⟦37ff4fa30⟧ Wang Wps File

    Length: 23071 (0x5a1f)
    Types: Wang Wps File
    Notes: PROGRESS MEETING NO.21    
    Names: »4532A «

Derivation

└─⟦e27572af5⟧ Bits:30006187 8" Wang WCS floppy, CR 0422A
    └─ ⟦this⟧ »4532A « 

WangText




…02…           

…02…KNN/840125…02……02…#
PROGRESS MINUTES
 OF MEETING NO.
 21
…02……02…CAMPS









                           
…02……02……02……02…          …02……0f……0f…84-01-25…02… 21.…02…CR A/S…0e……0e…
                                            

          Progress Minutes of Meeting No. 21 held at
          CHRISTIAN ROVSING A/S 25th January 1984


…0f……0f…SHAPE…0e……0e…

Ltc. H.Hofmann             Mr. K. Nybroe-Nielsen                 GQAR
Mr.  A. Gardiner           Mr. Uffe R. Holst
Mrs. Michel                Mr. Ole Eskedal                       
Mr.  Lohisse          Mr. J. Holm                
                           Mr. Jan Lauridsen     
                           Mr. Ib Johansen
                           QA  B. Strandtoft



         1.  S̲W̲ ̲T̲e̲s̲t̲ ̲R̲e̲p̲o̲r̲t̲s̲

             CR agreed to forward a weekly status report
             on SW integration and test. SHAPE stated
             that CR did not have to forward the SW
             Development Status Report any more.

         2.  E̲r̲r̲o̲r̲ ̲R̲e̲p̲o̲r̲t̲s̲

             SHAPE requested that a summary of the
             SW error reports were forwarded to SHAPE.
             SHAPE would appreciate a summary with
             number of new errors, number of corrected
             errors and number of outstanding errors
             which was necessary to follow the progress
             of the program. CR will evaluate the request
             (see item 7).

             CR invited SHAPE to evaluate the CR internal
             error reports.

         3.  M̲S̲P̲ ̲S̲o̲l̲u̲t̲i̲o̲n̲s̲ ̲a̲n̲d̲ ̲R̲e̲t̲r̲o̲f̲i̲t̲ ̲P̲l̲a̲n̲

             Solutions to the three TRACOR MSP problems
             (initial character lightness (printhead),
             keystatus/optical modem, power lamp short
             life) were presented to SHAPE. SHAPE was
             satisfied by the presented solution.

         4.  D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲R̲e̲v̲i̲e̲w̲

         4.1 S̲i̲t̲e̲ ̲L̲e̲v̲e̲l̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲M̲a̲n̲u̲a̲l̲

             a)  SHAPE will review the manual with
                 respect to incorporation of items
                 stated in MOM No. 19 item 13. Comments
                 will be forwarded to CR before Feb.1st,
                 1984 with cat.1 approval of the document,
                 provided that above mentioned items
                 are incorporated in principle.



             b)  Errors identified prior to 1st February
                 and later up to 2 months before SPA1
                 will be incorporated in next issue
                 of the maintenance manual.

             c)  The manual will be delivered to SHAPE
                 for print approval and subsequently
                 be submitted at SPA.

             d)  Errors detected later will be covered
                 by the DCN activity on a regular basis.


         4.2 M̲M̲D̲ ̲H̲/̲W̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲M̲a̲n̲u̲a̲l̲,̲ ̲I̲s̲s̲u̲e̲ ̲2̲,̲ ̲8̲3̲0̲6̲1̲4̲

             a)  On page 2-63 "Repair and Replacement"
                 CR will include page number of the
                 referenced Replacement Procedures.

             b)  Related to Applicable Documents on
                 page 2 of the cover sheets  and the
                 title at the actual referenced documents
                 CR will include "MMD" to the already
                 specified documents.

             c)  When updated the MMD manual will be
                 in cat. 1.


         4.3 F̲r̲e̲q̲u̲e̲n̲c̲y̲ ̲S̲t̲a̲b̲i̲l̲i̲z̲e̲r̲

             a)  The enclosure for the letter LU/ktd/LET/0520,
                 1983-08-23 are photos to be included
                 in the Frequency Stabilizer Manual,
                 Issue 2, 830301. Mr. Bentley will
                 check the quality.

             b)  SHAPE will consider it as change pages
                 and upon insertion of changes pages
                 in subject manuals SHAPE will review
                 and make a decision on approval.


         4.4 S̲t̲a̲t̲.̲M̲u̲x̲.̲ ̲M̲a̲n̲u̲a̲l̲s̲

             a)  SHAPE will check the drawings' quality
                 to be included in the Stat.Mux.Maintenance
                 Manual. The drawings to be included
                 in the manual are enclosed the letter
                 ref: LU/aml/LET/0564, 1983-12-06.

             b)  CR will forward a new issue of the
                 Stat.Mux.User's Manual incl. enlarged
                 photos in improved print quality.




         4.5 P̲T̲R̲/̲P̲ ̲a̲n̲d̲ ̲V̲I̲I̲/̲V̲2̲8̲ ̲L̲/̲L̲ ̲A̲d̲a̲p̲t̲o̲r̲ ̲M̲a̲n̲u̲a̲l̲s̲

             a)  CR will include the two manuals in
                 the same binder.

             b)  The manuals will include a cover sheet
                 describing the trouble shooting procedure
                 to test the combination of the PTR/P
                 and L/L Adaptor.

             c)  Tools and Test Equipment, and test
                 procedures which are not applicable
                 to CAMPS will be crossed out.


         4.6 N̲u̲m̲b̲e̲r̲i̲n̲g̲ ̲o̲f̲ ̲M̲a̲n̲u̲a̲l̲s̲

             SHAPE accept that CR will keep the existing
             document numbering of the manuals and
             handbooks in CAMPS.

         5.  U̲s̲e̲r̲ ̲M̲a̲n̲u̲a̲l̲s̲ ̲a̲t̲ ̲S̲i̲t̲e̲s̲

             On SHAPE request CR agreed to deliver
             an updated user manual 2 weeks after start
             of the 240 hours test.

             After review and acceptance by SHAPE,
             CR will print the contractual required
             number for distribution. SHAPE requested
             that the CAMPS System Description Manual
             (CPS/SDM/001) and the CAMPS User Manual
             were distributed to the sites before the
             SPA, as fast as possible after SHAPE approval.

             CR agreed to evaluate the request and
             forward an answer within 2 weeks.


         6.  R̲e̲l̲a̲y̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲

             CR will produce test procedures to verify
             the relay function. CR agreed to deliver
             the test procedures at the latest one
             week after start of the 240 hours test.

             The in plant verification will be executed
             just after completion of the 240 hours
             test, if the test procedures at that time
             are approved by SHAPE.

             It is emphasized that test of the relay
             function is not part of the 240 hours
             test, but that the relay function will
             be formally tested during the functional
             test.



             The operational verification will take
             place simulated during the 3rd period
             of the operational test and live once
             3 CAMPS sites are operational and interlinked.
             Prior to SHAPE SPA all other related ICDs
             and design documents will be updated and
             sent to SHAPE for approval.

         7.  A̲l̲g̲o̲r̲i̲t̲h̲m̲ ̲t̲o̲ ̲c̲o̲u̲n̲t̲ ̲M̲D̲S̲D̲

             On SHAPE request, CR agreed to deliver
             the SW error rate versus time throughout
             the Syst I&T phase. From that point in
             time when all SW has been integrated and
             tested. CR will split the data into the
             error categories as defined in the 240
             hours test (cat. 1, 2, 3, cosmetic).

             CR will deliver this information only
             on an informal basis. CR stated that delivery
             of MDSD or calculation of the MDSD is
             not part of the contractual deliveries.

             In reply SHAPE referred to the acceptance
             test plan 4.6.5 last clause and CAMPS
             System Requirements 4.2.2.2d.

             SHAPE requires that these data shall be
             used as a parameter for reliability prediction
             and wants to know, how CR intends to calculate
             the MDSD probability. CR stated that in
             line with MOM 39, item 10, CR will deliver
             the methods and results of the calculation
             2 days before the start of the 240 hours
             test.


         8.  V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

             SHAPE proposes that CR representative,
             in cooperation with SHAPE's RST, shall
             verify procedures in the Maintenance Manual.
             This activity will take place at SHAPE.

             CR in principle agrees to allocate manpower
             resources, max. duration 1 week, and will
             inform SHAPE of schedule and furhter planning
             details. The mutually agreed errors and
             omissions will be incorporated in the
             Maintenance Manual.




         9.  N̲a̲v̲s̲o̲n̲a̲r̲ ̲Q̲u̲o̲t̲a̲t̲i̲o̲n̲

             Ref: CAMPS tlx. 1040.
             The quotation validity date is extended
             until 1st February 1984.


         10. M̲e̲r̲d̲a̲n̲ ̲G̲r̲o̲u̲p̲ ̲I̲n̲c̲.̲ ̲S̲u̲p̲p̲o̲r̲t̲

             Ref: Let. 84-3135 dated 12th January.

             CR stated that the level of work caused
             by the request in the referenced letter
             was undefined. CR agreed to support the
             Merdan Group Inc. with information, if
             the work level is limited to a half-day
             meeting at CR.


         11. S̲i̲t̲e̲ ̲L̲e̲v̲e̲l̲ ̲D̲a̲t̲a̲b̲a̲s̲e̲

             Actually the site data are on input sheets
             in card image format. SHAPE and CR decided
             that the most efficient way could be found
             to load the site data on CAMPS, among
             the 3 alternatives.

             1.  Using punched cards.

             2.  Using a disk pack.

             3.  Convert punched cards into tape.

             CR and SHAPE agreed that a "dry run" of
             the procedure for forwarding the site
             level database should be executed within
             2 weeks. The "dry run" should be:

             a.  SHAPE forwards punched cards for one
                 site to CR.

             b.  CR transfers the punched card to magnetic
                 tape at CR.

             c.  The site level database is controlled
                 and verified with the validation program
                 at CR. SHAPE will be provided a list
                 of inconsistencies.

             SHAPE is willing to try to use the CAMPS
             system at SHAPE to store data for one
             site on to a disk pack. The disk pack
             will then be sent to CR, the data will
             be loaded on CAMPS and a list of inconsistences
             will be provided by CR to SHAPE. CR will
             provide SHAPE the disk pack and the necessary
             support software to input and store the
             data.



             After these two trials, CR and SHAPE will
             define which is the most suitable way
             to load the site data on to the CAMPS
             system.

             The schedule shall be: 

             Week 5: SHAPE will send punched cards
                     for a big site (if possible by
                     courier).

                     SHAPE will return by telex responding
                     on the feasability to use the
                     disk solution.

             Week 6: CR will convert punched cards
                     into tape and generate a database
                     (including validation) and return
                     result to SHAPE.

                     SHAPE will to the best of their
                     ability try to produce a tape
                     on the same site data and submit
                     it to CR.


         12. T̲R̲W̲ ̲D̲a̲t̲a̲ ̲D̲i̲s̲c̲l̲o̲s̲u̲r̲e̲

             SHAPE had no status on this issue as requested
             in the previous progress minutes.


         13. P̲a̲y̲m̲e̲n̲t̲s̲

             CR is constantly seeing delay in payments
             of our substantial amount of money. CR,
             therefore, insist on close this issue
             within the month of January 1984.


         14. T̲R̲W̲ ̲v̲i̲s̲i̲t̲ ̲t̲o̲ ̲C̲R̲

             CR welcomed that a TRW engineer from the
             certification team visited CR to get technical
             clarification and information.


         16. J̲a̲c̲q̲u̲e̲s̲ ̲W̲e̲l̲l̲e̲k̲e̲n̲s̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲t̲i̲o̲n̲ ̲o̲n̲ ̲R̲S̲T̲3̲
             ̲C̲o̲u̲r̲s̲e̲

             SHAPE requested that JW should attend
             2 x 2 weeks of RST Course No. 3.

             SHAPE will forward a list of subjects
             which is needed for the student.



             CR shall provide a schedule for 2 x 2
             weeks of the training which shall include
             as much as possible of the subjects defined
             by the SHAPE message to CR.


         17. S̲t̲u̲d̲e̲n̲t̲s̲ ̲o̲n̲ ̲R̲S̲T̲3̲ ̲C̲o̲u̲r̲s̲e̲

             Reference: CPS/101/tlx/1113.

             CR raised the notice to SHAPE (please
             refer to the last item in referenced telex)
             regarding the performance of two students
             on the RST3 Course. It is CR's opinion
             that the students will not be able to
             pass the course with a result satisfying
             the requirements. However, CR is willing
             to let the students remain on the course,
             but will teach the course in accordance
             with normal student capability.

             SHAPE will investigate the situation with
             the host nations.


         18. T̲r̲a̲i̲n̲i̲n̲g̲ ̲a̲t̲ ̲N̲C̲S̲-̲L̲a̲t̲i̲n̲a̲

             SHAPE has informed CR that according to
             NCS instructors it will not be possible
             to conduct the training at NCS by NCS
             instructors subsequent to MT9, mainly
             because of insufficient hands-on experience
             with the total system.

             CR suggested the following solution:

             -   SPA of NCS-Latina is advanced to immediately
                 after SPA of Site 1, and instead of
                 one CR-instructor conducting the 7
                 weeks MT9 course, CR will send two
                 instructors for 4 weeks to tutor the
                 NCS instructors in use of the equipment
                 and its repair, and solve all training
                 issues applicable within this timeframe.
                 This takes place after SPA of the
                 site.

             -   When the CR-instructors have left
                 NCS, the NCS- instructors will have
                 the time up to MT9 to become familiar
                 with the system in detail.

             -   NCS-instructors will then do the MT9
                 course alone.

                 SHAPE will investigate the suggestion
                 and reply CR. If SHAPE finds the suggestion
                 in order, CR shall provide a schedule
                 for the implementation.



                 A possible outcome of the suggestion
                 is that it may be necessary to postpone
                 the depot level training at CR to
                 obtain instructor availability to
                 do as suggested.

                 SHAPE will investigate this possibility
                 and answer CR.


         19. P̲r̲e̲f̲o̲r̲m̲a̲t̲t̲e̲d̲ ̲M̲e̲s̲s̲a̲g̲e̲s̲

             CR will implement for the inplant SW test
             the six preformatted messages already
             delivered in December 1982. In order to
             provide more background information SHAPE
             provide CR with additional documentation
             as follows:

             1)  A Dat P-3 Vol 2-5

             2)  ACE Directive 80-50 Vol 3 (ACE-REP)

             Before the Operational Test CR and SHAPE
             will use the tools for preformatted message
             production to generate and include in
             an operational system a number of messages
             chosen from the above documents.


         20. S̲R̲S̲/̲I̲C̲D̲ ̲U̲p̲d̲a̲t̲e̲ ̲-̲ ̲E̲C̲P̲ ̲3̲8̲

             CR pointed out that it is urgent to review
             these updates as they form the baseline
             for the acceptance testing.

             SHAPE is willing to continue to be cooperative
             and intends to review these updates as
             soon as possible.


         21. 2̲4̲0̲ ̲H̲o̲u̲r̲ ̲T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲ ̲(̲C̲P̲S̲/̲T̲P̲R̲/̲0̲0̲7̲)̲

             CAMPS log 1559 was reviewed and discussed
             as follows:

             a)  No disagreement.



             b)  Preformatted messages.

                 The six examples of preformatted messages
                 provided by SHAPE will be used as
                 follows:

                                       user 1       user
                                                    2            user
                                                                 3

                             Test case 6            
                                                    
                                                    1            
                                                                 
                                                                 2 
                                                                   
                                                                   1

                             Test case 9            
                                                    
                                                    3            
                                                                 
                                                                 4 
                                                                   
                                                                   3

                             Test case 26           
                                                    
                                                    5            
                                                                 
                                                                 6 
                                                                   
                                                                   5


             c)  User Deletion of messages

                 A message is stored by SAR after termination
                 of the Prepare New Message transaction
                 by selection of either Release or
                 Coordinate in format A3. This stored
                 First Draft can be retrieved but not
                 altered in any way. It is therefore
                 not in a stage of preparation and
                 thus cannot be deleted by the user.

             d)  ECP 38 presented to SHAPE for review
                 (see item 20) contains proposals for
                 procedural changes in supervisory
                 message handling functions. TPR/007
                 is consistent with these proposed
                 changes.

         22. L̲o̲a̲d̲ ̲T̲e̲s̲t̲ ̲D̲e̲m̲o̲n̲s̲t̲r̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲S̲R̲S̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

             CR explained to SHAPE how the performance
             requirements of SRS para 3.4.1 are to
             be verified during in plant SW test. The
             following agreement was reached:

             1)  Para 3.4.1.2-5 will be verified as
                 defined in MOM 20 para 22.

             2)  Para 3.4.1.6 timing requirements will
                 be verified using a special test set-up.
                 SHAPE shall await the Technical note
                 defining the test set up.

             3)  Para 3.4.1.7 cannot all be verified
                 through the DSMT HW test and FAT site
                 1-16. In particular para 3.4.1.7 will
                 be verified by outgoing data declarations.

             4)  Para 3.4.1.8-10 can be verified as
                 defined in MOM 20 para 22.




         23. B̲a̲n̲k̲ ̲G̲u̲a̲r̲a̲n̲t̲e̲e̲ ̲o̲n̲ ̲C̲A̲M̲P̲S̲

             CR informed SHAPE that the bank guarantee
             on the CAMPS contract in Handelsbanken
             will be transferred to a similar bank
             guarantee in Privatbanken.

             CR agreed to forward information about
             Privatbanken together with information
             of the rating of the bank.

             CR will investigate which invoices and
             costs of the bank guarantee for the past
             which have to be reimbursed by SHAPE.

             CR agreed to forward a description of
             the guarantee transfer between the banks
             including details of the role of Eksportkreditr>det
             .

             CR agreed to forward details of the cost
             impact for SHAPE.

         24. S̲t̲a̲t̲u̲s̲ ̲o̲f̲ ̲P̲a̲y̲m̲e̲n̲t̲s̲

             Ref. letter log 1564.
             The referenced letter was discussed in
             detail. The conclusion of each issue is
             as follows:

             Invoice No. 30756: Payment received by
             CR on 24 January

             Invoice 25958. CR will forward creditnote
             for D.Kr. 5,621.90.

             Invoice 30963. SHAPE will forward the
             proof of payment.

             Invoice 30611. SHAPE will forward the
             proof of payment.

             Invoice 30619. CR has received payment.

             Invoice 34569. CR will forward a credit
             note for D.Kr. 300,000.-. SHAPE has effected
             all other payment on this invoice.

             Invoice 31173. CR will check when the
             payment is received.

             Invoice 34567. Payment received by CR
             on 11th January.

             Invoice 34577. Missing payment in process
             for payment by SHAPE.



             Invoice 35752. SHAPE will provide evidence
             for payment.

             Invoice 35755. SHAPE has payment in process.

             Invoice 36808 and 36807. Payment has been
             received by CR.

             Invoice 25945. SHAPE will investigate
             the invoice.

             CR will appreciat very much, if SHAPE,
             on an informal basis will fill out the
             "SHAPE Payments Sheet" attached in appendix
             B, and forward it on a monthly basis e.g.
             at the progress meetings. SHAPE agreed
             to do this.


         25. C̲R̲ ̲u̲s̲e̲ ̲o̲f̲ ̲F̲u̲t̲u̲r̲e̲ ̲S̲H̲A̲P̲E̲ ̲P̲r̲o̲p̲e̲r̲t̲y̲ ̲f̲o̲r̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲
             ̲a̲n̲d̲ ̲T̲e̲s̲t̲i̲n̲g̲

             CR put SHAPE's attention to PMOM No. 15
             item 10.
             SHAPE does not accept CR's position.

         26. E̲C̲O̲ ̲F̲o̲r̲m̲

             To accomplish CR action item No. 291 the
             HW ECO Form is attached as appendix C.
             SHAPE will review the form for approval.

         27. D̲r̲a̲f̲t̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲ ̲U̲p̲d̲a̲t̲e̲

             SHAPE forwarded a draft contract update,
             attached as Appendix D. CR will review
             and comment.

         28. C̲A̲M̲P̲S̲ ̲V̲i̲d̲e̲o̲ ̲T̲a̲p̲e̲

             SHAPE presented the complete Video tape
             produced for the purpose of introduction
             of ACE Senior Officers to CAMPS. CR has
             been pleased with the content and the
             quality.

















                   APPENDIX A
                  ************


         6.2 T̲E̲S̲T̲ ̲C̲L̲O̲C̲K̲

         6.2.1   G̲e̲n̲e̲r̲a̲l̲

             A single reference test clock shall be
             provided in the test room with a visible
             start/stop mechanism. The clock shall
             be started and stopped in accordance with
             the test criteria outlined below. In addition,
             3 independent test logs shall be provided,
             one by error category.

         6.2.2   C̲l̲o̲c̲k̲ ̲a̲n̲d̲ ̲L̲o̲g̲ ̲B̲e̲h̲a̲v̲i̲o̲u̲r̲ ̲f̲o̲r̲ ̲a̲n̲ ̲E̲r̲r̲o̲r̲
                 ̲O̲c̲c̲u̲r̲r̲a̲n̲c̲e̲

             The following rules shall apply in accordance
             with enclosure 1.:

             (1) The test clock reflects the accumulated
                 test time which is passed without
                 exceeding the allowable error rate.

                 The test clock shall be reset when
                 the maximum allowable number of errors
                 in any category has been exceeded.
                 The test clock shall always be reset
                 to the time of the first time the
                 maximum allowable errors for that
                 category is attained. This means that
                 the test clock is always in line with
                 the worst test log.

             (2) T̲e̲s̲t̲ ̲L̲o̲g̲ ̲ ̲2̲4̲0̲ ̲h̲o̲u̲r̲s̲

                 Each test log shall be reset when
                 the maximum allowable number of errors
                 is exceeded. The test log shall always
                 be reset to the time of the max. allowable
                 number of errors in the logged category.

             (3) Test Log  240 hours for one or 2 categories
                 but not a̲l̲l̲ ̲t̲h̲e̲ ̲3̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                 a)  When, for one category, more than
                     240 hours of operation is logged
                     then this will be taken into account
                     in incrementing the time to which
                     the test log is reset.



                 b)  Formula to reset the log:

                     If A     =    time of max.allowable
                                   # of errors.

                        B     =    time of operation
                                   exceeding 240 hours
                                   without error.

                        C(n)  =    time which to reset
                                   the log after any
                                   B has occurred

                         n    =    # of errors after
                                   240 hours.

                     First time of occurrence:

                     C (1)    =    A + B

                     After:

                     C(n)     =    C (n-1) + (??

                 c)  These formulas are valid with
                     the restriction that the reset
                     point of a log never approaches
                     a point nearer than 208 hours
                     of the test clock. This means
                     that the last 32 hours of the
                     in-plant test must be executed
                     error free.












               A P P E N D I X   B
         ******************************










               A P P E N D I X   C
         ******************************










               A P P E N D I X   D
         ******************************



         C̲h̲a̲n̲g̲e̲ ̲t̲o̲   Page 14 of 65: Master Program
                     Schedule
                 Article 8

    Subpara. 8.1 is now clarified as follows
    ----------------------------------------

         A.  Subarticle 8.1 is now clarified as follows:

             In accordance with SHAPE and CR agreement
             as recorded in PMOM 20 the following modification
             of the Installation Testing and PSA Schedule
             is now modified as follows.

  T̲e̲s̲t̲i̲n̲g̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲                             D̲a̲t̲e̲ ̲o̲f̲
  ̲E̲v̲e̲n̲t̲

                                        O̲p̲t̲i̲m̲i̲s̲t̲i̲c̲      P̲e̲s̲s̲i̲m̲i̲s̲t̲i̲c̲

  240 hour test: Start of test:         84.01.23        84.02.27
  240 hour test: Completion             84.02.24        84.04.30

  Functional test: Start                84.02.25        84.05.01
  Functional test: Completion           84.03.25        84.05.30

  Operational test: Start               84.03.26        84.05.31
  Operational Test: Completion          84.05.26        84.08.15


         B.  Subarticle 8.4 is now modified by the
             addition of the following supplemental
             paragraph:

             "Depot Level Spare Parts as listed in
             Annex A to the Contract Amendment No.8
             shall be delivered to SHAPE in two separate
             lots for southern and northern depots
             to be delivered no later than Provisional
             Site Acceptance (PSA)".

             I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲S̲e̲q̲u̲e̲n̲c̲e̲

             The Installation Sequence Table as provided
             by Amendment No.7 is hereby modified as
             stated in the table below.

             The reasons for the modification are as
             follows:

             (a) Change within the implementation of
                 site is justified as follows:

                 Site No.14:  Shall be used by CR as
                 a reference system to carry out software
                 maintenance during the different testing
                 periods to be carried out at CR.

             (b) Site No.12:  Shall be made available
                 to SHAPE directly after the completion
                 of the "240 Hrs.Test" to carry out
                 SHAPE/TRW penetration test.



          CAMPS SITE RELATED MILESTONE
          ----------------------------


                  (1)     (2)
Instal.          Location Civil     ATBB Dwg.     Instalation
                                                        
                                                     PSA
Seq.             Work               Start         Earliest     Latest
--------------------------------------------------------------------------
 1    SHAPE      1981-9   1981-12   04-04-83      1984-06-04   84-09-01

 2    NORTHAG/   1981-12  1982-06   20-06-83      1984-06-04   84-09-01
      2ATAF

 3    AFCENT/    1981-11  1982-07   08-08-83      )
      AAFCE

 4    SONOR      1982-03  1982-08   22-08-83      )

 5    NCS        1982-05  1982-10   10-10-83      )

 6    UKAIR      1982-02  1982-12   10-01-84      )

 7    MEDNOR-    1982-06  1982-11   11-01-84      )
      EAST

 8    NATO Hq    1982-07  1983-01   20-02-84      )

 9    BALTAP     1981-10  1982-05   19-03-84      )

10    COMNON     1982-10  1983-04   25-04-84      )            See
                                                               Note

11    AFNORTH    1982-08  1983-02   30-05-84      )

12    LS/5ATAF   1982-12  1983-14   10-08-84      )

13    MEDEAST    1982-04  1982-09   13-08-84      )

14    LSE/6ATAF  1982-09  1983-03   20-08-84      )

15    AFSOUTH    1982-11  1983-04   24-09-84      )

16    CENTAG     1982-01  1983-02   01-10-84      1984-11-15



                 For the purpose of this test CR will
                 make available to SHAPE the same testing
                 configuration as used by CR during
                 the 240 hours test (Site No.12 equipment
                 connected to CR's test drive).

                 Furthermore CR agrees to provide to
                 SHAPE/CR software engineering support
                 and hardware maintenance support during
                 the test.

             (c) The installation of site No.7 and
                 4 has been rescheduled at the end
                 of the schedule.

             (d) CR will be permitted to perform ECO
                 update up to and inclusive of the
                 last site SPA provided CR notifies
                 SHAPE of its intention and requests
                 access to site at least 5 working
                 days prior to the planned date of
                 the modification.

             The Site Provisional Acceptance for Site
             No.1 to 16 will take place between 1984-06-04
             and shall be completed no later than 1984-11-15.

             The SPA shall be carried out by a maximum
             of three teams. CR and SHAPE will prepare
             no later than 60 days from the planned
             SPA Site 1 date the details of the site
             acceptance testing schedule.

             P̲a̲g̲e̲ ̲2̲7̲ ̲o̲f̲ ̲6̲5̲,̲ ̲a̲r̲t̲i̲c̲l̲e̲ ̲1̲4̲:

             Software Test Plan: No change.