UKAIR CCIS ADPE - PART
II SYS/84-04-15
TECHNICAL PROPOSAL
Page
6̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
6.1 G̲E̲N̲E̲R̲A̲L̲
The following is a brief description of how CR intends
to manage the installation and transportation of the
UKAIR CCIS equipment, and a description of what is
included in the price proposal.
6.2 P̲L̲A̲N̲N̲I̲N̲G̲ ̲A̲N̲D̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲
CR will prepare an installation plan which outlines
the various tasks to be accomplished regarding site
preparation and installation. Furthermore the plan
will specify the responsibilities of CR and customer.
CR will prepare a transportation plan which describes
in details the tasks to be performed concerning transportation
of the equipment, such as notification procedures,
customs procedures, packaging, packing and marking
etc.
At each of the three sites involved in this proposal,
CR will carry out a site survey to determine equipment
room layout, power distribution, ducting, signal cabling
and other details concerning the installation of the
CR equipment.
The result of the site survey will be documented in
a site survey report.
30 days prior to start of installation, CR will carry
out a site verification at each of the three sites,
to ensure that the site has been prepared in accordance
with the customer approved "Site Preparation Requirements".
The result of the Site verification will be documented
in a Site Verification Report for each site.
6.3 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
Based on the site survey report and the equipment characteristics,
CR will prepare a "Site Preparation Requirements (SPR)"
document, which will specify the preparations that
customer must undertake in order to prepare the individual
sites for installation of the proposed equipment. This
proposal is based on that customer provides standard
computer rooms with raised floors, airconditioning,
power and ground according to the specifications outlined
in section D of the RFP, and distribute power and ground
to CR equipment, provide and install ducts for power
as well as signal cabling. The SPR will contain equipment
room layout drawings, physical and electrical characteristies
of the equipment and other requirements to above mentioned
facilities. The SPR will be delivered to customer for
approval 4 months prior to start of installation.
Upon customer approval of the SPR, CR will prepare
an "Equipment Installation Drawings" (EID) document
for each site, and deliver it to customer for approval
2 months prior to start of installation. The EID will
contain the electrical layout of the equipment and
other information necessarry for installation of the
CR provided equipment, including a power up and checkout
procedure. During the installation, the drawings will
be updated, if necessary, to reflect the "as installed"
situation.
After complete installation of a site, CR will produce
an "Installation Manual". This manual will contain
the updated installation drawings, layout drawings
and an installation procedure. The Installation Manual
will be submitted to customer not later than 3 months
after completion of installation at each of the two
operational sites.
6.4 S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲(̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲S̲i̲t̲e̲)̲
At the development site, the following installations
are quoted:
- Development system.
- PSWHQ basic configuration.
- AWHQ equipment.
The installation charges comprises the following:
* Reciept and unpacking of equipment at site.
* Physical and electrical installation of the proposed
equipment incl. connection to customer provided
power outlets.
* Provision and installation of signal cables interconnecting
the proposed CR equipment.
* Power up and test of the equipment.
The proposal is based on the following assumptions:
* Tempest installation (i.e. metalducts for power
and signal cables) is not required at the development
site.
* Customer will provide the power installations,
including outlets at the CR EQUIPMENT; as specified
in the "Site Preparation Requirements".
* The room(s) is a standard computer room with raised
floor, aircondition etc. The enviromental conditions
shall be at least as specified for the HQ's in
the RFP.
P̲S̲W̲H̲Q̲ ̲a̲n̲d̲ ̲A̲W̲H̲Q̲ ̲s̲i̲t̲e̲s̲
At the two HQ sites the following installations are
quoted:
P̲S̲W̲H̲Q̲
- Local area network.
- Basic PSWHQ configuration.
A̲W̲H̲Q̲
- AWHQ equipment
The installation charges comprises the following:
* Provision and installation of 6400m opto cable
for the local area network in customer provided
ducts.
* Provision and installation of the optoconnectors
for the local area network.
* Dismounting and packing of the equipment at the
development site, prior to shipment to final site.
* Reciept and unpacking of equipment at final sites.
* Physical and electrical installation of the proposed
equipment at the two HQ-sites including fittings
and tubes for connection to customer provided metal
ducts.
* Connection to customer provided power installations.
* Provision and installation of all signal cables
required for the proposed equipment i.e. signal
cables interconnecting CR provided equipment and
trunk cables, connecting the CR provided equipment
to the required number of external comm. lines.
* TEMPEST installation as required in the RFP.
* Power up and test of the CR equipment.
The proposal is based on the following assumptions:
* Customer will provide and run cable ducts, and
make wall and floor penetrations as necessary,
for the local area network.
* Custome will prepare the site in accordance with
the "Site Preparation Requirements" i.e. provide
power and ground cabling and distribution, provide
and install power and signal cable ducts.
* External signal connections can be established
within the computer room.
* The room is a standard computer room with raised
floor, aircondition etc.
6.5 T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲C̲H̲A̲R̲G̲E̲S̲
The transportations have been quoted as follows:
The deliveries from CR Ballerup will be delivered CIF
site, based on the assumption that the sites are located
within a radius of 200 km from London. The CIF deliveries
comprises the following:
- packaging and packing labour
- shipping
- transportation by air or/and truck
- insurance.
The packing of equipment at the development site prior
to shipment to final site, is incorporated in the installation
price.
The transportation from the development site to the
final sites have not been quoted by CR, and is not
included in the price. However, these transportations
and the coordination of same, can be incorporated when
the exact site locations are known to CR.
7̲ ̲ ̲M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲S̲P̲A̲R̲E̲S̲
7.1 M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲
The UKAIR CCIS systems can be maintained in two different
ways, either by direct on site support within normal
working hours through a maintenance engineer placed
within the CSC organisation, or by an call service,
where field engineers will be awailable from CHRISTIAN
ROVSING A/S. Both options are priced in the Commercial
proposal.
7.2 S̲P̲A̲R̲E̲S̲
Recommended spare parts lists calculated in accordance
with chapter 7.2.1 are shown in Figure 7.2-1 and Figure
7.2-2.
7.2.1 O̲p̲t̲i̲m̲u̲m̲ ̲S̲p̲a̲r̲e̲s̲ ̲S̲u̲p̲p̲o̲r̲t̲ ̲S̲t̲r̲a̲t̲e̲g̲y̲
The calculation of numbers of spare parts will be done
by use of Poissons distribution probability.
In order to determine the number of spare modules it
is assumed that the failure rate of each module (circuit
board) ha an exponential distribution. This approximation
holds true for electronic equipment throughout its
useful life, i.e. wear-out phenomena can be ignored.
It can be shown that the probability of observing exactly
i failures over a period of t operating hours is given
by the Poisson distribution:
(t/MTBF)…0e…i…0f… x exp (-t/MTBF)
p (i) = ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
i!
The Period t corresponds to the accumulated operating
period for the involved modules.
Figure 7.2-1
RSPL for PSWHQ
Figure 7.2-2
RSPL for AWHQ
7.2.2 N̲a̲t̲o̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
7.2.2.1 S̲u̲p̲p̲l̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲N̲C̲B̲
Christian Rovsing A/S will supply data on items to
be codified consistent with the "Reference Method"
which is the method of identification used by the Danish
NCB. As part of the basic contract Christian Rovsing
A/S will codify a maximum of 200 items.
7.2.2.2 A̲d̲d̲i̲t̲i̲o̲n̲a̲l̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
Christian Rovsing A/S will codify items in excess of
the 200 on terms to be stipulated in the contract.
7.2.2.3 S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲D̲e̲s̲i̲g̲n̲ ̲C̲h̲a̲n̲g̲e̲ ̲N̲o̲t̲i̲c̲e̲s̲ ̲(̲S̲P̲D̲C̲N̲)̲
Christian Rovsing A/S will supply SPDCN's during the
equipment warranty period free of charge. Subsequent
to expiration of warranty SPCDN's will be supplied
at terms specified by contract.
7.3 T̲O̲O̲L̲S̲ ̲A̲N̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
This section contains a list of tools and test equipment
necessary for the maintenance.
S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲O̲O̲L̲S̲
Table 7.3.1-2 lists one set of standard multipurpose
tools with suitcase.
S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲O̲O̲L̲S̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Nomenclature Manufacturer Type
No.
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Screwdriver, Plainhead Weralit 435-0,4-50
Screwdriver, Plainhead Weralit 435-0,5-80
Screwdriver, Plainhead Weralit 435-0,6-120
Screwdriver, Plainhead Weralit 435-0,8-200
Screwdriver, Plainhead Weralit 434-1,0-125
Screwdriver, Plainhead Weralit 434-1,0-250
Screwdriver, Plainhead Weralit 434-1,2-175
Screwdriver, Plainhead Weralit 434-1,6-200
Screwdriver, Stubby Xcelite S 141
Screwdriver, Watchmaker-set Erem TS-6N
Screwdriver, Philips Weralit 350PR-0-60
Screwdriver, Philips Weralit 1-80
Screwdriver, Philips Weralit 2-100
Screwdriver, Philips Weralit 2-300
Screwdriver, Philips Weralit 2-150
Screwdriver, Philips Weralit 4-200
Screwdriver, Stubby Xcelite SX 102
Screwdriver, Voltage Tester Weralit 2253-3-40
Wrench, Metric Belzer 1953
M-5x10
Wrench, Metric Belzer 1953
M-6x7
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Nomenclature Manufacturer Type No.
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Wrench, Metric Belzer 1953M-8x9
Wrench, Metric Belzer 1953M-10x11
Wrench, Metric Belzer 1953M-12x13
Wrench, Metric Belzer 1953M-14x15
Wrench, Metric Belzer 1931N-M-4,5x5,5
Wrench, Inches Belzer 1953Z-1/4x5/16"
Wrench, Inches Belzer 1953Z-3/8x7/16"
Wrench, Inches Belzer 1/2 x 9/16"
Wrench, Adjustable Bacho 4"
Wrench, Adjustable Bacho 6"
Wrench, Adjustable Bacho 8"
Wrench, Adjustable Bacho 10"
Socket Wrench Set 4-14 Tecos
Socket Wrench Set 3/16-9/16" Tecos
Side Cutter Erem 84E
Side Cutter Erem 196-6"
Side Cutter Belzer 2678
Pair of Pliers, Flat Nose Erem 124
Pair of Pliers, Point Nose Erem 41
Pair of Pliers, Bent Nose Belzer 2477G
Pair of Pliers, "Polygrip" Belzer 2615M
Pair of Pliers, "Polygrip" Belzer 2624B
Pipe Wrench, 3", 45…0e…o…0f… Nose Dowidat 176
Wire Stripper Belzer 3418B
Pair of Tweezers Erop 24
Pair of Tweezers Erop 21S/200
Steel Scissors Erop 24
Unbraco Keys, Set 2-8 mm Weralit 950/7-SM
Unbraco Keys, Set 2/64-1/4" Weralit 950/7-SZ
Hammer, SUPERFLEX Head Belzer 3625-27
Solderiron with transformer Weller TCP-24V,7
Solderpoint Weller PT-6
Solder Weller 60-40
Desoldering pump Erem PS 200
A
Electric Torch (Flashlight) Pencil
Wrapwire Metric 10-51
Suitcase f/hand tools TC TC100 MT
Double lid f/suitcase TC A 5-12
room
Double lid f/suitcase TC A - 18
room
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
One vacuumcleaner with a soft rubber mouthpiece is
required at each main site for preventive maintenance.
Table 7.3-1
Standard Tools
S̲T̲A̲N̲D̲A̲R̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
Table 7.3-2 lists the standard test equipment required
during performing maintenance at a site.
All measure and monitoring devices comply with the
stability and accuracy demanded throughout the system.
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Nomenclature Manufacturer Type No. QTY
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Data Communications Tester Tektronix 834 1
Multimeter Fluke 8020 A 2
Oscilloscope Tektronix 465 B 1
Test Set 921-T NU DATA 921-T 1
Optical Multimeter PHONODYNE Model 11
XE 1
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Table 7.3-2
Standard Test Equipment
…02…S̲P̲E̲C̲I̲A̲L̲ ̲T̲O̲O̲L̲S̲ ̲A̲N̲D̲ ̲T̲E̲S̲T̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
Table 4-1 lists special tools and test equipment required
during performing maintenance at a site.
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Nomenclature Manufacturer QTY
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Extender Board CR 1
Extender Board CR 1
Extender Board CR 1
V24 Loopback Adaptor CR 1
LTU Loopback Adaptor CR
Tool Scale Spring CDC 1
SCR-DR TOPRQUE 2/35" CDC 1
Extender Card CDC 1
Alignm.Carr.Spindle CDC 1
Head Adjustment CDC 1
SCR-DR TRQ Hex Bit CDC 1
Adp. Speed Sensor CDC 1
Extractor Module CDC 1
Disk Pack, AL-DISK CDC 1
Disk Pack, Data CDC 1
Dust Remover, Spray CDC 1
Field Test Unit CDC 1
OPTO Termination Kit Versitron 1
OPTO Loopback Cable CR 1
Table 7.3-3
Special Tools and Test Equipment
8̲ ̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲
8.1 T̲R̲A̲I̲N̲I̲N̲G̲
8.1.1 C̲o̲u̲r̲s̲e̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
The students shall be skilled technicians who have
received basic training in ADP Equipment operation
and maintenance.
8.1.2 I̲n̲i̲t̲i̲a̲l̲ ̲T̲e̲s̲t̲ ̲a̲n̲d̲ ̲C̲o̲u̲r̲s̲e̲ ̲E̲x̲a̲m̲i̲n̲a̲t̲i̲o̲n̲
The students shall receive an initial test before the
start of the courses. Examination of the students will
be held during the training courses.
8.1.3 L̲a̲n̲g̲u̲a̲g̲e̲
The courses will be conducted in English and the documentation
will be in English.
8.1.4 L̲e̲s̲s̲o̲n̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
One course-week consists of 30 lessons of 45 minutes.
8.1.5 F̲i̲n̲a̲l̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲
The proposed training will be finalized upon agreement
between CR and CSC.
8.1.6 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 6 per class.
8.1.7 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
8.1.7.1 S̲i̲t̲e̲ ̲L̲e̲v̲e̲l̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲
6 weeks.
8.1.7.2 D̲e̲p̲o̲t̲ ̲L̲e̲v̲e̲l̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲
6 weeks.
8.1.7.3 S̲y̲s̲t̲e̲m̲ ̲O̲p̲e̲r̲a̲t̲i̲o̲n̲ ̲C̲o̲u̲r̲s̲e̲
2.5 weeks is recommended instead of 6 weeks as required
in the RFP.
8.1.8 C̲o̲u̲r̲s̲e̲ ̲P̲r̲o̲f̲i̲l̲e̲
Practical and theoretical training, ratio 1 to 1.
8.1.9 L̲o̲c̲a̲t̲i̲o̲n̲
The courses will be conducted in UK.
8.1.10 C̲o̲u̲r̲s̲e̲ ̲S̲t̲a̲r̲t̲
The courses will start after installation at the Development
Sites.
8.2 D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
8.2.1 L̲a̲n̲g̲u̲a̲g̲e̲
The manuals and handbooks for maintenance and operation
will be in English.
8.2.2 R̲e̲p̲r̲o̲d̲u̲c̲i̲b̲l̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
All documents will be easily reproducible.
8.2.3 D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲S̲t̲a̲n̲d̲a̲r̲d̲
The delivered documentation will be of good commercial
standard. Previously delivered NATO documents will
be available and accepted by CSC.
All delivered documentation will describe the actual
equipment specified under this proposal. Modifications
will be made to hardware and software.
The documentation will be sufficient to perform operation
and maintenance of the equipment proposed.
8.2.4 R̲e̲v̲i̲e̲w̲
The documentation will be subject to Design Review,
Configuration Control and Acceptance Procedures.
8.2.5 D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲C̲h̲a̲n̲g̲e̲s̲
Documentation Change Notices of all product changes
will be delivered for a 15 year period after final
acceptance at PSWHQ, development site, PSWHQ upgrade
and AWHQ site.
8.2.6 F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
The proposed documentation will be finalized upon agreement
between Christian Rovsing A/S and CSC.