nd monitoring are effected through periodic design reviews with hardware and software
engineering managers.
The primary management controls are based on a well-planned WBS, master schedule
and budget. Firm baselines established early in the projet provide the basis for
managing it. (see FIGURE 3-3).
The WBS consists of a family tree of hardware, software, services and tasks organized
to define and geographically display the work to be accomplished for a successful
implementation of the poject. As a planning tool, it defines the work packages for
planning, scheduling and cost control, negotiated and approved project changes are
reflected in the baseline WBS.
The master schedule incorporates customer-directed
milestones and indicates the timing relationships of
the WBS elements. Detailed plans derived from the master
schedule establishwork package milestones.
The budget baseline allocates the resources between
operating departments following contract award. Work
authorisations are timephased based on schedule constraints.
Internal budget allocations allow for the retainment
of