outer nut into the right hand penetration of rack F and the filter box. Tighten the
fitting from inside the filterbox by the inner nut (see ATBB drawing 116).
b) Repeat step a) for the left hand penetration of rack F.
c) Repeat step a) for theother end of the conduit to be mounted in the ferrous duct
above rack F (see ATBB drawing 110/116).
d) Mount the 75 mm metallic conduit on the outside of the steel tubes and tighten
it by the clamps.
e) The low speed medium (LSM) cables W855-859 and
W814 for the PTP/PTR are pulled through the waveguide
of the metallic duct, through the left hand pene-
tration of rack F and ito the filter box (see ATBB
drawing 125).
f) Other cables: W731 CCIS
W732 SCARS
W733 CRT
W741-742 Colocated Tare
W813 OCR
are pulled throughthe waveguide of the metallic
duct, through the right hand penetration of rack
F and into the filter box.
g) The metallic cables are now ready for termination
by H/N.
h) When the metallic cables have been connected by
H/N, see ATTB drawing 125,the cables will be finally
marked with cable No. markers.
5.5 R̲E̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲R̲A̲C̲K̲S̲
5.5.1 M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲D̲i̲s̲k̲ ̲D̲r̲i̲v̲e̲s̲
The 3 separately packed disk drives, 1 MMD for rack
A, 1 SMD for rack B, and 1 MMD for rack C are unpacked
and installed accordingto the instructions in the CAMPS
Packing Procedure, ref. doc. CPS/AUX/021.
5.5.2 M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲F̲l̲o̲p̲p̲y̲ ̲D̲i̲s̲k̲ ̲S̲t̲a̲t̲i̲o̲n̲
a) Remove the front panel located below the watchdog
crate. (Pos. 1A2A6).
b) The floppy disk cabinet containing the two floppy
dsk drives is installed on the two slides.
c) The cabinet is locked by mounting and tightening
the front panel by the 6 6mm screws.