⟦43b7e2744⟧ Wang Wps File

    Length: 21723 (0x54db)
    Types: Wang Wps File
    Notes: CRT/TSS/001               
    Names: »1402A «

Derivation

└─⟦c9afadba6⟧ Bits:30006061 8" Wang WCS floppy, CR 0093A
    └─ ⟦this⟧ »1402A « 

WangText

…00……00……00……00……00…-…0a……00……00…-…0b…-…0f…-…00…-…01…-…05…-…07…,…0b…,…0c…,…0d…,…01…,
,…07…+…08…+…09…+…0d……86…1                                             …02…           …02…   …02…        

…02…CRT/TSS/001

…02…GT/811123…02……02…
FACTORY ACCEPTANCE TEST SPECIFICATION
AND PROCEDURE…02…ISSUE 1…02…CRT








4.1.19   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲A̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲



4.1.19.1 T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1   Connect the equipment under test with the supporting
             equipment as shown in figure 4.1.19-1.

         2.1 Check the LTUX-S configuration. The correct configuration
             is described in Appendix A para. 3.1.1.

             The device no. of LTUX-S no. 1 shall be set to
             13…0f…H…0e… and for LTUX-S no. 2 to 14…0f…H…0e….

         2.2 Check that the Stat. Mux. configuration is in accordance
             with the description of Appendix E.

         3   Set the Mode select switch on the BSM-X no. 1 to
             "MAN" and the Bus select switch to "1". On BSM-X
             no. 2 and no. 3 the switches shall be set to "MAN"
             and "OFF".

         4   Turn power on supporting equipment.

         5   Turn power on equipment under test.

         6   Boot test drive system as described in Appendix
             F, part I.



4.1.19.2 T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.1.19-1
         TEST CONFIGURATION SITE 4A  (SHEET 1 OF 2)



















































         FIGURE 4.1.19-1
         TEST CONFIGURATION SITE 4A (SHEET 2 OF 2)


4.1.19.3 T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 1/19


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Interface to TDX-bus, CRT channels,
                        and Crypto/Modem, and Stat. Mux. Multiplexing
                        Traffic flow control

         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1       Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication


            COMMENTS













                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR




4.1.19.4 T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.



4.1.20   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲B̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲



4.1.20.1 T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1   Connect the equipment under test with the supporting
             equipment as shown in figure 4.1.20-1.

         2.1 Check the LTUX-S configuration. The correct configuration
             is described in Appendix A para. 3.1.1.

             The device no. of LTUX-S no. 2 shall be set to
             13…0f…H…0e… and for LTUX-S no. 1 to 14…0f…H…0e….

         2.2 Check that the Stat. Mux. configuration is in accordance
             with the description of Appendix E.

         3   Set the Mode select switch on the BSM-X no. 1 to
             "MAN" and the Bus select switch to "1". On BSM-X
             no. 2 and no. 3 the switches shall be set to "MAN"
             and "OFF".

         4   Turn power on supporting equipment.

         5   Turn power on equipment under test.

         6   Boot test drive system as described in Appendix
             F, part I.



4.1.20.2 T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.1.20-1
         TEST CONFIGURATION SITE 4B  (SHEET 1 OF 2)



















































         FIGURE 4.1.20-1
         TEST CONFIGURATION SITE 4B (SHEET 2 OF 2)


4.1.20.3 T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 1/20


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Interface to TDX-bus, CRT channels,
                        and Crypto/Modem, and Stat. Mux. Multiplexing
                        Traffic flow control

         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1       Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication


            COMMENTS













                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR




4.1.20.4 T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.



4.1.21   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲C̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲



4.1.21.1 T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1   Connect the equipment under test with the supporting
             equipment as shown in figure 4.1.21-1.

         2.1 Check the LTUX-S configuration. The correct configuration
             is described in Appendix A para. 3.1.1.

             The device no. of LTUX-S no. 3 shall be set to
             13…0f…H…0e… and for LTUX-S no. 4 to 14…0f…H…0e….

         2.2 Check that the Stat. Mux. configuration is in accordance
             with the description of Appendix E.

         3   Set the Mode select switch on the BSM-X no. 2 to
             "MAN" and the Bus select switch to "1". On BSM-X
             no. 1 and no. 3 the switches shall be set to "MAN"
             and "OFF".

         4   Turn power on supporting equipment.

         5   Turn power on equipment under test.

         6   Boot test drive system as described in Appendix
             F, part I.



4.1.21.2 T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.1.21-1
         TEST CONFIGURATION SITE 4C  (SHEET 1 OF 2)



















































         FIGURE 4.1.21-1
         TEST CONFIGURATION SITE 4C (SHEET 2 OF 2)


4.1.21.3 T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 1/21


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Interface to TDX-bus, CRT channels,
                        and Crypto/Modem, and Stat. Mux. Multiplexing
                        Traffic flow control

         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1       Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication


            COMMENTS













                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR




4.1.21.4 T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.



4.1.22   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲D̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲



4.1.22.1 T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1   Connect the equipment under test with the supporting
             equipment as shown in figure 4.1.22-1.

         2.1 Check the LTUX-S configuration. The correct configuration
             is described in Appendix A para. 3.1.1.

             The device no. of LTUX-S no. 5 shall be set to
             13…0f…H…0e…, for LTUX-S no. 4 to 14…0f…H…0e…, for LTUX-S no. 3
             to 15…0f…H…0e… and for LTUX-S no. 6 to 16…0f…H…0e….

         2.2 Check that the Stat. Mux. configuration is in accordance
             with the description of Appendix E.

         3   Set the Mode select switch on the BSM-X no. 2 and
             no. 3 to "MAN" and the Bus select switch to "1".
             On BSM-X no. 1 the switches shall be set to "MAN"
             and "OFF".

         4   Turn power on supporting equipment.

         5   Turn power on equipment under test.

         6   Boot test drive system as described in Appendix
             F, part I.



4.1.22.2 T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.1.22-1
         TEST CONFIGURATION SITE 4D,  (SHEET 1 OF 2)



















































         FIGURE 4.1.22-1
         TEST CONFIGURATION SITE 4D,  (SHEET 2 OF 2)


4.1.22.3 T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 1/22


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Interface to TDX-bus, CRT channels,
                        and Crypto/Modem, and Stat. Mux. Multiplexing
                        Traffic flow control

         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1       Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication


            COMMENTS













                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR




4.1.22.4 T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.



4.1.23   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲D̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲,̲ ̲V̲2̲8̲ ̲(̲L̲/̲L̲)̲ ̲L̲i̲n̲e̲s̲



         This section has been incorporated in 4.1.22.





         These pages are intentionally left blank.



4.1.24   T̲e̲s̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲4̲E̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲



4.1.24.1 T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1   Connect the equipment under test with the supporting
             equipment as shown in figure 4.1.24-1.

         2.1 Check the LTUX-S configuration. The correct configuration
             is described in Appendix A para. 3.1.1.

             The device no. of LTUX-S no. 6 shall be set to
             13…0f…H…0e… and for LTUX-S no. 5 to 14…0f…H…0e….

         2.2 Check that the Stat. Mux. configuration is in accordance
             with the description of Appendix E.

         3   Set the Mode select switch on the BSM-X no. 3 to
             "MAN" and the Bus select switch to "1". On BSM-X
             no. 1 and no. 2 the switches shall be set to "MAN"
             and "OFF".

         4   Turn power on supporting equipment.

         5   Turn power on equipment under test.

         6   Boot test drive system as described in Appendix
             F, part I.



4.1.24.2 T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.1.24-1
         TEST CONFIGURATION SITE 4E (SHEET 1 OF 2)



















































         FIGURE 4.1.24-1
         TEST CONFIGURATION SITE 4E  (SHEET 2 OF 2)


4.1.24.3 T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 1/23


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Interface to TDX-bus, CRT channels,
                        and Crypto/Modem, and Stat. Mux. Multiplexing
                        Traffic flow control

         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1       Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication


            COMMENTS













                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR




4.1.24.4 T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.



4.2      T̲E̲S̲T̲G̲R̲O̲U̲P̲ ̲2̲

         The tests in this testgroup are performed to verify
         the ability of the Stat. Mux. to recover from a transmission
         error.

         The test is performed with remote site 4C equipment
         and main site equipment normally used for site 4C and
         4D.

         Compared to the tests in testgroup 1 the following
         additional capabilities are demonstrated with this
         test:

             Recovery from transmission errors (SDS para. 3.2.1.1
             b.2)).

             The transmission error is introduced on the mux-line
             by inverting a single databit. This enables read-out
             of the number of retransmissions from the Stat.
             Mux.



4.2.1    T̲e̲s̲t̲ ̲o̲f̲ ̲N̲o̲r̲m̲a̲l̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲ ̲t̲o̲ ̲8̲ ̲c̲h̲a̲n̲n̲e̲l̲s̲

         This section has intentionally been deleted.





         These pages intentionally left blank.




4.2.2    T̲e̲s̲t̲ ̲o̲f̲ ̲R̲e̲c̲o̲v̲e̲r̲y̲ ̲f̲r̲o̲m̲ ̲T̲r̲a̲n̲s̲m̲i̲s̲s̲i̲o̲n̲ ̲E̲r̲r̲o̲r̲s̲



4.2.2.1  T̲e̲s̲t̲ ̲S̲e̲t̲-̲U̲p̲

         1       Connect the equipment under test with the supporting
                 equipment as shown in figure 4.2.2-1. Note
                 the special wiring within rack H.

         2.1     Check the LTUX-S configuration. The correct
                 configuration is described in Appendix A para.
                 3.1.1.

                 The device no. of LTUX-S no. 3 shall be set
                 to 13…0f…H…0e… and for LTUX-S no. 4 to 14…0f…H…0e….

         2.2     Check that the Stat. Mux. configuration is
                 in accordance with the description of Appendix
                 E.

         3       Set the Mode select switch on the BSM-X no.
                 2 to "MAN" and the Bus select switch to "1".
                 On BSM-X no. 1 and no. 3 the switches shall
                 be set to "MAN" and "OFF".

         4       Turn power on supporting equipment.

         5       Turn power on equipment under test.

         6       Boot test drive system as described in Appendix
                 F, part I.



4.2.2.2  T̲e̲s̲t̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲

         Perform initialization as described in Appendix F,
         Part II.























































         FIGURE 4.2.2-1
         TESTGROUP 2, TEST CONFIGURATION
         (SHEET 1 OF 2)



















































         FIGURE 4.2.2-2
         TESTGROUP 2, TEST CONFIGURATION
         (SHEET 2 OF 2)


4.2.2.3  T̲e̲s̲t̲ ̲S̲t̲e̲p̲s̲


                                        G̲R̲O̲U̲P̲/̲T̲E̲S̲T̲ ̲N̲O̲.̲:̲ 2/1


         F̲U̲N̲C̲T̲I̲O̲N̲:̲      Recovery from transmission error.


         R̲E̲F̲.̲ ̲S̲D̲S̲ ̲P̲A̲R̲A̲:̲ 3.2.1.1, 3.2.1.2, and 3.2.3

         D̲A̲T̲E̲:̲

          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         PROC.   ACTION                 EXPECTED RESULT
         STEP
         NO.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         ̲ ̲ ̲ ̲ ̲ ̲

         1.      Start up the test by   Print out on the Line
                 writing:               Pinter identical with
                 DO DELTA.TEST ̲4  CR    the print out in Appendix
                 on the console         D, apart from the time
                                        indication.
         1.2     While the MSPs are
                 printing, push the     On the MSPs a print
                                        out 
                 button on the "bit-    of "FOX" messages will
                                        
                 printer"               appear.

         1.3     Read the number of     One transmission shall
                 retransmissions by     have taken place
                 aid of a data ter-
                 minal connected to
                 the Stat. Mux. 
                 Command Port.



            COMMENTS


                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                TEST WITNESSES


                                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                        ̲ ̲ ̲ ̲ ̲ ̲
                                                 TEST QA GQAR



4.2.2.4  T̲e̲s̲t̲ ̲T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲

         1   When the line printer connected to the test drive
             system has stopped, the print out is ready for
             comparison with the listing of Appendix D.

         2   Close-down by

         2.1 Remove the discettes from the floppy-drive.

         2.2 Turn power off the equipment under test.

         2.3 Turn power off the supporting equipment.
























               A  P  P  E  N  D  I  X    A
            ---------------------------------

                    TEST DRIVE SYSTEM



         A̲ ̲ ̲T̲e̲s̲t̲ ̲D̲r̲i̲v̲e̲ ̲S̲y̲s̲t̲e̲m̲

         The Test Drive System is described in

         CRT TEST PACKET USERS MANUAL
         FIX/0000/USM/0005
























               A  P  P  E  N  D  I  X    B
            ---------------------------------

                    TERMINAL EQUIPMENT




         B̲.̲ ̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲

         1.  E̲q̲u̲i̲p̲m̲e̲n̲t̲

             1.1 V̲D̲U̲ ̲w̲i̲t̲h̲ ̲O̲p̲t̲o̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲

                 The VDU with Opto Interface is a Delta Data
                 VDU model 7260T with OMDT module type OM-1
                 installed.

             1.2 V̲D̲U̲ ̲w̲i̲t̲h̲ ̲V̲2̲8̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲

                 The VDU with V28 Interface is a Delta Data
                 VDU model 7260T.

             1.3 M̲S̲P̲ ̲w̲i̲t̲h̲ ̲V̲2̲8̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲

                 The MSP is a TRACOR MSP model 8000 RO.

         2.  D̲a̲t̲a̲ ̲S̲p̲e̲e̲d̲s̲

             The Terminal Equipment shall be set to 1200 bit/s
             operation.
























               A  P  P  E  N  D  I  X    C
            ---------------------------------

                   INTERFACE EQUIPMENT




         C̲.̲ ̲I̲N̲T̲E̲R̲F̲A̲C̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         1.  C̲r̲y̲p̲t̲o̲

             The Crypto is a SHAPE supplied BID 1000.

         2.  M̲o̲d̲e̲m̲

             The Modem is a SHAPE supplied synchronuos modem
             for 2400 and 4800 bit/s operation.
























               A  P  P  E  N  D  I  X    D
            ---------------------------------

         Print out for 8 channel test


























               A  P  P  E  N  D  I  X    E
            ---------------------------------

Statistical Multiplexer…01……01…Configuration for Factory Acceptance Test



         E̲.̲ ̲S̲t̲a̲t̲.̲ ̲M̲u̲x̲'̲s̲ ̲-̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲
            T̲e̲s̲t̲

         1.  Set all stat. mux's switches "open"

         2.  Select a Master stat. mux.

         3.  Set master-mux switches as follows:

             B̲a̲s̲e̲    M̲o̲d̲u̲l̲e̲ S̲w̲i̲t̲c̲h̲ ̲1̲

             Pos 1   Open             Not used
             Pos 2          Closed    Normal Operation (Modem
                                      Clock)
             Pos 3          Closed    Down line load enabled
             Pos 4   Open             Flow Control by CTS
             Pos 5   Open             Data Compression Disabled
             Pos 6   Open             Echoplex Disabled
             Pos 7          Closed    EIA Controls enabled
             Pos 8          Closed    Master Unit

             B̲a̲s̲e̲    M̲o̲d̲u̲l̲e̲ S̲w̲i̲t̲c̲h̲ ̲2̲

             Pos 1          Closed    Synchronous operation
             Pos 2          Closed    Modem clock
             Pos 3   Open   
             Pos 4   Open
             Pos 5   Open             Not used
             Pos 6   Open
             Pos 7   Open             Terminal Control Disabled
             Pos 8   Open             Sync loss Disconnect Disabled

         4.  All Other Switches, Base module  S3, S4, Exp. Module
             S1, S2.

             B̲a̲s̲e̲    M̲o̲d̲u̲l̲e̲ S̲w̲i̲t̲c̲h̲ ̲2̲

             Pos 1   Open
             Pos 2          Closed    1200 bps/8 bit data/ 
                                      1 bit-step
             Pos 3   Open
             Pos 4          Closed
             Pos 5   Open
             Pos 6          Closed    1200 bps/8 bit data/
                                      1 bit-step
             Pos 7   Open
             Pos 8          Closed



         5.  Set slave-mux switches as follows:

             B̲a̲s̲e̲    M̲o̲d̲u̲l̲e̲ S̲w̲i̲t̲c̲h̲ ̲1̲

             Pos 1   Open
             Pos 2   Open
             Pos 3          Closed    Down line load enabled
             Pos 4   Open
             Pos 5   Open
             Pos 6   Open
             Pos 7   Open
             Pos 8   Open             Slave unit

             B̲a̲s̲e̲    M̲o̲d̲u̲l̲e̲ S̲w̲i̲t̲c̲h̲ ̲2̲

             Pos 1          Closed    Sync. operation
             Pos 2          Closed    Modem Clock
             Pos 3   Open
             Pos 4   Open
             Pos 5   Open
             Pos 6   Open
             Pos 7   Open
             Pos 8   Open

             All other switches shall be "open" in all positions































A  P  P  E  N  D  I  X    F…01…--------------------------------


         Part I:  Boot of Test Driver System
         Part II: Test Initialization