DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦2c16593e3⟧ Wang Wps File

    Length: 22428 (0x579c)
    Types: Wang Wps File
    Notes: PC/ATB/002    (Site 02)   
    Names: »2662A «

Derivation

└─⟦2b05c95ac⟧ Bits:30006158 8" Wang WCS floppy, CR 0067A
    └─ ⟦this⟧ »2662A « 

WangText




    2662A/ktd      …02…PC/ATB/002       

…02…HAU/821105…02……02…#
AS-TO-BE-BUILT DRAWINGS
PC SITE 02…02…Issue 1…02… P.C.













                 PROTOCOL CONVERTER
                 AS-TO-BE-BUILT DOCUMENTATION SITE 02
                 CONTRACT SHNMO-82-9205-INF

                 PC/ATB/002














                 Hans Haureberg




                 Kurt Nybroe-Nielsen







                 SHAPE (9), GJ, GT, DL, KPL, SN, JPR, ALF, OE,
                 KM, HAU















                     …0e…     Install. Mgr.   821105

                          Project Mgr.    821105…0f…
             2



             821105





    2662A/ktd                                  PC/ATB/002       

 AS-TO-BE-BUILT DRAWINGS…02…  HAU/821105…02…ii
 PC SITE 02
…02…  2…02…   P.C.














         820812                  All      Issue 1 of document

         821105                All      Issue 2
                                        General update





    2662A/ktd      …02…PC/ATB/002       

…02…HAU/821105…02……02…iii
AS-TO-BE-BUILT DRAWINGS
PC SITE 02…02…Issue 1…02… P.C.






                                      T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



     1 INTRODUCTION .................................  
       1 
       1.1 SCOPE ....................................  
           1 
       1.2 DOCUMENT FORMAT ..........................  
           2 
       1.3 REFERENCES ...............................  
           2 
       1.4 SYSTEM DIAGRAM ...........................  
           2 
       1.5 SITE IMPLEMENTATION SCHEDULE .............  
           2 
       1.6 REGULATIONS ..............................  
           3 

     2 RESPONSIBILITIES .............................  
       3 
       2.1 HOST NATION ..............................  
           3 
       2.2 PC CONTRACTOR ............................  
           4 

     3 PROTOCOL CONVERTER ROOM ......................  
       5 
       3.1 SITE PREPARATION  ........................  
           5 
       3.2 FLOORS ...................................  
           6 
       3.3 EQUIPMENT INSTALLATION ...................  
           7 
       3.4 POWER CONNECTION .........................  
           7 
       3.5 SIGNAL CABLING ...........................  
           7 
         3.5.1 Verification .........................  
               8 
         3.5.2 Conduit Installation .................  
               8 
         3.5.3 Termination of Opto Cables ...........  
               8 
         3.5.4 Termination of Metallic Cables .......  
               9 
         3.5.5 Cable Identification .................  
               9 

       3.6 VENTILATION AND COOLING REQUIREMENTS .....  10
           

     4 MAINTENANCE TERMINAL AND CABLING .............  11
       
       4.1 LOCATION .................................  11
           
       4.2 CABLING ..................................  11
           
         4.2.1 Termination of Opto Cable ............  11
               
         4.2.2 Cable Identification .................  12
               

       4.3 TERMINAL INSTALLATION ....................  12
           
         4.3.1 Power Connection .....................  12
               
         4.3.2 Opto Cable Connection ................  12
               

     5 OTHER CONNECTIONS ............................  13
       
       5.1 INTERCONNECTIONS .........................  13
           
         5.1.1 Cabling and Terminations .............  13
               




    2662A/ktd      …02…PC/ATB/002       

…02…HAU/821105…02……02…iv
AS-TO-BE-BUILT DRAWINGS
PC SITE 02…02…Issue 1…02… P.C.






     6 TABLES .......................................  14
       
       6.1 PHYSICAL DATA ............................  14
           
       6.2 PIN ASSIGNMENT IDF/FILTER BOX ............  14
           
       6.3 POWER CHARACTERISTICS ....................  14
           





     L̲I̲S̲T̲ ̲O̲F̲ ̲T̲A̲B̲L̲E̲S̲                                    
       

     6.1.1   Physical Equipment Data ................  15
             
     6.2.1   Pin Assignment IDF/Filter Box ..........  16
             
     6.3.1   Power Characteristics ..................  17
             




     L̲I̲S̲T̲ ̲O̲F̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲                              Drawing
     No.

     PC INSTALLATION ............................... 01-183

     PC RACK 
     POWER AND CONDUIT INTERFACE ................... 01-184

     PC RACK 
     EXTERNAL SIGNAL CABLE INTERFACE ............... 01-185

     MAINTENANCE VDU 
     POWER AND SIGNAL CABLE INTERFACE .............. 01-186




    2662A/ktd      …02…PC/ATB/002       

…02…HAU/821105…02……02…v
AS-TO-BE-BUILT DRAWINGS
PC SITE 02…02…Issue 1…02… P.C.



                                  D̲E̲F̲I̲N̲I̲T̲I̲O̲N̲S̲/̲A̲B̲B̲R̲E̲V̲I̲A̲T̲I̲O̲N̲S̲



         ACE COMSEC           Communication Security
         Adaptor-Crate        Compartment for modules
         ATBB                 As-To-Be-Built
         Assy                 Assembly
         CAMPS                Computer Aided Message Processing System
         CCIS                 Command and Control Information System
         CR                   Christian Rovsing A/S (Contractor)
         CWR                  Civil Works Requirements
         EMI                  Electro-Magnetic Interference
         Filter Box           Termination and filter box for all electrical signals interfacing with
                              the CAMPS computer
         HN                   Host Nation
         IDF                  Intermediate Distribution Frame, see Filter box
         J-box                Junction-box for cable outlet
         L/L                  Low Level
         PDB                  Power Distribution Board
         PC                   Protocol Converter
         PC-Contractor        Christian Rovsing A/S
         PLF                  Power Line Filter
         SCARS                Status and Control Alerting and Reporting System
         SHAPE                Supreme Headquarters Allied Powers Europe (Customer)
         TBD                  To be defined
         VDU                  Visual Display Unit
         W                    Cable reference number
         WWMCCS               World Wide Military Command and Control System






                     1  I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲



1.1      S̲C̲O̲P̲E̲

         This document specifies the Civil Works Requirements
         related to the Protocol Converter (PC) and shows how
         all the major assemblies of the PC equipment are to
         be installed and integrated.

         The customer (Host Nation) and the PC Contractor (Christian
         Rovsing A/S) are responsible for accomplishing the
         works as specified in this document.

         After review and approval by SHAPE and ACE COMSEC,
         the document will be the baseline for the site preparation
         and installation effort.

         The enclosed As-To-Be-Built drawings will be updated
         after the installation is completed to reflect the
         AS-BUILT situation. Any change made to the ATBB drawings
         during installation must be approved by ACE COMSEC
         and SHAPE.

         The preparation of this document is based on the site,
         data collected by SHAPE and given to CR per CAMPS log
         723 PC: 011.



1.2      D̲O̲C̲U̲M̲E̲N̲T̲ ̲F̲O̲R̲M̲A̲T̲

         This document is structured in the following sections:

         Section 1   Introduction
         Section 2   Responsibilities
         Section 3   PC Room
         Section 4   Maintenance Terminal and Cabling
         Section 5   Other Interconnections
         Section 6   Tables

         Sections 1 to 5 provide a brief description of the
         drawings in section 6. Section 6 contains typical equipment
         data.



1.3      R̲E̲F̲E̲R̲E̲N̲C̲E̲S̲

         PROTOCOL CONVERTER/HARDWARE ASSEMBLY BREAKDOWN
         Document Ref.: TBD

         This document will assist the installation team in
         reassembling the PC equipment after transportation
         to the site.



1.4      S̲Y̲S̲T̲E̲M̲ ̲D̲I̲A̲G̲R̲A̲M̲

         Drawing 1-183 lists all the CR provided equipment at
         site 02, shows the system signal cabling and also defines
         the basic responsibilities for this cabling.

         The PC equipment assembly is identified with a unit
         number and all interconnecting signal cables with a
         cable reference number (W).

         Cable numbers are also allocated for the auxiliary
         connections to be provided by Host Nation.



1.5      S̲I̲T̲E̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲

         The PC equipment will be delivered to site and installed
         together with the CAMPS equipment for mainsite 06.
         The CAMPS mainsite 06 installation is scheduled to
         start 1983.

         The following site implementation schedule is planned:

         September, 1982    Issue of As-To-Be-Built Drawings
         January, 1983      Site Preparation Works Completed
         February, 1983     Site Verification Completed
         March, 1983        Start of Installation



1.6      R̲E̲G̲U̲L̲A̲T̲I̲O̲N̲S̲

         a)  The converter installation shall conform with the
             relevant requirements for automatic processing
             devices contained in AMSG 719B.

             The modification of the converter equipment room
             for equipment installation with regard to power,
             ground, ground distribution, signal cabling, airconditioning
             etc. must, therefore, be carried out in accordance
             with AMSG 719B.

         b)  The power and ground installation is governed by
             national power and safety regulations.









                   2  R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲

         The following responsibilities and interfaces are defined
         for site preparation and site integration of the PC
         system (ref. drawing 1-183).



2.1      H̲O̲S̲T̲ ̲N̲A̲T̲I̲O̲N̲

         Host Nation is responsible for:

         a)  Modifying the allocated PC equipment room for installation
             of the converter equipment (i.e. power, grounding
             distribution, airconditioning etc). See chapter
             3 and drawing 01-183.

         b)  Providing and installing all conduits/cable trays
             for signal cables in the PC equipment room. See
             chapter 3.

         c)  Preparing the appropriate rooms for the maintenance
             terminal installation. See chapters 3 and 4 and
             drawing 01-183.



         d)  Determining routing and providing and installing
             all ducts/cable trays for signal cables between
             the maintenance terminal position and the PC rack.

         e)  Providing and installing the interconnecting cables
             between the PC IDF and other systems/equipment.
             
         
             PC Contractor will terminate the cables in the
             PC IDF. Host Nation will terminate the other end.
             See chapter 5.



2.2      P̲C̲ ̲C̲O̲N̲T̲R̲A̲C̲T̲O̲R̲

         The PC Contractor is responsible for:

         a)  Providing, installing, and terminating the optofibre
             cable for the maintenance VDU.

         b)  Physical installation of all PC Contractor provided
             equipment in the equipment room.

         c)  Connecting power and ground to all PC Contractor
             provided equipment.

         d)  Termination and connection of all signal cables
             to PC Contractor provided equipment.











                3  P̲R̲O̲T̲O̲C̲O̲L̲ ̲C̲O̲N̲V̲E̲R̲T̲E̲R̲ ̲R̲O̲O̲M̲

         This section describes the PC rack installation in
         room cc24.

         See drawing 1-183.



3.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲

         The preparation works by Host Nation include:

         -   Distribution of power to the J-box below the PC
             rack as specified on drawing 01-183.

         -   Filtered (pink) power 220V/50Hz with the characteristics
             per table 6.3.1 is required.

         -   Installation of signal cables and ducts up to (below)
             the PC rack. The ducts will be terminated in J-boxes
             to suit the CR conduit installations. See drawing
             1-184.

         -   All signal cables are to be temporarily labelled
             with the allocated cable reference number (W) and
             left with a length of 3 meters outside the cable
             ducts/J-boxes to reach the connection points inside
             the rack. See drawings 1-183 and 1-184.

         -   Plinth cutout below the PC-rack for cable entry
             as specified below.

         The Site preparation by Host Nation concerning PC-equipment
         installation will be inspected by CR as part of the
         CAMPS mainsite 06 verification.



3.2      F̲L̲O̲O̲R̲S̲

         a)  The PC-rack requires bottom cable entrance.

             The PC-rack is, therefore, to be installed on a
             plinth or in a room with false floors. The minimum
             height of the false floor/plinth must be 250 mm
             (see drawing 1-184).

         b)  The equipment load calculated from table 6.1.1
             will be:

              ̲ ̲ ̲3̲5̲0̲ ̲ ̲ …0f…= 470 kg/m…0e…2
             1.2x0.62

             The distributed load is considerably lower. If
             a work space of 1.3 m in front and 1 m at rear
             is included the load will be:

              ̲ ̲ ̲3̲5̲0̲ ̲ ̲ …0f…= 161 kg/m…0e…2
             3.5x0.62

             Adding personnel (2x75 kg) and test equipment (50
             kg) the distributed load will be: 254 kg/m…0e…2…0f….

         c)  The required floor cutout for cable entry to the
             PC-rack is shown on drawing no 1-184.

             Note that the PC-rack has 4 levellers of [ 30 mm,
             which are located close to the penetrations. The
             design load from each leveller is 90 kg concentrated
             load.…86…1         …02…   …02…   …02…   …02…                      
                                 
3.3      E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         See drawing 1-184.

         The EMI shielded PC rack will be shipped as assembled
         at the CR plant.

         Equipment data - see table 6.1.1.

         The four levelers at the bottom of the rack are to
         be adjusted to ensure equal weight distribution.

         The internal rack cabling required at the site is shown
         in ref (1), The Hardware Assembly Breakdown.



3.4      P̲O̲W̲E̲R̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲O̲N̲

         See drawing 1-184.

         The installation team will provide and install the
         metallic conduit between the power J-box below the
         rack and perform the equipment power connection.

         Note that the ACE COMSEC approved grounding concept
         requires the metallic power conduit to be in electrical
         contact with the PC rack only. The power conduit, therefore,
         is to be insulated from the filtered PDB.

         The power cable and the insulated secure/safety ground
         will be connected to the PLF on the front of the rack.

         Drawing 1-184 gives details of the conduit installation
         and the termination of the different power wires in
         the PLF.



3.5      S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲I̲N̲G̲

         This sub-section describes all external signal cables
         interfaced to the PC rack.

         The interface for metallic cables to the IDF/Filter
         box is described in para 3.5.4.





3.5.1    V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         The metallic cables for the interconnections to the
         PC Filter Box are planned to be installed by Host Nation
         prior to the start of the CR installation. These cables
         will be temporarily labelled with the designated cable
         number for identification. Verification inspection
         information will be contained in the Site Verification
         Report.



3.5.2    C̲o̲n̲d̲u̲i̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         CR will provide and install the signal cable interface
         conduits required for the IDF/Filter box.

         See details on drawing 1-184.

         The ferrous duct for the metallic cables will be electrically
         connected to the PC rack via the interface conduit.



3.5.3    T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲s̲

         The opto cable passes through the IDF/Filter box and
         terminates into an individual opto module in the front
         of the adapter-crate. See drawing 1-185.

         The adapter-crate reference number is tabulated in
         drawing 1-183. Drawing 1-185 shows the location of
         the opto and L/L adapter modules, internal rack cabling
         and details of the opto cable termination in the opto
         module.

         The opto cable consists of two fibres, one white -
         one black. At the PC rack interface, the white fibre
         is dedicated for receive signals and will be connected
         to the jack marked "in" on the opto modules. The black
         fibre accordingly has been dedicated for transmit signals
         and si to be connected to the "out" jack.

         The opto fibres will be terminated by CR.





3.5.4    T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲M̲e̲t̲a̲l̲l̲i̲c̲ ̲C̲a̲b̲l̲e̲s̲

         The metallic cable interface point is the Filter box
         located at the rear bottom of the PC rack. See drawing
         1-184 and -185.

         Cable entry is via port 3 in the bottom of the rack.

         CR will provide connector and terminate the interface
         cables at the filter box.

         The metallic cables are provided and installed by Host
         nation.

         The filter box is equipped with 25 pin connectors as
         specified in drawing 1-185.

         Mating connector type and pin assignments/wire lists
         for the different types of channels is specified in
         table 6.2.1.

         The jackfield layout and details of the connector installation,
         including the required cable shield grounding, are
         shown in drawing 1-185.



3.5.5    C̲a̲b̲l̲e̲ ̲I̲d̲e̲n̲t̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         All external interface cables to the PC rack will be
         permanently labelled with their allocated cable ref
         No (WXX) by PC contractor.

         To facilitate the identification of the cables, the
         labels will be installed close to the connectors.



3.6      V̲E̲N̲T̲I̲L̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲C̲O̲O̲L̲I̲N̲G̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         a)  As all rack mounted equipment has internal blowers
             using ambient room air for forced ventilation,
             the CAMPS system does not require any direct cooling.

         b)  The equipment is designed to operate in a closed
             environment with a temperature range of 10…0e…o…0f…C to
             40…0e…o…0f…C and with a max change in temperature of 10…0e…o…0f…C
             per hour.

         c)  Ambient room air for forced ventilation is drawn
             into the crate assemblies through the filters in
             the front doors. The air is deflected upwards and
             leaves the cabinet through the top panel grills
             (see fig. 3.6.1).

         d)  Data for the heat dissipation of the equipment
             is found in table 6.1.1.




























               Fig. 3.6.1…01…PC Rack Air Flow



           4  M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲ ̲A̲N̲D̲ ̲C̲A̲B̲L̲I̲N̲G̲

         This section describes the installation of the VDU
         allocated as the maintenance terminal.

         Drawing 1-183 identifies the maintenance terminal by
         unit number, designated cable number, and room location.



4.1      L̲O̲C̲A̲T̲I̲O̲N̲

         The location of the terminal as shown in drawing 1-183
         has been specified by local command.

         The Host Nation preparation works related to the maintenance
         terminal include:

         -   Provision of power and ground for the terminal
             position as per drawing 1-186.

         -   Provision of terminal table/trolley.



4.2      C̲A̲B̲L̲I̲N̲G̲

         The opto cable, protected by a rubber tube, will be
         run by PC contractor along the wall above the false
         floor in order to make the trolley movable.

         Contractor will terminate and connect the opto cable.



4.2.1    T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲

         See drawing 1-176.

         The opto-cable leaves the PC rack through the port
         1 waveguide as shown. The opto cable will be protected
         against physical damage by a rubber grommet or similar
         device and enters the VDU via the waveguide port. 



         The opto cable connection to the optical modem card
         is shown in drawing 01-186. The white fibre is to be
         connected to the transmitter jack ("out") of the opto
         module and the black fibre to the receive jack ("in").



4.2.2    C̲a̲b̲l̲e̲ ̲I̲d̲e̲n̲t̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         Permanent cable identificaton labels at the rear of
         the terminal are to be installed as described in para
         3.4.5 and as indicated in drawing 1-186.



4.3      T̲E̲R̲M̲I̲N̲A̲L̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         The terminal is to be installed on a Host Nation provided
         table/trolley. See drawing 1-183.



4.3.1    P̲o̲w̲e̲r̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲

         See drawing 1-186.

         The VDU has plug connection. The terminal plug may
         need to be replaced by CR to fit Host Nation standard
         outlets.

         The power outlet will be switched or unswitched as
         required by local regulations. A 3 pin outlet with
         line, neutral, and safety ground is required as specified
         on drawing 1-183.



4.3.2    O̲p̲t̲o̲ ̲C̲a̲b̲l̲e̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲

         See drawing 1-186.





                5  O̲T̲H̲E̲R̲ ̲I̲N̲T̲E̲R̲C̲O̲N̲N̲E̲C̲T̲I̲O̲N̲S̲

         This section describes the connection of other systems
         requiring an electrical signal interface to the PC.



5.1      I̲N̲T̲E̲R̲C̲O̲N̲N̲E̲C̲T̲I̲O̲N̲S̲

         As seen from the system diagram drawing 1-183, the
         following connections are applicable for site 02:

         a)  PC - CAMPS
         b)  PC - CAMPS spare
         c)  PC - WWMCCS
         d)  PC - WWMCCS spare



5.1.1    C̲a̲b̲l̲i̲n̲g̲ ̲a̲n̲d̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲s̲

         Host Nation is responsible for all cabling out of the
         PC IDF/Filter box.

         Pin assignment and wire lists for the different types
         of channels are specified in table 6.2.1.

         Cable terminations in the IDF/Filter box are shown
         in drawing 1-185. CR will terminate and connect all
         cables in the IDF.





                        6  T̲A̲B̲L̲E̲S̲

         This section contains PC equipment data and electrical
         signal interface requirements.



6.1      P̲H̲Y̲S̲I̲C̲A̲L̲ ̲D̲A̲T̲A̲

         Table 6.1.1 gives equipment size, weight, access requirements,
         and heat dissipation.



6.2      P̲I̲N̲ ̲A̲S̲S̲I̲G̲N̲M̲E̲N̲T̲ ̲I̲D̲F̲/̲F̲I̲L̲T̲E̲R̲ ̲B̲O̲X̲

         Table 6.2.1 gives recommendation as to type of mating
         connector for the metallic cable interface in the filter
         box and specifies the pin assigment and signal reference.



6.3.1    P̲O̲W̲E̲R̲ ̲C̲H̲A̲R̲A̲C̲T̲E̲R̲I̲S̲T̲I̲C̲S̲

         Table 6.3.1 gives the input power characteristics for
         the PC equipment.



















 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                       SIZE        WEIGHT      POWER       
  HEAT
                       (cm)         (kg)    CONSUMPTION    DISSIPATION
 D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲ ̲ ̲ ̲ ̲W̲i̲d̲t̲h̲ ̲D̲e̲p̲t̲h̲ ̲H̲e̲i̲g̲h̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲K̲W̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲(̲K̲c̲a̲l̲/̲h̲)̲ ̲ ̲ ̲

 P.C. Rack     62   120   180     350       1.200          1500

 VDU           48    76    43      40       0.250           220
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲















              Table 6.1.1…01…Physical Equipment Data










 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲

    FILTERBOX CONNECTOR J26-J30             RECOMMENDED WIRING
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲O̲F̲ ̲I̲N̲T̲E̲R̲F̲A̲C̲E̲ ̲C̲A̲B̲L̲E̲
 ̲ ̲

  PIN  CIRCUIT                              CAMPS          WWM
  
 ̲ ̲N̲O̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲C̲C̲S̲
 ̲ ̲

        2    103                            Transmitted
                                            Data   X             X
        3    104                            Recieved
                                            Data   X             X
        4    105                            Request
                                            to Send                 X
        5    106                            Clear to
                                            Send                 X
        6    107                            Data Set
                                            Ready  X             X
        7    102                            Signal
                                            GND    X             X
        8    109                            Data Carrier
                                            Detect               X
       15    114                            Transmitter
                                            Clock                X
       17    115                            Receiver
                                            Clock  X             X
       20    108/2                          Data Terminal
                                            Ready  X             X
       24    113                            Transmitter
                                            Clock  X             
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                                        NOTE                     LEGEND
                                        SIGNAL REFERENCE:
                                        28L - V24                X
                                                                 -
                                                                 REQUIRED
                                                  
                                               18 PIN
                                         9600 bd  













    Table 6.2.1…01…Pin Assignment IDF/Filter Box



         The PC equipment is designed to comply with the following
         power characteristics.

         P̲o̲w̲e̲r̲ ̲I̲n̲p̲u̲t̲

         Phase:                Single- or 3-phase, and ground
                               (*)

         Voltage:              Nominal value:    380/220V AC
                                    
                               Tolerances:       +10%/-15%

         Frequency:            Nominal value:    50Hz
                               Tolerances:       + 10%/-10%

         Harmonic distortion:  Max 5%

         Transients:           Non-repetitive impulsive interference
                               with a magnitude not to exceed
                               500 volts, pulse rise and fall
                               times not faster than 10 microseconds
                               and a total duration of maximum
                               1 millisecond.The available impulse
                               energy at the equipment power
                               inlet should not exceed 5J.

         (*) The PC equipment requires only single phase 
             circuits from the PC PDB.












                       Table 6.3.1
                  Power Characteristics