⟦3c1a9ca48⟧ Wang Wps File

    Length: 3968 (0xf80)
    Types: Wang Wps File
    Notes: Telex/ITC-McLean          
    Names: »2654A «

Derivation

└─⟦2a5bfc292⟧ Bits:30006223 8" Wang WCS floppy, CR 0221A
    └─ ⟦this⟧ »2654A « 

WangText






To:   ITC-McLean
Attn: Don Iverson

Fm:   Christian Rovsing A/S

ref:  OCR/Doc. 2654A/tlx/0001

Subj: List of content for OCR proposal.

After the review of the OCR IFB we propose, as we agreed at
 our last meeting, the following list of content for our combined
 bid. If you wish to modify certain sections, please let us know.

For the sections marked with ITC, we expect to include your
 input.  Sections marked with (ITC) is expected to be combined
 effort. Other sections to be completed by CR.


P̲a̲r̲t̲ ̲1̲:̲ ̲T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲

         Vol. I:    PIP
         Vol. II:   Certificates and Contract appreciation
         Vol. III:  Technical Specification
         Vol. IV:   Corporate Capabilities

P̲a̲r̲t̲ ̲2̲:̲ ̲P̲R̲I̲C̲E̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲

1.      Project Management and Organization             CR A/S
1.1     Overall Project Approach
1.2     Management and Organization
1.3     Implementation Procedures
  1.3.1 Work Breakdown Structure
  1.3.2 Operation Procedures
  1.3.3 Cost Control 
  1.3.4 Contracts Management and Administration
  1.3.5 Problem recognition and Resolution


2.      Project Implementation Schedule       CR
2.1     Master Work Breakdown Structure (WBS)(ITC)
2.2     Detailed WBS                         (ITC)
2.3     Time and Milestone schedule


3.      Technical Implementation Approach     CR/ITC
3.1     System Engineering Plan
  3.1.1 Requirements Specification
  3.1.2 Design/Procurement Specification
  3.1.3 Test Specification


4.      Reliability and Maintainability       ITC
4.1     Reliability/Maintainability Model
4.2     Availability Verification

5.      T̲E̲S̲T̲I̲N̲G̲


5.1     Test Philosophy
5.2     Test Plan and Procedures
5.3     Factory Acceptance Test    
        (Phase I) - General                  (ITC)
5.4     Factory Acceptance Test
        (Phase I) - Specific                 (ITC)
5.5     Site Functional Test (Phase II)
5.6     Site Operational Test (Phase III)


6.      D̲E̲L̲I̲V̲E̲R̲Y̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲              CR


7       QUALITY CONTROL/QUALITY ASSURANCE


7.1     QC/QA Philosophy                       CR
7.2     HW Manufactoring MQA                   ITC
7.3     SW Development QA                      ITC


8       T̲R̲A̲I̲N̲I̲N̲G̲                               CR

9       M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲P̲H̲I̲L̲O̲S̲O̲P̲H̲Y̲ ̲ ̲A̲N̲D̲
        S̲P̲A̲R̲E̲ ̲P̲R̲O̲V̲I̲S̲I̲O̲N̲I̲N̲G̲                  (ITC)

9.1     Maintenance Philosophy
  9.1.1 Site Level Maintenance
  9.1.2 Depot Level Maintenance
9.2     Spare Provisions
  9.2.1 Site Level
  9.2.2 Depot Level


10      D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲


10.1    Documentation Philosophy
10.2    Operators Manual                     ITC
10.3    Users Guide                          ITC
10.4    Site Technical Manual                ITC
10.5    Depot Technical Manual               ITC
10.6    Inventory                            ITC


V̲O̲L̲U̲M̲E̲ ̲ ̲I̲I̲:̲ ̲ ̲C̲E̲R̲T̲I̲F̲I̲C̲A̲T̲E̲S̲ ̲C̲O̲M̲P̲L̲I̲A̲N̲C̲E̲ ̲S̲H̲E̲E̲T̲S̲.̲
             C̲O̲N̲T̲R̲A̲C̲T̲U̲A̲L̲ ̲A̲P̲P̲R̲E̲C̲I̲A̲T̲I̲O̲N̲


1.      Certificate of Origin                ITC
2.      List of NATO Nation Users            ITC
3.      Bid guarantee                        CR
4.      Compliance Sheets                   (ITC)
5.      Contractual Appreciation             CR


V̲O̲L̲ ̲I̲I̲I̲:̲ ̲T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲


1.      Introduction
2.      System Overview
3.      Hardware Specifications
        (Dimension, Characteristics, Drawings etc.)
4.      Software Specification

5.      Installation Requirements

6.      Environment Specification
6.1     EMP Sysceptibility
6.2     Shock and Vibration Specificatin
6.3     Heat Dissipation
6.4     Dust
6.5     (Other Requirements your System may have)

7.      Tools and Test Equipment
8.1     Priced List of Tools and Test Equipment


V̲O̲L̲U̲M̲E̲ ̲I̲V̲:̲ ̲C̲O̲R̲P̲O̲R̲A̲T̲E̲ ̲C̲A̲P̲A̲B̲I̲L̲I̲T̲I̲E̲S̲


1.      Introduction

2.      Christian Rovsing A/S

3.      ITC/COMPUSCAN
3.1     Coporate History
3.2     Relevant Experience
  3.2.1 Involvement in OCR
  3.2.2 Involvement in Tempert
3.3     Manufacturing Facilities
3.4     QA/QC Provisions



Best Regards
Christian Rovsing A/S