⟦67eee1225⟧ Wang Wps File

    Length: 10008 (0x2718)
    Types: Wang Wps File
    Notes: Conf.chang.cont.stand.    
    Names: »0076A «

Derivation

└─⟦83a4a04d1⟧ Bits:30005815 8" Wang WCS floppy, CR 0002A
    └─ ⟦this⟧ »0076A « 

WangText

…00……00……00……86…1                                              …02…           …02…   …02…         

 SD/STD/003

…02…801020…02……02…#
CONFIGURATION CHANGE CONTROL STANDARD
…02……02…CAMPS








                1  T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲


…02…1  SCOPE .......................................   4 to
 7

…02……02…1.1  CLASSIFICATION OF CHANGES................   4
…02……02…1.2  HARDWARE ................................   5
…02……02…1.3  SOFTWARE ................................   6
…02……02…1.4  DOCUMENTS ...............................   6
…02……02…1.5  DRAWINGS ................................   7

…02…2  AUTHORIZATION ...............................   7 to
 8

…02……02…2.1  TECHNICAL AUTHORIZATION .................   7…02……02……02…2.2
  INSTALLATION AUTHORIZATION ..............   8

…02…3  CONFIGURATION CHANGE REQUISITES .............   8 to
 9

…02……02…3.1  CHANGE PROPOSALS ........................   8
…02……02…3.2  CHANGE ORDERS ...........................   9

…02…4  CONFIGURATION CHANGE REGISTRATION ...........   9 to
 11

…02……02…4.1  IDENTIFICATION ..........................  10
…02……02…4.2  DESCRIPTION .............................  10
…02……02…4.3  DISTRIBUTION ............................  11







                         1  S̲C̲O̲P̲E̲



         This standard is a derivative of Configuration Management
         Standard Manual SD/STM/006 and has the same scope and
         applicability as that document.



1.1      C̲L̲A̲S̲S̲I̲F̲I̲C̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲C̲H̲A̲N̲G̲E̲S̲

         Changes in the configuration of any CI after baseline
         has been established will be classified as either Class
         I or Class II.  Class I changes are those proposed
         changes that affect "form, fit, or function".  Class
         II changes have no effect on performance, interchangeability,
         cost, maintainability, reliability, or delivery schedules.
         CCB approval prior to implementation of a Class II
         change normally is not required.  However, such changes
         are subject to post facto classification review by
         the CCB.  Examples of Class II engineering changes
         are:  a change in documentation only (e.g., correction
         of errors, addition of clarifying notes or views),
         and a change in hardware (e.g., substitution of an
         alternative material if a specific material is not
         required).  Class I ECP's are used when one or more
         of the following factors is affected:

         a)  Baselines

         b)  Technical requirements to include (but not limited
             to) performance outside stated tolerances; reliability,
             maintainability or survivability outside stated
             tolerances; weight, balance, moment of inertia;
             interface characteristics.

         c)  Non-technical contractual provisions such as fee;
             cost to customer schedules; guarantees or deliveries.



         d)  Other factors:  NATO furnished equipment (NFE);
             Safety; Electromagnetic characteristics; Operational,
             test or maintenance computer programs; configuration
             to the extent that retrofit action would be taken;
             operation and maintenance manuals for which adequate
             change/revisions funding is not on existing contracts;
             interchangeability, substitutability or replaceability,
             as applied to CI's and to all sub-assemblies and
             parts of repairable CI's, excluding the pieces
             and parts of non-repairable sub-assemblies; skills,
             manning, training, bio-medical factors or human
             engineering design.

         e)  Class I engineering changes to privately developed
             items occur when the change affects the contractually
             specified form, fit, function, cost or delivery
             schedule of the item.



1.2      H̲A̲R̲D̲W̲A̲R̲E̲

         Configuration change control applies to hardware items
         which are previously approved.

         Class II changes to such items can be made in cases
         where the change is of minor importance, i.e. no effect
         is measureable to the function of the hardware or software
         implied, and the part number is not changed.

         In case of Class I change, i.e. where the function
         of hardware, or software, is changed, or the part number
         is changed, it is the responsibility of the Configuration
         Management to check that applicable software, documents,
         and drawings, are simultaneously changed.





1.3      S̲O̲F̲T̲W̲A̲R̲E̲

         Configuration change control applies to all software
         items which have been approved and implemented (catalogued).

         All Class I software changes must result in an updating
         of the version and/or patch number of the software
         item in question.

         A new version/patch of a software item cannot be released
         by Configuration Management until

         -   it has been approved by QAD
         -   all implications to other software, hardware, and
             documents have been analysed
         -   applicable simultaneous changes to other software,
             hardware, and documents have been performed.



1.4      D̲O̲C̲U̲M̲E̲N̲T̲S̲

         Configuration Change Control applies to all documents
         previously approved and released.

         Any Class I change to a such document implies the change
         of the issue and/or change status number.

         A changed document cannot be accepted under Configuration
         Management until any applicable simultaneous changes
         are made to other documents, software, hardware, or
         drawings.

         Obsolete issue of a document should be kept centrally
         for verification purposes until a completely new issue
         has been released.





1.5      D̲R̲A̲W̲I̲N̲G̲S̲

         Configuration Change Control applies to all drawings
         which have been approved by QAD and filed as such.

         Any Class I change to a such drawing implies the change
         of its issue status.

         A changed drawing cannot be accepted under Configuration
         Control until any applicable simultaneous changes have
         been made to other drawings or documents.

         Obsolete issues of drawings should be kept centrally
         for verification purposes until otherwise decided by
         QAD.









                     2  A̲U̲T̲H̲O̲R̲I̲Z̲A̲T̲I̲O̲N̲



         The responsibility of authorization of configuration
         changes are divided in two parts: The technical authorization
         and the installation authorization.



2.1      T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲A̲U̲T̲H̲O̲R̲I̲Z̲A̲T̲I̲O̲N̲

         The Technical Authorization of a Class I change is
         outside the scope of CM. Decisions are made by the
         Change Control Board (CCB). Class II changes are subject
         to post facto review by CCB.

         Rules are found in plans and standards for CCB.





2.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲U̲T̲H̲O̲R̲I̲Z̲A̲T̲I̲O̲N̲

         CM has the responsibility for Installation Authorization.

         Before authorizing a change for installation CM must
         check

         -   feasibility (change control board)
         -   quality (QAD)
         -   consistency (simultaneous installation of mutually
             dependent changes)









            3  C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲C̲H̲A̲N̲G̲E̲ ̲R̲E̲Q̲U̲I̲S̲I̲T̲E̲S̲



         This chapter describes the requisites and tools for
         change of configurations.



3.1      C̲H̲A̲N̲G̲E̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲S̲

         Any staff member may propose changes to configuration
         items. Likewise proposals may originate from the user/customer.

         To obtain immediate consideration any proposal for
         a change of configuration items must be written on
         or accompanied by the appropriate change request form,
         the Engineering Change Proposal (ECP).




         The change proposal should be sent to the book captain
         or team leader responsible for the configuration item
         in question.

         The change proposal must be thoroughly scrutinized
         by the responsible leader and QAD, and - in case of
         Class 1 change - after approval by Change Control Board
         (CCB) it may be accepted. If a change proposal to one
         configuration item implies influence on other items,
         an additional change proposal must be issued, and cross
         reference must be established.



3.2      C̲H̲A̲N̲G̲E̲ ̲O̲R̲D̲E̲R̲S̲

         As soon a change proposal has been approved a copy
         is sent to CM, who registers it as a pending change.

         The change proposal is converted into a change order
         on/or accompanied by the appropriate form: Engineering
         Change Order (ECO).

         Upon completion of the change and the subsequent QAD
         approval, CM is advised, whereupon appropriate steps
         are taken to issue Installation Authorization as stated
         in section 2.2 of this standard by means described
         in TBD.









           4  C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲C̲H̲A̲N̲G̲E̲ ̲R̲E̲G̲I̲S̲T̲R̲A̲T̲I̲O̲N̲



         Any change to a configuration item must be registered
         by CM following the rules set down in this chapter.





4.1      I̲D̲E̲N̲T̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         Changes are registered on forms as described in chapter
         3.

         Those forms are identified by numbers assigned by CM.
         None of those forms may be issued until they have been
         registered by CM and assigned the said number, and
         the configuration item involved must also be registered
         by CM.

         CM will keep a cross referencing file making it possible
         to recognize any pending change both by change form
         number and by configuration item identification.



4.2      D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲

         A copy of any document describing a change to a configuration
         item must be filed by the CM. However, for pending
         changes a very brief decription may be satisfactory
         provided reference is made to a full description and
         to the person holding this description.

         Full description of the change must be filed by CM
         at completion of the change (and approval by QAD).
         This description must include a statement of the necessity
         of distribution of a new issue or version. This statement
         must clearly indicate whether

         -   the change makes it necessary to immediately distribute
             a new issue/version

         -   distribution of a new issue/version is dependent
             on other (identified) change(s) i.e must wait for
             completion of that/those.

         -   distribution may be done occasionally.




4.3      D̲I̲S̲T̲R̲I̲B̲U̲T̲I̲O̲N̲

         CM keeps a cross reference file with entry by change
         document identification and by configuration item identification
         clearly indicating changes completed but not yet distributed.

         Likewise, CM keeps a cross reference file with the
         same entry points for distributed changes. This file
         clearly indicates

         -   which changes have been distributed by a certain
             issue/version

         -   which issue/version includes a certain change.