⟦5f3811e6b⟧ Wang Wps File

    Length: 7903 (0x1edf)
    Types: Wang Wps File
    Notes: MOM NR. 39                
    Names: »4345A «

Derivation

└─⟦fa2167417⟧ Bits:30006184 8" Wang WCS floppy, CR 0396A
    └─ ⟦this⟧ »4345A « 

WangText




…02…

…02…KNN/831123…02……02…#
MINUTES OF MEETING NO. 39
…02……02…CAMPS











         CR/SHAPE
                                        831123   39              CR
                                                                 A/S

                           Minutes of Meeting held
                           at Christian Rovsing A/S
                           from 20th - 23rd November
                           1983.




         Ltc H. Hofmann         Mr. K. Nybroe-Nielsen
         Mr. D.A. Gardiner      Mr. U. Holst
         Mrs. F. Michel         Mr. O. Rene Petersen







              The agenda was as follows:

               1. MOU on the conduct of the 240 hour
                  test.

               2. Updates to CPS/TPR/007 (In Plant
                  Test Procedures).

               3. Data base for 240 hour test/functional
                  test and operational test.

               4. Preformatted messages implementation.

               5. VDU scenarios for load test.

               6. Relay function implementation and
                  test.

               7. Completion of the system integration
                  and test cases.

               8. Shipment of site 06 - missing spare
                  VDU and MSP.

               9. NATO funds for training.

              10. Cost evaluation for national security
                  clarification. (SW change).

              11. Outstanding payment.

              12. Change of low speed ports configuration.

              13. CAMPS/Nics Tare interface Testing.

              14. Test Room.


          1.  M̲O̲U̲

              CR strongly believes that the existing
              baseline documents i.e. CAMPS contract,
              System Requirements, Acceptance Plan
              and Acceptance Test Procedures very detailed
              defines the CAMPS 240 hours test all
              of which SHAPE have approved.

              CR and SHAPE agreed to the MOU attached
              as Annex A to be the baseline for the
              conduct of the 240 hours test.

              Exempt from CR's agreement is the current
              wording of the following paras of Annex
              A which are 6.2.1 and 6.2.2. CR will
              return with their proposal within one
              week.

              SHAPE stated not to be in the position
              to start the 240 hours test unless a
              complete understanding will be mutually
              agreed.

              In addition SHAPE stated its expectation
              in accordance with the contract that
              CR would reimburse SHAPE additional travel
              costs in case of a unsuccessful end of
              the testing as outlined in para 11 of
              annex A.

              CR stated that they intend to use the
              CAMPS contract as the vehicle for this
              issue.

          2.  U̲p̲d̲a̲t̲e̲s̲ ̲t̲o̲ ̲C̲P̲S̲/̲T̲P̲R̲/̲0̲0̲7̲ ̲-̲ ̲I̲n̲ ̲P̲l̲a̲n̲t̲ ̲T̲e̲s̲t̲
              ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

              a)  Updates to user, supervisor packages
                  and following SHAPE telex no. 1480
                  (same subject) have been reviewed
                  and comments were given by SHAPE
                  to CR.

              b)  CR has presented and explained updates
                  to external channels packages (TRC/PTR,
                  CCIS, and SCARS) - SHAPE will review
                  updates and send comments to CR.

          3.  D̲a̲t̲a̲ ̲B̲a̲s̲e̲ ̲f̲o̲r̲ ̲2̲4̲0̲ ̲H̲o̲u̲r̲s̲ ̲T̲e̲s̲t̲/̲F̲u̲n̲c̲t̲i̲o̲n̲a̲L̲
              ̲a̲n̲d̲ ̲O̲p̲e̲r̲a̲t̲i̲o̲n̲a̲l̲ ̲T̲e̲s̲t̲

              SHAPE telex no. 1473 has been discussed,
              one main problem is still foreseen by
              SHAPE: It was never the intention to
              fix the circuit numbers by circuit type
              as CR did. (e.g. Nics Tare circuit has
              to be number 1) SHAPE will investigate
              if this is acceptable.



          4.  P̲r̲e̲f̲o̲r̲m̲a̲t̲t̲e̲d̲ ̲M̲e̲s̲s̲a̲g̲e̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲t̲i̲o̲n̲

              Six messages are defined by SHAPE for
              implementation CR is currently considering
              the five more simple cases. SHAPE insists
              to see the sixth cast (ORBATSEA) implemented
              also before start of 240 hours test.

              CR estimates that the sixth case (ORBATSEA)
              will extend the schedule with approximately
              one month.

              CR is willing to have this implemented
              prior to completion of the functional
              test SHAPE.

              SHAPE refers to CPS/TPR/007 para 2.1.2.2.1.

          5.  V̲D̲U̲ ̲S̲c̲e̲n̲a̲r̲i̲o̲s̲ ̲f̲o̲r̲ ̲L̲o̲a̲d̲ ̲T̲e̲s̲t̲

              The section of the TPR/007 with load
              test was checked against the SRS section
              3.4.1 concerning performance. SHAPE requested
              CR to demonstrate to SHAPE that the requirements
              are met, especially in the areas of peak
              character input/output rate, cross office
              delay, and terminal transaction and retrieval
              response times.

              CR agreed that TPR007 approved currently
              does not specify detailed procedures
              for verification of specific performance
              requirements. Unless contained in already
              specified test procedures. CR does not
              feel it has any contractual obligation
              in this area.

              SHAPE disagrees with CR feeling CR does
              have a contractual obligation to demonstrate
              performance requirements are met.

              The VDU scenarios for the load test were
              explained. A set of test scripts for
              the VDU simulator of the test drive system
              will be available prior to test start.
              CR will find a means to simulate the
              OCR outgoing message load which is currently
              not produced by the test drive system.

          6.  R̲e̲l̲a̲y̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲

              CR stated that this capability has been
              implemented but that no test cases will
              be added to the CAMPS acceptance tests
              in order to demonstrate this capability.



          7.  C̲o̲m̲p̲l̲e̲t̲i̲o̲n̲ ̲o̲f̲ ̲t̲h̲e̲ ̲S̲y̲s̲t̲e̲m̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲
              ̲a̲n̲d̲ ̲T̲e̲s̲t̲ ̲C̲a̲s̲e̲s̲

              CR agreed that the system integration
              and test cases results cannot be forwarded
              prior to the end of December 1983.

              CR stated that the start of 240 hours
              test has no dependency to this event.

          8.  S̲h̲i̲p̲m̲e̲n̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲0̲6̲ ̲-̲ ̲M̲i̲s̲s̲i̲n̲g̲ ̲S̲p̲a̲r̲e̲ ̲V̲D̲U̲
              ̲a̲n̲d̲ ̲M̲S̲P̲

              The spare VDU and MSP missed to be shipped
              by CR to site 06 will be provided.

          9.  N̲A̲T̲O̲ ̲F̲u̲n̲d̲s̲ ̲f̲o̲r̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲

              See Annex C.

              A copy of letter from the Chairman of
              Budget Committee was forwarded to SHAPE
              and commented by CR to highlight the
              background.

              It was agreed that both parties will
              draft an agenda for a CAMPS familiarization
              seminar to be presented to NATO for approval
              and funding.

          10. C̲o̲s̲t̲ ̲E̲v̲a̲l̲u̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲N̲a̲t̲i̲o̲n̲a̲l̲ ̲S̲e̲c̲u̲r̲i̲t̲y̲
              ̲C̲l̲a̲s̲s̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

              An informal budgettary quotation was
              forwarded.

          11. O̲u̲t̲s̲t̲a̲n̲d̲i̲n̲g̲ ̲P̲a̲y̲m̲e̲n̲t̲

              Due to the investigation CR Provided
              a list of outstanding payments (See annex
              B).

              SHAPE will review this list and send
              comments.

          12. C̲h̲a̲n̲g̲e̲ ̲o̲f̲ ̲L̲o̲w̲ ̲S̲p̲e̲e̲d̲ ̲P̲a̲r̲t̲s̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲

              Deleted from the agenda.

          13. C̲A̲M̲P̲S̲/̲N̲i̲c̲s̲ ̲T̲a̲r̲e̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲ ̲T̲e̲s̲t̲i̲n̲g̲

              See Annex D.

              SHAPE gave test procedures to CR. These
              procedures will be used druing the functional
              test.




          14. T̲e̲s̲t̲ ̲R̲o̲o̲m̲

              The test room will be of a size sufficient
              to accommodate the system under test
              and its peripherals as well as both test
              teams of CR and SHAPE: No other activity
              than 240 hours testing will take place
              in this test room. This excludes even
              a partial use of the room for other purposes
              by means of provisional separation of
              those parts.



                ANNEX A…01…---------


          10. M̲D̲S̲D̲-̲P̲R̲O̲B̲A̲B̲I̲L̲I̲T̲Y̲

              In addition to the initial verification
              of the functional and operational performance
              of the CAMPS system the 240 hours test
              together with the preceding test activity
              during systems integration and test has
              to form the basis for calculations of
              the MDSD probability. Refer CAMPS Acceptance
              Plan CPS/PLN/012, Section 4.6.5, and
              SRS, Section 4.2.2.2 d). At T-2 working
              days CR will present, therefore, the
              reliability prediction obtained from
              the preceding system I & T activity.

              During the 240 h test CR will continue
              to calculate the MDSD probability based
              on a mutually agreed formula.



          11. T̲E̲S̲T̲ ̲T̲E̲R̲M̲I̲N̲A̲T̲I̲O̲N̲

              The test shall end successfully when
              the test clock has reached 240 hours.
              The test shall end unsuccessfully and
              be restarted under the conditions of
              para 2.1 for the following reasons:

              o   System instability resulting in unavailability
                  of the system so that the accumulated
                  test time of 5 days, under the conditions
                  of para 2.2, is not reached within
                  7 working days.

              o   The SHPAE test director states that
                  due to the number and/or kind of
                  SW errors/HW defects exceeding the
                  allowable error rate CR was not sufficiently
                  prepared to start the test.



          12. T̲E̲S̲T̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲

              Within 2 days after the successful end
              of testing Chief, SHNMO will state acceptance
              upon recommendation of the SHAPE test
              director.