⟦58c064bd6⟧ Wang Wps File

    Length: 22299 (0x571b)
    Types: Wang Wps File
    Notes: Sub.Manag.plan and Proce. 
    Names: »0089A «

Derivation

└─⟦b676ca540⟧ Bits:30006070 8" Wang WCS floppy, CR 0026A
    └─ ⟦this⟧ »0089A « 

WangText



0…0b…0…01…/…08…/…86…H
      
      
      
      
      
      
      
    …02…  
      
   …02…   …02…
      
   

…02…CPS/PLN/001



…02…KNN/801031…02……02…#

SUBCONTRACTOR
 MANAGEMENT
 PLAN AND
 PROCEDURES

…02……02…CAMPS















                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



…02…1  INTRODUCTION ...............................   4

…02…2  PRECONTRACT PROCEDURES ......................  5  
    

…02…3  SUBCONTRACT MANAGEMENT ORGANIZATION
        AND RESPONSIBILITIES ........................
  6 to  7

…02…4  GENERAL MANAGEMENT CONCEPT ..................  8

…02…5  SUBCONTRACTS MANAGEMENT PROCEDURES ..........  9 to
 13

…02……02…5.1  MILESTONES/BASELINES ....................  9
…02……02…5.2  TECHNICAL REVIEWS ....................... 10
…02……02……02…5.2.1  System Requirements Review .......... 10
…02……02……02…5.2.2  System Design Review ................ 10
…02……02……02…5.2.3  Preliminary Design Review ........... 11
…02……02……02…5.2.4  Critical Design Review .............. 11
…02……02……02…5.2.5  Verification Readiness Inspection ... 11
…02……02……02…5.2.6  Final Acceptance Review ............. 11

…02……02…5.3  PROGRESS REPORTING ...................... 12
…02……02……02…5.3.1  Regular Progress Meetings ........... 12
…02……02……02…5.3.2  Progress Reports .................... 12

…02……02…5.4  WORKING MEETINGS ........................ 12
…02……02…5.5  INSPECTIONS ............................. 13

…02…6  TECHNICAL AND SUBCONTRACT 
        CHANGE PROCEDURES ...........................
 14 to 15

…02……02…6.1  CHANGE CONTROL BOARDS ................... 14
…02……02…6.2  TYPE OF CHANGES ......................... 14
…02……02…6.3  CHANGE CONTROL BOARD PROCEDURES ......... 15

…02…7  COMMUNICATION ............................... 15 to
 16

…02……02…7.1  COMMUNICATION ........................... 15
…02……02……02…7.1.1  Problem Reports ..................... 15
…02……02…7.2  DIRECTIVES FROM SUBCONTRACTOR MANAGER ... 16
…02……02…7.3  VISITS .................................. 16

…02…8  QUALITY ASSURANCE AND 
        CONFIGURATION MANAGEMENT ....................
 17

…02…9  SUBCONTRACTOR MANAGEMENT REQUIREMENT ........ 18

…02……02…9.1  ORGANIZATION ............................ 18
…02……02…9.2  WBS ..................................... 18


                     1̲ ̲ ̲I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲



         a)  Management of subcontractors supplying software
             and hardware will be an important task in the CAMPS
             program.

         b)  The purpose of this management procedure manual
             is therefore to specify general management procedures
             to be imposed on subcontractors.

         c)  The outlined procedures shall be applied all major
             external sub-contractors.

         d)  The described procedures should be regarded as
             guide- lines from which the procedures applied
             to each sub- contractor should be derived according
             to the size, complexity and type of subcontract.

         e)  Management procedures shall always be tailored
             to the level, so it is suitable for the specific
             subcontract. Both excessive and insufficient procedures
             will result in increased costs.

         f)  While sections 4 thru 6 apply especially to subcon-
             tracting of tasks involving large elements of H/W
             and/- or S/W developments, sections 2, 3, and 7
             thru 9 apply to both development tasks and to procurement
             of off- -the-shelf supplies.

         g)  Notwithstanding any detailed procedures given in
             this document sub-contractors should be aware that,
             mutatis mutandis, the general and specific clauses
             of the SHAPE/CR contract apply equally to them.







                2̲ ̲ ̲P̲R̲E̲C̲O̲N̲T̲R̲A̲C̲T̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲



         a)  Normally the starting point for selection of sub-
             contractors is established when the system requirements
             have been completed and approved, since this baseline
             outlines what to be produced.

         b)  From the system requirements a Statement of Work
             or a technical supply specification may be derived
             to be included in a Request for Quotation and at
             a later stage a subcontract or in case of in-house
             sub- contractors in a Project Work Authorization.

         c)  All external RFQs and Subcontracts should be approved
             prior to issue or signature by both CR Contracts
             Management and CR Financial Control.

         d)  CR Contracts Management shall ensure that the sub-
             contract complies with all subcontract requirements
             included in the contract between CR and SHAPE,
             and that all security aspects of engaging the specific
             sub- contractor for the CAMPS program are covered.

         e)  Furthermore CR Contracts Management shall ensure
             that all general and special requirements to the
             sub- contractor following from this document are
             made part of the contract between him and CR.

         f)  CR Financial Control shall ensure that all financial
             aspects for the subcontract are covered and that
             especially the payment schedule supports CRs sub-
             contract management, e.g. by milestone payments.

         g)  All in-house subcontracts should be approved prior
             to issue of Project Work Authorization by CR Financial
             Control to ensure that the in-house Cost and Schedule
             Control Procedures are applied.







3̲ ̲ ̲S̲U̲B̲C̲O̲N̲T̲R̲A̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲



         a)  In the following the organization required to support
             subcontracting is presented.

         b)  The subcontract management function is supported
             by Contracts Management Financial Control and Systems
             Engineering.

         c)  In all cases of subcontract origination and preparation
             the program manager is responsible for ensuring
             the correct technical content of the subcontract.
             The contracts manager is responsible for terms
             and conditions of the subcontract as described
             in chapter 2.

         d)  During normal operation the program manager is
             responsible for the assurance that the subcontractor's
             performance is maintained with respect to technical
             performance, schedule and cost requirements.

         e)  On a day-to-day basis, individual planners and
             analysts will monitor progress of their assigned
             subsystem, assess the results with their respective
             managers, and together with him will develop and
             implement solutions to deviations from the plan.

         f)  In addition, significant deviations from the plan
             will immediately be brought to the attention of
             the program manager.

         g)  The Quality Assurance department will be responsible
             for surveillance of the subcontractors implementation
             of the applicable part of the Quality Assurance
             Program.











          4̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲C̲O̲N̲T̲R̲O̲L̲ ̲C̲O̲N̲C̲E̲P̲T̲



         a)  The basic management approach is to establish a
             suit- able number of goals (milestones) which during
             the total development cycle can be used to measure
             cost/- schedule and technical performance.

         b)  For each development item to be managed milestones
             should be established with intervals of 1 to 2
             months. When milestones are established it should
             be considered that the deliveries can be used to
             evaluate progress (i.e. cost/schedule and technical
             performance of the subproject).

         c)  The other area to be considered in subcontract
             management are the means that are used to measure/-
             evaluate subproject progress.

         d)  Before presenting the specific management concept
             the socalled sequential phase model is presented
             as this forms the basis for the concept.

         e)  The typical phases of a development task are

             -   requirements specification
             -   preliminary design
             -   interface specification
             -   detailed design
             -   implementation
             -   integration and test
             -   acceptance
             -   maintenance

         f)  The sequential phase model has as a strict requirement
             that each phase is 100% completed before the next
             phase is initiated.

         g)  Most errors are introduced during the first phases
             of the project. If they are not corrected before
             the con- secutive phases are initiated, these errors
             are imple- mented into the design and the final
             product, where the costs to correct the errors
             are much greater.

         h)  Another problem that often occurs when the sequential
             phase model is not used, is, that the configuration
             management system is overloaded, which adds further
             problems to the project.


           5̲ ̲ ̲S̲U̲B̲C̲O̲N̲T̲R̲A̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲



         All procedures specified within this document shall
         be mandatory for CAMPS development subcontractors.



5.1      M̲I̲L̲E̲S̲T̲O̲N̲E̲S̲/̲B̲A̲S̲E̲L̲I̲N̲E̲S̲

         a)  The term "milestone" will in this manual be used
             as an important or critical event and/or activity
             that must occur in the project cycle in order to
             achieve project objectives.

         b)  The milestone is to be considered in the light
             that events culminate in a management review/audit
             refer sections 5.2 and 5.3 and decision process.

         c)  It is only when an approval decision has been reached
             the milestone events are considered to be completed
             (Baselined).

         d)  All baselined specifications, documents, products
             etc. shall be controlled by the change procedures
             described in section 6.

         e)  These change procedures should be considered in
             the light of the objective to use the sequential
             phase model that is described in section 4.

         f)  Milestone planning is used to

             -   quantify project objectives

             -   define significant events

             -   determine the sequence in which milestones
                 must occur

             -   establish time-line schedule for accomplishment
                 of the milestones

             -   through periodic updating of the time-line
                 schedule reflect current status, evaluate progress
                 and arrive to decisions to continue, limit,
                 accelerate, redirect, or otherwise control
                 the project effort.


5.2      T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲R̲E̲V̲I̲E̲W̲S̲

         a)  This procedure prescribes the requirements of technical
             review on system, equipment and computer programs
             procured for CAMPS.

         b)  The reviews make up decision points whether to
             proceed or not. After reviews the subcontractor
             and/or program manager decide whether to approve
             the specification or not. If not approved the subcontractor
             must not proceed further until the milestone has
             been approved.



5.2.1    S̲y̲s̲t̲e̲m̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲S̲R̲R̲)̲

         The objective of this review is to ascertain the adequacy
         of the contractor's efforts in defining system requirements.
          It will be conducted when a significant portion of
         the system functional requirements has been established.



5.2.2    S̲y̲s̲t̲e̲m̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲S̲D̲R̲)̲

         a)  This review will be conducted when the definition
             effort has proceeded to the point where system
             re- quirements and the design approach are more
             precisely defined. This review will be in sufficient
             detail to ensure a technical understanding between
             the contractor (and through him his sub-contractors)
             and the procuring activity on (1) the system segments
             identified in the system specification, and (2)
             the configuration items (CIs) identified in the
             CI specifications.

         b)  A Configurations Item (CI) is defined in this document
             as the deliverable items of a Work Package; e.g.
             a hardware unit, a software program, a plan, a
             speci- fication, test results, or a user hand book.





5.2.3    P̲r̲e̲l̲i̲m̲i̲n̲a̲r̲y̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲P̲D̲R̲)̲

         These reviews shall be conducted for each CI prior
         to the detail design process to (1) evaluate the progress
         and technical adequacy of the selected design approach;
         (2) determine its compatibility with the performance
         requirements of the CI specification; and (3) establish
         the existence ad compatibility of the physical and
         functional interfaces between the CI and other items
         of equipment or facilities.



5.2.4    C̲r̲i̲t̲i̲c̲a̲l̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲C̲D̲R̲)̲

         This review shall be conducted by the subcontractor
         for each CI when detail design is essentially complete.
         The purpose of this review will be to (1) determine
         that the detail design of the CI under review satisfies
         the design requirements established in the CI specification
         and (2) establish the exact interface relationships
         between the CI and other items of equipment and facil-
         ities.



5.2.5    V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲R̲e̲a̲d̲i̲n̲e̲s̲s̲ ̲I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲ ̲(̲V̲R̲I̲)̲

         The VRI is conducted to approve that the actual (CI)
         product complies with its specifications prior to the
         formal verification.



5.2.6    F̲i̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲F̲A̲R̲)̲

         At delivery of a (CI) product a FAR will be conducted.
         The FAR requires the successful completion of the veri-
         fication testing and demonstration to the prime con-
         tractor.









5.3      P̲R̲O̲G̲R̲E̲S̲S̲ ̲R̲E̲P̲O̲R̲T̲I̲N̲G̲



5.3.1    R̲e̲g̲u̲l̲a̲r̲ ̲P̲r̲o̲g̲r̲e̲s̲s̲ ̲M̲e̲e̲t̲i̲n̲g̲s̲

         a)  The meetings are conducted by CAMPS subcontractor
             manager or by an authorized representative.

         b)  The primary objective of these meetings are to
             review and evaluate, on a regular basis, progress
             on which management decisions can be based.

         c)  The primary presentation materials by the subcontract
             manager shall be the monthly status of accomplishments,
             plans, schedules, and problems/issues.



5.3.2    P̲r̲o̲g̲r̲e̲s̲s̲ ̲R̲e̲p̲o̲r̲t̲s̲

         a)  Instead of regular progress meetings (monthly or
             weekly) progress reporting can be used.

         b)  The objective of the progress report is to report
             on accomplishments, plans, schedules and problems/issues.



5.4      W̲O̲R̲K̲I̲N̲G̲ ̲M̲E̲E̲T̲I̲N̲G̲S̲

         a)  Technical or/and administrative problems might
             occur during program development.  In order to
             solve the problems working meeting will be scheduled.

         b)  A working meeting between subcontractors must never
             be scheduled without informing the CR CAMPS program
             office at least 48 hours before.  This office can,
             whenever it wants, send representatives to such
             meetings.



         c)  A working meeting can also take place between the
             program office and the subcontractor in which case
             the program office conducts the meeting.

         d)  The initiator of a meeting is responsible for providing
             the following items.

             1)  meeting location
             2)  meeting agenda
             3)  meeting schedule
             4)  meeting participant list
             5)  minutes of meeting
             6)  action lists and close out of actions



5.5      I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲S̲

         a)  The subcontractor manager has the authority to
             initiate inspections.  However, these shall be
             coordinated with the QA Department.

         b)  Inspections are used to evaluate the performance
             of the subproject.

         c)  Inspections can be initiated due to routine or
             emer- gency.

         d)  The different types of inspections are:

         -   procedure inspection
         -   program code inspection
         -   hardware item inspections

         e)  In addition the QA Department has authority to
             initiate inspection of the subcontractor QA functions
             and other activities with quality implications.











      6̲ ̲ ̲T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲A̲N̲D̲ ̲S̲U̲B̲C̲O̲N̲T̲R̲A̲C̲T̲ ̲C̲H̲A̲N̲G̲E̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲



         a)  Once a baseline is frozen, it must be well identified
             and fully considered in the perspective of the
             total program.

         b)  When the product is established all changes, no
             matter how small, must be processed through a well
             defined change control process.

         c)  A similar change procedure applies to non-technical
             contractual changes.



6.1      C̲H̲A̲N̲G̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲ ̲B̲O̲A̲R̲D̲S̲

         a)  Within the program office, the group that administers
             change control is known as the Change Control Board
             (CCB). The CCB is the only authority to act on
             changes as well as vaiwers/deviations. The primary
             function of the CCB is to control the baseline.

         b)  The CCB is not a voting organization. The program
             manager or his representative is chairman and is
             responsible for the final decision on any proposed
             change to the baseline.

         c)  The membership of the CCB normally includes top
             managers for each functional area.



6.2      T̲Y̲P̲E̲S̲ ̲O̲F̲ ̲C̲H̲A̲N̲G̲E̲S̲

         a)  All proposed engineering changes that affect one
             or more of the baselines - functional, allocated
             or product are classified as class I engineering
             change proposals (ECPs).

         b)  Proposed engineering changes that do not affect
             "form, fit and function" even though they may involve
             a change to the contractor's engineering or manufactoring
             data are classified as CLASS II engineering changes.



         c)  In addition to ECP's the CCB also acts on all major
             critical deviations and waivers against the baseline.
             When approved deviations and waivers give the sub-
             contractor relief from the technical requirements.
             Permanent departures from a baseline must be ac-
             complished by ECP action rather than by deviations
             or waivers.



6.3      C̲H̲A̲N̲G̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲ ̲B̲O̲A̲R̲D̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲

         The subcontractor manager has responsibility to estab-
         lish and maintain all change control procedures in
         accordance with the CAMPS configuration plan and pro-
         cedures.









                     7̲ ̲ ̲C̲O̲M̲M̲U̲N̲I̲C̲A̲T̲O̲N̲



7.1      R̲E̲P̲O̲R̲T̲S̲



7.1.1    P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲p̲o̲r̲t̲s̲

         a)  The reports should be used by the subcontractor
             to inform the subcontracts manager about conditions
             activ- ities or events that jeopardize or have
             the potential of adversely effecting the program
             objectives, schedule etc.

         b)  Examples of situations calling for a problem report
             include changes in key-personnel, delay in purchased
             components and/or equipment etc.





7.2      D̲I̲R̲E̲C̲T̲I̲V̲E̲S̲ ̲F̲R̲O̲M̲ ̲T̲H̲E̲ ̲S̲U̲B̲C̲O̲N̲T̲R̲A̲C̲T̲S̲ ̲M̲A̲N̲A̲G̲E̲R̲

         Directives from the subcontracts manager to the sub-
         contractor can be of technical and administrative nature.
         Examples on directives are:

         -   changes in existing procedures or introduction
             of new, that are contractual regulated

         -   changes in plans

         -   initiation of production, test etc.

         -   changes in financial control procedures



7.3      V̲I̲S̲I̲T̲S̲

         Visits to prime contractor or subcontractor shall be
         made in response to request either by the prime or
         the subcontractor. Under normal conditions such visits
         should be coordinated in advance. The request for a
         visit shall contain the following information:

         -   purpose of visit
         -   date and item of arrival
         -   participants, names, departments
         -   brief agenda
         -   document to be discussed as enclosed or referenced
             if established documents
         -   estimate of time required











    8̲ ̲ ̲Q̲U̲A̲L̲I̲T̲Y̲ ̲A̲S̲S̲U̲R̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲



         a)  The subcontractor shall implement a quality assurance
             system and a configuration management system which
             comply with the quality Assurance plans applicable
             to the project.

         b)  The Quality Assurance Department of Christian Rovsing
             A/S (QAD) shall inspect this system and evaluate
             its adequacy.

         c)  All results of subcontractors QA activities, such
             as reports, logs, etc. shall be open for inspection
             by QAD.

         d)  The final responsibility towards the purchaser
             for all QA activites lies with QAD.











         9̲ ̲ ̲S̲U̲B̲C̲O̲N̲T̲R̲A̲C̲T̲O̲R̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲



         The subcontractor shall normally apply the same pro-
         cedures as the prime contractor. In the following are
         outlined some specific requirements.



9.1      O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲

         The subcontractor shall provide an organization chart
         with responsibilities assigned to it.



9.2      W̲O̲R̲K̲ ̲B̲R̲E̲A̲K̲D̲O̲W̲N̲ ̲S̲T̲R̲U̲C̲T̲U̲R̲E̲ ̲(̲W̲B̲S̲)̲

         The subcontractor shall provide a WBS and associated
         Work Package description for his subsystem that will
         be used as a frame work for

         -   planning/scheduling
         -   estimating costs
         -   assignment of responsibility



                        A̲P̲P̲E̲N̲D̲I̲X̲ ̲A̲



A.1      A̲t̲l̲a̲n̲t̲i̲c̲ ̲R̲e̲s̲e̲a̲r̲c̲h̲ ̲C̲o̲r̲p̲o̲r̲a̲t̲i̲o̲n̲ ̲(̲A̲R̲C̲)̲

         In order to achieve an optimal and compliant TEMPEST
         design solution, Christian Rovsing A/S has subcontracted
         Atlantic Research Corporation to provide the necessary
         consultancy assistance.



A.2      S̲c̲h̲e̲d̲u̲l̲e̲

         The consultancy assistance was initiated during April
         1980 and is planned to be complete at the beginning
         of November 1980.  A schedule for each of the activities
         described in section A.3 is presented below.



A.3      T̲a̲s̲k̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲

         ACP task 1 is to evaluate the cage solution contra
         the rack solution.

         ARC task 2 is to produce a technical report to be used
         for Request For Quotation (RFQ) on the "rack solution".

         ARC task 3 is to establish a proposal on the "rack
         solution" based on the common agreement reach between
         CR A/S and SHAPE 29/10 - 31/10 1980.
















                        A̲P̲P̲E̲N̲D̲I̲X̲ ̲B̲



B.1      T̲e̲c̲h̲n̲i̲c̲a̲l̲ ̲P̲u̲r̲c̲h̲a̲s̲i̲n̲g̲ ̲(̲T̲P̲)̲

         The terminal purchasing activities was initiated the
         1/7, 1980 and is planned to be completed by the 15/12
         1980.

         The terminal equipment to be purchased are

         -   VDU's
         -   Medium Speed Printers
         -   Paper Tape Reader/Puncher
         -   High Speed Printers.



B.2      S̲c̲h̲e̲d̲u̲l̲e̲

         Attached is a schedule for the purchasing activities
         and the deliveries of terminal equipment which are
         described in section B.3 below.



B.3      T̲a̲s̲k̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲

         TP task 1 is Request For Proposal (RFQ)

         TP task 2 is to evaluate the bidders and to select
         compliant bidders which culminates in a "Short-Listing"
         of the bidders.

         TP task 3 is a commonality study between CAMPS and
         SCARS II terminal equipment with the objective to select
         the same type of equipment for both systems.

         TP task 4 is a final negotiation and order placement.

         TP task 5 covers the delivery plan/schedule for the
         purchased equipment.  The terminal equipment will be
         delivered in 15 deliveries of equal size each month
         from the beginning of June 81.











                        A̲P̲P̲E̲N̲D̲I̲X̲ ̲C̲



C.1      C̲h̲r̲i̲s̲t̲i̲a̲n̲ ̲R̲o̲v̲s̲i̲n̲g̲ ̲C̲o̲r̲p̲e̲r̲a̲t̲i̲o̲n̲

         In order to achieve the highest skills available within
         Christian Rovsing two major SW packages have been subcontracted
         to Christian Rovsing Corporation

         The tasks consists of a Test Drive System (TDS) and
         communication software/firmware related to the NICS/TARE,
         SCARS II and ACE CCIS channels.



C.2      S̲c̲h̲e̲d̲u̲l̲e̲

         Attached is a schedule for the development tasks, which
         are described below.



C.3      T̲a̲s̲k̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲

         Christian Rovsing Corporation task 1 is to develop
         a Test Drive System (TDS) as described in the Work
         Package Description.

         Christian Rovsing Corporation task 2 is to develop
         software/firmware related to the NICS/TARE, SCARS II
         and ACE CCIS interfaces as described in Work Package
         4.3.3.1-4.3.3.3.