DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦383307ee9⟧ Wang Wps File

    Length: 35148 (0x894c)
    Types: Wang Wps File
    Notes: PC PROJECT IMPLEMENTATION 
    Names: »2006A «

Derivation

└─⟦676de05ed⟧ Bits:30006247 8" Wang WCS floppy, CR 0153A
    └─ ⟦this⟧ »2006A « 

WangText



…0b…    …0b……05……0a……0b……0a……0c……0a……0d……0a…
…0a……07……09……08……09……09……09……01……08……08……08……86…1    
      
      
      
      
      
      
     …02… 
      
    …02…  
 …02…     
   

…02…     
      

…02…   / 
     …02……02…#
PROTOCOL
 CONVERTER
PROJECT
 IMPLEMENTATION
 PLAN 
…02……02…PC














                   A̲ ̲P̲ ̲P̲ ̲E̲ ̲N̲ ̲D̲ ̲I̲ ̲X̲ ̲ ̲ ̲F̲


                ̲P̲R̲O̲J̲E̲C̲T̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲







1.       S̲C̲O̲P̲E̲



         This document specifies the Management Plan for the
         CAMPS/SCARS/WWMCCS Protocol Converter Project, hereinafter
         referred to as PC.


2.       P̲R̲O̲J̲E̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲&̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



2.1      O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲

         A decicated Project Office will be established within
         the Systems Division - see Fig. 2.1.

         The Project Office will have total system responsibility,
         cognizance, and control authority in order to coordinate
         in-house activities and provide close liaison with
         the customer throughout the duration of the project.

         Overall direction for the project is to be provided
         by an administratively distinct Project Office. It
         will operate under a Project Manager whose sole responsibility
         will be the management of the PC project. The Project
         Manager will be the prime interface between Christian
         Rovsing A/S and Shape.

         The Project Manager will also undertake the tasks of
         Engineering Management, Operations Management and be
         supported by the Logistics Manager. Fig. 3.1-2 depicts
         the project management task structure.

         Within the supporting functional departments PC activities
         will be assigned as project entities.

         The site installations, provisioning, documentation,
         training and field support aspects of the PC will be
         planned and coordinated by the Logistics Manager supported
         by the Logistics Support staff of Christian Rovsing
         A/S.

         The Project Office will establish the baseline for
         work breakdowns, specifications, schedules and budgets;
         it will monitor variances and initiate correctve action.


















































                        fig. 2-1.


















































                        fig. 2-2.


2.2      S̲T̲A̲F̲F̲I̲N̲G̲

         The following is a list of staff for key positions
         on the PC project:

         Project/Engineering/Software Manager: TBD

         Logistics Manager:  Ole Eskedal

         Site Installation Manager:  Kurt Mikkelsen

         Documentation and Training Manager:  Ole Ren} Petersen



2.3      P̲R̲O̲J̲E̲C̲T̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲

         The Project Implementation Plan, PIP, will establish
         a firm baseline for all activities against which status,
         progress and performance can be evaluated and controlled.

         PIP will be used as a management tool to provide visibility
         and control of the project. It describes the schedule,
         performance control system, the detailed Work Breakdown
         Structure (WBS), the project administration, the interfaces
         with Shape and other aspects of the project.

         The PIP will have a well defined structure. Each section
         will identify the activity, its organization and operating
         procedures. A Work Breakdown Structure, WBS, for the
         activity will be related to the schedule network consistent
         with the master schedule and correlated with the associated
         WBS elements of other activities. Documentation produced
         by the activity will be listed. Finally, a cross-reference
         with contractual items will be made for accountability
         of deliverable items and unique requirements.


2.3.1    T̲o̲p̲-̲L̲e̲v̲e̲l̲ ̲W̲o̲r̲k̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲ ̲S̲t̲r̲u̲c̲t̲u̲r̲e̲ ̲(̲W̲B̲S̲)̲

         The WBS will be the framework for establishing work
         packages, schedules and budgets for managing the project
         and will provide the baseline for performance evaluation.

         A project tasks overview is shown in Fig. 2.3-1.

         For each of the major tasks a further breakdown has
         been generated detailing hardware, software, and support
         tasks. These WBS elements will become work packages
         for reporting, scheduling and cost control.

         Changes to the WBS will be under configuration management
         and require Project Office approval. Combined with
         the master schedule milestones for engineering, operations
         and logistics, the WBS will become the system-level
         plan.

         Project Management is the first task described by the
         tasks overview in figure 2.3-2.



















































                       fig. 2.3-1.


















































                       fig. 2.3.-2.


         The tasks of the main management functions are breifly
         outlined below:

         M̲P̲F̲ ̲P̲r̲o̲j̲e̲c̲t̲ ̲M̲a̲n̲a̲g̲e̲r̲.  As the executive responsible
         for successful execution of the project, the Project
         Manager has authority over and is responsible for budget
         allocation, cost, control, schedule and timely performance,
         technical cognizance of design and development, and
         control of production, test integration and support
         activities. The Project Manager will report directly
         to the senior management for prompt resolution of project
         issues.


         E̲n̲g̲i̲n̲e̲e̲r̲i̲n̲g̲ ̲M̲a̲n̲a̲g̲e̲r̲.  The systems engineer will be
         responsible for the ultimate technical performance
         and compliance of the installations. He provides the
         correct technical interpretation of all the requirements.
         He plans, directs, monitors, audits and controls the
         design, development, testing, installation and cut-over
         of the PC with regard to all technical aspects. He
         provides the technical liaison with Shape and with
         the in-house development and production groups. This
         position wil be filled by the Project Manager.


         O̲p̲e̲r̲a̲t̲i̲o̲n̲s̲ ̲M̲a̲n̲a̲g̲e̲r̲.  This manager will provide the
         liaison between the Project Office and the procurement
         and production activities. Scheduling, cost control,
         configuration control, production status, and quality
         control are his major concerns. He is responsible for
         establishing and maintaining an up-to-date baseline
         configuration and to access the status and quality
         of the production during implementation. The position
         will be filled by the Project Manager.


         L̲o̲g̲i̲s̲t̲i̲c̲s̲ ̲M̲a̲n̲a̲g̲e̲r̲.  The installation and site support
         tasks will be combined under one manager. The Logistics
         Manager will be responsible for site surveys, delivery
         and installation, training, maintenance, spares, documentation
         and site support. Logistic support tasks will be carried
         out by staff from the integrated Logistics Support
         Department of Christian Rovsing A/S.


         Q̲u̲a̲l̲i̲t̲y̲ ̲A̲s̲s̲u̲r̲a̲n̲c̲e̲ and C̲o̲n̲t̲r̲a̲c̲t̲s̲ ̲A̲d̲m̲i̲n̲i̲s̲t̲r̲a̲t̲i̲o̲n̲ are
         corporate staff functions carried out for all projects.
         Intensive support will be given during start up and
         critical phases and will continue throughout the duration
         of the project.



2.3.2    O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

         Formal operating procedures and management methods
         will be used by the Project Office to control the project.

         Management procedures define the methods used within
         Christian Rovsing A/S for planning, work assignment,
         monitoring and coordination of activities within a
         project.

         The Project Office operates within these well-established
         procedures and is responsible for:

         P̲l̲a̲n̲n̲i̲n̲g̲:          Evaluation of contract requirements
                            and allocation of work to the 
                              various functional groups.

         W̲o̲r̲k̲ ̲A̲s̲s̲i̲g̲n̲m̲e̲n̲t̲:   Assurance of work statements, 
                            specification, budgets and schedule
                            requirements.

         M̲o̲n̲i̲t̲o̲r̲i̲n̲g̲:        Periodic review of technical schedule
                            and cost performance applying 
                            programme control through budget
                            authorization.

         C̲o̲-̲o̲r̲d̲i̲n̲a̲t̲i̲o̲n̲:     Co-ordination of all project activi-
                            ties between operating departments.

         Internal management procedures have been developed
         as a practical cost/schedule control system which produce
         valid, auditable and timely performance reports. Variances
         from budget and schedule are quickly identified and
         significant deviations are flagged for immediate project
         management attention and corrective action.


         Technical supervision and monitoring are effected through
         periodic design reviews with hardware and software
         engineering staff.

         The primary management controls are based on a WBS,
         master schedule and budget. Firm baselines established
         early in the project provide the basis for management;
         see Fig. 2.3-3.

         The WBS consists of a family tree of hardware, software,
         services and tasks organized to define and geographically
         display the work to be accomplished for a successful
         implementation of the project. As a planning tool,
         it defines the work packages for planning, scheduling
         and cost control. Negotiated and approved project changes
         are reflected in the baseline WBS.

         The master schedule incorporates customer-directed
         milestones and indicates the timing relationships of
         the WBS elements. Detailed plans derived from the master
         schedule establish work package milestones.

         The budget baseline allocates the resources between
         operating departments following contract award. Work
         authorizations are timephased based on schedule contraints.

         All detailed packaged identified and assigned from
         the WBS are defined by an internal statement of work,
         schedule, and budget thus establishing a performance
         measurement baseline.

















































                       fig. 2.3-3.


2.3.3    C̲o̲n̲t̲r̲a̲c̲t̲s̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲ ̲&̲ ̲A̲d̲m̲i̲n̲i̲s̲t̲r̲a̲t̲i̲o̲n̲

         Contracts Management and Administration is a staff
         function within the company providing support to the
         Project Manager.

         The function is responsible for the following:

         o   Contract terms and conditions in relation to the
             customer

         o   Contract terms and conditions for purchase orders
             on sub-contractors and suppliers of standard equipment
             and supplies

         o   Project budgets
         o   Invoicing
         o   Settlement of suppliers and sub-contractors
         o   Finance
         o   Cost control

         The function is required to keep such cost and accounting
         records as are required to perform audit consistent
         with Danish Law and according to the terms and conditions
         of the contract.

         The function is responsible for the conversion of all
         capacity and other budgets and plans into economic
         terms permitting the safe establishment of rolling
         budgets and long range financial forecasts.



2.3.4    P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲c̲o̲g̲n̲i̲t̲i̲o̲n̲ ̲&̲ ̲R̲e̲s̲o̲l̲u̲t̲i̲o̲n̲



2.3.4.1  P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲c̲o̲g̲n̲i̲t̲i̲o̲n̲

         From project start to start of acceptance test the
         exchange of information between the Project Manager
         and Shape is performed via:

         -   regular meetings
         -   progress reports, and
         -   telexes, letters and telephone.



         The information to be exchanged makes it possible for
         Shape to monitor the project and product and thus enables
         Shape to intervene if some deficiencies which might
         not be covered by the specification are foreseen.

         In case that such deficiencies should occur, these
         are handled a s Change Requests, which are acted upon
         by the Project Manager specifying the cost and schedule
         impact that the change might create.

         However, in case that the Project Manager recognizes
         that a specific requirement cannot be fulfilled within
         the frame of the project he immediately informs Shape
         and includes suggestions for the solution.



2.3.4.2  M̲e̲e̲t̲i̲n̲g̲s̲

         During the period of design, development and implementation
         regular meetings are held between Shape and the Project
         Manager at the contractors factory in Ballerup. Discussions
         at these meetings deal with the concept of the equipment,
         the various solutions affecting the operation, and
         possible modifications and changes, which are requested
         during the period.

         In order to achieve a minimum response time in decision,
         the mutual agreeable changes and conclusions obtained
         during these meetings automatically form part of the
         work statement and the specification.2.3.4.3

         R̲e̲p̲o̲r̲t̲i̲n̲g̲

         The reporting by the Project Manager consists of:

         -   progress reports
         -   minutes of progress meetings.

         Progress Reports describing critical activities regarding
         design, manufacturing and management are submitted
         at monthly intervals.

         The contents of Progress Reports are typically as follows:



         o   Technical Status
         o   Problems Outstanding
         o   Schedule Status & Report
         o   List of documents received and submitted within
             the reporting period
         o   Action Item List



2.3.4.4  P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲s̲o̲l̲u̲t̲i̲o̲n̲

         Whenever internal problems and deviations are ascertained
         the Project Manager refers the matter to the responsible
         party.

         The Project Manager takes action if responsibility
         for the problem discovered is difficult to place.

         QA problems within production are referred to the Project
         Manager.



2.3.4.5  C̲u̲s̲t̲o̲m̲e̲r̲ ̲C̲o̲o̲r̲d̲i̲n̲a̲t̲i̲o̲n̲

         Possible problems which may arise and which require
         Shape action are reported directly to Shape by telex
         for necessary floow-up and action, whatever the case
         may be.


3        W̲O̲R̲K̲ ̲B̲R̲E̲A̲K̲D̲O̲W̲N̲ ̲S̲T̲R̲U̲C̲T̲U̲R̲E̲ ̲A̲N̲D̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲



3.1      W̲B̲S̲

         The design, implementation, installation and commisioning
         of the Protocol Converter require the following Work
         Packages to be performed by Christian Rovsing A/S:


         1.  P̲R̲O̲G̲R̲A̲M̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲

         1.1 Program Management

         1.2 Monthly Progress Reviews

         1.3 Project Implementation Plan


         2.  S̲Y̲S̲T̲E̲M̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲

         2.1 Systems Engineering Management/Technical Coordination

         2.2 System Requirements Review

         2.3 System Requirements Specification

         2.4 Test Plan

         2.5 Test Procedures

         2.6 Reliability Program


         3.  H̲A̲R̲D̲W̲A̲R̲E̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         3.1 Equipment Handbook Preparation

         3.2 Equipment Manufacturing


         4.  S̲O̲F̲T̲W̲A̲R̲E̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲

         4.1 Software Management



         4.2 Software Design Specification (Sub-system level)

         4.3 Software Design Specification (Program level)

         4.4 Program Coding and Unit Testing


         5.  S̲Y̲S̲T̲E̲M̲ ̲I̲N̲T̲E̲G̲R̲A̲T̲I̲O̲N̲

         5.1 Site 1 In-factory Integration and Testing

         5.2 Site 2 In-factory Integration and Testing

         5.3 Site 3 In-factory Integration and Testing

         5.4 Factory Test site 1

         5.5 FAT site 2

         5.6 FAT site 3


         6.  I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         6.1 Management and Planning

         6.2 Site Preparation

         6.2.1 Site Survey

         6.2.2 Site Verification

         6.2.3 As-Built-Doc.

         6.3 Transportation

         6.3.1 Site 1

         6.3.2 Site 2

         6.3.3 Site 3


         6.4 Installation

         6.4.1 Site 1



         6.4.2 Site 2

         6.4.3 Site 3


         7   A̲C̲C̲E̲P̲T̲A̲N̲C̲E

         7.1 Provisional site Acceptance Test (PSA) site 1

         7.2 PSAT site 2

         7.3 PSAT site 3

         7.4 Final Site Acceptance Test, site 1

         7.5 FSAT site 2

         7.6 FSAT site 3


         8   T̲R̲A̲I̲N̲I̲N̲G̲

         8.1 Training Plan

         8.2 Hardware Maintenance

         8.3 On-the-Job Training

         8.3.1 site 1

         8.3.2 site 2

         8.3.3 site 3


         9   D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲

         9.1 Equipment Handbook

         9.2 Maintenance Handbook

         9.3 Inventory

         9.4 Software Documentation




         10  M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲S̲U̲P̲P̲O̲R̲T̲

         10.1 Hw Warranty site 1

         10.2 Hw Warranty site 2

         10.3 Hw Warranty site 3

         10.4 Spares

         10.4.1 RSPL

         10.4.2 ASPL



3.2      P̲r̲o̲g̲r̲a̲m̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

         The program schedule is shown overleaf.





4        S̲Y̲S̲T̲E̲M̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲ ̲P̲L̲A̲N̲



4.1      I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲

         The Systems Development Plan comprises the following
         tasks:

         o   System Engineering

         o   Hardware Specification

         o   Software Development

         o   System Integration



4.2      S̲Y̲S̲T̲E̲M̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲

         System Engineering consists of the following tasks:

         o   System Requirements Specification/Review

         o   Test Plan

         o   Test Procedures

         o   Reliability Program.



4.2.1    S̲y̲s̲t̲e̲m̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         Appendix xx of this contract is the system requirements
         baseline for the protocol converter.



4.2.2    T̲e̲s̲t̲ ̲P̲l̲a̲n̲s̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

         Subsequent to the system specification a Final Test
         Plan and Test Procedures will be specified. The test
         will be:



         o   Factory Acceptance Tests

         o   Provisional Site Acceptance Test (PC-WWMCCS)

         o   Final Site Accptance Test (CAMPS/SCARS-PC-WWMCCS)



4.2.3    R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲ ̲P̲r̲o̲g̲r̲a̲m̲

         The reliability program will be conducted in accordance
         with section 4 of the system requirements specification.
          As specified in section 7.8.1 all modules of the converter
         have MTBF values greater than 3500 hours.  The MTBF
         varification required in the SRS section 4.6.1.1. will,
         therefore, be performed in accordance with section
         4.6.1.1.2 of the SRS.

         The MTTR of the converter (faultfinding) is set to
         1 hour.  The MTTR verifications will, therefore, take
         place in accordance with section 4.6.1.2.2 of the SRS.



4.3      H̲a̲r̲d̲w̲a̲r̲e̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         The Protocol Converter Hardware will be specified in
         the Equipment Handbook in accordance with the requirements
         of section 10.4 of the SRS.



4.4      S̲o̲f̲t̲w̲a̲r̲e̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲

         Software development consists of the following tasks:

         o   Assembly of documentation for:

             -   System Software (AMOS)
             -   Maintenance and Dianostics, software.
             -   Support Software

         o   Specification of the following software:

             -   Application software

         o   Coding of Application Software

         o   Unit testing of the software.


         Software Design specification for the application software
         will be produced in accordance with ACE Directive 007:

             Subsystem Design Spec.

             Program (module) Design Spec.



4.5      S̲y̲s̲t̲e̲m̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲

         Each system will be integrated and tested in the factory.
         The software will in the final system resite in EPROM.
         To ease the test of the first system, all software
         will be prepared on a floppy disc and loaded into RAM.
         When the converter have been finally accepted the program
         will be issued in an EPROM.





5.       T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         Transportation and Installation will be performed by
         the ILS department of the Systems Division. It comprises
         the following tasks for each site.

         -   Site survey

         -   Site requirements specification

         -   Site Verification. Transportation and Installation
             planning.

         -   Transportation to Site

         -   Installation and checkout

         The requirements are specified in the SRS.





6.       A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲T̲E̲S̲T̲I̲N̲G̲ ̲A̲N̲D̲ ̲H̲A̲N̲D̲O̲V̲E̲R̲.̲

         Acceptance Testing of the protocol converter is performed
         in three separate testphases:

         -   Factory acceptance test
         -   Provisional site acceptance
         -   Final site acceptance.



6.1      T̲e̲s̲t̲ ̲P̲l̲a̲n̲ ̲a̲n̲d̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

         All acceptance test tasks will be specified in a Testplan
         and associated procedures.



6.2      F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲

         Each protocol converter will pass through a formal
         Factory Acceptance Test prior to shipment. The Factory
         Acceptance Test will be documented in the Test Plkan
         and the Test Procedures. The Factory Acceptance Test
         comprises the following separate tests:

         1.  COMSEC verification at the factory

         2.  Functional test of hardware and software. The functional
             test will be performed with the PC connected to
             CAMPS system on one side and to a modified converter
             at the other side. The modified converter will
             simulate WWMCCS

             The COMSEC verification will be performed by purchaser
             in accordance with the description given in the
             SRS.



6.3      P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲o̲n̲-̲s̲i̲t̲e̲ ̲T̲e̲s̲t̲i̲n̲g̲

         After installation and checkout of the first converter
         at Shape, the converter will be connected to the colocated
         WWMCCS system for verification of the PC-WWMCCS interface
         and the function of the converter.



         The test will use the built-in test messages present
         in the protocol converter.

         The provisional site acceptance test will be specified
         in the Test Procedures.



6.4      F̲i̲n̲a̲l̲ ̲S̲i̲t̲e̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲

         Each converter will pass through a final acceptance
         test. The converter will be hocked-up to both the WWMCCS
         system and the CAMPS system and a functional test of
         the system will be performed in accordance with the
         Test Procedure. After the functional test the converter
         will be subject to a COMSEC on-site verification.

         Testing of the SCARS II interface will take place at
         the first site where a SCARS II is available.



6.5      F̲i̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲

         Final Acceptance is the act whereby SHAPE will acknowledge
         by protocol that Christian Rovsing A/S has fully demonstrated
         that a site is complete and ready for initial operation
         and will take place when the following requirements
         have been met:

         1)  Completion of the agreed Final Acceptance Test.

         2)  Verification of the site inventory.

         3)  If applicable, availability of a mutually agreed
             discrepancy list showing the agreed date for clearance
             of each listed discrepancy.

         The Hardware Warranty period will commence at the date
         of Final Acceptance.

         Software Warranty will commence at the date of Final
         Acceptance of the first converter.





7.       M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲S̲U̲P̲P̲O̲R̲T̲



7.1      M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲E̲n̲g̲i̲n̲e̲e̲r̲i̲n̲g̲

         a)  The maintenance section of the Logistics Department
             is responsible for giving appropriate input to
             System Engineering to ensure that the Converter
             will meet the requirements for maintainability.

         b)  The maintenance section will work closely with
             Systems Engineering to ensure consistency in determination
             of the MTBF and MTTR figures.

         c)  The development of the Maintenance Plan and associated
             procedures will be done by the maintenance function.

         d)  In the area of deliverable documentation the maintenance
             section will generate the Maintenance Manual and
             conduct maintenance related training.



7.2      F̲i̲e̲l̲d̲ ̲S̲u̲p̲p̲o̲r̲t̲

         a)  Field Support will be managed by the maintenance
             section. The two major activities are:

             1)  Coordinate the implementation of field changes

             2)  Coordinate warranty repairs.

         b)  All questions forwarded to the project office by
             customer relating to equipment already installed
             and accepted will be coordinated by the Field Support
             function.



7.3      S̲p̲a̲r̲e̲s̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲

         a)  The maintenance section is responsible for the
             specification, acquisition, packaging and delivery
             of spares, repair and repairable subassemblies.
             A …86…1         …02…   …02…   …02…   …02…                         
                              
             priced Recommended Spare Parts List (RSPL) will
             be submitted to customer.Provisioning Conferences
             will be held at contractors facility, planned and
             conducted by the maintenance function.

         b)  An approved Spare Parts List (ASPL) will be negotiated
             with the customer and incorporated in the contract
             by amendment.

         c)  Spare Parts Design Change Notices (SPDCN) will
             be issued and controlled by the maintenance function.



7.4      T̲o̲o̲l̲s̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲s̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲

         The Maintenance function will specify all tools and
         test equipments to be supplied under the contract.
         Furthermore, a priced list of tools and test equipment
         will be submitted to customer for all items required
         at each site and maintenance depot to support the equipment
         supplied



7.5      C̲a̲l̲i̲b̲r̲a̲t̲i̲o̲n̲

         The Maintenance function is responsible for the generation
         and implementation of a calibration program for the
         test equipment supplied.



7.6      F̲a̲i̲l̲u̲r̲e̲ ̲R̲e̲p̲o̲r̲t̲i̲n̲g̲

         The generation and implementation of a Failure Reporting
         System will be the responsibility of Maintenance Engineering.
         All incoming reports will be recorded and analyzed
         by maintenance engineering, and the corrective action
         coordinated with Contractor's Program Office if appropriate.

         Annotated copies of the reports will be received by
         Systems Engineering who may participate in the analysis.





7.7      P̲l̲a̲n̲s̲ ̲a̲n̲d̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

         The following documentation will be developed. Some
         of the plans listed below may make reference to subplans
         and procedures which already are in existence or will
         be developed under this program.

         1)  Maintenance Plan
         2)  RSPL
         3)  ASPL
         4)  List of Tools and Test Equipment
         5)  Maintenance Handbooks



7.8      M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲P̲l̲a̲n̲ ̲-̲ ̲o̲u̲t̲l̲i̲n̲e̲

         The system will be delivered with Maintenance and Diagnostics
         software with the aim of performing fault isolation
         to board level (module level).

         As the 8 converters are installed at only 3 sites we
         recommend that the system is backed up by a set of
         spares at each site for 90 days. and one depot level
         set of spares for 270 days.

         A number of modules are identical to the CAMPS modules
         and the converter can therefore share these spare parts
         with the CAMPS system. The baseline assumes that a
         CAMPS system is present at all the three sites where
         the converter is installed.

         The RSPL is based on the following reliability model
         and MTBF/MTTR figures:

         All modules used in the converter are reliability wise
         placed in series. There is no redundant modules within
         one converter. Each site has one redundant converter.
         When a converter fails all signallines are patched
         to the spare converter and traffic can continue. The
         time for patching is expected to be less than 10 minutes.





7.8.1    C̲a̲l̲c̲u̲l̲a̲t̲e̲d̲ ̲R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲

         M̲o̲d̲u̲l̲e̲ ̲n̲a̲m̲e̲       M̲T̲B̲F̲         Backed up by CAMPS spares

         1.Minicrate with
           power           26300    38  Watchdog crate

         2.CPU-SCM         36500    28  
         3.64k RAM         29600    30  128k RAM
         4.EPROM 32k       10873    92
         5.LTU-CAMPS       27600    36
         6.LTU-WWMCCS      27600    36
         7.LIA-CPS      10000000     0.1       X
         8.LIA-WWMCCS   10000000     0.1       X
         9.V24 Filter    5000000     0.2       X
         10.Mains Filter  625000     1.6       X
         11.Power Filter  625000     1.6       X
         12.CTX crate
            with power     31250    32         X
                                  -------

             TOTAL                 295
                                  --------

         Equivalent to MTBF = 3390 hours.

         MTTR of a faulty converter = 1 hour

         MTTR for switch to spare converter = 0.2 hours



7.8.2    R̲S̲P̲L̲

         a)  Recommended Spares per site (90 days)

                Name              Number

             -CPU/SCM                1
             -LTU single channel     1
             -32k EPROM              1
             -64k RAM                CAMPS 128k RAM can be used.



         b)  Recommended spares at depot (270 days)


             -CPU/SCM                1
             -LTU                    1
             -32k EPROM              1
             -64k RAM                CAMPS 128k RAM can be used.



8.       T̲R̲A̲I̲N̲I̲N̲G̲



8.1      O̲r̲g̲a̲n̲i̲z̲a̲t̲i̲o̲n̲

         a)  Logistics Department is responsible for all customer
             training on programs undertaken by the Systems
             Division of Christian Rovsing A/S. The training
             organization also has the respsonsibility for the
             development of manuals and handbooks. The combination
             of training and development of manuals and handbooks
             ensures an efficient training of customer's personnel.

         b)  The material used for training is essentially the
             same documentation which the technician later will
             work with on site. Training material will be delivered
             in accordance with the contract.

         c)  The training section of Logistics Department is
             headed by a section manager who has technical writer/instructors
             reporting to him.

         d)  Other divisions and departments within the company
             will supply training courses and instructors on
             request.

         e)  The training requirements are specified in the
             SRS.



8.2      D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲a̲n̲d̲ ̲C̲o̲n̲d̲u̲c̲t̲i̲o̲n̲ ̲o̲f̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲C̲o̲u̲r̲s̲e̲s̲

         a)  The development of the individual courses which
             make up the CAMPS Training Program will take place
             in the training section and in other departments
             of the company. However, the overall responsibility
             for compliance with the contract and System Requirements
             Specification lies with Training Manager.

         b)  The following courses shall be developed:

             1)  HW Maintenance Training
             2)  On-The-Job Training.


8.2.1    H̲a̲r̲d̲w̲a̲r̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲

         This course encompasses hardware maintenance and operation
         of the converter. Since the maintenance philosophy
         is based on module replacement no hardware training
         to component level is required. This course will be
         held at Christian Rovsing A/S' premesses.



8.2.2    O̲n̲-̲T̲h̲e̲-̲J̲o̲b̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲

         This course will provide OJT to the Operator. The course
         will be conducted on the sites. The course material
         will be based on the handbooks.





9        D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲

         The following documentation items/tasks will be performed:

         -   Equipment Handbook

         -   Hardware Maintenance Handbook

         -   Engineering Drawings (as - installed)

         -   Inventory list per site

         -   Software Documentation As-Built.

         A specification of the documents is given in the SRS.





10.      Q̲U̲A̲L̲I̲T̲Y̲ ̲A̲S̲S̲U̲R̲A̲N̲C̲E̲

         The Quality Assurance Manager (QAM) is responsible
         for all QA tasks within the company. This includes
         the establishment and control of general QA procedures
         and special QA procedures for dedicated projects.

         The Engineering Drawing Office and Secretariat operate
         in accordance with the procedures established and controlled
         by the QAM.

         The Quality Assurance Manager is, in particular, responsible
         for the following:



10.1     P̲a̲r̲t̲s̲ ̲a̲n̲d̲ ̲M̲a̲t̲e̲r̲i̲a̲l̲ ̲(̲P̲&̲M̲)̲

         P&M is responsible for procurement control, vendor
         evaluation & qualification, and performs a support
         function for receiving inspection and purchasing.



10.2     R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲

         This is a supervision function available for all projects.
         Reliability analysis, trade-offs, and tests are performed
         by the project team under the supervision and control
         of QA.



10.3     Q̲u̲a̲l̲i̲t̲y̲ ̲C̲o̲n̲t̲r̲o̲l̲ ̲(̲Q̲C̲)̲

         This includes the establishment and control of general
         QC procedures within the company and special QC procedures
         for dedicated projects, and the establishment and control
         of QC requirements relating to subcontractors and suppliers.

         The QC function is in particular responsible for:

         -   Evaluation of quality control plans
         -   Evaluation of inspection plans
         -   Incoming inspection of parts and materials and
             subcontractual items
         -   In-process inspection


         -   End-item acceptance test
         -   Shop procedures
         -   Control of special procedures
         -   Methology and calibration relating to test instrument
             and tools
         -   Electrical and environmental tests
         -   Entrance control and cleanlines control of restricted
             clean room areas
         -   Control of packing & shipping
         -   Trend reporting
         -   Quality audits



10.4     Q̲A̲-̲P̲o̲l̲i̲c̲y̲

         The Quality Assurance Policy of the company is defined
         in "Quality Assurance Policy" which is an internal
         standard.

         Based on this policy, the company has implemented a
         standard QA-system which is compliant with "NATO Quality
         Control System Requirements for Industry", AQAP-1.



10.5     Q̲A̲-̲S̲y̲s̲t̲e̲m̲

         The standard QA system comprises a series of functions
         among which are:

         a)  Q̲u̲a̲l̲i̲t̲y̲ ̲P̲l̲a̲n̲n̲i̲n̲g̲

             At an early point in the contract performance,
             the quality requirements are reviewed and a contract
             related Quality Plan is established. This plan
             is based on the standard QA system but may contain
             amendments or exemptions, if necessary. The plan
             contains detailed scheduling of QA participation
             in such activities like design reviews, factory
             test, acceptance test, etc.

         b)  D̲e̲s̲i̲g̲n̲ ̲C̲o̲n̲t̲r̲o̲l̲

             The QA system provides strict control of all new
             designs of both hardware and software. Design …86…1
                     …02…   …02…   …02…   …02…                             
                          
             Reviews are scheduled and performed and no design
             is released for production/programming without
             proper approval.

         c)  C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲C̲h̲a̲n̲g̲e̲ ̲C̲o̲n̲t̲r̲o̲l̲

             A Configuration and Change Control system assures
             that all necessary documentation is established
             and baselined. Also software is placed under control
             after programming and development test. The Change
             Control is managed by a board with participation
             of a customer representative, if required.

         d)  W̲o̲r̲k̲ ̲I̲n̲s̲t̲r̲u̲c̲t̲i̲o̲n̲s̲

             In all areas where necessary for quality, work
             instructions and standards are established. Standards
             define the required quality level and instructions
             define processes needed to reach that level.

         e)  I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲

             Detailed procedures are established for Inspection
             and Tests to be performed during development, production
             and upon completion of the contract (acceptance
             test).

         f)  All inspection and test results - as well as any
             other events significant for the documentation
             of the product quality - are recorded and kept
             in the QA files until completion of the contract.





11.      C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲

         The Configuration Management function covers the following
         areas:

         o   Organization
         o   Items under configuration control
         o   Configuration identification
         o   Configuration Control
         o   Status accounting
         o   Configuration audit

         Christian Rovsing A/S Configuration Management acts
         as chairman of the Configuration Control Board. All
         requests for changes go through the CCB.

         The following items are under Configuration Control:

         o   Specifications and Procedures
         o   Engineering Drawings
         o   Change Documentation
         o   Hardware and Software Items

         All items released as part of the baseline configuration
         as well as subsequent change documentation to these
         items are identified for the purpose of Configuration
         Control with one or more of the following numbers:

         o   Drawing or part number
         o   Revision number
         o   Serial number
         o   Specification description
         o   Change identification number

         Configuration Control is divided into three major tasks:

         o   Change analysis
         o   Change classification
         o   Approval of changes.

         The Configuration Control Board (CCB) is involved in
         all areas.




         The Configuration Management function gets involved
         in updating of the PIP and other plans of the project
         by the fact that DATA MANAGEMENT is handled by configuration
         control.

         The changes are normally initiated through the project
         office but controlled by Configuration Management.


12.      C̲U̲S̲T̲O̲M̲E̲R̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲Y̲

         Customer is responsible for the following tasks:

         1.  Provision of a CAMPS, SCARS II and WMMCCS at the
             dates scheduled for test.

         2.  Provision of adjustable test time  in CAMPS, SCARS
             II and WMMCCS during prime working hours.

         3.  Preparation of site in accordance with contractor
             specified site requirements.

         4.  Provision of the signal cables from CAMPS, SCARS
              II and WMMCCS to the converter.

         5.  Provision of test network and personnel as specified
             in the test plan and the test procedures. It is
             assumed the contractor personnel will operate the
             converter during acceptance test, whereas customer
             personnel will aperate intercon systems and test
             equipment.