲
a) 220V/50Hz Power supplies will be provided by SHAPE/Host
Nation at all main and remote sites except UKAIR
where the nominel voltage is 240V.
b) If consistent with national regulations the following
colour coding shall apply:
Line: Brown
Neutral: Blue
Ground: Yellow/green
In conformance with national regulations each end
of the neutral and ground wire shall be clearly
marked (coloured sleeves or coloured durable adhesive
tape).
c) Protective devices for the mains power installation
shall be provided by SHAPE/Host Nation.
Circuit breakers which operate to make or break
A.C. power lines shall make or break all conductors
at the same time. The neutral wire shall not pass
through any fuse. All fuses and circuit breakers
shall be so located such that they are readily
accessible.
d) Utility outlet sockets for operation of each terminal
shall be specified in the CWR and provided by SHAPE/Host
Nation as close as possible to the required installation
site of a terminal. The outlet sockets shall be
of a uniform 220V A.C. standard type with ground
and break of line according to the national standard
for each installation. The socket shall be of a
type that only allows the plug to mate in the correct
orientation.
e) Contractor shall provide his requirements for the
power installation specifying the required number
of utility outlet sockets as part of the Civil
Works Requirements Package.
f) Customer will provide for Standard Power Cables
laid in unperforated sheet metal ducts with lids
or conduits (fixed or flexible) in the room at
the remote location where the CRT-rack are installed.
3.7.1.2.5 G̲r̲o̲u̲n̲d̲i̲n̲g̲
a) CRT at mainsites: The grounding concept for CAMPS
main sites shall apply. (Ref. CPS/TCN/023).
b) CRT-racks at remote locations will be provided
with a secure ground by SHAPE/Host Nation. The
ground may be the third wire of a 3wire power-cable
from the power distribution board to the CRT-rack
or a separate wire run within the same conduit.
c) SHAPE/Host Nation will provide CRT-terminals with
3pin power outlets, the third wire of which will
provide either a secure or safety ground. The ground
wire may be the third wire of a 3wire power cable
from the power distribution board to the power
outlet or a separate wire run within the same conduit.
d) Both grounds (secure and safety) shall conform
to national regulations.
3.7.1.2.6 S̲p̲a̲c̲e̲ ̲a̲n̲d̲ ̲A̲c̲c̲e̲s̲s̲
a) The space required for the CRT-rack at the remote
location will be specified by CR as part of the
CAMPS CWR.
b) A minimum floor to ceiling height of 220 cm. without
a raised floor or 2 meters minimum in case of a
raised floor will be provided in the room at the
remote location where the CRT-rack is installed.
The following dimensions are required as the minimum
envelope along the equipment access route of any site:
Height 1.70 meters
Width 0.65 meters
Length 3.70 meters
3.7.1.2.7 S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲
a) Immediately following contract award CR will perform
formal site surveys at each remote terminal site,
if appropriate. A site survey questionnaire will
be completed by each site and submitted to CR.
If the questionnaire is considered complete, a
site survey may not be necessary.
b) If a survey is considered necessary, subject to
coordination with CR, SHAPE will arrange a visit
ot the site. The purpose of the site survey is
to ensure that the contractor has collected the
necessary information to prepare CWR and As-To-Be-Built
drawings.
c) SHAPE representatives will assist contractor to
collect the relevant information to be used to
prepare the site for installation of the CRT equipment.
At least one of SHAPE representatives on each site
survey team will be authorized to make decisions
and to sign a survey protocol on behalf of SHAPE.
d) S̲i̲t̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
1) During the site survey, the contractor will
gather all information needed for preparation
of Civil Works Requirements, As-To-Be-Built
drawings, and As-Built drawings. The contractor
will also provide general CRT system information
to the Host Nation to support the Host Nation's
preliminary design of site preparation works.
2) It is anticipated that the contractor will be
required to make only one site survey at each
site. It is the responsibility of SHAPE that
all necessary information is available to the
contractor. If one or more subsequent site visits
are required because of a contractor omission
during the original site survey such visit(s)
shall be the responsibility of the contractor.
If subsequent survey effort is required because
of a failure by SHAPE or the site users to fulfil
their obligations such survey effort shall not
be carried out before a mutual agreement between
the contractor and SHAPE has been reached.
3) The contractor's planning baseline for preparation
of Civil Works Requirements is the site survey,
or site survey questionnaire. If SHAPE advises
the contractor of site modifications accomplished
after the site survey, the contractor will incorporate
these changes into his Civil Works Requirements
provided that he is notified of the changes
no later than 3 months prior to either the contractually
specified submission date or the actual submission
date, whichever is later.
4) The approved Civil Works Requirements are the
Contractor's planning baseline for his preparation
of As-To-Be-Built drawings. SHAPE is responsible
to ensure that any site modifications made after
Civil Works Requirements approval are identified
to the contractor for his incorporation into
the
As-To-Be-Built Drawings. The contractor shall
incorporate these changes in the As-To-Be-Built
drawings provided the changes are identified
to the contractor no later than 2 1/2 months
prior to either the contractually specified
submission date or the actual submission date,
whichever is later.
3.7.2 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲a̲n̲d̲ ̲S̲u̲p̲p̲o̲r̲t̲
If an error is detected at the remote site, the user
may replace a suspected terminal with a spare one.
The same applies for the Statistical Multiplexer. If
the fault cannot be rectified by the user at the remote
site, the maintenance personnel at the corresponding
main site must be called upon. Preventive maintenance
must likewise be carried out by personnel from the
main site and/or remote site.
3.7.3 S̲p̲a̲r̲e̲s̲ ̲a̲n̲d̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
3.7.3.1 S̲u̲p̲p̲l̲y̲ ̲o̲f̲ ̲P̲a̲r̲t̲s̲
The current maintenance philosophy is based on one
spare statistical multiplexer available at the remote
terminal location. These units can be replaced by the
user.
Contractor will not specify any spareparts for the
remote terminal location.
3.7.3.2 N̲A̲T̲O̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
Subassemblies will be codified in accordance with the
CRT contract.
3.7.4 T̲r̲a̲i̲n̲i̲n̲g̲
In accordance with CR's proposals and Letter of Intent
from customer no formal training is contemplated on
CRT equipment.
4̲ ̲ ̲S̲Y̲S̲T̲E̲M̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲
This section specifies the quality assurance provisions
applicable to verify the equipment. It also identifies
the associated verification documentation.
4.1 T̲E̲S̲T̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲ ̲M̲E̲T̲H̲O̲D̲S̲
The unit verification requirements will be met by one
of the following methods:
a) T̲e̲s̲t̲
This method is a functional verification, such
as actual operation wherein the element of verification
is instrumented, measured, or displayed directly.
All hardware shall be tested to demonstrate its
proper functioning, its interfaces and its performance.
b) A̲n̲a̲l̲y̲s̲i̲s̲
This method is a non-functional verification, such
as deduction or translation of data, review of
analytical data, or performance of a detailed analysis.
The aim of the analysis is to discover:
1) Misinterpretations of the approved specification
or the design.
2) Errors, omission or inconsistencies in the above
or in the documentation.
3) Nonconformance to the agreed standards.
c) E̲x̲a̲m̲i̲n̲a̲t̲i̲o̲n̲/̲I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲
This method is a non-functional verification, such
as visual inspection of the physical characteristics
of the item or of the documentation associated
with the item.
4.2 V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲
a) The verification efforts are divided into hardware
and system verification.
b) The verification will be divided into two classes
which are
I - Internal verification
II - External verification
c) Only class II verifications shall be approved by
SHAPE.
d) Class I verifications shall be approved by CR's
internal QA only, but may be inspected by SHAPE's
QAR.
e) The verification efforts shall be divided into
the verification type defined below.
f) H̲A̲R̲D̲W̲A̲R̲E̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
C̲l̲a̲s̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲T̲y̲p̲e̲ ̲
I Production Verification
II Factory Acceptance Test
g) S̲Y̲S̲T̲E̲M̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
C̲l̲a̲s̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲T̲y̲p̲e̲ ̲
II Comsec On-site Verification
II Site Functional Test
4.2.1 H̲a̲r̲d̲w̲a̲r̲e̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
4.2.1.1 P̲r̲o̲d̲u̲c̲t̲i̲o̲n̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
The production verification which is internal (class
I) is the verification to be performed on each unit,
module and subsystem following manufacture to ensure
that all items are in accordance with product specification
prior to system integration.
4.2.1.2 F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲
When a CRT-link has been integrated at the factory,
a test will be carried out to verify that all hardware
fulfils the functional specifications. This is an external
verification (class II).
4.2.2 S̲y̲s̲t̲e̲m̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
4.2.2.1 C̲O̲M̲S̲E̲C̲ ̲O̲n̲-̲S̲i̲t̲e̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
a) When the CRT equipment has been installed on-site,
a COMSEC verification will be performed by the
ACE COMSEC authorities.
b) Customer will conduct the verification and Christian
Rovsing A/S test engineers will assist in operating
the system. The COMSEC on-site verification is
a formal verification (class II). The verification
shall take place in conjunction with the Site functional
test.
4.2.2.2 S̲i̲t̲e̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲
a) Site functional test is the act whereby SHAPE will
acknowledge by protocol that CR has fully demonstrated
that a CRT-link is complete and ready for initial
operation and will take place when the following
requirements have been met:
1) Completion of an agreed Site functional test
2) Verification of the site inventory
3) If applicable, availability of a mutually agreed
discrepancy list showing the agreed date for clearance
of each listed discrepancy.
4.3 F̲A̲C̲T̲O̲R̲Y̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲S̲I̲T̲E̲ ̲F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲T̲E̲S̲T̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
4.3.1 G̲e̲n̲e̲r̲a̲l̲
The quality and quantity of documentation produced
and delivered by contractor for Factory Acceptance
and Site functional tests is determined solely by the
extent to which customer and contractor have agreed
to test the equipment (i.e. requirements stated in
this Requirements and Design Specification).
Documentation for class I test (contractor's internal
verification) will be developed for in-house use only.
4.3.2 F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲
Factory Acceptance Test Document shall contain the
procedures for the tests, that have to be performed
on each equipment and its associated accessories, following
manufacture, to ensure that all items to be delivered
are in accordance with the requirements of the contract,
prior to shipment from the factory.
4.3.3 S̲i̲t̲e̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲
This document shall contain all test procedures and
inspections that are necessary to verify that the equipment
has been correctly installed and to demonstrate that
the remote terminals are able to communicate with CAMPS.
It shall also contain a check list of all items that
should be supplied under terms of the contract such
as accessories, spare parts, tools, test equipment
and documentation.
4.3.4 T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
Each procedure shall, where applicable, include as
a minimum the following:
a) The title of the proposed procedure and a list
of all required test equipment, where applicable.
b) Required test limits, where applicable.
c) A detailed step-by-step procedure written so that
the procedure can be understood by technician.
d) A block diagram of the required test set-up if
more than two test connections are involved.
4.3.5 T̲e̲s̲t̲ ̲R̲e̲s̲u̲l̲t̲ ̲F̲o̲r̲m̲s̲
The Test Results Forms to be used in conjunction with
the test procedures may be part of the test procedure
itself. They shall contain as a minimum a space for
inclusion of:
a) Test location and date
b) Equipment type and serial number(s)
c) Test procedure reference number and issue number
d) Type of test equipment employed
e) Test Results
f) Comments
g) Signatures of official representatives of the contractor
and the customer.
4.3.6 A̲p̲p̲r̲o̲v̲a̲l̲ ̲a̲n̲d̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲
A copy of each class II test document complete with
samples of the associated test result forms, shall
be submitted to SHAPE for approval at least thirty
days before the scheduled date for commencement of
the associated tests. Submittal will take place only,
if SHAPE has not previously approved the document.
SHAPE and the contractor shall mutually agree on any
changes to the scope and content during the period
between submission of the test procedures and the scheduled
date for commencement of the associated tests.
5̲ ̲ ̲S̲Y̲S̲T̲E̲M̲ ̲D̲E̲S̲I̲G̲N̲
This chapter presents a more detailed description of
the different H/W assemblies which have been identified
in chapter 3.
To provide a more comprehensive understanding of the
Remote Terminals System, each of the assemblies are
broken down into basic functional elements (i.e. crate,
buses and modules), and each of these is given a detailed
functional/mechanical description. The equipment is
divided in two major assemblies:
1) The main site equipment
2) The remote site equipment
5.1 M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
The aim of the equipment positioned at the mainsite
is to collect the datachannels for connection to the
remote site and perform the necessary multiplexing/demultiplexing
to enable communication via a single data link.
The datachannels may originate from
1) A LTUX belonging to the CRT equipment and connected
to the TDX-bus of CAMPS
2) CAMPS data channel expansion capacity (Expansion
LTUXs)
3) Separate channels interfaced via the CAMPS filterbox
4) A single data channel reserved for future connection
to a LTUX capable of handling an OCR
For the purpose of point 3) above a low-level signal
adaption capability is necessary.
The major functional subassemblies used on the Main
Site are shown in fig. 5.1-1::
1) TDX crate assembly
2) Adaptor crate assembly
3) Statistical Multiplexer
5.1.1 T̲D̲X̲ ̲C̲r̲a̲t̲e̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
The TDX modules, the LTUX-S and the BSM-X, are housed
in a standard CR80S 19" CTX Crate.
Besides the TDX modules the TDX Crate Assembly houses
the Power Supply modules, and when reconfiguration
option 2 is implemented, the OMDTs will be placed in
the TDX Crate Assembly.
The position of the modules in the TDX Crate Assembly
is restricted to the positions indicated in fig. 5.1.1-1.
5.1.1.1 C̲T̲X̲-̲C̲r̲a̲t̲e̲
The CTX Crate consists of a front crate and a rear
crate. On the back panel of the front crate is a bus
motherboard (Printed Circuit board) for module interconnection
and also edgeconnectors for the front crate mounted
modules.Refer to section 5.3.1.1 for further mechanical
specifications.
The CTX motherboard connector signals are shown in
fig. 5.1.1-2 (4 sheets).
All signals in the V24/V28 I/O area (refer to fig.
5.1.1-2 conform with the CCITT V28 electrical specifications,
with the exception of the supply voltage connections.
The Supply Voltage is an ac voltage with the following
specification.
Voltage: 9 V…0f…RMS…0e…
Max. Current: 4.2 A
The remaining Motherboard signals TDX-TX-DATA, TDX-TX-EN,
TDX-REC-1, and TDX-REC-2 conform to the following specification:
Drivers:
2,4V = V…0f…OH…0e…= 5V
OV = V…0f…OL…0e…= 0.5 V
I…0f…OHMax …0e…= 15mA
I…0f…OLMax …0e…= 24mA
Receivers:
2V = V…0f…IH…0e… = 5V
OV = V…0f…IL…0e… = 0,8 V
I…0f…IL…0e… = 0,2 mA
I…0f…IH…0e… = 0,02 mA
Notes: 1) The V24 Monitors form part of the maintenance
equipment, and are only mounted during
maintenance operation.
2) The OMDTs belong to the Remote Site Equipment,
and are only mounted when reconfiguration
option 2 is implemented.
FIGURE 5.1.1-1…01…T̲D̲X̲ ̲C̲R̲A̲T̲E̲ ̲A̲S̲S̲E̲M̲B̲L̲Y̲,̲…01…M̲A̲X̲.̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
]
FIGURE 5.1.1-2 (sheet 1 of 4)…01…C̲T̲X̲ ̲M̲O̲T̲H̲E̲R̲B̲O̲A̲R̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲P̲I̲N̲S̲,̲ ̲P̲O̲S̲.̲ ̲1̲
̲&̲ ̲2̲
FIGURE 5.1.1-2 (sheet 2 of 4)…01…C̲T̲X̲ ̲M̲O̲T̲H̲E̲R̲B̲O̲A̲R̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲P̲I̲N̲S̲,̲…01…P̲O̲S̲.̲ ̲3̲,̲4̲,̲5̲,̲6̲,̲1̲1̲,̲1̲2̲,̲
̲1̲3̲ ̲&̲ ̲1̲4̲
FIGURE 5.1.1-2 (sheet 3 of 4)…01…C̲T̲X̲ ̲M̲O̲T̲H̲E̲R̲B̲O̲A̲R̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲P̲I̲N̲S̲,̲ ̲P̲O̲S̲.̲ ̲7̲
̲&̲ ̲1̲5̲
FIGURE 5.1.1-2 (sheet 4 of 4)…01…C̲T̲X̲ ̲M̲O̲T̲H̲E̲R̲B̲O̲A̲R̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲P̲I̲N̲S̲,̲…01…P̲O̲S̲.̲ ̲8̲,̲ ̲9̲,̲ ̲1̲0̲,̲
̲1̲6̲,̲ ̲1̲7̲ ̲&̲ ̲1̲8̲
5.1.1.2 B̲S̲M̲-̲X̲
The BSM-X, the TDX Bus Switching and Monitoring module
provide two interface functions:
- Interfaces the dualized TDX buses of CAMPS to the
TDX Crate Assy. Single TDX Bus structure through
a Bus switch circuitry.
- Interfaces the CAMPS CCB (Configuration Control
Bus) to the TDX Crate Assy control and monitoring
facilities through an addressable serial/parallel
conversion circuitry.
The addressable serial/parallel conversion circuitry
(An addressable UART) is the TDX Crate Assy interface
to the CAMPS Watchdog.
Fig. 5.1.1.2-1 shows the BSM-X principle diagram.
The Bus switch circuitry, selecting one of the dualized
TDX buses as the internal TDX bus, is controlled either
by the CAMPS Watchdog Processor or by a switch on the
BSM-X front panel. The source of control is selected
via another front panel mounted switch selecting either
Automatic mode, enabling Watchdog Processor control,
or Manual mode enabling manual TDX bus selection.
The BSM-X is a standard CR80S front crate module occupying
1 crate position.
P̲o̲w̲e̲r̲ ̲C̲o̲n̲s̲u̲m̲p̲t̲i̲o̲n̲
+ 5V: 2A
+ 12V: 0,15A
- 12V: 0,15A
5.1.1.2.1 B̲S̲M̲-̲X̲ ̲P̲a̲n̲e̲l̲
External connections (CCB, TDX Bus # 1 and # 2) are
provided via the BSM-X Panel, a front panel in the
rear crate. Flatcables connect the BSM-X panel connections
to the CTX motherboard. The BSM-X panel is a CR80S
rear crate module occupying 2 crate positions.
FIGURE 5.1.1.2-1…01…T̲H̲E̲ ̲B̲S̲M̲-̲X̲
5.1.1.3 L̲T̲U̲X̲-̲S̲
The LTUX-S is the standard interface to the TDX bus.
The LTUX-S provides 4 V24/V28 communication channels.
On the front panel are four switches that can be used
to enable/disable each of the four communication channels.
The LTUX-S is built around a standard microprocessor
using standard microprocessor interface LSIs as interface
between the TDX bus and the user applications.
5.1.1.3.1 T̲D̲X̲ ̲B̲u̲s̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
The LTUX-S provides up to 16 full duplex individual
logical channels between the user application and the
TDX bus. The microprocessor supports both application
processing of the TDX interface, TDX protocol and TDX
channel set-up. The sum of bandwidth assigned to the
logic channels through the LTUX-S is dynamically changeable
by the CAMPS System.
Overleaf is found the block diagram of the LTUX-S,
fig. 5.1.1.3.1-1.
The TDX bus signals are buffered, by bus receivers
and a tri-statable driver, before they are routed to/from
the code converter circuit. In this circuit the incoming
SPL-D data stream is converted to NRZL data and a clock
(CLK). The outgoing data stream is converted to SPL-D
code synchronized to CLK. When an incoming frame is
received, the State Controller gets a request from
the serial to parallel converter and the contents of
the frame is routed byte by byte to FIFO 1.
During this transfer some of the bytes in the frame
are checked or compared "on the fly" by the State Controller.
The contents of the MUX no. field, indicating the next
device to transmit, is compared with the device number
(set on a DIL-switch), and if equal and no CRC errors
are detected the transmitter part is activated and
a frame will be transmitted when bit 241 of the incoming
data stream has been reached.
FIGURE 5.1.1.3.1-1…01…T̲H̲E̲ ̲L̲T̲U̲X̲-̲S̲
The contents of the DEVICE NO. field, indicating the
destinee of the frame, is compared to the device number,
and if equal the contents of FIFO 1 is transferred
to FIFO 2. If FIFO 2 is not empty this transfer is
cancelled and FIFO 1 is cleared to be ready for the
next incoming frame. When the transfer from FIFO 1
to FIFO 2 has succeeded the LTUX-S CPU is interrupted.
The interrupt routine (FRAME-routine) transfers the
frame from FIFO 2 to a free ringbuffer within the CPU
memory space, and the Incoming Scan routine transfers
the frame from the ringbuffer to a data buffer associated
to one out of ten protocol descriptors identified by
the CR-ID block in the incoming frame and simultaneously
executes the TDX protocol on the frame. Via the protocol
descriptor the frame is fetched by either the System
S/W (channel 0-1) or by Application S/W (channel 2-15).
Transfer is shown schematically on fig. 5.1.1.3.1-2
(2 sheets).
When the transmitter part of the State Controller has
been activated by an incoming frame, it starts to send
the start-FLAG followed by the frame which is transferred
byte by byte from FIFO 3 to the parallel to serial
converter. After the last byte an end-FLAG is generated,
the CPU is interrupted and will now move the next outgoing
frame from a channel buffer in the memory to FIFO 3.
If no frame is available the CPU does nothing and the
next time the transmitter is activated FIFO 3 will
be empty and no frame is transmitted.
The frame to be transmitted comes from a data buffer
fetched, via a protocol descriptor, by the Outgoing
Scan routine and routed to FIFO 3 directly while executing
the TDX protocol on the frame.
The processor part consists of a PROM-memory area,
a data memory area, serial input/output interface circuits
for four V24 channels, a timer and interrupt control
circuit and an I/O port used for reading a mode select
switch (DIL-switch) and for control of the State Controller.
The mode select switch can be used by the Application
S/W. For example to determine characteristics of the
V24 channels such as:
- baudrate
- V24 protocol
FIGURE 5.1.1.3.1-2 (Sheet 1 of 2)…01…L̲T̲U̲X̲-̲S̲ ̲D̲A̲T̲A̲ ̲T̲R̲A̲N̲S̲F̲E̲R̲
FIGURE 5.1.1.3.1-2 (Sheet 2 of 2)…01…L̲T̲U̲X̲-̲s̲ ̲D̲A̲T̲A̲ ̲T̲R̲A̲N̲S̲F̲E̲R̲
The timer circuit has one software controlled timer
with interrupt access to the CPU. It handles one external
interrupt from the State Controller and it controls
two baud rate generators set up by software.
5.1.1.3.2 M̲e̲c̲h̲a̲n̲i̲c̲a̲l̲ ̲a̲n̲d̲ ̲E̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
The LTUX-S is a standard CR80S module placed in the
TDX Crate Assembly. The LTUX-S bus connector layout
is shown on fig. 5.1.1.3.2-1.
P̲o̲w̲e̲r̲ ̲C̲o̲n̲s̲u̲m̲p̲t̲i̲o̲n̲ ̲o̲f̲ ̲t̲h̲e̲ ̲L̲T̲U̲X̲-̲S̲
+ 5 Volt: 3 A
+ 12 Volt: 0,15
- 12 Volt: 0,15 A
FIGURE 5.1.1.3.2-1…01…L̲T̲U̲X̲-̲S̲ ̲B̲U̲S̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲L̲A̲Y̲-̲O̲U̲T̲
5.1.1.3.3 U̲s̲e̲r̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
The 4 asynchronous V24 channels of the LTUX-S will
normally be connected to the Statistical Multiplexer
via a V24 Back Panel (type BP 8).
If reconfiguration option 2 is implemented the OMDTs
from the Remote Site will be moved to the Main Site
and installed in the TDX-crate assembly, after disconnection
of the Statistical Multiplexers. In this case the four
V24 channels will be interfaced to the VDUs and MSPs,
moved from the Remote to the Main Site installation,
via the moved OMDTs.
For maintenance purposes, it is possible to monitor
the V24 channels by aid of a V24 Monitor Panel (not
installed, part of CAMPS Maintenance equipment).
5.1.1.3.4 V̲2̲4̲ ̲B̲a̲c̲k̲ ̲P̲a̲n̲e̲l̲
External V24/V28 connections to/from the TDX-crate
assembly are provided via the V24 Back Panel, where
four 25 pole connectors are situated (CANNON DB25 or
equivalent)
A flatcable connects the V24 circuits connections to
the LTUX-S motherboard connector. A strapping field
on the back panel may be used for DTE to/from DCE conversion.
The V24 Back Panel is a CR80S rear crate module occupying
4 crate positions.
5.1.1.3.5 O̲M̲D̲T̲
The OMDTs will only be mounted in the TDX-crate assembly
if reconfiguration option 2 is implemented.
For a description of the OMDT refer to section 5.2.2.1.
5.1.1.3.6 V̲2̲4̲ ̲M̲o̲n̲i̲t̲o̲r̲ ̲P̲a̲n̲e̲l̲
The V24 Monitor Panel is part of CAMPS Maintenance
Equipment and only used during Maintenance Operations.
The V24 Monitor Panel may be inserted in crate position
# 5 or 6 and 13 or 14 to monitor the V24 traffic on
the LTUX in position # 3 respectively # 11.
The V24 Monitor Panel is a standard CR80S front crate
module occupying 2 crate positions.
5.1.1.4 T̲D̲X̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲
The TDX power supply is a standard CR80S module. The
TDX Power Supply, as seen from fig. 5.1.1.4-1, provides
3 regulated power outputs:
- + 5 Volt
- + 12 Volt
- - 12 Volt
The +5 Volt power supply is a 20 KHz push-pull converter
operating direcly on the rectified mains voltage.
The +12 Volt and -12 Volt power supplies are fed from
a full wave rectified transformer output.
The +12 Volt power supply is regulated by a conventional
PWM (Pulse Width Modulated) regulator.
The -12 Volt power supply is regulated by a PWM regulator.
E̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
Maximum load:
+ 5 Volt: 32 A
+ 12 Volt: 2,8A
- 12 Volt: 1,2A
Noise & ripple: Better than 60 mV…0f…pp…0e…
Input Voltage: 220V…0f…ac…0e…+10/-15%
50 Hz + 30/-10%
5.1.1.4.1 M̲a̲i̲n̲ ̲P̲o̲w̲e̲r̲ ̲P̲a̲n̲e̲l̲
The TDX Power Supply is interfaced to the Main Power
via the Main Power Panel, which contains a mains switch,
fuse and some HF-filtering components.
The Main Power Panel is a CR80S rear crate module occupying
2 crate positions.
FIGURE 5.1.1.4-1…01…T̲D̲X̲ ̲P̲O̲W̲E̲R̲ ̲S̲U̲P̲P̲L̲Y̲
5.1.1.5 O̲p̲t̲o̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲
The Opto Power Supply is identical to the Adaptor Power
Supply. Refer to section 5.1.2.3 for a description.
5.1.2 A̲d̲a̲p̲t̲o̲r̲ ̲C̲r̲a̲t̲e̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
The Adaptor Crate Assembly contains the V28(L/L) adaptors
to be used when reconfiguration option 1 is implemented.
On site 10, the V28(L/L) adaptors are also used to
interface the CAMPS Expansion LTUX channels to the
Remote Terminal System.
Besides the V28(L/L) adaptors, the Adaptor Crate Assembly
contains the Adaptor Power Supply. These modules are
housed in CTX-crate. Refer to section 5.1.1.1 for a
description of the CTX-crate. The position of the modules
in the Adaptor Crate is depicted in fig. 5.1.2-1.
FIGURE 5.1.2-1…01…A̲D̲A̲P̲T̲O̲R̲ ̲C̲R̲A̲T̲E̲ ̲A̲S̲S̲E̲M̲B̲L̲Y̲,̲ ̲M̲A̲X̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
5.1.2.1 V̲2̲8̲ ̲(̲L̲/̲L̲)̲ ̲A̲d̲a̲p̲t̲o̲r̲
The V28 (L/L) adaptor Type 1 converts standard CCITT
V24/V28 signal levels within 4 data channels to V24/V28(L/L)
signals, and vice versa.
Fig. 5.1.2.1-1 shows the V28 (L/L) Adaptor, block diagram.
The V28(L/L) adaptor is a standard CR80S module occupying
2 crate positions.
a) I̲n̲t̲e̲r̲f̲a̲c̲e̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲
1) S̲t̲a̲n̲d̲a̲r̲d̲ ̲V̲2̲8̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
The standard V28 side of the V28(L/L) adaptor
performs as a DCE and conforms with CCITT recommendation
V28. The following interchange circuits (ref.
CCITT V24) are provided for each of the four
data channels:
102 Signal ground
103 Transmitted data
104 Received data
105 Request to Send
107 Data Set Ready
108/2 Data terminal ready
The V28 side of the adaptor interfaces to the
motherboard. The pin allocation is shown in
fig. 5.1.2.1-2.
2) L̲o̲w̲ ̲L̲e̲v̲e̲l̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
On the front panel, 4 V24 connectors type D-25
are situated, forming the low level Interface.
Electrically, the Low Level Interface conforms
with MIL-STD-188C, except for polarity (see
below).
The waveshaping performed on the interchange
circuits is according to the requirement at
1200 bps, which is the maximum bit rate supported
by the module. The V28(L/L) Adaptor is capable
of driving a cable length of up to 275 meters.
Functionally the interchange signals correspond
to CCITT V24. The adaptor will be strapped to
perform as DCE or a DTE device.
The polarity of the interchange circuits 103
and 104 may be reversed by use of a strap. This
enables the user to select signal polarity according
to MIL-STD-188C or V28 on the Low Level Interface.
b) P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
The V28(L/L) adaptor, type 1 shall be powered from
a 2 x 9V AC power source:
A̲C̲ ̲P̲o̲w̲e̲r̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
Supply voltage: 2 x 9V AC + 10%/- 15%
Frequency: 50 Hz + 10%/- 10%
Current consumption: Max 2,1 A/module
FIGURE 5.1.2.1-1…01…V̲2̲8̲(̲L̲/̲L̲)̲ ̲A̲d̲a̲p̲t̲o̲r̲,̲ ̲T̲y̲p̲e̲ ̲1̲
B̲L̲O̲C̲K̲ ̲D̲I̲A̲G̲R̲A̲M̲
FIGURE 5.1.2.1-2…01…V̲2̲8̲(̲L̲/̲L̲)̲ ̲A̲D̲A̲P̲T̲O̲R̲ ̲T̲Y̲P̲E̲ ̲1̲…01…B̲U̲S̲ ̲C̲O̲N̲N̲E̲C̲T̲O̲R̲ ̲L̲A̲Y̲O̲U̲T̲
5.1.2.2 V̲2̲4̲ ̲B̲a̲c̲k̲ ̲P̲a̲n̲e̲l̲
The V24 Back Panel is used to interface four standard
V24/V28 data channels to the motherboard of the Adaptor
Crate Assembly.
The V24 Back Panel is identical with the Back Panel
used in the TDX-crate assembly. Ref. to section 5.1.1.3.4.
5.1.2.3 A̲d̲a̲p̲t̲o̲r̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲
The Adaptor Power Supply is a CR80S rear module occupying
8 crate positions. The Adaptor Power Supply provides
the necessary power to supply adaptors for 8 channels,
implemented by any combination of V28(L/L) adaptors
and OMDTs.
The module provides 2 x 9V AC outputs.
E̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲(̲e̲a̲c̲h̲ ̲o̲u̲t̲p̲u̲t̲)̲:̲
Output voltage: 9V AC + 10%/- 15%
Output frequency: 50 Hz + 10%/- 10%
Harmonic Distortion: max. 5%
Maximum Load: 4,2 A
5.1.3 S̲t̲a̲t̲i̲s̲t̲i̲c̲a̲l̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲
The CR supplied statistical multiplexer features full
duplex statistical multiplexing of 8 V24 channels,
with variable length block transmission, dynamic bandwidth
assignment and error control.
It is housed in a 19" rack-mount case 2U high (8,9
cm).
The status display is visible through the front panel
and all switches are front accessible after removal
of the front panel.
5.1.3.1 S̲t̲a̲t̲i̲s̲t̲i̲c̲a̲l̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲ ̲T̲r̲a̲n̲s̲m̲i̲s̲s̲i̲o̲n̲
The transmission between the statistical multiplexers
is carried out by a special statistical multiplexer
serial communication protocol.
The channel interface control signals are transmitted
via the protocol in form of a special control character,
generated each time one of the control signals changes
from On to Off or vice-versa. Two interface control
signals may be transmitted in each direction per channel.
The transmisson of variable length data blocks according
to the loading of the individual channels, allows the
stat. mux. to take account of average traffic loading
on the mux-line, since it can make use of its buffer
storage to accomodate temporary peak loading on individual
channels.
5.1.3.2 E̲r̲r̲o̲r̲ ̲C̲o̲n̲t̲r̲o̲l̲
Retransmisson on error is implemented automatically
between the stat. muxes using a full-duplex go-back-n-automatic-retransmission-request
(ARQ) scheme. The transmitting stat. mux. appends a
cyclic redundancy check (CRC) scheme. The transmitting
stat. mux. appends a cyclic redundancy check (CRC)
character to each transmitted data-block in the protocol.
This CRC is re-calculated to check the block errors
at the receiving stat. mux.
5.1.3.3 B̲u̲f̲f̲e̲r̲ ̲C̲o̲n̲t̲r̲o̲l̲
The buffer capacity (approximately 15K bytes) is allocated
dynamically to the channels as required, rather than
being fixed portions.
However, buffer overflow may occur, either because
of excessive retransmissions or prolonged peak channel
activity. If a buffer overflow is about to occur, the
stat. mux terminates the flow of data into its buffer,
by dropping the circuit 106 control signal on the V24
channels to the associated equipment.
5.1.3.4 C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲
All configuration parameters are switch selected using
DIP switches to configure the units. To further simplify
system configuration, switch selection of configuration
parameters is required at one site only. This is done
by switch selection of master and slave on each unit.
All configuration data is then automatically down-line
loaded from the master to the slave unit, at power-up
or reconfiguration of channels.
5.1.3.5 C̲h̲a̲n̲n̲e̲l̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
The Channel interfaces are CCITT V24/CCITT V28 serial
asynchronous full duplex interfaces available on female
(DCE) standard D-25 S connectors.
The available interchange circuits are:
102 Signal Ground
103 Transmitted Data
104 Received Data
105 Request to Send
106 Ready for sending
107 Data set ready
108.2 Data Terminal ready
5.1.3.6 M̲u̲x̲-̲L̲i̲n̲e̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲
The mux-line interface is a CCITT V24/special V28(L)
serial synchronous full-duplex interface available
on a male (DTE) standard D-25P connector.
The special V28(L) interface is implemented on a MIL-STD-188C
interface with CCITT V28 voltage polarities.
The available interchange circuits are:
102 Signal Ground
103 Transmitted Data
104 Received Data
105 Request to Send
106 Ready for sending
109 Received line signal detector
114 Transmitter signal element timing
115 Receiver signal element timing
5.1.3.7 P̲o̲w̲e̲r̲
The stat. mux. is connected to 220 V AC mains. The
power consumption is less than 150 watts.
5.1.4 S̲y̲n̲c̲h̲r̲o̲n̲e̲o̲u̲s̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲
The CR supplied synchroneous multiplexer is a 2 channel
data concentator feature full duplex multiplexing of
2 statistical multiplexer and operate as the CR supplied
Statistical Multiplexer.
It is housed in a 19" rack-mont case 2U high (8,9 cm).
5.1.5.1 R̲e̲s̲y̲n̲c̲h̲r̲o̲n̲i̲z̲a̲t̲i̲o̲n̲ ̲M̲o̲n̲d̲u̲l̲e̲
The Resynchronization mondule consist of two functionally
independent circuits each controlling one HOST-CRYPTO
v24-interface channel. Each channel has the ability
of initially synchronizing and resynchronizing its
V24 line.
5.1.5.2 P̲o̲w̲e̲r̲
The Resync. mondule is placed in front of a CTX-Crate
and the power consumption is typical 19 watts.
5.2 R̲E̲M̲O̲T̲E̲ ̲S̲I̲T̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
The aim of the equipment positioned at the remote site
is to distribute the datachannels to the terminals
connected at the remote site, and to perform the multiplexing/demultiplexing
to enable communication with the main site via a single
modem Line.
The terminals to be connected at the remote site can
be divided in the following categories:
1) VDUs
2) MSPs
3) Other equipment connected to separate channels
4) A single datachannel reserved for a future connection
to an OCR.
Of the 8 datachannels normally 4 are terminated in
an optical link to the terminals, and 4 are terminated
in a V28(L/L) connection to the terminals.
The data channels are fed through a filter box when
leaving the CAMPS Remote Terminal Rack.
The major functional subassemblies used on the Remote
Site are shown in figure 5.2-1:
1) Statistical Multiplexer
2) Opto Crate Assembly
FIGURE 5.2-1…01…C̲A̲M̲P̲S̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲…01…R̲E̲M̲O̲T̲E̲ ̲S̲I̲T̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲(̲T̲Y̲P̲I̲C̲A̲L̲)̲…01…F̲r̲o̲n̲t̲ ̲e̲l̲e̲v̲a̲t̲i̲o̲n̲,̲
̲d̲o̲o̲r̲ ̲r̲e̲m̲o̲v̲e̲d̲
5.2.1 S̲t̲a̲t̲i̲s̲t̲i̲c̲a̲l̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲
The Statistical Multiplexer used on the remote site
is identical with the Statistical Multiplexer used
on main site. Refer to section 5.1.3 for a description.
The Remote site stat. mux forms a pair together with
the corresponding stat. mux on main site; in this pair
one shall be set as Master, and one as Slave.
5.2.2 O̲p̲t̲o̲ ̲C̲r̲a̲t̲e̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
The Opto Crate assembly contains the V28(L/L) Adaptors
and OMDTs which perform the signal adaption on the
datachannels to be connected with the terminal equipment.
Furthermore the Opto Crate assembly contains an Opto
Power Supply.
These modules are housed in a CTX crate. Refer to section
5.1.1.1 for a description of the CTX-crate.
The position of the modules in the Opto Crate Assembly
is depicted in fig. 5.2.2-1.
5.2.3 S̲y̲n̲c̲h̲r̲o̲n̲e̲o̲u̲s̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲
The sync. mux. used on the remote site is identical
with the sync. mux. used on main site. Refer to section
5.1.4 for a description.
Note: The V24 monitors form part of the maintenance
equipment and are only mounted during maintenance
operation.
FIGURE 5.2.2-1…01…O̲P̲T̲O̲ ̲C̲R̲A̲T̲E̲ ̲A̲S̲S̲E̲M̲B̲L̲Y̲
5.2.2.1 O̲p̲t̲i̲c̲a̲l̲ ̲M̲u̲x̲/̲D̲e̲m̲u̲x̲ ̲T̲r̲a̲n̲s̲c̲e̲i̲v̲e̲r̲ ̲(̲O̲M̲D̲T̲)̲
a) The OMDTs are one channel units, delivered in 3
versions serving the same functions but in different
shape to fit the housing equipment:
One type for Delta 7260T VDU (OM-1),
One type for CTX crate mounting (OM-2), and
One type for Tracor 8000 RO MSP (OM-3).
b) The OMDT interfaces one V24/V28 channel. It converts
the electrical information to infra-red light pulses
in a serial protocol ready for opto-cable transmission
and vice-versa.
In the protocol, data and control bits are multiplexed
together, added with frame synchronization, converted
to Manchester code and send off as light pulses.
Reversely the receiver detects the light pulses,
makes electrical output which is decoded and demultiplexed.
The OMDT performs as a DCE on the electrical side.
The following interchange circuits are supported
102 Signal Ground
103 Transmitted Data
104 Received Data
105 Request to Send
106 Ready for sending
107 Data set ready
108.2 Data Terminal ready
c) P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
1) The OMDT OM-1 shall be powered from a 110 V
AC power source.
A̲C̲ ̲P̲o̲w̲e̲r̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
Supply voltage: 110 VAC + 20%/-18%
Frequency: 50 Hz + 10%/-10%
Current Consumption: max 0,25 A/module
2) The OMDT OM-2 shall be powered from a 2 x 9V
AC power source:
A̲C̲ ̲p̲o̲w̲e̲r̲ ̲r̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
Supply voltage: 2 x 9 V AC + 10%/-15%
Frequency: 50 Hz + 10%/-10%
Current Consumption: max. 1A/module
3) The OMDT OM-3 shall be powered from a 10 V AC
power source.
A̲C̲ ̲P̲o̲w̲e̲r̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
Supply voltage: 10 V AC + 10%/-15%
Frequency: 50 Hz + 10%/-10%
Current Consumption: max 0,30 A/module
5.2.2.2 V̲2̲8̲(̲L̲/̲L̲)̲ ̲A̲d̲a̲p̲t̲o̲r̲
For a description of the V28 (L/L) Adaptor refer to
section 5.1.2.1.
5.2.2.3 V̲2̲4̲ ̲B̲a̲c̲k̲ ̲P̲a̲n̲e̲l̲
The V24 Back Panel is used to interface four V24/V28
data channels to the motherboard of the Opto Crate
assembly. The V24 Back Panel is identical with the
V24 Back Panel used on the Main Site. Refer to section
5.1.1.3.4 for a description.
5.2.2.4 O̲p̲t̲o̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲y̲
The Opto Power Supply is identical with the Adaptor
Power Supply used on the Main Site. Refer to section
5.1.2.3.
5.2.2.5 V̲2̲4̲ ̲M̲o̲n̲i̲t̲o̲r̲ ̲P̲a̲n̲e̲l̲
The V24 Monitor Panel is part of CAMPS Maintenance
equipment, and only used during maintenance operations.
The V24 monitor Panel may be inserted in crate position
# 5 or 6 and 13 or 14 to monitor the V24 traffic between
Statistical Multiplexer and Terminal equipment.
The V24 Monitor Panel is a standard CR80 S front crate
module occupying 2 crate positions.
5.3 R̲A̲C̲K̲ ̲A̲N̲D̲ ̲S̲U̲B̲-̲A̲S̲S̲E̲M̲B̲L̲I̲E̲S̲
This section describes the design of the racks used
for CRT including:
a) The CR80S mechanical system
b) Other rack mounted equipment
c) The EMI shielded racks.
The figures 5.3-1 and 5.3-2 identify the assemblies
placed in the racks on main- and remote sites respectively.
FIGURE 5.3-1 (Sheet 1 of 2)…01…C̲A̲M̲P̲S̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲…01…M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲4̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲…01…(̲M̲A̲X̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲)̲…01…F̲r̲o̲n̲t̲
̲e̲l̲e̲v̲a̲t̲i̲o̲n̲,̲ ̲d̲o̲o̲r̲s̲ ̲r̲e̲m̲o̲v̲e̲d̲
FIGURE 5.3-1 (Sheet 2 of 2)…01…C̲A̲M̲P̲S̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲…01…M̲A̲I̲N̲ ̲S̲I̲T̲E̲ ̲4̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲…01…(̲M̲A̲X̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲I̲T̲O̲N̲)̲…01…F̲r̲o̲n̲t̲
̲e̲l̲e̲v̲a̲t̲i̲o̲n̲,̲ ̲d̲o̲o̲r̲s̲ ̲r̲e̲m̲o̲v̲e̲d̲
FIGURE 5.3-2…01…C̲A̲M̲P̲S̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲…01…R̲E̲M̲O̲T̲E̲ ̲S̲I̲T̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲(̲T̲Y̲P̲I̲C̲A̲L̲)̲…01…F̲r̲o̲n̲t̲ ̲e̲l̲e̲v̲a̲t̲i̲o̲n̲,̲
̲d̲o̲o̲r̲ ̲r̲e̲m̲o̲v̲e̲d̲
5.3.1 C̲R̲8̲0̲S̲ ̲M̲e̲c̲h̲a̲n̲i̲c̲a̲l̲ ̲S̲y̲s̲t̲e̲m̲
This section describes the parts that forms the CR80
S mechanical system.
5.3.1.1 C̲T̲X̲ ̲C̲r̲a̲t̲e̲
Fig. 5.3.1-1 shows the crate layout. The Crate assembly
is for 19" rack mounting.
Figure 5.3.1-2 shows a standard CR80S module, which
is inserted in the front crate. A PCB connector is
placed on the rear edge of each module.
A motherboard placed on the rear of the front crate
provides the interconnections between the modules and
carries rear crate connectors for connection of signal
and power cables.
Back panel subassemblies, such as Main Power Panel,
Adaptor power supply, V24 Back Panel and BSM-X panel
are mounted on the front of the rear crate. These Back
Panel Subassemblies are connected to the motherboard
rear crate connectors by cables.
Some front crate modules carry signal connectors on
the front panel.
FIGURE 5.3.1-1…01…C̲R̲8̲0̲S̲ ̲C̲R̲A̲T̲E̲
FIGURE 5.3.1-2
F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲M̲O̲D̲U̲L̲E̲
5.3.1.2 C̲o̲o̲l̲i̲n̲g̲ ̲o̲f̲ ̲C̲R̲8̲0̲S̲ ̲C̲r̲a̲t̲e̲s̲
The TDX, Opto and Adaptor Crate assemblies are cooled
by the CR80S fan assembly, see fig. 5.3.1-3.
The fan assembly is used for cooling of two CR80 S
crates placed one above the other with the fan assembly
placed below as shown on fig. 5.3.1-4.
The air intake is at the front of the fan assembly
and air is blown up through the front crate of the
CR80S crates.
The output air stream is directed backwards and will
leave the rack through perforations in the top plate
cover of the rack.
5.3.1.3 C̲a̲b̲l̲e̲ ̲C̲h̲a̲n̲n̲e̲l̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
Beneath each CR80S crate a Cable Channel Assembly is
placed. The purpose of this assembly is to guide cables
from the front to the rear side of the rack, without
disturbing the effectiveness of the cooling.
The height of the Cable Channel Assembly is 1U.
FIGURE 5.3.1-3…01…C̲R̲8̲0̲ ̲S̲ ̲F̲A̲N̲ ̲A̲S̲S̲E̲M̲B̲L̲Y̲
FIGURE 5.3.1-4…01…A̲I̲R̲F̲L̲O̲W̲ ̲I̲N̲ ̲C̲R̲8̲0̲S̲ ̲C̲R̲A̲T̲E̲S̲
5.3.2 R̲a̲c̲k̲-̲M̲o̲u̲n̲t̲e̲d̲ ̲P̲e̲r̲i̲p̲h̲e̲r̲a̲l̲s̲ ̲a̲n̲d̲ ̲S̲p̲e̲c̲i̲a̲l̲ ̲A̲s̲s̲e̲m̲b̲l̲i̲e̲s̲
This section describes the configuration items of the
Main site racks (fig. 5.3-1) and remote site racks
(fig. 5.3-2), which are not included in the CR80S system
(see sections 5.3.1).
5.3.2.1 S̲t̲a̲t̲i̲s̲t̲i̲c̲a̲l̲/̲S̲y̲n̲c̲h̲r̲o̲n̲e̲o̲u̲s̲ ̲M̲u̲l̲t̲i̲p̲l̲e̲x̲e̲r̲
Physical Dimensions:
The stat. mux. is housed in a 19" rack mounting box,
2U high.
The rack mounting box measures:
Width: 483 mm
Height: 89 mm
Depth: 279 mm
Weight: less than 10 kgs.
For further description see section 5.1.3/5.1.4.
5.3.2.2 P̲o̲w̲e̲r̲ ̲L̲i̲n̲e̲ ̲F̲i̲l̲t̲e̲r̲
The power supply lines are entering the racks through
power line filters for protection against noise and
spikes on the power lines.
A power line filter is designed as a box placed on
the inside surface of the rack wall and forming a cavity
in the EMI surface.
Power line filters used for CRT are placed in CAMPS
Line Termination Rack E in multibay configurations.
On remote sites and mainsite 10, a powerline filter
is included in the stand alone rack.
5.3.2.3 M̲a̲i̲n̲s̲ ̲S̲w̲i̲t̲c̲h̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
a) The main switch assembly are placed in the front,
bottom position of all racks.
Power switches and elapsed time indicators are
placed on the front panel. The mains switch is
a dual single-phase assembly sourced from the Power
Line Filter.
b) On Main Site 10 (UKAIR) the Main Switch Assembly
performs a step-down transformation from 240 VAC
to 220 VAC.
5.3.2.4 P̲o̲w̲e̲r̲ ̲D̲i̲s̲t̲r̲i̲b̲u̲t̲i̲o̲n̲ ̲P̲a̲n̲e̲l̲
The power distribution panels branches the power lines
into the number of power input sources required by
the assemblies of the rack.
5.3.2.5 F̲i̲l̲t̲e̲r̲ ̲B̲o̲x̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲
All V24 channels to external equipment are passed through
the Filter Box facility of CAMPS Line termination rack
F in multi-bay configurations. On remote sites and
main site 10 a filter box is included in the stand
alone rack. The principle of the Filter Box design
is shown on fig. 5.3.2-1.
The Filter Box forms a cavity in the EMI shielding
surface of the rack.
Electrical cables are conducted from the assemblies
containing V28(L) adapters to a position at the Filter
Box, where a feed through connector, containing RF-filters,
passes the signals through the EMI shield, formed by
the rack.
Opto cables are passed through the waveguide of the
Filter Box in the stand alone racks.
All signal cables are leaving the rack through the
attached cable duct.
A cover has to be removed to get access to the connectors
of the external electrical cables.
FIGURE 5.3.2-1…01…F̲I̲L̲T̲E̲R̲ ̲B̲O̲X̲…01…P̲R̲I̲N̲C̲I̲P̲L̲E̲S̲ ̲O̲F̲ ̲D̲E̲S̲I̲G̲N̲
5.3.3 E̲M̲I̲ ̲S̲h̲i̲e̲l̲d̲e̲d̲ ̲R̲a̲c̲k̲s̲
A CRT Main Site Installation includes 1 or 2 Racks,
named Rack G and H. The CRT Remote Site Installation
includes a single rack.
The Racks serve 2 major tasks.
a) They contain a 19" Rack-system for mounting of
assemblies, units, and cables.
b) The rack assemblies provide an EMI shielding to
reduce electromagnetic radiation from the enclosed
equipment.
Fig. 5.3.3-1 shows a single rack. The max. dimensions
shown give the maximum envelope of the rack.
The rack has 2 doors, a front door and a rear door.
The front door allows full access to the mounted equipment.
Front and rear door are of equal size and are hinged
at the same side of the rack.
The doors and the cabinet are made of steel.
Two perforated areas in the front door allow air intake
for cooling of equipment. The top cover plate of the
cabinet is perforated to allow output of cooling airflow.
The gaps between doors and cabinet are blocked by gaskets
of conducting material.
The tightness of these gaskets is important for TEMPEST
performance. The gaskets are wear-out items with a
3 to 5 year service lifetime.
The 19" panel mounting rail system included in the
cabinet is mounted on insulation blocks and the mounted
equipment is thus galvanically insulated from the EMI
Shield.
The "useful depth" of the rack is the distance between
the mounting surfaces of the front and rear mounting
rails. The useful depth is 101 cm.
FIGURE 5.3.3-1…01…S̲I̲N̲G̲L̲E̲ ̲E̲M̲I̲-̲R̲A̲C̲K̲,̲ ̲D̲I̲M̲E̲N̲S̲I̲O̲N̲S̲
5.3.3.1 S̲t̲a̲n̲d̲ ̲A̲l̲o̲n̲e̲ ̲R̲a̲c̲k̲s̲
The stand alone racks are used on all Remote Sites
and on Main Site 10 (UKAIR).
The stand alone racks have side walls welded to the
cabinet to form one continuous EMI shield, when doors
are closed.
The stand alone racks have provisions for 6 knock-outs
in the top cover plate. All cabling (power and data
channels) will enter the stand alone racks in the top.
A schematic of the top cover plate is shown in fig.
5.3.3-2.
5.3.3.2 M̲u̲l̲t̲i̲-̲B̲a̲y̲ ̲R̲a̲c̲k̲-̲A̲s̲s̲e̲m̲b̲l̲y̲
At all main sites, except no. 10, the racks containing
the CRT main site equipment will be connected to the
CAMPS Line Termination Rack Assembly to form a multi-bay
rack. These multi-bay racks consist of single racks,
bolted together with conducting gaskets inserted. No
side walls are mounted between neighbouring racks.
When the doors are closed the multi-bay rack forms
one continuous EMI shield. The racks to be assembled
in a multi-bay configuration have provisions for 3
knock outs in the top cover plate and 3 in the bottom.
However they will not be used in the standard CRT design,
as the cabling normally will enter through the CAMPS
Line Termination Racks.
5.3.3.3 P̲o̲w̲e̲r̲,̲ ̲H̲e̲a̲t̲,̲ ̲a̲n̲d̲ ̲W̲e̲i̲g̲h̲t̲
In fig. 5.3.3.3-1 is shown the phases of Start-up.
a) Initial peak period.
In the initial period the current is defined by
initial currents due to saturation in transformers
and load currents for capacitors.
Period length and current waveform are depending
on the characteristics of the power source as well.
Peak current values of 10-50 times the current
value in use and a period length less than 100
ms are expected.
The power line filters inserted on the power lines
entering the equipment room will influence the
initial peak period.
b) S̲t̲a̲r̲t̲ ̲P̲e̲r̲i̲o̲d̲
The start period is defined by the start-up of
AC-motors in the racks.
AC-motors are used in Fan assemblies.
The start period will be in the range 2-20 secs.
c) U̲s̲e̲ ̲P̲e̲r̲i̲o̲d̲
Use period characteristics are the characteristics
of the equipment in normal use after termination
of start-up phenomena.
The power and weight data of the individual racks are
tabulated in fig. 5.3.3.3-2.
The values shall be considered as typical.
FIGURE 5.3.3.3-1…01…S̲t̲a̲r̲t̲-̲u̲p̲ ̲C̲u̲r̲r̲e̲n̲t̲s̲,̲ ̲D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲s̲
CONSUMPTION USE START HEAT AIRFLOW WEIGHT
---------------- CURRENT DISSIPA- M…0e…3…0f…/S KG
POWER, CURRENT, AMP TION W
KVA A
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲
Main Site Equip.
Rack G, J 0,80 3,7 4,0 750 0.06 450
Rack H, I 1,00 4,5 4,8 900 0.06 460
Remote Site Equip.
Rack 0,45 2,0 2,3 500 0,06 450
FIGURE 5.3.3.3-2…01…I̲N̲D̲I̲V̲I̲D̲U̲A̲L̲ ̲R̲A̲C̲K̲S̲,̲ ̲P̲O̲W̲E̲R̲ ̲A̲N̲D̲ ̲W̲E̲I̲G̲H̲T̲…01…T̲Y̲P̲I̲C̲A̲L̲ ̲V̲A̲L̲U̲E̲S̲
5.3.3.4 G̲r̲o̲u̲n̲d̲i̲n̲g̲ ̲o̲f̲ ̲R̲a̲c̲k̲s̲ ̲a̲n̲d̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲i̲n̲ ̲R̲a̲c̲k̲s̲
The panel mounting rails in the racks are mounted insulated.
Thus, all equipment in one rack is grounded together,
but basically insulated from the exterior rack.
A ground-wire connects the rack-mounted equipment to
the rack in one point. This point is connected to the
exterior ground wire connection point.
When more racks are joined to form a multi-bay rack
assembly, they are connected around the joining perimeters
to form one continuous cabinet. In the cabinet the
rack mounted equipment is connected to one common point.
This point is connected to the exterior ground wire
connection point of the cabinet.