DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦5a767f7e4⟧ Wang Wps File

    Length: 39556 (0x9a84)
    Types: Wang Wps File
    Notes: site preparation          
    Names: »0005A «

Derivation

└─⟦26e1ab804⟧ Bits:30005814 8" Wang WCS floppy, CR 0001A
    └─ ⟦this⟧ »0005A « 

WangText



7…09…7…01…6…08…6…0e…5
4…08…4…0f…4…05……86…1
 
 
 
 
 
 
 
 
 …02…
 
 
 
 
 …02…
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 …02…
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
- #
 -













                        APPENDIX A

                    STATEMENT OF WORK






                    S̲T̲A̲T̲E̲M̲E̲N̲T̲ ̲O̲F̲ ̲W̲O̲R̲K̲



                         1̲ ̲ ̲S̲C̲O̲P̲E̲



         Subcontractor shall deliver material and services in
         accordance with requirements stated in this section.









      2 ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲E̲Q̲U̲E̲N̲C̲E̲ ̲A̲N̲D̲ ̲D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲



         The installation sequence is listed in Appendix D for
         information only.  Subcontractors schedule of deliverables
         is contained in Appendix B.

         The requirements concerning contractors and customers
         responsibilities are attached as Appendix D for information
         only.  Whereever mentioned "site civil work drawings"
         in appendix D this statement shall be interpreted as
         "civil works requirements".









                    3̲ ̲ ̲W̲O̲R̲K̲ ̲B̲R̲E̲A̲K̲-̲D̲O̲W̲N̲



         This Statement of Work describes subcontractors effort
         in preparing the sites for installation of the CAMPS
         equipment.

         The effort is divided into the following work packages:



         P̲h̲a̲s̲e̲ ̲1̲ ̲

         1.  Preparation of site surveys.  (WP ref. 4.1.3).

         2.  Accomplishment of site surveys (WP ref. 4.1.2).

         3.  Preparation of site Civil Works  requirements (WP
             ref. 4.2).

         4.  Preparation of as-to-be-built drawings (WP ref.
             4.3).

         P̲h̲a̲s̲e̲ ̲2̲

         5. Activities during the site preparation period (WP
         ref. 4.4). Including a site verification procedure
         (WP Ref. 4.5).

         P̲h̲a̲s̲e̲ ̲3̲

         6. Accomplishment of site verification. (WP ref. 4.5)

         7. As-built documentation (WP ref. 4.6)











           4̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



4.1      S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲



4.1.1    A visit to each site is scheduled May 21 through July
         4 l980.

         Details concerning each visit and sequence of sites
         will be subject to coordination between shape and CR.



4.1.2    The purpose of site surveys is to gather information
         necessary to prepare the site civil works requirements,
         the as-to-built drawings and to verify host nation
         delivered documents/drawings.

         Subcontractors respobsibilities will include but not
         be limited to the following tasks:

…02…1.       To determine physical location of each piece of equipment
         in cooperation with customer including the combination
         of staff cell equipment i.e obtain  name and relevant
         identification of all staff cells.

…02…2.       To determine runs of all interface cables and interconnecting
         cables between contractors equipments.  It will be
         decided whether or not the cables is to be run in cable
         ducts.

…02…         Furthermore it will be determined if false floor or
         false ceilings are required.

…02…         To determine I.D.F. location and all cables which have
         to pass the I.D.F.

…02…3.       To investigate existing environmental control facilities.

…02…4.       To determine requirements to power and light installations.
          The quantity, type and location of utility outlets
         and light armatures in conjunction with major equipment
         locations will be considered.



…02…5.       To determine requirements to grounding systems.  A
         terminal or jack near to each piece of major equipment
         is to be provided by customer.  The survey team will
         determine location and type of this terminal or jack.

…02…6.       To verify the access routes, along which major equipments
         have to be moved from entrance to installation area.
          The smallest access dimension is to be measured and
         compared with the largest piece of equipment.

…02…7.       To determine the nature and relevance of other civil
         works and installations, at site.

…02…8.       To determine on on-site logistic support. (custom clearance,
         receiving of equipment and spares, handling of equipment
         etc.).

…02…9.       To verify ACE COMSEC and territorial host nation requirements
         to the installations, and to determine restrictions
         or limitions, if any, to the installation work to be
         performed.

…02…10.      To establish and interface to the CAMPS responsible
         site personnel and other local authorities involved
         and to get an agreement on site facilities and support
         required in order for contractor to perform work on
         site, such as:

             Support concerning customs and national legislation,
             handling support, temporary storage, access and
             on site facilities and services for contractors
             personnel, on site liasion etc.

…02…11.      To discuss and to clarify the on site responsibilities
         of contractor and customer.

…02…12.      To complete the site survey  questionaire developed
         by subcontractor.  This includes the responsibility
         for getting Host Nation personnel or SHAPE representatives
         to provide the necessary information.

         All agreements and decisions made or taken during each
         site survey is to be documented and signed in a site
         survey protocol.





4.1.3    The following tasks/documents shall be accomplished
         by subcontractor prior to the site survey:

…02…1.       A procedure or checklist, which identifies all inspections,
         examinations and verifications to be carried out during
         the site surveys. It shall further describe all areas
         of decisions to be taken during each site visit. (Location
         of major equipment, runs of cables, power, logistic
         support etc.). This document shall be reviewed by contractor.

…02…         Reference to applicable requirements shall be made
         (system, IFB, contract requirements, human engineering,
         power and safety regulations etc.).

…02…2.       A site survey questionaire, which list all the general
         questions concerning transport, access to site, access
         to rooms allocated for camps, physical characteristics
         of camps rooms, data concerning installation etc.

…02…3.       A document package for each site will be provided by
         customer prior to site survey. 

…02…         The adequacy of this package will be verified during
         site survey. The drawings shall be reviewed prior to
         site survey and if necessary, supplementary drawings
         must be requested by subcontractor at each site visit.

…02…4.       Physical characteristics of equipment to be installed
         will be prepared by contractor.  The data will be preliminary
         and cover the following items:

…02…         Equipment dimensions; weight, power comsumption/heating,
         configuration, floor space, floor load, clearance dimensions,
         mounting requirements, grounding requirements etc.

…02…5.       General requirements concerning civil works based on
         data supplied in 4. above:

…02…         Construction requirements to camps rooms, light and
         mainpower, airconditioning, grounding, cabling, cable
         ducts. etc.





4.2      C̲I̲V̲I̲L̲ ̲W̲O̲R̲K̲S̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲



4.2.1    G̲e̲n̲e̲r̲a̲l̲

         The civil works requirements should, as a minimum,
         be in the form of engineering drawings and written
         text describing all civil works that need to be accomplished
         to prepare the site for contractors equipment installation.
         This documentation must be in sufficient technical
         detail to instruct a civil works contractor in the
         site design required.

         Requirements concerning civil works to be performed
         by Host Nation is to be delivered to customer in accordance
         with Appendix B.

         The requirements will be reviewed and modified by SHAPE
         or Host Nation, if appropriate, to meet the Host Nation
         laws and regulation.



4.2.2    S̲u̲b̲m̲i̲t̲t̲a̲l̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲S̲u̲b̲c̲o̲n̲t̲r̲a̲c̲t̲o̲r̲



4.2.2.1  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲

         Preliminary equipment characteristics and hardware
         configuration must reflect final decision on hardware
         configuration and EMI protection and will be submitted
         to subcontractor at least 8 months prior to scheduled
         submission of Civil Works requirements.  (See app.
         "B").

         Final delivery of data will be submitted to subcontractor
         at least 3 months prior to scheduled submission of
         Civil Works Requirements.

         Until the final delivery of data from contractor to
         subcontractor, subcontractor will incorporate the changes
         in his documentation with no impact on cost and schedule.





4.2.2.2  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲C̲u̲s̲t̲o̲m̲e̲r̲

         As stated in the contract it is subcontractors responsibility
         to obtain the necessary data from customer to generate
         the Civil Works Requirements.



4.2.3    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲C̲i̲v̲i̲l̲ ̲W̲o̲r̲k̲s̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

         The following data will form the basis for preparing
         the site Civil Works Requirements.

         1-  H/N drawings/documents delivered per ref. 4.1.3.(3).

         2-  The information gathered during the site surveys
             per ref. 4.1.2.

         3-  The equipment characteristics and hardware configuration
             per ref. 4.2.2.1.

         4-  Additional information obtained after site survey
             per ref. 4.2.2.2.

         5-  H/N drawings/documentation of cable runs outside
             the CAMPS Room provided by SHAPE.



4.2.4    The documentation to be prepared will include but not
         be limited to the following:

         1-  Physical layout of major equipment per ref. 4.1.2.
             (1).

         2-  Cable runs of all interface cables and interconnecting
             cables to be run inside the CAMPS room (ref. 4.1.2.
             (2)) and cable ducts if applicable.

         3-  Airconditioning Requirements and interfacing per
             ref. 4.1.2 (3).

         4-  Power installation requirements and interfacing
             per ref. 4.1.2 (4)



         5-  Grounding Systems Requirements and Interfacing
             per ref. 4.1.2 (5).

         6-  Cable runs outside the CAMPS room based on information
             obtained from customer.



4.3      A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲ ̲



4.3.1    G̲e̲n̲e̲r̲a̲l̲

         As-to-be-built drawings is to be delivered to SHAPE
         in accordance with appendix B.

         The as-to-be-built drawings are to be reviewed and
         approved by SHAPE (to include ACE COMSEC approval).

         The documentation shall provide full details of how
         all the major assemblies of the CAMPS equipment at
         each location are to be physically installed and electrically
         integrated.



4.3.2    S̲u̲b̲m̲i̲t̲t̲a̲l̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲S̲u̲b̲c̲o̲n̲t̲r̲a̲c̲t̲o̲r̲



4.3.2.1  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲

         Final data will be submitted to subcontractor at least
         3 months before scheduled submission of As-to-be-built
         drawings.

         Data will include:

         a-  Cable numbers, reference designators of plugs and
             jackets, wire lists for all power and signal cables.

         b-  Cross connection frames and patch panel details.





4.3.2.2  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲C̲u̲s̲t̲o̲m̲e̲r̲

         As stated in the contract it is subcontractors responsibility
         to obtain the necessary data from customer to generate
         As-To-Be-Built drawings.



4.3.3    D̲r̲a̲w̲i̲n̲g̲s̲/̲D̲o̲c̲u̲m̲e̲n̲t̲s̲ ̲t̲o̲ ̲b̲e̲ ̲P̲r̲e̲p̲a̲r̲e̲d̲

         The documents shall be prepared for each location and
         include all relevant information covering the following:

         a-  Floor and wall plans showing all cable runs within
             the CAMPS equipment room. Cable runs must be CAMPS
             related or have COMSEC implications. 

             Signal cable runs from CAMPS equipment room to
             user terminals shall be incorporated. (Information
             on the routing of the cable-runs will be provided
             by customer).

         b-  Plan showing grounding system related to CAMPS
             with description of conductors, electrodes and
             joints. Drawings and specification to be provided
             by customer.

         c-  Cable racking and cable runs with cable numbers
             and cable functions to include as appropriate all
             terminating points, connections, connectors and
             sockets. The functions of all conductors shall
             be shown.

         d.  Physical layout (plan and elevation) of all major
             equipments.

         e.  Ventilation and environmental control systems that
             impact on COMSEC. Drawings and specifications to
             be supplied by customer if installed or modified
             after site survey.

         f.  Cross-connection frames and patch panel details.
             

         g-  Power distribution boards, cabling, wiring and
             distribution schemes showing position of filters
             if fitted. Drawings and specificatons to be supplied
             by customer.



         h-  Ancillary equipment that have COMSEC implications.
             Drawings and specification to be provided by customer
             if installed or modified after site surveys.

         i-  Layout and cable runs of all intercomm equipment
             having a COMSEC impact relative to CAMPS equipment.
             Drawings and specification to be supplied by customer
             if installed after site surveys.



4.4      A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲ ̲D̲U̲R̲I̲N̲G̲ ̲T̲H̲E̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲P̲E̲R̲I̲O̲D̲

         The site preparation period will commence with Subcontractors
         delivery of Civil Works Requirements for the first
         site.

         During this period, effort is on final coordination
         and liason in connection with the carrying out of site
         civil works, in addition to generation and delivery
         of Civil Works Requirements and as-to-be-built drawings.

         Customer will issue approval or a list of deficiences
         of the drawings within 15 days after receipt (see appendix
         D).

         All changes submitted by customer resulting from the
         construction works as well as minor design modifications
         to contractors equipment shall result in update of
         the master documentation file, and be incorporated
         in the preliminary version of as-built documentation.



4.5      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲O̲N̲

         The verification of each site is scheduled to take
         place as stated in appendix B.





4.5.1    The verification shall prove if the site is ready for
         installation of the CAMPS equipment.

         The proving will consist of inspections and tests according
         to a Site Verification Procedure.

         The procedure will be prepared on the basis of subcontractors
         civil works requirements, as-to-be-built drawings and
         host nation civil works drawings.

         The procedure is to be signed off by the participants
         and issued as a Site Verification Report.

         Discrepancies found during the verificaton will be
         recorded together with corrective actions to be taken
         and completion data of action taken.

         Site verification is considered completed when the
         Site Verification Report has been submitted to the
         contractor.



4.5.2    E̲f̲f̲o̲r̲t̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲

         1-  One visit each site with the following participants
             as a minimum:

             -   one CR representative
             -   one SHAPE representative
             -   one H/N representative

         2-  Preparation of a site verification procedure to
             be approved by CR.



4.6      A̲S̲-̲B̲U̲I̲L̲T̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲



4.6.1    G̲e̲n̲e̲r̲a̲l̲

         As-built documentation for each site is to be delivered
         in accordance with appendix B.



         The documentation shall provide full details of how
         all major assemblies of the supplied equipment at each
         location have been physically installed and electrically
         integrated.



4.6.2    S̲u̲b̲m̲i̲t̲t̲a̲l̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲S̲u̲b̲c̲o̲n̲t̲r̲a̲c̲t̲o̲r̲



4.6.2.1  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲

         During site installation a copy of the as-to-be-built
         drawings will be marked up by contractor to reflect
         any deviations and submitted to Subcontractor. The
         marked-up drawings will be reviewed by subcontractor
         and submitted to SHAPE for approval. SHAPE will ensure
         approval within 15 days of submittal.



4.6.3    D̲r̲a̲w̲i̲n̲g̲s̲/̲D̲o̲c̲u̲m̲e̲n̲t̲s̲ ̲t̲o̲ ̲b̲e̲ ̲P̲r̲e̲p̲a̲r̲e̲d̲

         The as-built documentation for each site will comprise
         the documentation described in para 4.3.3 (i.e. updated
         as-to-be-built drawings) and is to be supplied to SHAPE
         as follows:

         1-  Preliminary As-Built documentation to be delivered
             at time of Site Provisional Acceptance.

         2-  Final As-Built documentation 3 months after preliminary
             version





                        APPENDIX B

                 SCHEDULE OF DELIVERABLES





                                         Appendix B


                                  SCHEDULE OF DELIVERABLES


DESCRIPTION                                 SCHEDULED DELIVERY
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

P̲H̲A̲S̲E̲ ̲1̲:̲ ̲ ̲S̲U̲R̲V̲E̲Y̲ ̲A̲N̲D̲ ̲D̲E̲S̲I̲G̲N̲
P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲:̲

SITE SURVEY PROCEDURE/QUESTIONAIRE          1980-05-20

PRELIM. REQUIREMENTS/SPECIFICATIONS         1980-05-20

DRY RUN AT SHAPE                            1980-05-13

SITE SURVEY, START OF                       1980-05-20

S̲I̲T̲E̲ ̲C̲I̲V̲I̲L̲ ̲W̲O̲R̲K̲S̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲:

SITE  1                                     1981-08
SITE  2                                     1981-09
SITE  3                                     1981-10
SITE  4…02…1981-11
SITE  5                                     1981-12
SITE  6                                     1982-01
SITE  7                                     1982-02
SITE  8                                     1982-03
SITE  9                                     1982-04
SITE 10                                     1982-05
SITE 11                                     1982-06
SITE 12                                     1982-07

A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲:̲

SITE  1                                     1981-11
SITE  2                                     1981-12
SITE  3                                     1982-01
SITE  4                                     1982-02
SITE  5                                     1982-03
SITE  6                                     1982-04
SITE  7                                     1982-05
SITE  8                                     1982-06
SITE  9                                     1982-07
SITE 10                                     1982-08
SITE 11                                     1982-09
SITE 12                                     1982-10




D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲                                 S̲C̲H̲E̲D̲U̲L̲E̲D̲ ̲D̲E̲L̲I̲V̲E̲R̲Y̲

P̲H̲A̲S̲E̲ ̲2̲:̲ ̲ ̲F̲I̲N̲A̲L̲ ̲C̲O̲O̲R̲D̲I̲N̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲

C̲O̲O̲R̲D̲I̲N̲A̲T̲I̲O̲N̲ ̲R̲E̲L̲A̲T̲E̲D̲ ̲T̲O̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲
A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

CCORDINATION SITE  1
COORDINATION SITE  2
COORDINATION SITE  3
COORDINATION SITE  4
COORDINATION SITE  5
COORDINATION SITE  6
COORDINATION SITE  7
COORDINATION SITE  8
COORDINATION SITE  9
COORDINATION SITE 10
COORDINATION SITE 11
COORDINATION SITE 12
SITE VERIFICATION PROCEDURE ALL SITES       1982-05

P̲H̲A̲S̲E̲ ̲3̲:̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲U̲P̲D̲A̲T̲E̲

S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲:

SITE VERIFICATION SITE  1                   1982-07
SITE VERIFICATION SITE  2                   1982-08
SITE VERIFICATION SITE  3                   1982-09
SITE VERIFICATION SITE  4                   1982-10
SITE VERIFICATION SITE  5                   1982-11
SITE VERIFICATION SITE  6                   1982-12
SITE VERIFICATION SITE  7                   1983-01
SITE VERIFICATION SITE  8                   1983-02
SITE VERIFICATION SITE  9                   1983-03
SITE VERIFICATION SITE 10                   1983-04
SITE VERIFICATION SITE 11                   1983-05
SITE VERIFICATION SITE 12                   1983-06



A̲S̲-̲B̲U̲I̲L̲T̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲:̲

PRELIMINARY AS-BUILT DOCUMENTATION SITE  1  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  2  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  3  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  4  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  5  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  6  1983-04
PRELIMINARY AS-BUILT DOCUMENTATION SITE  7  1983-05
PRELIMINARY AS-BUILT DOCUMENTATION SITE  8  1983-06
PRELIMINARY AS-BUILT DOCUMENTATION SITE  9  1983-07
PRELIMINARY AS-BUILT DOCUMENTATION SITE 10  1983-08
PRELIMINARY AS-BUILT DOCUMENTATION SITE 11  1983-09
PRELIMINARY AS-BUILT DOCUMENTATION SITE 12  1983-10

Final As-Built Documentation                3 months after preliminary version.

N̲O̲T̲E̲:̲

PAB must submit his documentation to SHAPE at the dates listed above.  Documentation to be approved
 by CR per clause 10 of this contract must be submitted prior to above date in time to keep the
 SHAPE delivery schedule.










                                         APPENDIX E


                                 DOCUMENTATION REQUIREMENTS











                 A̲.̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲



         The following is SHAPE's requirements to documentation
         as stated in the CAMPS IFB:



A.1.1…02…P̲a̲p̲e̲r̲

         The documents, exclusive of covers, shall be printed
         on a good grade of white paper of sufficient weight
         and substance to permit printing on both sites. The
         paper size will be DIN A4. The paper used for fold-out
         drawings shall be of a quality and thickness that permits
         repeated opening and folding without cracking or tearing
         at the folds.



A.1.2    B̲i̲n̲d̲i̲n̲g̲



A.1.2.1  The documents shall be bound between hardbacked covers
         that incorporate a metal binding system which will
         permit easy removal and insertion of pages, photographs,
         illustrations and drawings and which will permit the
         documents to lie flat when opened at any page.



A.1.2.2  The information on pull-out sheets bound in the hard-backed
         covers shall be positioned so that it is clear of the
         text of its associated document when opened up so that
         the reader can readily cross-refer between text, drawings
         and illustrations.



A.1.2.3  If they are not accountable items for security reasons,
         excessively large drawings may be placed in pockets
         formed in the rear covers of binders, or in the case
         of, as-built and installation instructions, to contain
         large drawings in separate folders equipped with a
         fastening arrangement to prevent accidental loss and
         spillage of the contents.





A.1.2.4  The cover and title page of the document shall show
         the classification of the document, manufacturer of
         the equipment, number of the document and its issue
         number, number of the contract and the date of issue.
         In the case that a subject is covered in more than
         one volume then an indication of the contents of each
         manual shall be shown.The title and number of the document
         shall also be shown on the spine of the cover if applicable.



A.1.3    N̲u̲m̲b̲e̲r̲i̲n̲g̲



A.1.3.1  The pages of Sections and Chapters are to be separately,
         and sequentially numbered beginning with the number
         one in each case, with the associated Section or Chapter
         number added as a prefix. The page numbers are to be
         inserted at the centre of the lower margin above the
         classification or in the appropriate box if preprinted
         formsheets are used.



A.1.3.2  Paragraphs, sub-paragraphs, and sub-sub-paragraphs,
         are to be numbered sequentially commencing with one,
         and sub-paragraphs are to have the associated paragraphs
         number added as a prefix (i.e. 1.1., 1.2., 1.3., etc.)
         and sub-sub-paragraphs, the associated sub-paragraph
         number added as a prefix (i.e. 1.1.1., 1.1.2., 1.1.3.
         etc.). The maximum depth will be 4 (i.e. 1.1.1.1) unless
         otherwise agreed.



A.1.3.3  For sub-divisioning identification, lower-case alphabetical
         characters enclosed in half brackets shall be used
         (i.e. (a), (b), (c), etc). For sub-sub-divisioning,
         upper-case Arabic numerals enclosed in half brackets
         shall be used (i.e. (1), (2), (3), etc).



A.1.3.4  Tables shall be captioned and allocated a Table Number
         having the Section or Chapter number as appropriate
         added as a prefix (e.g. Table 1.1.). Tables may be
         included as a part of the text or printed on a fold-out
         sheet. When printed on a fold-out sheet, the table


         number must be positioned on the fold-out portion so
         that it is visible on opening the document to which
         it belongs.



A.1.4    P̲r̲e̲f̲a̲c̲e̲



A.1.4.1. Each separately bound document (manual) shall commence
         with a set of introductory pages, and when a manual
         or set of documentation consists of only one separately
         bound document, the introductory pages shall consist
         of the following:

         a)  Title pages with the security classification of
             the handbook, manufacturer of the equipment, number
             of the handbook and its relevant issue number,
             number of the relevant contract and date of issue.

         b)  When applicable instructions covering treatment
             for electric shock.

         c)  Amendment history sheet.

         d)  Record of modifications to the equipment.

         e)  Introduction giving the purpose of the handbook
             and instructions for its use.

         f)  Table of contents listing the titles of all sections,
             headings and sub-headings, together with relevant
             paragraph and page numbers.

         g)  Detailed list of all tables together with relevant
             table and page numbers.

         h)  Detailed list of all drawings, illustrations and
             photographs together with relevant reference and
             page numbers.

         j)  Legend explaining all abbreviations and symbols
             used in the text and on the drawings.

         k)  Photographs of the major items/bays described in
             the handbook.





A.1.4.2  When a manual or set of documentation consists of more
         than one volume, each separately bound volume, section
         or part, shall contain a set of introductory pages
         as described, plus an additional page inserted after
         the front sheet containing an abbreviated list of contents
         for the complete manual or set of documentation, as
         applicable.



A.1.4.3  Wherever possible, photographs, drawings and illustrations
         shall be bound in the same cover as the associated
         text. In addition when a manual or set of documentation
         consists of more than one separately bound document
         the first document of the series shall be identified
         as the master document and shall contain all information
         of a general nature applicable to all documents of
         the series.



A.1.5    P̲r̲i̲n̲t̲i̲n̲g̲ ̲a̲n̲d̲ ̲T̲y̲p̲e̲



A.1.5.1  A conventional typewriter font shall be employed for
         the printing of all letters and figures in the text
         of all documents.



A.1.5.2  All titles and headings shall be underlined.



A.1.5.3  Operation and maintenance manuals shall be printed
         using either a multilith or offset process.



A.1.6    L̲a̲n̲g̲u̲a̲g̲e̲



A.1.6.1  All documents shall be written in the English language.





A.1.6.2  All descriptions shall be written clear and in precise
         manner, using unambiguous English and a minimum of
         words. Wherever feasible descriptions and procedures
         shall be supported either by diagrams and photographs
         or other types of illustrations to facilitate understanding
         of the text by personnel having only a working knowledge
         of the English language.



A.1.7    S̲e̲c̲u̲r̲i̲t̲y̲ ̲C̲l̲a̲s̲s̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         Manuals and documents shall be classified in accordance
         with the classification of the information included
         therein. The relevant classification of a document
         shall be printed at the centre top and bottom of all
         pages, photographs illustrations and drawings, and
         at the centre top and bottom of the front cover of
         all binders. The highest classification of any section
         of a document shall be printed on the cover of that
         binder.
         Applicable document for security classification is
         "NATO Document CM(55)15 Final" "Security within the
         North Atlantic Treaty Organization"



A.1.8    P̲h̲o̲t̲o̲g̲r̲a̲p̲h̲s̲,̲ ̲I̲l̲l̲u̲s̲t̲r̲a̲t̲i̲o̲n̲s̲ ̲a̲n̲d̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲



A.1.8.1  All titles and included text and annotations shall
         be in the English language in addition to any other
         language that may be employed. To facilitate correlation
         the figure numbers are to be preceded by the associated
         chapter or section number as appropriate (e.g. Figure
         1.1.).



A.1.8.2  The lettering and layout of drawings shall be in accordance
         with recognized industrial or national standards. Hand-lettering
         shall be avoided except on advance information copies
         and for marking up as-to-be-built documents during
         site implementation.





A.1.8.3  Symbols, when employed, shall be defined so that there
         can be no confusion in their interpretation. The definitions
         may, at the discretion of the contractor, be given
         on the drawings or collectively in the associated document
         in the form of a glossary.



A.1.8.4  The use of drawings and illustrations that exceed 1
         x 1.5 metres shall be avoided. Where necessary the
         scale shall be shown.



          B̲ ̲ ̲Q̲U̲A̲N̲T̲I̲T̲Y̲ ̲O̲F̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲



                               PAB shall deliver the
                               following quantities
                               of documentation.


                               Description            SHAPE        CR
                                ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                               ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                               Site survey report     2 each site  1 each site
                                                      (SHAPE 1, site 1)
                               Host nation drawings                1 each site
                               C̲i̲v̲i̲l̲ ̲w̲o̲r̲k̲ ̲r̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
…02…Preliminary…02…4 each site         2 each site
                               Final                  4 each site  4 each site
                               A̲s̲-̲t̲o̲-̲b̲e̲-̲b̲u̲i̲l̲t̲ ̲d̲r̲a̲w̲i̲n̲g̲s̲
                               Preliminary            4 each site  2 each site
                               Final                  4 each site  4 each site
                                                      (SHAPE 2, site 2)
                               Site Verification procedure          1 each site
                               Site Verification report            2 each site 1 each site
                                                      (SHAPE 1, site 1)


                               A̲s̲-̲b̲u̲i̲l̲t̲ ̲d̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ 

                               Marked up ATBB…02…1 each site           1 each site
                               Preliminary as-built doc.           2 each site 2 each site
                                                      (SHAPE 1, site 1)
                               Final as-built doc.    4 each site  2 each site
                                                      (SHAPE 2, site 2)


                         C̲ ̲C̲O̲P̲I̲E̲S̲



         At least one set of the documentation delivered to
         CR in para B above shall be a reproducable copy. (i.e.
         transparent or film copies of drawings are required).







                      D̲ ̲ ̲M̲A̲S̲T̲E̲R̲ ̲F̲I̲L̲E̲



         PAB shall store all of masters documentation material
         for a period of min. 10 years after last submittal
         under this contract.









                        A̲P̲P̲E̲N̲D̲I̲X̲ ̲D̲


                     Clauses 9 and 21

                            of

                      Main Contract


                     C O N T R A C T


                         between

        Supreme Headquarters Allied Powers Europe

         (in the following referred to as SHAPE)



                           and



                  Christian Rovsing A/S
                       2, Lautrupvang
                       DK-2750  Ballerup
                       Denmark



           (in the following referred to as CR)

                            on

              the supply to SHAPE by CR of a

         Computer Aided Message Processing System

         (in the following referred to as CAMPS)


P̲A̲R̲A̲G̲R̲A̲P̲H̲ ̲9̲ ̲ ̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲E̲Q̲U̲E̲N̲C̲E̲

9.1      The following is an installation sequence of main CAMPS
         sites:

…02…         (1)   SHAPE, Casteau, BE
…02…         (2)   BALTAP, Viborg, DK
…02…         (3)   NCS, Latina, IT
…02…         (4)   AFSOUTH, Naples, IT
…02…         (5)   AFCENT/AAFCE, Boerfink, GE
…02…         (6)   NORTHAG/2ATAF, Maastricht, NL
…02…         (7)   CENTAG/4ATAF, Ruppertsweiler, GE
…02…         (8)   AFNORTH, Kolsaas, NO
…02…         (9)   COMNON, Reitan, NO
…02…         (10)  UKAIR, High Wycombe, UK
…02…         (11)  LANDSOUTH/5 ATAF, Vicenza, IT
…02…         (12)  LSE/6ATAF, Izmir, TU

…02…         (13)  MEDNOREAST, Ankara, TU   )
…02…         (14)  MEDEAST, Athens, GR      )     OPTIONS
…02…         (15)  SONOR, Holmenkollen, NO  )
…02…         (16)  NATO, Evere, BE          )



9.2      The above listed sequence is subject to the following
         conditions:

         (1) Sites listed above as (1) and (2) in subparagraph
             9.1, those sites being, respectively, SHAPE and
             BALTAP, will remain fixed in sequence for the life
             of the contract.

         (2) SHAPE shall have the right, for a period of thirteen
             months after contract signature, to resequence
             all sites other than the aforementioned sites (1)
             and (2).

         (3) During the fourteenth and twentyfirst months period
             after contract signature, SHAPE shall have the
             right to resequence the last six main sites, other
             than option sites, which appear on the Installation
             Sequence list as of the expiration of the thirteenth
             month after contract signature.

         (4) Any resequencing allowed by subparagraphs (2) and
             (3) hereinabove, shall be without any price or
             delivery date adjustment.

         (5) Any resequencing not authorized under subparagraphs
             (1) thru (3) hereinabove shall be subject to price
             and/or delivery date adjustment, as appropriate.


PARAGRAPH 21 S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲



21.1     G̲e̲n̲e̲r̲a̲l̲

         Site Preparation and Installation shall be carried
         out according to the following general rules:

21.1.1   Customer is responsible for site preparation.

21.1.2   Contractor is responsible to provide site civil work
         drawings.  These drawings will contain the information
         needed to prepare the site for equipment installation.
          In addition, contractor will provide A-T-B-B drawings.
          These drawings will contain all details of how all
         major assemblies of the equipment at each location
         will be physically installed and electrically integrated.

21.1.3   Contractor is responsible to determine site readiness
         and agree to same subsequent to his inspection/checkout
         of site.  After site acceptance, contractor is responsible
         for equipment installation.

21.2     S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲

21.2.1   C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲

         All site civil work drawings must be given to SHAPE
         12 months prior to commencement of site installation.
          All A-T-B-B drawings must be given to SHAPE not later
         than 9 months prior to start of installation to include
         ACE Comsec approval.  SHAPE will issue approval or
         a list of deficiencies of the drawings within 15 days
         after receipt.

21.2.2   C̲u̲s̲t̲o̲m̲e̲r̲…88…s̲ ̲r̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲

…02…a)       To perform all work necessary and pay all associated
         costs to make the site ready for installation of contractors
         equipment according to contractors site civil work
         drawings as modified by SHAPE or the territorial host
         nation, if appropriate, to meet territorial host nation
         laws and requlations.

…02…b)       Customer will remain responsible for all site preparation
         until site has been verified and accepted as ready
         for installation by CR



…02…c)       If CR is prevented from commencing or performing installation
         work according to schedule due to the sites being unfinished
         or if, having arrived at the site, the contractors
         staff and/or supplies are denied access to the site,
         a claim will be submitted by contractor.  This claim
         will be resolved under clause 37 of SHAPEs General
         Provisions "SHAPE delay of work".

…02…d)       Customer will notify contractor of a sites readiness
         no less than 30 calendar days prior to the anticipated
         date the site will be ready.  Once SHAPE certifies
         that a site is ready for installation, the Contractor
         will be required to verify that the site is acceptable
         within fourteen calender days of a formal request by
         SHAPE to accomplish the verification.  This inspection
         date may be modified by mutual agreement of SHAPE and
         CR.


21.3…02…S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

21.3.1   C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲…88…s̲ ̲r̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲

         Subject to coordination with SHAPE, contractor may
         move equipment onto site subsequent to approval of
         site readiness.  The installation of equipment will
         be done in accordance with the following:

         At each main site contractor will:

…02…a)       Deliver and install CAMPS central equipment within
         the confines of a shielded enclosure.  The dimensions
         of the shielded enclosure and other relevant physical
         characteristics shall be forwarded as part of contractors
         civil works specifications.  Contractor will perform
         all installations inside the shielded enclosure.

…02…b)       Deliver the proposed number of supervisors positions
         and a maintainance position and connect them with secure
         cables to the central equipment.

…02…c)       Deliver the proposed number of user terminals and connect
         them with secure cables to the central equipment.

…02…d)       Connect the proposed number of colocated SCARS, CCIS
         and TARE interface cables (secure) to the central equipment.

…02…e)       Connect the proposed number of distant TARE channels
         with secure cables to the central equipment.



…02…         Contractor will provide and install the distribution
         frame and the proposed modems.  Customer will provide
         and install the cryptographic equipment, and make all
         conections except for the cables from the distribution
         frame to the central equipment.


21.3.2…02…C̲u̲s̲t̲o̲m̲e̲r̲…88…s̲ ̲r̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲

         Customer…08…s responsibilities are set forth below:

         Customer will perform the following civil works according
         to contractor…08…s specifications:

…02…a)       Perform all light and mainpower installations to feed
         and maintain the proposed equipment (power cabling,
         circuit breakers, fuses, light armatures, distribution
         to outlets, and outlets), except within the confines
         of the shielded enclosure.

…02…b)       Provide and install raised floors if required and all
         cable ducts including ducts under raised floors if
         applicable to run the cables.

…02…c)       Run all signal cables (supplied by contractor), except
         cabling within the confines of the CAMPS room.

…02…d)       NATO lines (TARE, CCIS, SCARS) terminate at a specified
         plug, jack or terminal IDF from which contractor shall
         take over responsibility.

…02…e)       Perform all installation required to maintain the environmental
         conditions (temperature, humidity) specified.  Customer
         will install ventilation ducts, if required, according
         to civil works drawings. Contractor will perform all
         installations directly to the shielded enclosure.

…02…f)       Perform all other installations not directly related
         to the CAMPS equipment, if any (alarms, voice activated,
         intercom. o.e.)

…02…R̲e̲m̲o̲t̲e̲ ̲T̲A̲R̲E̲ ̲l̲o̲c̲a̲t̲i̲o̲n̲s̲

         Customer wil perform all civil works at the remote
         TARE locations as described in the Civil Works Drawings.


                       APPENDIX F:

                         OPTIONS


                        1̲ ̲G̲E̲N̲E̲R̲A̲L̲



         a)  The sites listed below are optional sites to be
             exercised later.

         b)  PAB shall submit a quotation for each of these
             sites if requested so by CR. The request for Quotation
             will be issued by CR only if scope of work has
             significantly changed. 









                 2̲ ̲ ̲O̲P̲T̲I̲O̲N̲A̲L̲ ̲M̲A̲I̲N̲ ̲S̲I̲T̲E̲S̲:̲



         a)  MEDNOREAST

         b)  SONOR

         c)  ATHENS

         d)  NATO



                3̲ ̲ ̲O̲P̲T̲I̲O̲N̲A̲L̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲A̲R̲E̲S̲:̲



         2 optional remote TARES are identified:

         REMOTE LOCATION                    RELATED MAINSITE

         1.  KOLSAAS                            SONOR

         2.  BALTAP                             BALTAP


               4̲ ̲ ̲O̲P̲T̲I̲O̲N̲A̲L̲ ̲R̲E̲M̲O̲T̲E̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲










         Remote Location                            Related
                                                    Mainsite

SITE                          

NO       NAME                 CATEGORY REMARKS

 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


1        UKAIR                I                     UKAIR

2        AFNORTH              I                     AFNORTH

3        COMNON               I                     COMNON

4        BALTAP               TBD                   BALTAP

5        AFCENT               )III     same         (AFCENT/AAFCE
6        AAFCE                )        main site    (

7    (   NORTHAG              )TBD     joint        (NORTHAG/2ATAF
     (   2ATAF                )        comcenter    (

8    (   CENTAG               )TBD     joint        (CENTAG/4ATAF
     (   4ATAF                )        comcenter    (

9    (   AFSOUTH              )TBD     joint        (AFSOUTH
     (   AIRSOUTH             )        comcenter    (
     (   DEPSTRIK FORSO.      )                     (

10       NAVSOUTH              TBD                  (AFSOUTH

11   (   MARAIMED             )TBD     joint        (AFSOUTH
     (   SUBMED               )        comcenter    (



12       AFSOUTH ADV.CMD.                           (AFSOUTH

13       LS                   )III     same         (LANDSOUTH
14       5ATAF                )        main site    (

15       LSE                  )III     same         (LSE/6ATAF
16       6ATAF                )        main site    (

17       SONOR                )I       same         (SONOR
18       NAVSONOR             )III     main site    (

19       MEDEAST               TBD                  MEDEAST

20       MEDNOREAST           TBD                   MEDNOREAST




                        5̲ ̲P̲R̲I̲C̲E̲S̲




        a) U̲n̲i̲t̲ ̲P̲r̲i̲c̲e̲s̲

        Each main site                       Nkr.  137,200

        Each Remote TARE Site                Nkr.  18,000

        Each Remote Terminal Site
        Cat  I (see below)                   Nkr.  16,000

        Each Remote Terminal Site
        Cat. II (see below)                  Nkr.  29,000

        Each pair of Remote Terminal Sites
        cat. III calculates as follows:

        Price for one of the two sites is    Nkr.  16,000
        Price for the other site is TBD
        i.e. either cat. I or II.  



        b) D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲ ̲o̲f̲ ̲C̲a̲t̲e̲g̲o̲r̲i̲e̲s̲


        C̲A̲T̲E̲G̲O̲R̲Y̲ ̲I̲:

        Remote location seperated by less than 5 km from main
        location.

        C̲A̲T̲E̲G̲O̲R̲Y̲ ̲I̲I̲:̲

        Remote location seperated by more than 5 km from main
        location.

        C̲A̲T̲E̲G̲O̲R̲Y̲ ̲I̲I̲I̲

        Two remote locations with same Main Site.







         OPTIONAL REMOTE TERMINALS

               R̲E̲M̲O̲T̲E̲ ̲L̲O̲C̲A̲T̲I̲O̲N̲                   R̲E̲L̲A̲T̲E̲D̲
                                                 ̲M̲A̲I̲N̲
                                                 ̲S̲I̲T̲E̲            C̲A̲T̲E̲G̲O̲R̲Y̲

               UKAIR                             UKAIR           I
               AFNORTH                           AFNORTH         I
               COMNON                            COMNON          I
               BALTAP                            BALTAP          TBD
               AFCKNT        SAME       (        AFCENT/AAFCE    TBD
               AAFCE         MAINSITE   (                        TBD

               NORTHAG ) JOINT                   NORTHAG/2
                                                 ATAF            TBD
               2 ATAF  ) COMCONTOR                               

CENTAG    ) JOINT            CENTAG/4 ATAF       TBD
4 ATAF    ) COMCONTOR                            



AFSOUTH           ) SAME                          
                                                 (
                                                  
                                                  
                                                  
                                                  
                                                  
                                                  
                                                  
                                                                 
AIRSOUTH          ) COMCONTOR                     
                                                 (
                                                  
                                                  
                                                  
                                                  
                                                  
                                                  
                                                  
                                                                 
DEPSTRIK FORSOUTH )                               
                                                 (
                                                  
                                                  
                                                  
                                                  
                                                  
                                                  
                                                                 
                                 (                
 
NAUSOUTH                         (AFSOUTH                        TBD
                                 (                
 
MARAIRMED ) SAME                 (                
 
SUBMED    ) COMCONTOR            (                
 
                                 (                
 
AFSOUTH ADV. CMD POST            (                
 

LS                                                
                                                 (LANDSOUTH
                                                  
                                                  
                                                  
                                                                 TBD
5 ATAF                         (                 

LSE                            (LSE/6 ATAF       TBD
6 ATAF                         (                 

SONOR                          (SONOR            I
NAUSONOR                       (                 TBD

MEDEAST                      MEDEAST             TBD

MEDNOREAST                   MEDNOREAST          TBD