⟦67b1fcb56⟧ Wang Wps File

    Length: 17150 (0x42fe)
    Types: Wang Wps File
    Notes: UKAIR CCIS, TECHNICAL     
    Names: »4781A «

Derivation

└─⟦a4aed27c0⟧ Bits:30006016 8" Wang WCS floppy, CR 0463A
    └─ ⟦this⟧ »4781A « 

WangText







UKAIR CCIS ADPE - PART
 II                  SYS/84-04-15

TECHNICAL PROPOSAL      
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        
                        Page
                        
                        
                        





                     6̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



6.1      G̲E̲N̲E̲R̲A̲L̲

         The following is a brief description of how CR intends
         to manage the installation and transportation of the
         UKAIR CCIS equipment, and a description of what is
         included in the price proposal.



6.2      P̲L̲A̲N̲N̲I̲N̲G̲ ̲A̲N̲D̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲

         CR will prepare an installation plan which outlines
         the various tasks to be accomplished regarding site
         preparation and installation. Furthermore the plan
         will specify the responsibilities of CR and customer.

         CR will prepare a transportation plan which describes
         in details the tasks to be performed concerning transportation
         of the equipment, such as notification procedures,
         customs procedures, packaging, packing and marking
         etc.

         At each of the three sites involved in this proposal,
         CR will carry out a site survey to determine equipment
         room layout, power distribution, ducting, signal cabling
         and other details concerning the installation of the
         CR equipment.

         The result of the site survey will be documented in
         a site survey report.

         30 days prior to start of installation, CR will carry
         out a site verification at each of the three sites,
         to ensure that the site has been prepared in accordance
         with the customer approved "Site Preparation Requirements".
         The result of the Site verification will be documented
         in a Site Verification Report for each site.





6.3      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲

         Based on the site survey report and the equipment characteristics,
         CR will prepare a "Site Preparation Requirements (SPR)"
         document, which will specify the preparations that
         customer must undertake in order to prepare the individual
         sites for installation of the proposed equipment. This
         proposal is based on that customer provides standard
         computer rooms with raised floors, airconditioning,
         power and ground according to the specifications outlined
         in section D of the RFP, and distribute power and ground
         to CR equipment, provide and install ducts for power
         as well as signal cabling. The SPR will contain equipment
         room layout drawings, physical and electrical characteristies
         of the equipment and other requirements to above mentioned
         facilities. The SPR will be delivered to customer for
         approval 4 months prior to start of installation.

         Upon customer approval of the SPR, CR will prepare
         an "Equipment Installation Drawings" (EID) document
         for each site, and deliver it to customer for approval
         2 months prior to start of installation. The EID will
         contain the electrical layout of the equipment and
         other information necessarry for installation of the
         CR provided equipment, including a power up and checkout
         procedure. During the installation, the drawings will
         be updated, if necessary, to reflect the "as installed"
         situation.

         After complete installation of a site, CR will produce
         an "Installation Manual". This manual will contain
         the updated installation drawings, layout drawings
         and an installation procedure. The Installation Manual
         will be submitted to customer not later than 3 months
         after completion of installation at each of the two
         operational sites.





6.4      S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲(̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲S̲i̲t̲e̲)̲

         At the development site, the following installations
         are quoted:

         -   Development system.
         -   PSWHQ basic configuration.
         -   AWHQ equipment.

         The installation charges comprises the following:

         *   Reciept and unpacking of equipment at site.

         *   Physical and electrical installation of the proposed
             equipment incl. connection to customer provided
             power outlets.

         *   Provision and installation of signal cables interconnecting
             the proposed CR equipment.

         *   Power up and test of the equipment.

         The proposal is based on the following assumptions:

         *   Tempest installation (i.e. metalducts for power
             and signal cables) is not required at the development
             site.

         *   Customer will provide the power installations,
             including outlets at the CR EQUIPMENT; as specified
             in the "Site Preparation Requirements".

         *   The room(s) is a standard computer room with raised
             floor, aircondition etc. The enviromental conditions
             shall be at least as specified for the HQ's in
             the RFP.

         P̲S̲W̲H̲Q̲ ̲a̲n̲d̲ ̲A̲W̲H̲Q̲ ̲s̲i̲t̲e̲s̲

         At the two HQ sites the following installations are
         quoted:

         P̲S̲W̲H̲Q̲

         -   Local area network.
         -   Basic PSWHQ configuration.

         A̲W̲H̲Q̲

         -   AWHQ equipment



         The installation charges comprises the following:

         *   Provision and installation of 6400m opto cable
             for the local area network in customer provided
             ducts.

         *   Provision and installation of the optoconnectors
             for the local area network.

         *   Dismounting and packing of the equipment at the
             development site, prior to shipment to final site.

         *   Reciept and unpacking of equipment at final sites.

         *   Physical and electrical installation of the proposed
             equipment at the two HQ-sites including fittings
             and tubes for connection to customer provided metal
             ducts.

         *   Connection to customer provided power installations.

         *   Provision and installation of all signal cables
             required for the proposed equipment i.e. signal
             cables interconnecting CR provided equipment and
             trunk cables, connecting the CR provided equipment
             to the required number of external comm. lines.

         *   TEMPEST installation as required in the RFP.

         *   Power up and test of the CR equipment.

         The proposal is based on the following assumptions:

         *   Customer will provide and run cable ducts, and
             make wall and floor penetrations as necessary,
             for the local area network.

         *   Custome will prepare the site in accordance with
             the "Site Preparation Requirements" i.e. provide
             power and ground cabling and distribution, provide
             and install power and signal cable ducts.

         *   External signal connections can be established
             within the computer room.

         *   The room is a standard computer room with raised
             floor, aircondition etc.





6.5      T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲C̲H̲A̲R̲G̲E̲S̲

         The transportations have been quoted as follows:

         The deliveries from CR Ballerup will be delivered CIF
         site, based on the assumption that the sites are located
         within a radius of 200 km from London. The CIF deliveries
         comprises the following: 

         -   packaging and packing labour 
         -   shipping  
         -   transportation by air or/and truck 
         -   insurance.

         The packing of equipment at the development site prior
         to shipment to final site, is incorporated in the installation
         price.

         The transportation from the development site to the
         final sites have not been quoted by CR, and is not
         included in the price. However, these transportations
         and the coordination of same, can be incorporated when
         the exact site locations are known to CR.





                7̲ ̲ ̲M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲S̲P̲A̲R̲E̲S̲



7.1      M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲

         The UKAIR CCIS systems can be maintained in two different
         ways, either by direct on site support within normal
         working hours through a maintenance engineer placed
         within the CSC organisation, or by an call service,
         where field engineers will be awailable from CHRISTIAN
         ROVSING A/S. Both options are priced in the Commercial
         proposal.



7.2      S̲P̲A̲R̲E̲S̲

         Recommended spare parts lists calculated in accordance
         with chapter 7.2.1 are shown in Figure 7.2-1 and Figure
         7.2-2.



7.2.1    O̲p̲t̲i̲m̲u̲m̲ ̲S̲p̲a̲r̲e̲s̲ ̲S̲u̲p̲p̲o̲r̲t̲ ̲S̲t̲r̲a̲t̲e̲g̲y̲

         The calculation of numbers of spare parts will be done
         by use of Poissons distribution probability.

         In order to determine the number of spare modules it
         is assumed that the failure rate of each module (circuit
         board) ha an exponential distribution. This approximation
         holds true for electronic equipment throughout its
         useful life, i.e. wear-out phenomena can be ignored.

         It can be shown that the probability of observing exactly
         i failures over a period of t operating hours is given
         by the Poisson distribution:

                       (t/MTBF)…0e…i…0f… x exp (-t/MTBF)
            p (i) =     ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                  i!

         The Period t corresponds to the accumulated operating
         period for the involved modules.
























































                       Figure 7.2-1

                      RSPL for PSWHQ




















































                       Figure 7.2-2

                      RSPL for AWHQ



7.2.2    N̲a̲t̲o̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲



7.2.2.1  S̲u̲p̲p̲l̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲N̲C̲B̲

         Christian Rovsing A/S will supply data on items to
         be codified consistent with the "Reference Method"
         which is the method of identification used by the Danish
         NCB. As part of the basic contract Christian Rovsing
         A/S will codify a maximum of 200 items.



7.2.2.2  A̲d̲d̲i̲t̲i̲o̲n̲a̲l̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         Christian Rovsing A/S will codify items in excess of
         the 200 on terms to be stipulated in the contract.



7.2.2.3  S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲D̲e̲s̲i̲g̲n̲ ̲C̲h̲a̲n̲g̲e̲ ̲N̲o̲t̲i̲c̲e̲s̲ ̲(̲S̲P̲D̲C̲N̲)̲

         Christian Rovsing A/S will supply SPDCN's during the
         equipment warranty period free of charge. Subsequent
         to expiration of warranty SPCDN's will be supplied
         at terms specified by contract.


7.3      T̲O̲O̲L̲S̲ ̲A̲N̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         This section contains a list of tools and test equipment
         necessary for the maintenance.

         S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲O̲O̲L̲S̲

         Table 7.3.1-2 lists one set of standard multipurpose
         tools with suitcase.



                      S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲O̲O̲L̲S̲

 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Nomenclature                    Manufacturer  Type
                                                   No.
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Screwdriver, Plainhead          Weralit       435-0,4-50
     Screwdriver, Plainhead          Weralit       435-0,5-80
     Screwdriver, Plainhead          Weralit       435-0,6-120
     Screwdriver, Plainhead          Weralit       435-0,8-200
     Screwdriver, Plainhead          Weralit       434-1,0-125
     Screwdriver, Plainhead          Weralit       434-1,0-250
     Screwdriver, Plainhead          Weralit       434-1,2-175
     Screwdriver, Plainhead          Weralit       434-1,6-200
     Screwdriver, Stubby             Xcelite       S 141
     Screwdriver, Watchmaker-set     Erem          TS-6N
     Screwdriver, Philips            Weralit       350PR-0-60
     Screwdriver, Philips            Weralit       1-80
     Screwdriver, Philips            Weralit       2-100
     Screwdriver, Philips            Weralit       2-300
     Screwdriver, Philips            Weralit       2-150
     Screwdriver, Philips            Weralit       4-200
     Screwdriver, Stubby             Xcelite       SX 102
     Screwdriver, Voltage Tester     Weralit       2253-3-40
     Wrench, Metric                  Belzer        1953
                                                   M-5x10
     Wrench, Metric                  Belzer        1953
                                                   M-6x7



 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Nomenclature                  Manufacturer  Type No.
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Wrench, Metric                Belzer        1953M-8x9
     Wrench, Metric                Belzer        1953M-10x11
     Wrench, Metric                Belzer        1953M-12x13
     Wrench, Metric                Belzer        1953M-14x15
     Wrench, Metric                Belzer        1931N-M-4,5x5,5
     Wrench, Inches                Belzer        1953Z-1/4x5/16"
     Wrench, Inches                Belzer        1953Z-3/8x7/16"
     Wrench, Inches                Belzer        1/2 x 9/16"
     Wrench, Adjustable            Bacho         4"
     Wrench, Adjustable            Bacho         6"
     Wrench, Adjustable            Bacho         8"
     Wrench, Adjustable            Bacho         10"
     Socket Wrench Set 4-14        Tecos         
     Socket Wrench Set 3/16-9/16"  Tecos         
     Side Cutter                   Erem          84E
     Side Cutter                   Erem          196-6"
     Side Cutter                   Belzer        2678
     Pair of Pliers, Flat Nose     Erem          124
     Pair of Pliers, Point Nose    Erem          41
     Pair of Pliers, Bent Nose     Belzer        2477G
     Pair of Pliers, "Polygrip"    Belzer        2615M
     Pair of Pliers, "Polygrip"    Belzer        2624B
     Pipe Wrench, 3", 45…0e…o…0f… Nose     Dowidat       176
     Wire Stripper                 Belzer        3418B
     Pair of Tweezers              Erop          24
     Pair of Tweezers              Erop          21S/200
     Steel Scissors                Erop          24
     Unbraco Keys, Set 2-8 mm      Weralit       950/7-SM
     Unbraco Keys, Set 2/64-1/4"   Weralit       950/7-SZ
     Hammer, SUPERFLEX Head        Belzer        3625-27
     Solderiron  with transformer  Weller        TCP-24V,7
     Solderpoint                   Weller        PT-6
     Solder                        Weller        60-40
     Desoldering pump              Erem          PS 200
                                                 A
     Electric Torch (Flashlight)                 Pencil
     Wrapwire                      Metric        10-51
     Suitcase f/hand tools         TC            TC100 MT
     Double lid f/suitcase         TC            A 5-12
                                                 room
     Double lid f/suitcase         TC            A - 18
                                                 room
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


     One vacuumcleaner with a soft rubber mouthpiece is
     required at each main site for preventive maintenance.

                     Table 7.3-1
                    Standard Tools





         S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         Table 7.3-2 lists the standard test equipment required
         during performing maintenance at a site.

         All measure and monitoring devices comply with the
         stability and accuracy demanded throughout the system.



 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Nomenclature               Manufacturer   Type No.      QTY
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                                                             
                                                             
     Data Communications Tester Tektronix      834           1
     Multimeter                 Fluke          8020 A        2
     Oscilloscope               Tektronix      465 B         1
     Test Set 921-T             NU DATA        921-T         1
     Optical Multimeter         PHONODYNE      Model 11
                                               XE            1
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲























                     Table 7.3-2
               Standard Test Equipment




…02…S̲P̲E̲C̲I̲A̲L̲ ̲T̲O̲O̲L̲S̲ ̲A̲N̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         Table 4-1 lists special tools and test equipment required
         during performing maintenance at a site.



 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Nomenclature             Manufacturer        QTY
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

     Extender Board           CR                   1
     Extender Board           CR                   1
     Extender Board           CR                   1
     V24 Loopback Adaptor     CR                   1
     LTU Loopback Adaptor     CR                  
     Tool Scale Spring        CDC                  1
     SCR-DR TOPRQUE 2/35"     CDC                  1
     Extender Card            CDC                  1
     Alignm.Carr.Spindle      CDC                  1
     Head Adjustment          CDC                  1
     SCR-DR TRQ Hex Bit       CDC                  1
     Adp. Speed Sensor        CDC                  1
     Extractor Module         CDC                  1
     Disk Pack, AL-DISK       CDC                  1
     Disk Pack, Data          CDC                  1
     Dust Remover, Spray      CDC                  1
     Field Test Unit          CDC                  1
     OPTO Termination Kit     Versitron            1
     OPTO Loopback Cable      CR                   1













                     Table 7.3-3
           Special Tools and Test Equipment




                     8̲ ̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲


8.1  T̲R̲A̲I̲N̲I̲N̲G̲



8.1.1                         C̲o̲u̲r̲s̲e̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲

     The students shall be skilled technicians who have
     received basic training in ADP Equipment operation
     and maintenance.



8.1.2                         I̲n̲i̲t̲i̲a̲l̲ ̲T̲e̲s̲t̲ ̲a̲n̲d̲ ̲C̲o̲u̲r̲s̲e̲ ̲E̲x̲a̲m̲i̲n̲a̲t̲i̲o̲n̲

     The students shall receive an initial test before the
     start of the courses. Examination of the students will
     be held during the training courses.



8.1.3                         L̲a̲n̲g̲u̲a̲g̲e̲

     The courses will be conducted in English and the documentation
     will be in English.



8.1.4                         L̲e̲s̲s̲o̲n̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲

     One course-week consists of 30 lessons of 45 minutes.



8.1.5                         F̲i̲n̲a̲l̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲

     The proposed training will be finalized upon agreement
     between CR and CSC.



8.1.6                         N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲

     Up to 6 per class.





8.1.7    C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲



8.1.7.1  S̲i̲t̲e̲ ̲L̲e̲v̲e̲l̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲

         6 weeks.



8.1.7.2  D̲e̲p̲o̲t̲ ̲L̲e̲v̲e̲l̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲

         6 weeks.



8.1.7.3  S̲y̲s̲t̲e̲m̲ ̲O̲p̲e̲r̲a̲t̲i̲o̲n̲ ̲C̲o̲u̲r̲s̲e̲

         2.5 weeks is recommended instead of 6 weeks as required
         in the RFP.



8.1.8    C̲o̲u̲r̲s̲e̲ ̲P̲r̲o̲f̲i̲l̲e̲

         Practical and theoretical training, ratio 1 to 1.



8.1.9    L̲o̲c̲a̲t̲i̲o̲n̲

         The courses will be conducted in UK.



8.1.10   C̲o̲u̲r̲s̲e̲ ̲S̲t̲a̲r̲t̲

         The courses will start after installation at the Development
         Sites.





8.2      D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲



8.2.1    L̲a̲n̲g̲u̲a̲g̲e̲

         The manuals and handbooks for maintenance and operation
         will be in English.



8.2.2    R̲e̲p̲r̲o̲d̲u̲c̲i̲b̲l̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲

         All documents will be easily reproducible.



8.2.3    D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲S̲t̲a̲n̲d̲a̲r̲d̲

         The delivered documentation will be of good commercial
         standard. Previously delivered NATO documents will
         be available and accepted by CSC.

         All delivered documentation will describe the actual
         equipment specified under this proposal. Modifications
         will be made to hardware and software.

         The documentation will be sufficient to perform operation
         and maintenance of the equipment proposed.



8.2.4    R̲e̲v̲i̲e̲w̲

         The documentation will be subject to Design Review,
         Configuration Control and Acceptance Procedures.



8.2.5    D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲C̲h̲a̲n̲g̲e̲s̲

         Documentation Change Notices of all product changes
         will be delivered for a 15 year period after final
         acceptance at PSWHQ, development site, PSWHQ upgrade
         and AWHQ site.


8.2.6    F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲

         The proposed documentation will be finalized upon agreement
         between Christian Rovsing A/S and CSC.