DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦4da56aa09⟧ Wang Wps File

    Length: 34286 (0x85ee)
    Types: Wang Wps File
    Notes:                           
    Names: »2919A «

Derivation

└─⟦81108f261⟧ Bits:30006114 8" Wang WCS floppy, CR 0183A
    └─ ⟦this⟧ »2919A « 

WangText

…00……00……00……00……00…A…0a…A…0b…A…0c…@…09…@…0d…@ ?…09…?…0e…? >…08…>…0a…>…0d…>…0e…>…00…>…01…>
>…86…1                                             …02…           …02…   …02…        






                       CR                       TRACOR
            QUANTITY                    QUANTITY
         Pr. Site  accum.  date       per shipm. accum.  ship
                                                         date
         --------------------------------------------------------

 1. Site 11         11     f]r        14          14     Oct.
                                                         82
 2. Site 10         21     17/11
 3. Site 11         32     82
 4. Site 13         41     6/12 82    
 Training
 (note)  4(9)       49     15/12 82
 5. Site 12         61     20/12 82   32…0e…1)…0f…        46     17/12
                                                         82
 6. Site 10         71     17/1 83    21          67     15/1
                                                         83
 7. Site  6         77     28/3 83     6          73     28/3
                                                         83
 8. Site 10         87     25/4 83    24          97     15/4
                                                         83
 9. Site 11         98     16/15 83   
10. Site  9        107     13/6 83    30         127     31/5
                                                         83
11. Site 11        118     11/7 83    30         157     30/6
                                                         83
12. Site 11        129     1/8 83     29         186     30/7
                                                         83
13. Site 12        141     22/8 83
14. Site 10        151     19/9 83    14         200     31/8
                                                         83
15. Site 20        171     17/10 83
16. Site 12        183     14/11 83

Note:    Totalt 9 printere p> training site, men 5 kan tages
         fra non-tempest shipment (14 printere).

1)       Tracor vil fors]ge at fremskynde delleverance p> enten
         7 ell. 18 printere til shipment 8/12-82.




Bjarne Berthold










Det Reiensenske Fond
Christian d. IX's Gade 3
1111  K]benhavn K




                                             1983-02-09
                               






Undertegnede tillader sig hermed at ans]ge om st]tte til studier
 ved INSEAD, Fontainebleau, Frankrig.

Kurset der har min interesse er et syv ugers kursus med betegnelsen
 "Executive Programme". Kurset afvikles i april/maj 1984 og tilmelding
 skal foreg> inden oktober 1983.

Det er ovenn`vnte tilmeldingsfrist, som g]r, at jeg s]ger st]tte
 p> nuv`rende tidspunkt og ikke afventer en senere uddeling af
 fondets midler.

Nedenfor g]res rede for f]lgende forhold:

         -   Personlige data
         -   Teoretisk uddannelse
         -   Anvendelse af st]tte
         -   St]rrelse af ans]gte st]tte
         -   Andre ans]gninger
         -   Baggrund for ans]gning
         -   Eksamensbeviser/udtalelser





Med venlig hilsen



Kurt Nybroe-Nielsen



                         

 a:  P̲e̲r̲s̲o̲n̲l̲i̲g̲e̲ ̲d̲a̲t̲a̲

     Kurt Nybroe-Nielsen
     Civilingeni]r, HD
     Mosevangen 11
     2860  S]borg

     F]dt: 30. oktober 1948, K]benhavn

     Tlf. privat:   01 67 90 84
     Tlf. arbejde:  02 65 11 44 (395/381)

 b:  T̲e̲o̲r̲e̲t̲i̲s̲k̲ ̲u̲d̲d̲a̲n̲n̲e̲l̲s̲e̲

     Civilingeni]r 1974, Svagstr]m
     HD 1977, Organisation

 c:  A̲n̲v̲e̲n̲d̲e̲l̲s̲e̲ ̲a̲f̲ ̲s̲t̲]̲t̲t̲e̲

     En eventuel st]tte vil blive brugt til syv ugers
     studie ved

     INSEAD, Fontainebleau, Frankrig
     "Executive Programme"

     Prisen for det kursus er ca. kr. 80.000, hvilket
     d`kker alle udgifter eksklusiv rejseudgifter.

 d:  S̲t̲]̲r̲r̲e̲l̲s̲e̲ ̲a̲f̲ ̲a̲n̲s̲]̲g̲t̲e̲ ̲s̲t̲]̲t̲t̲e̲:̲

     Idet jeg endnu ikke har modtaget st]tte fra anden
     side ]nskes st]rst mulig st]tte til delvis d`kning
     af oven- st>ende kursusudgifter.

 e:  A̲n̲d̲r̲e̲ ̲a̲n̲s̲]̲g̲n̲i̲n̲g̲e̲r̲

     Det skal oplyses at jeg har s]gt st]tte fra Arbejds-
     giverforeningens Jubil`umsfond. Herfra foreligger
     der imidlertid endnu ikke nogen afg]relse om st]tte.

 f:  B̲a̲g̲g̲r̲u̲n̲d̲ ̲f̲o̲r̲ ̲a̲n̲s̲]̲g̲n̲i̲n̲g̲ ̲o̲m̲ ̲s̲t̲]̲t̲t̲e̲

     Siden april 1977 har jeg v`ret ansat hos Christian
     Rovsing A/S.

     Baggrunden for ]nsket om en videreg>ende uddannelse
     inden- for ledelses- og forretningsm`ssige metoder
     skal dels ses i de ledelseskrav min nuv`rende stilling
     indeb`rer og dels i ]nsket om fremover at besk`ftige
     mig med ledelse p> et mere generelt niveau.

     For n`rv`rende er jeg afdelingsleder for et projekt,
     der best>r af 50 ingeni]rer, 8 teknikere og 5 sekret`rer.
     Ar- bejdsomr>der er salg, udvikling og levering
     af st]rre EDB systemer til udenlandske kunder.
     Alle ansatte i afdelingen er i ]jeblikket besk`ftiget
     med udvikling af et kommunika- tionssystem, hvor
     kontraktv`rdien er 230 mill. kr.

 g:  E̲k̲s̲a̲m̲e̲n̲s̲b̲e̲v̲i̲s̲e̲r̲/̲u̲d̲t̲a̲l̲e̲l̲s̲e̲r̲

     1)  Civilingeni]r
     2)  HD
     3)  Firmaudtalelse



Til: BHB, BHB, KM, OE, SRA, PMS

Fra: KNN

CC:  URH, JAL, GJ


V̲e̲d̲r̲.̲:̲ ̲S̲i̲t̲e̲ ̲1̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲

Den 21. Januar 1983 blev der afholdt et m]de for at
 f> identificeret og planlagt de aktiviteter, der er
 n]dvendige for at f> Site 1 afleveret hos SHAPE.

Der blev fokuseret p> 5 faser, som skal genneml]bes
 inden den funktionelle test finder sted. Disse faser
 er:

-    F`rdigg]relse af udest>ende hardware-opgaver inden
     nedpakning

-    Readyness inspection                     26/1 1983

-    Transport                                11/2 eller
     14/2 1983

-    Installation                             15/2 1983

-    Perioden mellem installation og functional Main
     CAMPS equipment software test p> site 1.

-    Build 1 demo preparation/presentation    3/3-7/3,
     14/3-17/3 1983

Derudover blev maintenance and diagnostic programmerne
 debateret.

Resultatet af m]det er beskrevet i det f]lgende.


1.   F̲@̲R̲D̲I̲G̲G̲[̲R̲E̲L̲S̲E̲ ̲A̲F̲ ̲H̲A̲R̲D̲W̲A̲R̲E̲-̲A̲K̲T̲I̲V̲I̲T̲E̲T̲E̲R̲ ̲F̲[̲R̲ ̲S̲H̲I̲P̲M̲E̲N̲T̲

 a)  PU

     ECO opdatering

 b)  CU

     ECO opdatering

 c)  TDX

     ECO opdatering



 d)  WATCHDOG

     Ingen aktiviteter

 e)  TERMINALER

     -   VDU: opdateres til PROM version 1.B

         Afklar software-konfigurationen i de nye prommer

         Skift MICRO-fuses

         Indf]r filter omkring Key-locks

     -   MSP

         Ingen aktiviteter

     -   PAPER TAPE READER/PUNCH

         Ingen aktiviteter


2.   R̲E̲A̲D̲Y̲N̲E̲S̲S̲-̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲

 a)  Inventory-listen bestemmer hvilket udstyr, der
     skal    KM/BHB
     v`re til r>dighed umiddelbart inden nedpakning.

 b)  Configurationsloggen bestemmer hvilke serienumre,
     der BHB
     indg>r i configurationen.

     Peripheral-configurationen b]r nu checkes. Dette       BHB
     b]r g]res i samarbejde med ILS
.
 c)  Det er Tove Nielsen, som har ansvaret for nedpakningen,
     derfor b]r Kurt Mikkelsen sikre sig, at Tove Nielsen
     har det forn]dne kendskab til opgaven.

 d)  Tidsplan (Se appendix A)

 e)  Forsikring

     Der skal tegnes forsikring omkring montage og trans-   KM
     port. Ligeledes b]r det unders]ges om brand- og
     tyveriforsikring er n]dvendig, efter at udstyret
     er
     ankommet hos SHAPE.

 f)  Software (M&D, LOAD, SCRATCH)                          BHB/KM

 g)  Software (COMSEC TESTING)                              BHB/KM




3.   T̲R̲A̲N̲S̲P̲O̲R̲T̲

 a)  Transport-procedurerne er beskrevet i detaljer
     i   KM
     dokumentet CPS/AUX/026.

 b)  Udpakningen og den interne transport p> site nr.
     1   KM
     bliver udf]rt i henhold til CPS/AUX/026 udvidet
     med
     MOM med titlen Site verification nr. 1.


4.   I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

 Omkring installation g`lder installations-procedurerne
 CPS/AUX/026.

 a)  Den fysiske installation varetages af KM               KM

 b)  Systemet aftestes efter installation. Dette foreg>r    KM
     ved hj`lp af de nuv`rende Factory Acceptance
     Procedurer for Site nr. 1.

 c)  COMSEC test

     P> den test anvendes de modificerede M&D programmer    KM/BHB
     for at kunne repetere input/output p> en enkelt
     ter-
     minal.

 d)  Tr`ning af installationsteknikere

     Det blev identificeret, at det er n]vdendigt at
     tr`ne
     installationsteknikerne. Dette g]res p> Site nr.
     6 Det er
     planlagt at k]re FAT 6 procedurerne og at S]ren
     Rasmussen skal supervisere.

 e)  Retrofit (MSP, KAU, LTUX, CCA, TIA)                    BHB

 f)  Retrofit af tidligere leveret VDU/Voodruff             BHB/KM


5.   P̲E̲R̲I̲O̲D̲E̲N̲ ̲M̲E̲L̲L̲E̲M̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲G̲ ̲F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲S̲O̲F̲T̲W̲A̲R̲E̲
     ̲T̲E̲S̲T̲

 Umiddelbart inden k]rslen af den funktionelle software
 test, er det n]dvendigt at opdatere hardware. Listen
 nedenfor udg]r den ]jeblikkelige status, som den kendes
 i dag.



 a)  PU

     STI:  2 - 3 udest>ende problemer mapped TDX support    BHB/KM

     TIA:  Som STI                                          BHB/KM

     CCA:  Skal skiftes                                     BHB/KM

     RAM:  @ndres til 512K moduler                          BHB/KM

 b)  CU

     CUCB: @ndres (fylder for meget)                        BHB/KM

     CCA:  Skal skiftes                                     BHB/KM

 c)  TDX

     STI og TIA er beskrevet under pkt. a) PU               BHB/KM

     LTUX-s: Den ny hardware-hybride skal indf]res og
     systemsoftwareapplikationen skal br`ndes i prommerne   BHB/KM

 d)  WATCHDOG

     Ingen `ndringer

 e)  TERMINALER

     -   VDU:  Man skal p>regne endnu en `ndring af
         prommer BHB

     -   DELTA DATA skal udsende en ECO p> micro fuses      BHB/KM

     -   MSP:    PCBerne skal p>regnes `ndret, muligvis     BHB
                 skal pyntelisten omkring vinduet s`ttes
                 p>.

     -   PTR/P: Ingen `ndringer.


6.   S̲C̲H̲E̲D̲U̲L̲E̲

 Tidsplanen for shipment af den f]rste site er 11/2
 eller 14/2 1983.


7.   M̲&̲D̲ ̲P̲R̲O̲G̲R̲A̲M̲ ̲@̲N̲D̲R̲I̲N̲G̲

 M&E programmet for TDX systemet skal `ndres.               BHB/OE



              S U M M A R Y…01…---------------





         o   Adjustment of Master Schedule by three months,
             except for the SHAPE Site



         o   Delivery of CAMPS Software in two increments



         o   Rescheduling of BALTAP From installation Sequence
             No. 2 to 10.





        A D V A N T A G E S…01…----------------------




         -   Increased likelihood that interfaces to TARE, SCARS/CCIS,
             and OCR will be available at the various sites


         -   Early shipment to SHAPE supports


             o   Presentation to future users


             o   Verification of test planning and environments


             o   Incremental verification of the system


             o   Correction of equipment if damaged during transportation


             o   Pressure on the CAMPS development team


             o   Increased credibility in the system within
                 NATO. Thus increasing user acceptance of the
                 system.


         -   BALTAP installation can take place based on a site
             which is completely ready








 D I S A D V A N T A G E S…01…-----------------------------





             o   CR cashflow problem due to increase in costs
                 and delayed payments.









V A L U E   O F   C A M P S   R E L E A S E   1…01…-----------------------------------------------------





         Percentage of total code:        81%




         Percentage of total functions:   77%










            P A Y M E N T S…01…------------------






         CAMPS Release 1:    80% of SPA payment





         CAMPS Final:        20% of SPA payment






       A C C E P T A N C E…01…-----------------------




         CAMPS release 1 shall be accepted as follows:



         -   160 hours in-plant test


         -    20 days functional test


         -    40 days operational test


         CAMPS final release shall be accepted as follows:



         -   80 hours in-plant test


         -   10 days functional test


         -   20 days operational test



  T E S T   S C H E D U L E…01…----------------------------





         CAMPS Release 1                      Start Date
         --------------------                 ----------------



         -   in-plant test                    14/4 - 31/4 1983

         -   functional test                   1/5 - 20/5 1983

         -   operational test                 20/5 - 31/6 1983





         CAMPS Final                          Start Date
         --------------------                 ----------------



         -   in-plant test                     1/7 -  7/7 1983

         -   functional test                   8/7 - 20/7 1983

         -   operational test                 21/7 - 15/8 1983



C O N T R A C T U A L    C O N S I D E R A T I O N S…01…----------------------------------------------------------






         The following areas in the contract shall be changed
         if the subject implementation adjustment is agreed.



         a)  Installation sequence and dates Spec. Prov. {8,
             {9.



         b)  Software implementation and acceptance, Spec. Prov.
             {14, {17, {18.



         c)  Bank guarantee



         Appendix B, D, and C shall be updated accordingly.



                     1̲ ̲ ̲I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲



         With reference to the quality issue on the 128K RAM
         module raised by SHAPE (FAT 1 discrepancy issue 2.2a,
         MOM no. 20) as concluded in MOM no. 23, CR hereby submit
         a Firm Fixed Proposal for updating the RAM module used
         in CAMPS PUs. 

         The document "Summary Report of CAMPS Software Memory
         Sizing", CPS/REP/004 (1) has been delivered to SHAPE.

         The memory budget estimate presented in this document
         is a little lower than 512K per PU.

         The recent budget estimates, at the same design baseline
         as presented in CPS/REP/004 (1), indicates a memory
         requirement above 512K.

         As standardization of memory modules only to include
         one module type has been agreed, Christian Rovsing
         A/S hereby submits a Firm Fixed Proposal for exchanging
         128K RAM modules with 512K RAM modules.

         The total number of modules to be exchanged is 88:

         a)  16 x 4 = 64 modules for sites
         b)           24 spare modules



                    2̲ ̲ ̲P̲R̲I̲C̲E̲ ̲Q̲U̲O̲T̲A̲T̲I̲O̲N̲



2.1      The following cost elements are related to this ECP.


2.1.1    Development and Qualification of
         updated module:                      Dkr.      540.000


2.1.2    Production start-up                  Dkr.      193.000




2.1.3    Replacement cost:  a)- b)            Dkr.    6.463.160

         The cost calculation is based on the assumption, that
         the CAMPS project will be able to sell the 40 128K
         RAM modules already ordered and delivered to the project.

         a)  88 512 K RAM modules
             price each: Dkr 138.668
             total                            Dkr.   12.202.784

         b)  88 128 K RAM modules
             price each: Dkr 65.223
             total                            Dkr.    5.739.624



2.1.4    Documentation update                 Dkr.      131.215


2.1.5    Total 2.1.1+2.1.2+2.1.3+2.1.4        Dkr.    6.787.375


2.2      Sharing of cost (2.1 above) between SHAPE and Christian
         Rovsing A/S is to be negotiated.



             3̲ ̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲ ̲A̲N̲D̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲ ̲I̲M̲P̲A̲C̲T̲


         Final delivery schedule will be established after received
         order.

         Primary planning tells that the first 512K RAM modules
         can be available from CR's production 4-6 months after
         received order.

         The 512K modules will be integrated and tested as part
         of the CAMPS systems through 1983.

         The current FAT-schedule is included in Appendix A.

         After having passed FAT at CR, the modules will be
         integrated in the Site-systems on the sites, which
         have passed FAT.





                  4̲ ̲ ̲B̲I̲D̲D̲I̲N̲G̲ ̲P̲R̲O̲V̲I̲S̲I̲O̲N̲S̲



4.1      V̲A̲L̲I̲D̲I̲T̲Y̲

         This proposal is open for acceptance until February
         14, 1983.


4.2      D̲E̲L̲I̲V̲E̲R̲Y̲

         Refer to paragraph 3. The modules need to be integrated
         in the sites prior to SPA.


4.3      A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲C̲R̲I̲T̲E̲R̲I̲A̲

         The 512K modules will be tested using CPS/TPR/006,
         Factory Acceptance Test Specification and Procedure,
         issue 1.1, test no. 2/1, Test case 3.


4.4      T̲Y̲P̲E̲ ̲O̲F̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲


         Prices given are firm fixed prices.



4.5      P̲A̲Y̲M̲E̲N̲T̲ ̲P̲L̲A̲N̲

         a)  At acceptance of proposal:       30% of overall
                                              costs

         b)  At first FAT:                    70% of non-recurring
                                              costs

         c)  At every FAT                     60% of recurrent
                                              cost

         d)  At SPA                           10% of recurrent
                                              cost





            5̲ ̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲ ̲C̲H̲A̲N̲G̲E̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲



5.1      Total 88 512 K RAM modules shall be delivered to replace
         88 128 K RAM Modules,

         Sites:  16 x 4  = 64 modules
         Spares:           24 modules


5.2      T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲S̲

         Please refer to appendix B, where the required updates
         for CPS/SDS/001 are included.


5.3      A̲F̲F̲E̲C̲T̲E̲D̲ ̲B̲A̲S̲E̲L̲I̲N̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲

         a)  CE-80-9009-INF  Main CAMPS Contract

         b)  CPS/SDS/001     CAMPS System Design Specification

         c)  CPS/SDS/017     Main CAMPS, Assy. Breakdown

         d)                  Test Reports for Sites having
                             passed FAT

         e)                  Inventory lists for shipped sites

         f)  CPS/AUX/003     CAMPS ASPL

         g)  CPS/AUX/029
             CPS/AUX/030     CAMPS Spare Parts list for Repair
                             Depot

         h)  CPS/TCM/005     Maintenance Manual for CAMPS Sites

         i)                  RAM, technical manual

         j)                  Instructors Manual, MT/RST course,
                             week no. 2

         k)                  Instructors Manual, RST course,
                             week no. 8





















A  P  P  E  N  D  I  X     A…01…----------------------------------





















A  P  P  E  N  D  I  X     B…01…----------------------------------



                     1̲ ̲ ̲I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲



1.1      This document has the following objectives:

         a)  Provide status for the quantity of equipment delivered
             from PDI to CAMPS prior to 821228.

         b)  Provide status for the quantity of equipment to
             be delivered in 1983, including Additional CAMPS
             Modules (ref e).


1.2      Two systems were delivered in 1982, which were not
         identified in the matrices of the original contract
         (ref a1, a2, a3), namely:

         (i)     System 0
         (ii)    Training (Comsec) System

         The updated matrices assumes that the delivery situation
         is corrected and updated as follows:

         a)  The training system is the 17th system with the
             configuration as delivered.

             (This system is currently Systems Division property).

         b)  System 0 will be used for Site No. 11 (last in
             sequence).

             As system 0 is a maximum configuration system,
             too much equipment has been delivered on a few
             items.

PDI action:  CAMPS proposes, that the discrepancy is eliminated
             by
Confirm      reducing the 2nd last delivery (site 4) accordingly.

         c)  The site no. 4 (2nd last in sequence) shall be
             equipped based on items from the DSMT-system, currently
             used by DD. The updated matrices identifies the
             additional quantities of items required for the
             update, as well as the quantity of items available
             from the DSMT-system are identified.



1.3          Thus, the following sites are still to be delivered:

             Sequence No.  6     Site 14
             Sequence No.  7     Site  3
             Sequence No.  8     Site 13
             Sequence No.  9     Site 10
             Sequence No. 10     Site 16
             Sequence No. 11     Site  8
             Sequence No. 12     Site  7
             Sequence No. 13     Site 12
             Sequence No. 14     Site  9
             Sequence No. 15     Site  4  (DSMT retrofitted)



                2̲ ̲ ̲T̲O̲T̲A̲L̲ ̲O̲R̲D̲E̲R̲E̲D̲ ̲Q̲U̲A̲N̲T̲I̲T̲Y̲



         The latest update of total ordered quantity of Equipment
         to be delivered from PDI to CAMPS according to ref
         a1) (=ref a2) and ref e) are identified as the sum
         of the following appended matrices:

         (i)     Appendix A: Main Locations

         (ii)    Appendix B: Changes to Remote Terminals, Main
                             Sites

         (iii)   Appendix C: Changes to Remote Terminals, Remote
                             Sites

         (iv)    Appendix D: Remote Tare, Remote Site

         (v)     Appendix E: Training System

         The only group of deliverable items not included in
         App. A-D above is the first lots of equipment delivered
         for CAMPS REMOTE TERMINALS. (This equipment is listed
         in CAMPS Equipment Matrix, CPS/TCN/041, Issue 3 and
         later).

         Appendix A includes all changes on CAMPS Main Sites.

         Apppendices B and C identifies changes on Remote Terminals
         compared to the original baseline of equipment already
         delivered (in 1981).





         3̲ ̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲D̲E̲L̲I̲V̲E̲R̲E̲D̲ ̲P̲R̲I̲O̲R̲ ̲T̲O̲ ̲ ̲8̲2̲1̲2̲2̲3̲



3.1      The following sites have been delivered 821223:

         Site 1  (ref d1)
         Site 2  (ref d2)
         Site 6  (ref d3)
         Site 5  (ref d4)
         Site 15 (ref d5)

         In addition two early systems have been delivered:

         "System 0"
         "Comsec System".

         "System 0" shall be retrofit to be site 11 (No. 16
         in sequence)

         Ccc-log shall be delivered accordingly.

         "Comsec System" shall be retrofit to be training system,
         i.e. the 17th system to be delivered according to ref
         a1).



3.2      The columns of appendices A, B, C, and D, which are
         named:

         Site 1
         Site 2
         Site 6
         Site 5
         Site 15
         Training System 
         Site 11

         identify the equipment already delivered except for
         discrepancies identified in the following comments:


3.2.1    S̲i̲t̲e̲ ̲1̲

PDI Action   a)  Final Ccc-log missing (ref d1)
         b)  Delivered Quantity OK.




3.2.2    S̲i̲t̲e̲ ̲2̲

PDI Action   a)  Delivered Quantity OK (ref d2), except for
                 2 TIAs missing.


3.2.3    S̲i̲t̲e̲ ̲6̲

         a)  Delivered Quantity OK (ref d3).


3.2.4    S̲i̲t̲e̲ ̲5̲

PDI Action   a)  Delivered Quantity OK (ref d4), except for
                 2 128K Ram's missing (See 3.2.8 below).


3.2.5    S̲i̲t̲e̲ ̲1̲5̲

PDI Action   a)  Delivered Quantity OK (ref d5) except for 3
                 128K Ram's missing (See 3.2.8 below).

JRD Action   The site equipment has just been delivered. Quantity
             is not checked by incoming inspection.


3.2.6    S̲i̲t̲e̲ ̲1̲1̲ ̲(̲S̲y̲s̲t̲e̲m̲ ̲0̲)̲

PDI Action   a)  Ccc-log dedicated for site 11 missing

         b)  Delivered Quantity OK, except for the e̲x̲c̲e̲e̲d̲i̲n̲g̲
             quantities identified in appendix G.


3.2.7    T̲r̲a̲i̲n̲i̲n̲g̲ ̲S̲y̲s̲t̲e̲m̲ ̲(̲C̲o̲m̲s̲e̲c̲ ̲S̲y̲s̲t̲e̲m̲)̲

PDI Action   a)  Ccc-log missing

         b)  Delivered Quantity according to Appendix E OK.


3.2.8    1̲2̲8̲K̲ ̲R̲a̲m̲ ̲M̲o̲d̲u̲l̲e̲s̲

         No more 128K Ram Modules shall be delivered.

         Missing 128K Ram modules are only mentioned in the
         sections above for invoice control purposes.




3.2.9    C̲C̲A̲ ̲M̲o̲d̲u̲l̲e̲s̲

         All CCA-modules delivered have been non-conforming
         (P/N 4.04221-01).

         Modules, P/N 4.04221-03 shall be delivered for replacement.

PDI action   A separate schedule for retrofitting -01 with -03
             shall be established.



        4̲ ̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲T̲O̲ ̲B̲E̲ ̲D̲E̲L̲I̲V̲E̲R̲E̲D̲ ̲A̲F̲T̲E̲R̲ ̲8̲2̲1̲2̲2̲3̲



         The following sites shall be delivered during the first
         7 months of 1983:

         Site 14
         Site  3
         Site 13
         Site 10
         Site 16
         Site  8
         Site  7
         Site 12
         Site  9
         Site  4*

         *   Site 4 is based on retrofit of the DSMT-system.
             A list of available equipment from the DSMT is
             provided in Appendix G).

PDI Action   Appendix H contains the delivery schedule wanted
             by SD/CAMPS. Please confirm prior to 830214.







         Bjarne Berthold









       A P P E N D I X   A:…01…**********************


         Equipment Matrix, CAMPS Main Sites

         1.  This matrix must be added with the matrices of
             appendices B, C, D, and E to provide the total
             deliverable quantity of equipment.

         2.  The difference between the Appendix A-matrix and
             the matrix of "Intern Meddelelse 309/365" can be
             found in appendix F of this IM.











       A P P E N D I X   B:…01…***********************

         Equipment Matrix: Changes to CAMPS Remote Terminals/Main
         Sites compared to already delivered equipment (del.
         in 1981).

         1.  This matrix must be added with the matrices of
             appendices A, C, D, and E to provide the total
             deliverable quantity of equipment.











       A P P E N D I X   C:…01…***********************

         Equipment Matrix: Changes to CAMPS Remote Terminals/Remote
         Sites compared to already delivered equipment (del.
         in 1981).

         1.  This matrix must be added with the matrices of
             appendices A, B, D, and E to provide the total
             deliverable quantity of equipment.










       A P P E N D I X   D:…01…***********************

         Equipment Matrix: Remote Tare/Remote Sites.

         1.  This matrix must be added with the matrices of
             appendices A, B, C, and E to provide the total
             deliverable quantity of equipment.












       A P P E N D I X   E:…01…***********************

         Equipment List: CAMPS Training System.

         1.  This matrix must be added with the matrices of
             appendices A, B, C, and D to provide the total
             deliverable quantity of equipment.












       A P P E N D I X   F:…01…***********************

         CAMPS, Main Sites: Matrix for changes to update the
         matrix of "Intern meddelelse nr. 309/365" to the matrix
         of Appendix A of this IM.













       A P P E N D I X   G:…01…***********************

         Matrix showing:

         a)  Additional equipment required to update the DSMT-equipment
             to Site 4:

         b)  Too much delivered equipment, when "system 0" is
             retrofit to Site 11.













       A P P E N D I X   H:…01…**********************


                Proposed Delivery Schedule




            PLANL@GNINGSM[DE…01……01…8. Februar 1983


         Tilstede: KNN, KM, PMS, IJO, BHB, JHO

A̲C̲T̲I̲O̲N̲E̲E̲


         1̲.̲ ̲M̲a̲n̲g̲e̲l̲ ̲p̲>̲ ̲V̲D̲U̲'̲e̲r̲

         6 SW-udviklingssystemer og tr`ningssystemet kr`ver
         6/16 af VDU'erne. Dvs. de 6 sidste systemer mangler
         VDU'er. Med nuv`rende schedule bliver det et problem
         pr. 1/6. Hvis S-systemer kr`ver yderligere 20 VDU'er
         bliver det et problem 1. maj.

         L]sning:

         a)  De VDU'er der er pakket ned efter FAT tages ud
             igen til brug. Dette udskyder problemet til 7.
             sidste shipment, dvs. 1. december 1983.

         b)  Der indk]bes yderligere Delta VDU'er. Der afventes
             SW maintenance system ordre.

KNN/JHO  c)  Der indk]bes non-tempest VDU'er. Relevant for 4
             S-maskiner og 2 D-maskiner.

         JHO laver plan for benyttelsen af VDUer.


         2̲.̲ ̲M̲a̲n̲g̲e̲l̲ ̲p̲>̲ ̲p̲r̲i̲n̲t̲e̲r̲e̲ ̲o̲g̲ ̲S̲M̲D̲-̲d̲i̲s̲k̲s̲

JHO      Det b]r unders]ges om der bliver problemer med printere
         (Tracor) eller disks. 


         3̲.̲ ̲H̲W̲-̲b̲e̲m̲a̲n̲d̲i̲n̲g̲

         Tidsplanen og bemandingen for HW tager ikke h]jde for
         arbejdskraft til maintenance af SW-systemer, eller
         st]rre ECO-opdateringer hen ad vejen. BHB foresl>r
         en arbejdsmand som aflastning for teknikerne ved
BHB      samlearbejde m.v. BHB skaffer arbejdsmand/praktikant
         til samlearbejde.




         4̲.̲ ̲A̲r̲b̲e̲j̲d̲s̲d̲e̲l̲i̲n̲g̲ ̲p̲a̲k̲k̲e̲h̲o̲l̲d̲/̲H̲W̲ ̲g̲r̲u̲p̲p̲e̲

         HW-gruppen skiller racks fra hinanden, hvorefter ILS
         
KM       pakkeansvarlige overtager systemet. ILS skal udpege
         en pakkeansvarlig for hvert system.


         5̲.̲ ̲O̲p̲t̲o̲-̲c̲a̲b̲l̲e̲s̲

         Der skal indk]bes opto-cables til test kabler til 3
         FAT-systemer, 5 SW-udviklingssystemer, 8 s`t til
BHB/KM   installationshold. L`ngder skal specificeres og termineringsarbejdskraft
         allokeres inden yderligere
KM/JHO   indk]b foretages.

JHO      Der bliver formentlig leveringsproblemer fra CAMPS
         lager da shipment af opto-cables sker tidligt. Desuden
         rekvirerer SHAPE 30% mere end planlagt. En ekstra ordre
         er sandsynlig.


         6̲.̲ ̲@̲n̲d̲r̲e̲t̲ ̲F̲A̲T̲-̲s̲e̲k̲v̲e̲n̲s̲

         For at spare flyttearbejde af SW-udviklingssystemer
         skal det unders]ges, om man kan flytte FAT-sekvensen.
JHO      F]rst skal det unders]ges, om det er tilladeligt rent
         kontraktuelt. Dern`st skal det unders]ges, om der er
         
KM       sites, der er kandidater til en af SHAPE for>rsaget
         SPA-
BHB      uds`ttelse. Sluttelig skal det unders]ges, hvilke sites
         det er praktisk muligt for HW-gruppen at fremskynde.


         7̲.̲ ̲A̲s̲-̲b̲u̲i̲l̲t̲ ̲d̲r̲a̲w̲i̲n̲g̲s̲

         Med en to m>neders installationsperiode vil det muligvis
         blive et problem at f> udgivet final as-built drawings
         ved SPA'en. Planen er at m]de op med prelimin`re As-built
         ved installation og levere h>ndrettede ved SPA, og
         endelig version 6 uger efter.
KNN/KM   KNN og KM kontrollerer, om det er kontraktuelt tilladeligt.




         8̲.̲ ̲A̲T̲B̲B̲

         SHAPE foretager hele tiden omplaceringer af brugerterminaler.
         KM's holdning er at det efter site verification kun
         sker mod betaling. Det b]r overvejes
KNN      om CR ikke b]r afkr`ve betaling p> et tidligere tidspunkt.


         9̲.̲ ̲D̲i̲s̲c̲ ̲P̲a̲c̲k̲s̲

JHO      Det skal kontrolleres, at der er nok til shipment efter
         nuv`rende plan.



         1̲0̲.̲ ̲I̲n̲v̲e̲n̲t̲o̲r̲y̲ ̲L̲i̲s̲t̲

         KM leverer input til inventory list. HW-gruppe opdaterer
         og leverer til KM.

         Problem-punkter ved site 1 er:

KM       -   tr`hylder

KM       -   CRT-kontraktens VDU'er og MSP'er skal leveres,
             hvorn>r?
             (CR skal komme med udspil)

BHB      -   Spares ikke leveret til CAMPS

         -   Kun 128K Ram sendes nu. F]rst senere sendes 512K
             Ram.

         -   Comsec test programmer

KM,KNN   Der skal foretages en verificering af at listen er
JHO,BHB  komplet.

KM       Kopi af mangelliste til KNN


         1̲1̲.̲ ̲B̲r̲a̲n̲d̲s̲l̲u̲k̲n̲i̲n̲g̲s̲h̲o̲l̲d̲

KNN      Der skal defineres 1 SW-, 1 HW- og 1 systemmand, der
         er beh]rigt clearede til at klare "brandsluknings"-opgaver
         ved SPA'er. Kjeld Alfast er pr. 1/4 allokeret til field
         support for installationsholdene.



         ILS planl`gger dog med at K. Alfast skal have en afl]ser.
         CAMPS' holdning er: Endnu er KJAs afl]ser i starten
         p> CAMPS (1/2 >r) eller ogs> er KJA fuld tid p> CAMPS
         hele perioden.


         1̲2̲.̲ ̲E̲C̲O̲-̲o̲p̲d̲a̲t̲e̲r̲i̲n̲g̲

         ECO-opdatering (HW) foretages som f]lger:

         -   inden FAT:                  HW-gruppe
         -   fra FAT til shipment:       HW-gruppe
         -   fra shipment til SPA:       ILS-installationshold
         -   fra SPA til under waranty:  ILS ved hj`lp af RST-tekniker
                                         hos SHAPE

         ILS vil internt diskutere denne problemstilling (omkostninger,
         investeringer, CR udstyr/OEM udstyr). Repair at CR
         equipment foretages indtil shipment af HW-gruppe. Repair
         af OEM equipment foretages indtil shipment af ILS-gruppe.


         1̲3̲.̲ ̲I̲n̲-̲H̲o̲u̲s̲e̲ ̲R̲e̲p̲a̲i̲r̲ ̲C̲e̲n̲t̲e̲r̲

PMS      ILS ans`tter nu en extra mand pr 1/4 til leder af ILS
         repair center. ILS vil da kunne reparere

         -   SW-udviklingssystemer
         -   CAMPS-Hardware (VDUer, disc drives, MSP)

         ILS vil sende alle reparationer af moduler retur til
         fabrikanterne.


         1̲4̲.̲ ̲M̲ ̲&̲ ̲D̲ ̲P̲r̲o̲g̲r̲a̲m̲m̲e̲r̲

         De nuv`rende programmer er gode nok til intern test.
         Der mangler 8-10 m>neders arbejde i at f> dem op p>
         et stade, man kan bygge videre p> (dokumentation, manglende
         program dele). Derefter kan de udbygges i brugervenlighed.

KNN,OE,KM    Det skal afg]res om dette b]r ske.

         ILS kommer med et tekniker-hold til at k]re FAT-test
         for derved at l`re M+D programmer at kende.



         HW-gruppens MD-programmer benyttes indtil videre af
         ILS installations-team.


         1̲5̲.̲ ̲E̲C̲O̲-̲f̲i̲l̲e̲

         ILS efterlyste en centralisering af ECO'er for b>de
         CR og OEM-udstyr. BHB oplyste at en s>dan allerede
         fandtes (CPS/TCN/057).

KNN      CAMPS vil p> godkendelseslisten for CR ECO'er, idet
         ECO-opdatering i h]jere grad b]r styres ud fra ]konomiske
         kriterier.

PMS      Maintenance-planen opdateres, s>ledes at den reflekterer,
         at SHAPE foretager ECO-opdatering af moduler til reparation
         i garantiperioden.

KNN,BHB  KNN og BHB pr]ver at oprette et Configurations Control
         Board for CAMPS via QA (medlemmer: BHB, KNN, PMS, EV).
         Underleverand]r-koordinator skal ogs> med i CCB.


         1̲6̲.̲ ̲S̲W̲-̲u̲d̲v̲i̲k̲l̲i̲n̲g̲s̲s̲y̲s̲t̲e̲m̲

         SW-gruppen f>r tildelt 3 store CAMPS-systemer og 2
         sm>.

         6 x 2 SMD'er skal der v`re p> disse CAMPS-systemer.

JHO      JHO kontrollerer om det er muligt.

JHO      JHO bestiller str]m og k]ling p> 1. sal til 3 ekstra
         systemer, samt indl`gger PAM p> stue-etage.


         1̲7̲.̲ ̲D̲i̲v̲e̲r̲s̲e̲

JHO      JHO skaffer tekniker til samling af PTR/P

KM       KM skaffer mand til opto-cable-terminering

KNN, BHB Spare part leverancer kontrolleres af KNN, BHB.

KNN,BHB  Indretningsplan til HW mv. leveres af KNN, BHB, JHO.
JHO




         1̲8̲.̲ ̲R̲e̲p̲a̲r̲a̲t̲i̲o̲n̲s̲ ̲S̲t̲a̲t̲u̲s̲

PMS      Der udarbejdes status for udstyr til reparationen PAW
         inddrages til reparationsarbejde.


         1̲9̲.̲ ̲R̲u̲p̲p̲e̲r̲t̲s̲w̲e̲i̲l̲e̲r̲-̲t̲e̲r̲m̲i̲n̲a̲l̲e̲r̲

         Ruppertsweiler 17 VDU'er og 7 MSP'er leveres til SHAPE
KM       site. Tages fra Site 2-lager. De skal v`re halvt opto-
         og halvt metallic forbundne.

URH      URH er dog actionee p> at afg]re dette med SHAPE.

         Terminalerne skal leveres for at kunne reproducere
         SW-fejl. SHAPE har ansvar for flytning til Ruppertsweiler.


         2̲0̲.̲ ̲"̲S̲i̲t̲e̲ ̲N̲u̲m̲b̲e̲r̲i̲n̲g̲ ̲a̲n̲d̲ ̲S̲e̲q̲u̲e̲n̲c̲e̲"̲

KM       Dette dokument b]r opdateres af KM efter ny schedule
         pr. januar 83.


         2̲1̲.̲ ̲S̲W̲-̲W̲a̲r̲r̲a̲n̲t̲y̲

         Leif Larsen og Carsten Pedersen udg]r SW-warranty team
         hos ILS fra juli 83.


         2̲2̲.̲ ̲M̲a̲n̲u̲a̲l̲e̲r̲-̲T̲C̲M̲

         Technical Manuals vil f]rst blive leveret til SHAPE
         i 11. time. Flere manualer fra CR er i dag i ynkelig
         stand.

KNN,BHB  KNN og BHB rykker Mogens B. Jacobsen. 3 TCN om V24
SRA      leveres til SHAPE efter omskrivning af HW-gruppe (SRA).

KNN      Tr`ning og dokumentation gennemg>s ved KNN. BL.a. vurderes
         SHAPE's kommentarer til Technical Manuals.

         CR har forpligtiget sig til overfor SHAPE at levere
         blokdiagrammer og printdiagrammer svarende til de forskellig
         ECO-levels.



         Til:    GJ, JKZ, KM[

         CC.:    HEL, KNN

         Fra:    BHB

A̲c̲t̲i̲o̲n̲:
         E̲m̲n̲e̲:̲ ̲O̲E̲D̲-̲S̲D̲/̲8̲0̲1̲2̲1̲8̲,̲ ̲i̲n̲k̲l̲.̲ ̲A̲m̲e̲n̲d̲m̲e̲n̲t̲ ̲1̲,̲2̲ ̲o̲g̲ ̲3̲

         ref.:   a)  Intern faktura nr. 107 (JKZ/GB 821122)
                 b)  CAMPS Intern Meddelelse nr. 452 (BHB/830128)
                 c)  PDI/035, Intern Meddelelse (LSJ/830201)
                 d)  Intern Meddelelse nr. 98 (JKZ/830131)
                 e)  CAMPS Intern Meddelelse Nr. 462 (BHB/830203)

         1.  Det kan i dag konstateres, at leverance til CAMPS
             iflg. ovenn`vnte kontrakt sker via PDI.

             Det m> derfor konkluderes, at kontrakten er overdraget
             fra ED til PD.

         2.  Der er imidlertid problemer m.h.t. status af leverancen
             af DSMT-systemets H/W, ref. a)-d).

         3.  Et andet problem vedr]rer muligheden for en fornuftig
             anvendelse af DSMT-HW, ref e):

             -   Visse moduler er `ldre end den baseline, der
                 er godkendt for CAMPS

             -   Visse moduler er d]mt uanvendelige af QA

GJ       4.  For at kunne disponere produktion af de sidste
KM[          CAMPS systemer, er det kritisk nu at f> afklaret:
JKZ
             a)  Status p> overdragelse af kontrakten OED-SD/801218,
                 specielt med hensyn til DSMT-HW.

             b)  Hvem ejer p.t. DSMT-HW?

BHB      5.  For at undg> forsinkelser i CAMPS leveringsplan,
KNN          vil der senest 14/3-83, blive afgivet bestilling
             p> erstatningsmoduler til produktionen.



         Bjarne Berthold





                                                    830318/URH















C A M P S…01……01…W E E K L Y   S T A T U S R E P O R T…01……01…F O R…01……01…S Y S T E M   I N T E G R A T I O
 N   &   T E S T







                        2̲ ̲ ̲S̲T̲A̲T̲U̲S̲

                (DEVIATIONS FROM SCHEDULE)


LI       DESCRITPION       COMMENT
-------------------------------------------------------------------

2.4.1    PERF. TESTS       Timing analysis performed on THP.

2.5.2.7.1                  SCRIPT GEN.   Will start appr. 830401.
                                         Delay due to ACCESS
                                         activities.

2.5.2.10 SITE 2-16 SW      Deferred until completion of 240-hour
         VER. PROCEDURES   test.

4.6.5.8  SYST. GEN         Activities planned until 830515.

4.6.5.9  DATABASE GEN.     The following tables are completed.
         PRGMS. DEV.       -   SCD
                           -   SDL
                           -   LO.PLA
                           -   GL.PLA
                           -   LO.RI
                           -   GL.RI
                           -   AIG
                           The only remaining table is the SIC
                           table wihich should be completed
                           on 830328.

4.6.7.2  STIMULATOR        New functions requested + refinements
         FOLLOW-UP

4.6.7    SYSTEM I&T        Scheduled activities

                           -   SAR2: not ready
                           -   SSC2: not ready
                           -   THP1: not ready
                           -   THP2: not ready

                           System I&T of above items has not
                           been initiated due to missing coordination
                           and delays in SW development.