⟦55f2e5ccd⟧ Wang Wps File

    Length: 10972 (0x2adc)
    Types: Wang Wps File
    Notes: Conf.Man.Plan             
    Names: »0064A «

Derivation

└─⟦83a4a04d1⟧ Bits:30005815 8" Wang WCS floppy, CR 0002A
    └─ ⟦this⟧ »0064A « 

WangText

…05……00……00……00……86…1                                              …02…           …02…   …02…         

…02…SD/PLN/006

…02…KFL/810219…02……02…#
CONFIGURATION MANAGEMENT PLAN
…02…SVO/800711…02…GENERAL








                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



   1  SCOPE ........................................ 
    4 
 
     1.1  PURPOSE .................................. 
      4 
     1.2  STANDARDS ................................ 
      4 

   2  ORGANIZATION ................................. 
    5 

   3  BASELINING ................................... 
    5 

     3.1  PROJECT IMPLEMENTATION PLAN .............. 
      5 
     3.2  BASELINE LEVELS .......................... 
      7 
     3.3  CONTROL OF PRODUCT ITEMS ................. 
      7 
     3.4  OEM SUPPLIES ............................. 
      7 

   4  IDENTIFICATION ............................... 
    8 

     4.1  ITEM IDENTIFIERS ......................... 
      8 
     4.2  NUMBER SERIES ............................ 
      8 
     4.3  MARKINGS ................................. 
      8 

   5  CONFIGURATION ITEM RETENTION ................. 
    9 

     5.1  GENERAL .................................. 
      9 
     5.2  PROCEDURES ............................... 
      9 
     5.3  HARDWARE STORAGE ......................... 
      9 
     5.4  SOFTWARE CONTROLLED LIBRARY .............. 
      9 
     5.5  DOCUMENT CONTROL CENTRE .................. 
      9 
       5.5.1  General .............................. 
        9 
       5.5.2  Filing ............................... 
       10 
       5.5.3  Indices .............................. 
       10 
       5.5.4  Access ............................... 
       10 

   6  CHANGE CONTROL ............................... 
   10 

     6.1  GENERAL .................................. 
     10 
     6.2  CHANGE PROPOSAL .......................... 
     11 
     6.3  CHANGE CONTROL BOARD ..................... 
     11 
     6.4  CHANGE IMPLEMENTATION AND RELEASE ........ 
     12 
     6.5  STATUS ACCOUNTING ........................ 
     12 





 …06…1         …02…   …02…   …02…   …02…                                 
            


                      1̲ ̲ ̲S̲C̲O̲P̲E̲



   This plan is a subplan of Quality Assurance Plan SD/PLN/001
   and has the same scope and applicability.



1.1  P̲U̲R̲P̲O̲S̲E̲

   The objective of Configuration Management is to establish
   the diciplines necessary to control the identity, the
   availability, the form and content of all items purchased
   or produced in order to be part of a project development.

   The configuration management is pertinent to all items
   belonging to a project whether those are hardware items,
   software items, document items, or drawing items. 
   Also the plans governing the development of a project
   is subject to Configuration Management.

   The only exception is such basic materials and components
   which are used as raw material in the production and
   which are governed by the Parts and Material Plan.

   The configuration management activities can be divided
   into four separate areas, which are:

   1-  Baselining

   2-  Identification of items

   3-  Controlling the availability of items.

   4-  Change control.



1.2  S̲T̲A̲N̲D̲A̲R̲D̲S̲

   A Configuration Management Standard Manual shall be
   maintained containing all the detailed standards and
   procedures necessary to practice the principles established
   in this plan. These standards may be inspected by a
   customer on request.







                     2̲ ̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



         All Configuration Management activities will be carried
         out under the authority of the Quality Assurance Department
         described in QA Plan SD/PLN/001 section 2.

         For each project the QAD will appoint one person as
         Configuration Manager who will be responsible for all
         activities depicted in this plan.









                      3̲ ̲ ̲B̲A̲S̲E̲L̲I̲N̲I̲N̲G̲



3.1      P̲R̲O̲J̲E̲C̲T̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲

         It is assumed that all projects complying to this plan
         is managed in accordance with a project implementation
         plan which defines the development cycle of the project
         and which defines a split of the project development
         into separate phases.

         The PIP shall also define reviews to take place as
         the conclusion of each development phase.

         The PIP shall specify as a minimum 4 baselines:

         -Requirements
         -Design
         -Test
         -Product

         Fig. 1 shows an example of a project development cycle
         with such phases and reviews defined.












                          FIG 1










3.2      B̲A̲S̲E̲L̲I̲N̲E̲ ̲L̲E̲V̲E̲L̲S̲

         Baselines may be defined in two levels:

         Internal baselines and
         external baselines

         External baselines involves the customer:

         That is the customer must participate in approval of
         the product which is baselined and he is also entitled
         to participate in the CCB (see paragraph 6.3) controlling
         such baselines.

         Internal baselines only involves in-house authorities
         such as management of the project and Quality Assurance
         Department. The CCB controlling such baselines will
         only consist of those authorities participating in
         the baselining.



3.3      C̲O̲N̲T̲R̲O̲L̲ ̲O̲F̲ ̲P̲R̲O̲D̲U̲C̲T̲ ̲I̲T̲E̲M̲S̲

         At the end of each development phase the produced items
         must be placed under configuration control.  A version
         of the item is declared as the official version which
         will be used as baseline for further development of
         the project.

         At the time of baselining all items are given a unique
         identification for future reference and the item (or
         a copy hereof) is placed in a controlled storage.

         All changes to a baselined item must be under official
         change control.



3.4      O̲E̲M̲ ̲S̲U̲P̲P̲L̲I̲E̲S̲

         All items received from the purchaser, or supplied
         by subcontractors or  other suppliers, shall be placed
         under configuration control as soon as incoming inspection
         in accordance with quality assurance plans has been
         performed.




                    4̲ ̲ ̲I̲D̲E̲N̲T̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



4.1      I̲T̲E̲M̲ ̲I̲D̲E̲N̲T̲I̲F̲I̲E̲R̲S̲

         All items placed under configuration control shall
         be given a unique identifier.

         The identifier shall contain a type code, a project
         code and a serial number.

         Detailed rules for the allocation of identifiers shall
         be found in the Configuration Management Standards
         Manual.




4.2      N̲U̲M̲B̲E̲R̲ ̲S̲E̲R̲I̲E̲S̲

         The Configuration Manager shall allocate and maintain
         number series for each type of item and allocate numbers
         in accordance with a standard manual.



4.3      M̲A̲R̲K̲I̲N̲G̲S̲

         All items shall be marked with the identifier and marking
         will be dependent on the type of item.

         Details about marking shall be prescribed in the Configuration
         Management Standard Manual.











             5̲ ̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲I̲T̲E̲M̲ ̲R̲E̲T̲E̲N̲T̲I̲O̲N̲



5.1      G̲E̲N̲E̲R̲A̲L̲

         All baselined Configuration Items must be retained
         in a controlled storage (except items covered by the
         parts and material plan).

         A storage faciliy appropriate for each type of items
         shall be established and maintained in a way that makes
         it possible for the Configuration Manager to control
         the availability and the integrity of all controlled
         items.



5.2      P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲

         Detailed procedure manuals for each type of storage
         shall be established under the joint responsibility
         of the Configuration Manager and the Authority who
         actually runs the storage.



5.3      H̲A̲R̲D̲W̲A̲R̲E̲ ̲S̲T̲O̲R̲A̲G̲E̲

         It will be the responsibility of the management of
         each project to establish a storage facility where
         all baselined hardware items can be retained.

         As hardware items may vary considerably in type and
         number from project to project it is necessary to establish
         a detailed procedure for hardware storage for each
         project - tailored to the needs of the project.

         The storage shall be established in a way which facilitates
         all control desiderations in accordance with this plan
         as well as standards derived from it.





5.4      S̲O̲F̲T̲W̲A̲R̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲L̲E̲D̲ ̲L̲I̲B̲R̲A̲R̲Y̲

         It will be the responsibility of the management of
         each project to establish a storage facility where
         all baselined Software items can be retained.

         The same considerations as described above for hardware
         apply to software.



5.5      D̲O̲C̲U̲M̲E̲N̲T̲ ̲C̲O̲N̲T̲R̲O̲L̲ ̲C̲E̲N̲T̲R̲E̲



5.5.1    G̲e̲n̲e̲r̲a̲l̲

         Copies of all documents, drawings, letters, etc. are
         filed in the Document Control Centre in order to ensure
         that all documents etc. will be available at any time.



5.5.2    F̲i̲l̲i̲n̲g̲

         The Document Control Centre copy of any document etc.
         is identified by marking it with a red stamp. The copies
         are registered with consecutive numbers and filed in
         that sequence.



5.5.3    I̲n̲d̲i̲c̲e̲s̲

         A number of indices are maintained to ensure easy access
         to any document etc. in the Document Control Centre.



5.5.4    A̲c̲c̲e̲s̲s̲

         Any staff member has access to the copies in which
         he/she has legal interest. No copy must be removed
         from the Document Control Centre without explicit permission
         from the person in charge of the Centre.


                    6̲ ̲ ̲C̲H̲A̲N̲G̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲



6.1      G̲E̲N̲E̲R̲A̲L̲

         All changes to items under configuration management
         must be controlled by the Configuration Manager according
         to the rules in the following sections.



6.2      C̲H̲A̲N̲G̲E̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲

         All changes must be initiated by the issue of a change
         proposal.

         All personnel engaged in a project development as well
         as all persons with legal interest in the product may
         issue change proposals.

         The Configuration Manager will receive change proposals
         and initiate necessary actions.  A detailed procedure
         shall be contained in Configuration Management Standard
         Manual which also shall specify the format of change
         proposals.



6.3      C̲H̲A̲N̲G̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲ ̲B̲O̲A̲R̲D̲

         All change proposals shall be presented to a change
         control board for decision before any actual change
         may take place.

         The change control board shall consist of at least
         one representative from the following:

         -   Customer (only for external baselines)
         -   Project Management
         -   Technical Experts
         -   Quality Assurance



         The Configuration Manager is responsible for arrangement
         of board meetings at a frequency appropriate to cope
         with the actual change traffic in the project in question.

         The Change Control Board shall evaluate all changes
         for technical, cost, schedule and management impacts
         and decide if, how, and when the change shall be implemented.

         The CCB decisions must be unanimous.  If this is not
         possible the issue shall be deferred for decision at
         higher management levels.



6.4      C̲H̲A̲N̲G̲E̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲R̲E̲L̲E̲A̲S̲E̲

         It is the responsibility of the project management
         to implement changes according to CCB decisions.

         After change implementation the new version of the
         item shall be registered and released for use by the
         Configuration Manager who shall also coordinate the
         release of mutually dependent changes.



6.5      S̲T̲A̲T̲U̲S̲ ̲A̲C̲C̲O̲U̲N̲T̲I̲N̲G̲

         The Configuration Manager shall keep a strict record
         of the change status of all items.

         The detailed format and content of this record shall
         be described in the Configuration Management Standard
         Manual.