⟦4c84fc2ad⟧ Wang Wps File

    Length: 11340 (0x2c4c)
    Types: Wang Wps File
    Notes: IDCN -EL-BIT Vol. II      
    Names: »4315A «

Derivation

└─⟦2d59e51b9⟧ Bits:30006026 8" Wang WCS floppy, CR 0397A
    └─ ⟦this⟧ »4315A « 

WangText

…07……00……86…1         …02…   …02…   …02…   …02…                                           




IDCN - VOLUME II                                  SYS/83-11-18

TECHNICAL PROPOSAL                                  Page   







   6  INSTALLATION ..................................
       

     6.1 EQUIPMENT INSTALLATION......................
         
     6.2 REQUIREMENT ANALYSIS........................
         
     6.3 INSTALLATION PLANING........................
         
       6.3.1 Site Survey.............................
           
       6.3.2 Installation Plan.......................
           
       6.3.3 Transportation Plan.....................
           
       6.3.4 Site Preparation Requirements...........
           
       6.3.5 Equipment Installation Drawings.........
           

     6.4 TRANSPORTATION OF THE EQUIPMENT.............
         
     6.5 SITE INSTALLATION...........................
         
     6.6 CHARGES ....................................
         
       6.6.1 Installation Changes ...................
           
       6.6.2 Transportation Charges .................
           


                     6̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



6.1      E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



6.2      R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲ ̲A̲N̲A̲L̲Y̲S̲I̲S̲

         a)  Contractor shall make the following major deliveries
             to ELBIT (customer):

             -   Transportation Plan
             -   Installation Plan
             -   Site Preparation Requirements (Site Facility
                 Plan)
             -   Equipment Installation Drawings
             -   Delivery and Installation of Equipment

         b)  The Transportation Plan shall describe contractors
             procedures for packaging and transportation. Packaging
             of central equipment and peripherals will correspond
             to the requirements for air and truck transport
             to the site.

         c)  The Installation Plan shall contain contractors
             planning of site cabling and equipment installation.
             Furthermore the Plan specifies the division of
             responsibilities between ELBIT and contractor concerning
             site preparation and installation.

         d)  Site Preparation Requirements (SPR) shall specify
             the extent of site preparation regarding structural
             and Ambient requirements customer must undertake
             before equipment can be installed. In order to
             generate the SPR Contractor will, jointly with
             ELBIT, carry out a Site Survey at each of the four
             node sites.

         e)  The equipment installation drawings (EID) shall
             show how the proposed equipment is installed and
             interconnected.

         f)  Delivery and installation of equipment will be
             performed in accordance with the master schedule
             after Contractor, in conjunction with ELBIT, has
             verified that each of the four node sites has been
             prepared in accordance with the Site Preparation
             Requirements. The equipment is delivered C.I.F.
             Site.


6.3      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲N̲I̲N̲G̲

         a)  The planning of the installation will start immediately
             after contract award. The time span from contract
             award to completion of installation can be divided
             in two major phases:

             1)  Site Preparation
             2)  Site Installation

         b)  The main activities in phase 1 are proposed as
             follows:

             1)  Site survey within five months after contract
                 award.

             2)  Preparation and delivery of an Installation
                 Plan and a Transportation Plan.

             3)  Preparation and delivery of site preparation
                 requirements 3 months prior to on-site installation.

             4)  Preparation and delivery of equipment installation
                 drawings one month prior to on-site installation.

             5)  Site readiness verification prior to start
                 of equipment installation.

                 The main activities in phase 2 are:

             6)  Transportation to site.

             7)  On-site installation.

         c)  A more detailed description of the phase 1 and
             2 activities is presented in the following sections.



6.3.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲

         a)  Contractor will, together with ELBIT, perform a
             site survey with customer participation at each
             of the four node sites. The purpose of the surveys
             will be to gather information for the preparation
             of site preparation requirements and plans for
             on-site integration and installation.



         b)  An important task to be performed in conjunction
             with customer during the survey meetings is to
             determine the layout of the equipment rooms, and
             the location of the terminal devices.

         c)  Building schematics and civil engineering drawings
             are to be used for the survey and should be handed
             over to contractor at start of the survey.



6.3.2    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲l̲a̲n̲

         An Installation Plan which outlines the various tasks
         to be accomplished concerning site preparation and
         installation will be issued.

         The plan will address the requirements to installation
         and outline the responsibilities of ELBIT and Contractor
         concerning site preparation and installation.

         The plan will be prepared to address the following
         installation issues:

         -   Site preparation and installation responsibilities
             and requirements.

         -   Accomplishment of site surveys and site verifications.

         -   Installation documentation (SPR, EID) requirements,
             preparation and delivery.

         -   Installation phase activities.



6.3.3    T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲P̲l̲a̲n̲

         A Transportation Plan which outlines the planning and
         coordination to be performed will be issued.

         The Plan will address the requirements to packing and
         transportation and be prepared to cover the following:

         -   Requirements for packing, packaging and transportation.

         -   CR preservation, packing, and packaging of equipment
             and spare parts.

         -   Marking and coding.



         -   Shipping documentation including, customs forms,
             and packing lists.

         -   Notice of shipment.



6.3.4    S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

         a)  Contractor will generate Site Preparation Requirements
             (SPR) concerning the preparation of each of the
             four node sites for installation of the proposed
             equipment. The SPR will be submitted to Customer
             for approval 3 months prior to start of installation.

         b)  The SPR will be based on the site data collected
             during the site survey, the equipment rooms layouts
             and the physical characteristics of the proposed
             equipment.

         c)  The SPR will contain requirements to access, space,
             power, power distribution, quantity and location
             of power outlets, heat dissipation cable ducting,
             etc.



6.3.5    E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  Contractor will deliver equipment installation
             drawings for each of the four nodes to Customer
             for approval 1 month prior to start of installation.

         b)  The approved installation drawings will be used
             for the installation of the proposed equipment
             on each site.

         c)  The equipment installation drawings will be based
             on the approved site preparation requirements,
             the hardware configuration and the equipment characteristics.

         d)  The drawings will show how the proposed equipment
             is to be installed and integrated.





6.4      T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲H̲E̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         a)  The delivery of equipment will follow the master
             schedule. Actual shipping dates are selected to
             be in accordance with the readiness of site and
             time for transportation.

         b)  The equipment will be shipped by air and truck
             and packed accordingly. Contractor will arrange
             the transportation so that his installation team
             will be present at site for receipt and unpacking
             of the equipment for the first node installation.

         c)  The packing and marking are proposed to be in accordance
             with Contractors standard procedures for CR80 equipment.
             The following is a brief discussion of the method:

         d)  The computer equipment is constructed in a modular
             fashion. i.e. 19" racks containing crate assemblies
             with plug-in modules. This is reflected in the
             packaging as follows:

             1)  Modules are packed in styrofoam containers
                 designed to fit each module size. A number
                 of modules are put into a cardboard box or
                 similar of Europe pallet standard size.

             2)  Crates are packed with styrofoam corners so
                 that they fit into a cardboard box of Europe
                 pallet standard size.

             3)  Each rack or cabinet bay is separately packed
                 on a wooden pallet, protected with styrofoam
                 corners, and wrapped in plastic sheets. A skeleton
                 of timber protects the five free surfaces.

             4)  Spare parts are packed individually in accordance
                 with the methods outlined in 1-3 above. In
                 addition spare parts are wrapped and sealed
                 in a plastic bag with silicagel for long term
                 storage. Each spare package is provided with
                 a label specifying contents.

         e)  Packing lists are forwarded with every shipping
             container. One copy of the packing list is enclosed
             in the container; on copy will be attached to the
             exterior of the container in an envelope clearly
             marked "packing list".



             Two copies of the packing lists shall be provided
             to the customer. Each packing list will show:

             -   Shipping address
             -   Package number
             -   Contract number
             -   Contract item number
             -   Item description
             -   Part number
             -   Serial Number (if available)
             -   Quantity shipped
             -   Date shipped

         f)  Each container is to be clearly marked on the exterior
             surface with at least:

             -   Project Title 
             -   Purchaser Contract Number
             -   Contract Item Number
             -   Manufacturer's name and address
             -   Ship to address

             In addition, each container is clearly labelled
             with the identification and number of pieces in
             the shipment and with precautionary labelling applicable
             to handling.



6.5      S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         a)  The contractor will set up an installation team
             to perform the installation of the first node,
             in conjunction with ELBIT. The purpose of the joint
             installation will be to enable ELBIT to perform
             the installation of the remaining hardware. The
             team will install the equipment in accordance with
             the Customer approved site installation drawings.
             Any changes during installation will be marked
             on the drawings. Corrected drawings will be submitted
             to Customer after completion of site installation.

         b)  Installation check-out encompassing hardware verification
             will be performed in accordance with an installation
             check-out procedure.



6.6      C̲H̲A̲R̲G̲E̲S̲



6.6.1    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲c̲h̲a̲r̲g̲e̲s̲

         The installation charges are based on the following
         assumptions:

         a)  All site preparations i.e. power, grounding, external
             signal cabling and termination, ducting, aircordition
             atc., are made by customer.

         b)  Site surveys can be made in one roundtrip.

         c)  Site verifications can be made in max. two roundtrips.

         The installation charges somprises the following:

         1)  Management and planing incl.:

             Installation plan
             Transportation plan
             Site survey
             Site verification
             Site preparation requirements
             Equipment installation drawings

         2)  Hardware installation of one node site.



6.6.2    T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲c̲h̲a̲r̲g̲e̲s̲

         The transportation charges comprises packing, packing
         labor, transportation and transportation insurance
         costs. The delivery is quoted CIF site.

         It is assumed that the equipment is delivered as 5
         shipments:

         -   One shipment for each of the four node systems
         -   One shipment for the spare system.

         It is also assumed that all equipment associated with
         one node site can be delivered at one location.