top - download
⟦63041e158⟧ Wang Wps File
Length: 9480 (0x2508)
Types: Wang Wps File
Notes: Spelunked
Names: »~ORPHAN44.08«
Derivation
└─⟦f44499b45⟧ Bits:30006204 8" Wang WCS floppy, CR 0303A
└─ ⟦this⟧ »~ORPHAN44.08«
WangText
…0a……00……00……00……00…,…0a……00……00…,…0b…,…0e…,…00…,…05…+…86…1 …02… …02… …02…
3806A/rt…02…CPS/TCN/070
…02…NPP/830610…02……02… #
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02……02…CAMPS
…0f…
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP
CPS/TCN/070
Niels Peder Pedersen
Kurt Nybroe-Nielsen
SHAPE ( ), KNN, KM, BHB, HAU, NPP, KLA,
CLA, SPN, PLN, QA, Config. Mgr., Library (5)
Install. Mgr. 830610
Issue 1
830610
…0e… ConfMgmt. 830610…86…1
…02…
…02… …02…
…0e… 3806A/rt …02…CPS/TCN/070
…02…NPP/830610…02……02…ii
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02……02… CAMPS…0f…
830610 All Issue 1 of Document
3̲8̲0̲6̲A̲…00…CPS/TCN/070
…00…rt …00…NPP
…00…CAMPS MOCK UP …00…1̲0̲…00…0̲6̲…00…8̲3̲…00…1̲1̲…00…0̲9̲…00… ̲ ̲ ̲3̲…00…5̲5̲…00… ̲1̲4̲3̲6̲0̲…00…1̲5̲…00…0̲8̲…00…8̲3̲…00…1̲3̲…00…3̲7̲…00…
̲ ̲ ̲ ̲…00…23…00… ̲ ̲ ̲ ̲89…00…1̲6̲…00…0̲8̲…00…8̲3̲…00…0̲9̲…00…1̲3̲…00…16…00…08…00…83…00…10…00…07…00…0303A…00… 25…00… ̲ ̲ ̲5̲…00…57…00… 248…00…
̲1̲7̲911…00……10……00……01……00……08……80……00……00……00… …10…F'…10……11……01…p*̲J̲…15……05……00……00……00……00……00……00……01…8
X…00……0a……00……00……00……00…,…02……00……00…,
,…06…+…09…+…0e…+…86…1 …02…
…02… …02…
3806A/rt…02…CPS/TCN/070
…02…NPP/830815…02……02… #
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02…Issue 1…02…CAMPS
…0f…
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP
CPS/TCN/070
Niels Peder Pedersen
Kurt Nybroe-Nielsen
SHAPE (5), KNN, KM, BHB, HAU, NPP, KLA,
CLA, SPN, PLN, QA, Config. Mgr., Library (5)
Install. Mgr. 830815
Issue 1.1
830815
…0e… ConfMgmt. 830815…86…1
…02…
…02… …02…
…0f… 3806A/rt …02…CPS/TCN/070
…02…NPP/830815…02……02…ii
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02…Issue 1…02… CAMPS…0e…
1 830610 All Issue 1 of Document
1.1 830815 2, 5, Update according to
7, 11 CAMPS Log No. 1278 and
13 Mock Up Site Survey
MOM
83-07-05.
…86…1
…02… …02…
…02…
3806A/rt …02… CPS/TCN/070
…02… NPP/830610…02……02…iii
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02……02… CAMPS
T̲A̲B̲L̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
1 INTRODUCTION .................................
1
2 GENERAL DESCRIPTION ......................... 1
2.1 CONFIGURATION ............................
1
2.2 SITE PREPARATION AND INSTALLATION PLANNING
4
2.2.1 Installation Schedule ................
4
3 SITE PREPARATION AND INSTALLATION REQUIREMENTS
4
3.1 RESPONSIBILITIS ......................... 4
3.2 EQUIPMENT TO BE INSTALLED ................
5
3.3 FACILITY REQUIREMENTS ....................
6
3.3.1 Access and Dimensions ................
6
3.3.2 Air Cooling .......................... 12
3.3.3 Power ................................ 12
3.3.4 Environmental Specifications ......... 14
APPENDIX A
1̲ ̲ ̲I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
This document contains typical equipment data and requirements
which should support territorial host nations preliminary
site design of the Depot Maintenance quipment and Training
for CAMPS, hereafter called CAMPS MOCK UP System.
…01…2̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲
2.1 C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
The CAMPS MOCK UP System Configuration is shown on
figure 2.1-1.
The CAMPS MOCK UP consists of a 3-bay rack containingboth
the processor and the line termination units. The CAMPS
MOCK UP has a number of work stations connected. Each
work station is dedicated to a specific repair or test
purpose. The system is managed from the maintenance
position.
The 3-bay rackconfiguration is shown on figure 2.1-2.…86…1
…02… …02… …02… …02…
Legend: Notes:
Opto Signal Cables 1 Opto
cables
provided,
installed,
and
terminated
by
CR
Metallic Signal Cables 2 Metallic cables
(Max. length 50 feet) provided, installed,
and terminated by
CR
Flat Cables 3 Metallic cables
(max. length 50 feet) provided, installed,and
terminated by SHAPE/THN
S Equipment by SHAPE/THN 4 Flat Cables provided,
installed, and
CR Equipment by CAMPS Contractor terminated by CR
Figure 2.1-1…01…CAMPS MOCK UP System…01…Configuration…86…1 …02… …02… …02… …02…
FIGURE 2.1-2…01…3-Bay Rack Configuration
2.2 S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲N̲I̲N̲G̲
2.2.1 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲
a) The CAMPS MOCK UP will be installed by CR installation
team. The CAMPS Resident Site technician wll participate
in the installation.
b) CR will submit Site preparation requirements (SPR)
to SHAPE based on the data obtained during a Site
survey and the equipment characteristics contained
in this document. The SPR will contain requirements
to pace, power, access etc.
The Site preparation requirements will be given
to SHAPE as early as possible no later than 5 months
prior to commencement of Site installation. SHAPE
shall issue approval or a list of deficiencies
of the documents withi 15 days after receipt.
c) CR will perform a Site readiness inspection at
the start of the installation.
3̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.1 R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲
The Site Preparation and Installation responsibilities
f CR and SHAPE are described in the contract and are
attached as appendix A for information.
3.2 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲T̲O̲ ̲B̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲E̲D̲
a) At each depot CR will provide and install (see
figure 2.1-1 or 3.1-1):
Pos. 1 One CAMPS MOCK UP Computer contained within
three 19" standard rcks.
Pos.2-3 One maintenance position consisting of
one VDU and one MSP and one table.
Pos.4-9 Five Work Stations for VDU, DISC, MUX,
PTP/R and V28 L/L adaptor test and repair.
Pos 12 One supervisor position consisting of one
VDU.
b) At ach depot SHAPE/THN will provide and install:
Pos.10 One position consisting of one VDU and
one table.
Pos.11 One position consisting of one PTP/R and
one table.
Pos. 12 One table for Supervisor VDU.
Pos.13 One position consisting of on MSP and one
table.
Pos.4-8 Five tables for the Fd, MMD, SMD, MUX and
Crate workstations.
c) The signal cables from CAMPS racks to the maintenance
position and the workstations will be provided,
installed and terminated with connectors as specfied
on figure 2.1-1.
d) Power and Power outlets will be provided by SHAPE/THN
as specified in appendix A.
3.3 F̲A̲C̲I̲L̲I̲T̲Y̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.3.1 A̲c̲c̲e̲s̲s̲ ̲a̲n̲d̲ ̲D̲i̲m̲e̲n̲s̲i̲o̲n̲s̲
a) The typical equipment layout (fig. 3.1-1) reflects
the floor spare required by cabinets and operator
positions. The acess dimensions for racks and terminal
equipment are shown on figure 3.3.1-1 and 3.3.1-2.
The racks are positioned such that sufficient clearance
is maintained for access to the front and rear
of the equipment. Otherwise, only few constraints
as to he placement of the equipment exist. The
final layouts will take into account human factors,
segregation of functional activities, access for
maintenance and other considerations or preferences
of the operative personnel.…86…1 …02… …02… …02… …02…
Figure 3.1-1…01…TYPICAL EQUIPMENT LAYOUT - CAMPS MOCK UP…86…1 …02… …02… …02… …02…
FIGURE 3.3.1-1…01…PHYSICAL DIMENSIONS OF RACKS…86…1 …02… …02… …02… …02… …02…
FIGURE 3.3.1-2…01…USER TERMINALS…01…TYPICAL LAYOUT AND ACCESS REQUIREMENTS…86…1 …02… …02… …02… …02…
One of the tasks to be performed at the Site Survey
is to work out the optimal layout in conjunction
with SHAPE/THN.
b) The floor load of the Computer equipment rack is
well wihin the Standard floor load limit of 1000
kg/m…0e…2…0f… for Computer floors as can be seen from the
following calculation:
Floor Load of heaviest rack:
̲ ̲W̲E̲I̲G̲H̲T̲ ̲ ̲ ̲ ̲