⟦401820b49⟧ Wang Wps File

    Length: 7560 (0x1d88)
    Types: Wang Wps File
    Notes: M W H Q  Min of mtg       
    Names: »2739A «

Derivation

└─⟦67e26c09b⟧ Bits:30006222 8" Wang WCS floppy, CR 0244A
    └─ ⟦this⟧ »2739A « 

WangText








                          A̲G̲E̲N̲D̲A̲

                   M̲I̲N̲U̲T̲E̲S̲ ̲O̲F̲ ̲M̲E̲E̲T̲I̲N̲G̲.


         A̲G̲E̲N̲D̲A̲


1.       -Question, Answers

2.       -Misc. points
         -Doc.
         -Training 
         -Installation
         -Spare parts
         -Q/A
         -Warrenty
         -Delivery

3.       -Pricing

1.       Concerning missing information in CRs proposal as stated
         in the telex dated 1982-09-01, a new drawing of 
         the MEDS will be provided to be in accordance with
         the rack layouts.

         The following subsection under section 1 correspond
         to the subsections in the referenced telex.

         CR has proposed to standardize on 5 inch floppy discs.
         Winchester disc could be offered as an option, but
         is was decided not to include this.

         Datasheets will be provided for tdx crate, floppy discs
         and wordprocessors/terminals.

1.2      The new drawing will include 2 pieces of 5 inch floppy
         disc for user data initialization instead of one disc.

1.3      The new configuration will only use one TDX bus throughout
         the total system instead of three buses. Hence two
         interfaces will not be needed anymore, i.e. two XNP
         with SCI's and two XCP's.

1.4      In the work breakdown XNA is a misspelling of XTA.
         CR explained that new H/W development is included in
         order to change the XTA from a commercial version to
         a unit to be installed in a TDX crate together with
         TDX controller and power supply.

1.5      The XTA is a much simpler device than a XNP with SCI.
         Basicallly the XTA is a buffer between a terminal and
         the TDX bus. The XNP with SCI is programmable and can
         interface intelligently with crypto devices and modems
         etc.





1.6      Signaal proposes a front loaded printer for the rack
         mounted printer. CR will find a solution. (Closed).

1.7      The drawings will have the LTU's deleted, because that
         is HSA delivery.

1.8      Shock and vibration on all units will fullfill CR80
         transportation specification, i.e. 1.5g vibration and
         3g schock.

1.9      Power supply requirements will be analysed and CR will
         make the answers more specific.

1.10     The terminals and the wordprocessor will be identical
         H/W-vice, except in amount of memory.

1.11     Only pascal is available for this application,whereas
         ADA is planned for in CR80 products.

1.12     The text used in the proposal will be reviewed and
         modified by CR.

1.13     The word "modified" terminal will be deleted, because
         the Deltaterminal will be identical to the CAMPS terminal
         except for fiber optics.

1.14     CR is responsible for all modified S/W in the wordprocessor.

1.15     New terminal and floppy disc dimension has been provided.

1.16     Floppy disc will be removed from racks to table top
         mounting.

1.17     see 1.14.

1.18     Radio transmission will be transparent to transmission
         of data to and from the MEDS.

1.19     VDU's will be connected through S-4 cables, i.e. a
         two wire connection. The two multiplexors used will
         be transparent to CR equipment. New interface board
         will be needed in VDU's and in mux-XTA interface. Signaal
         will provide a spec. on the S-4 cable, and CR will
         find a solution by introducing necessary conversion
         board in terminals and at the message shelter for connection
         to the exchange. The S-4 cable is suited for the V11
         interface, CR will investigate this.

1.20     The special cable between the two shelter will be a
         normal TDX cable, in an armed version. Signaal will
          provide this cable with connectors in accordance with
         CR specification, ref. CR80 handbook pg. 860 and pg
         865.




2.0      Miscellaneous

2.1      Regarding responsibility of installation CR has agreed
         to be responsible for installation in the Netherlands
         by having a supervisor at site, who will be in charge
         of the installation of CR equipment using Signaal installation
         personel. Signaal will take over responsibility when
         CR has succesfully installed the equipment. The MEDS
         will be delivered and paid as a subsystem independently
         of other subssystem.

2.2      Signaal has prepared the proposal following the IFB
         word by word, but made some exceptions. CR will proofread
         it and suggest any necessary change with the objective
         to be fully compliant. The document will be signed
         by CR and Signaal as basis for the agreement between
         CR and Signaal.

2.3      Spare part prices are needed for 1 month spare parts,
         i.e. components which is subject to failure by human
         errors during 1 month. No 12 months spare part prices
         are requested except establishing the RSPL.

2.4      Signaal requested a quote for a training of 20 operators
         to be performed in Huizen by CR.

2.5      DMKL does not requet an Installation Manual. CR will
         remove it from proposal.

2.6      Signaal provided CR with a list of QA procedures to
         be followed in the project. CR will comment.

2.7      Warranty will have to be extended from the normal 12
         months to 20 months. Signaal will provide the exact
         number of month by telex on October 8, 12982.

2.8      Rights to S/W will have to be solved by CR and the
         Signaal management.

2.9      CR has to include extra codification in the offer.

2.10     CR hereby states that we will maintain MEDS's H/W and
         S/W after delivery to DMKL.

2.11     The bid validity starts on November 4 and continue
         for 6 months.

2.12     Signaal would prefer CR to accept the same payment
         terms as DMKL has stated in the IFB, i.e. 30% on SOP
         and 70% on acceptance of H/W. CR may consider a 30%,
         
         60%, 10% on SOP, factory acceptance and scheduled final
         acceptance respectively. The updated price proposal
         is based on the above suggested 30, 60, 10 schedule.



2.13     Compliance sheets.

         CR will evaluate the consequence of accepting the responsibility
         for shock and vibration. (sec. 1.1).

         Codification: effort has to be expanded (sec. 3) CR
         will evaluation consequences.

         EMI/EMC. CR will update the offer with regard to fullfilling
         MIL-STD-461, which allows commercial standards (sec.
         1).

         ESD. CR will evaluate the risk of this requirement
         (see 2).

         AC power. 

         CR will change the tex in the proosal (see 3.5.1.).
         Increase in AC voltage will be more detailed in the
         proposal.


         Electrical safety (sec. 3.5.3) is accepted.

         RFI protection. (see 7.3.3) CR will evaluate consequence
         of providing cables to fullfill requirement (sec. 8.3.3),
         sec 9.3.1, (sec 10.5.1), 11.3.1.

         Floppy disc (sec 8.4). Comment to be deleted.

         Teleprinter interface needs XTA (sec 14.16-17-18).



                  3  C̲O̲S̲T̲ ̲C̲O̲N̲S̲I̲D̲E̲R̲A̲T̲I̲O̲N̲S̲


         Listed below are items that will affect the cost of
         the MEDS.


ITEM                              COST            COST
                                  INCREASE        DECREASE
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲

Signall Price Reduction request                       x
Shock and Vibration Req.             x
20 Month Warranty                    x
Operator Training                    x
Additional Units Codification        x
Only 1 Month Supply of Spares                         x
Q/A Cross Ref.                       x
AQAP-1 Certification                 x
(30,70%) Payment Schedule            x
EMI/EMC/RFI  Req.                    x
Transparent Subcontractor            x
No Installation Manual                                x
Operator Instruction Chart.          x
Assembly Breakdown Crossreference    x
Increased Install. Aid               x
H/W Config. Simplification                            x
V 11 I/F                             x
Price in HFL                                          x