DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦632842b9b⟧ Wang Wps File

    Length: 4245 (0x1095)
    Types: Wang Wps File
    Notes: PC/PLN/001                
    Names: »6313A «

Derivation

└─⟦1ebdd46fc⟧ Bits:30006237 8" Wang WCS floppy, CR 0625A
    └─ ⟦this⟧ »6313A « 

WangText




…02…PC/PLN/001

…02…851210…02……02…#
CCIS MACHINE ACCESS PLAN
CONTRACT SHNMO 85-9532/INF, LINE ITEM 1B…02……02…   PC












                    T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲







     1  GENERAL .....................................  
     1 

       1.1 PURPOSE ..................................  
           1 
       1.2 APPLICABLE DOCUMENTS .....................  
           1 

     2  TIME TABLE ..................................  
     2 

       2.1 TIME TABLE DATES .........................  
           2 
       2.2 DURATION OF TEST PERIODS .................  
           3 
       2.3 TIME OF TEST PERIODS .....................  
           3 
       2.4 END-SYSTEM STATE .........................  
           3 

     3  ASSUMPTIONS .................................  
     4 


                        1̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲



         This CCIS Machine Access Plan describes the duration
         of the various test periods needed to perform the validation
         activities for the CCIS-PC Interface Link as stated
         in PC/TPR/007.



1.1      P̲U̲R̲P̲O̲S̲E̲

         The purpose of the document is:

         a.  To define dates for the various test periods.

         b.  To define the state of the end-systems in each
             test period.

         c.  To define the configuration of the CAMPS end-system
             in the test periods.



1.2      A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲

         1.  PC INTERFACE STUDY,
             Contract SHNMO 85-9532/Inf.

         2.  PC VALIDATION PROCEDURE
             PC/TPR/007, preliminary issue



                      2̲ ̲ ̲T̲I̲M̲E̲ ̲T̲A̲B̲L̲E̲



         CR84 will suggest the following time table as shown
         below:



2.1      T̲I̲M̲E̲ ̲T̲A̲B̲L̲E̲ ̲D̲A̲T̲E̲S̲

         Time Table for CCIS-PC Interface Validation Activities:

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲1̲:

             Monday, 27 January, 86 - Friday 31 January, 86

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲2̲:

             Saturday 1 February, 86 - Sunday 2 February, 86

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲3̲:

             Monday 3 February, 86 - Friday 7 February, 86

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲4̲:

             Saturday 8 February, 86 - Sunday 9 February, 86

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲5̲:

             Monday 3 March, 86 - Friday 7 March, 86

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲ ̲6̲:

             Saturday 8 March, 86 - Sunday 10 March, 86



2.2      D̲U̲R̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲E̲S̲T̲ ̲P̲E̲R̲I̲O̲D̲S̲

         The duration of access to the CCIS Machine per day
         in each test period.

         Test period 1               1x3 hours/day
         Test period 2               2x3 hours/day
         Test period 3               1x3 hours/day
         Test period 4               2x3 hours/day
         Test period 5               1x3 hours/day
         Test period 6               2x3 hours/day



2.3      T̲I̲M̲E̲ ̲O̲F̲ ̲T̲E̲S̲T̲ ̲P̲E̲R̲I̲O̲D̲S̲

         The time suggested for the tests is placed outside
         normal working hours. CR84 defines normal working hours
         as 8.00 a.m. until 5.00 p.m.

         CR84 suggests the following timetable 

         T̲e̲s̲t̲ ̲P̲e̲r̲i̲o̲d̲                 T̲i̲m̲e̲ ̲o̲f̲ ̲D̲a̲y̲

         Test period 1:              6.00 p.m. until 9.00 p.m.

         Test period 2:              9.00 a.m. until 12.00 noon
                                     & 3.00 p.m. until 6.00
                                     p.m

         Test period 3:              6.00 p.m. until 9.00 p.m.

         Test period 4:              9.00 a.m. until 12.00 noon
                                     & 3.00 p.m. until 6.00
                                     p.m

         Test period 5:              6.00 p.m. until 9.00 p.m.

         Test period 6:              9.00 a.m. until 12.00 noon
                                     & 3.00 p.m. until 6.00
                                     p.m



2.4      E̲N̲D̲-̲S̲Y̲S̲T̲E̲M̲ ̲S̲T̲A̲T̲E̲

                                     Configuration
                                     CCIS      CAMPS

         Test period 1:              test      operational
         Test period 2:              test      operational
         Test period 3:              test      operational
         Test period 4:              test      test
         Test period 5:              test      operational
         Test period 6:              test      test


                      3̲ ̲ ̲A̲S̲S̲U̲M̲P̲T̲I̲O̲N̲S̲



         CR84 makes the following assumptions to the time table:

         a.  CR84 may change the dates for the test periods.

         b.  CR84 may define new test periods.

         c.  CR84 may delete unnecessary test periods.

         d.  The CAMPS System shall be available for CR84 engineers
             in the whole test period for reconfiguration etc.

         e.  The CAMPS System shall be under configuration control
             during the test periods. It will be SHAPE's responsibility
             to maintain the configuration control.

         f.  The CCIS Machine Room where the PC Test Computer
             will be placed and shall be accessable for the
             engineers from CR84 during normal working hours.

         g.  SHAPE shall supply an office for CR84's disposal
             during the test periods.


         h.  CR84 engineers shall be able to work from 8.00
             a.m. until 5.00 p.m. or the weekends, if necessary.