⟦76da779b9⟧ Wang Wps File

    Length: 10529 (0x2921)
    Types: Wang Wps File
    Notes: crt/pip/001               
    Names: »0736A «

Derivation

└─⟦ecb9329a3⟧ Bits:30006006 8" Wang WCS floppy, CR 0041A
    └─ ⟦this⟧ »0736A « 

WangText

…00……00……00……86…1                                              …02…           …02…   …02…        

…02…CRT/PIP/001

…02…GT/810526…02……02…#
CAMPS REMOTE TERMINALS PROJECT
IMPLEMENTATION PLAN…02……02…CAMPS/CRT









                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



   1  SCOPE ........................................ 
      4

   2  APPLICABLE DOCUMENTS ......................... 
      4

   3  ORGANIZATION ................................. 
      4

     3.1 RESPONSIBILITIES .......................... 
        5
     3.2 COMMUNICATIONS  ........................... 
        6
     3.3 INTERFACE WITH PURCHASERS QUALITY ASSURANCE 
         REPRESENTATIVE ............................ 
        7

   4  IMPLEMENTATION SCHEDULE ...................... 
      8

   4.1 PROJECT PHASES .............................. 
      8
       4.1.1 Project Planning....................... 
          8
       4.1.2 General Specification.................. 
          8
       4.1.3 Design................................. 
          9
       4.1.4 Production............................. 
          9
       4.1.5 Factory Test........................... 
          9

     4.2 REVIEWS ................................... 
        9
       4.2.1 Project Implementation Readiness
             Inspection ............................ 
              9
       4.2.2 System Requirement Review ............. 
          9
       4.2.3 Critical Design Review ................ 
         10
       4.2.4 Verification Readiness Inspection ..... 
         10
       4.2.5 Factory Acceptance Review ............. 
         10

     4.3 SCHEDULE CONTROL .......................... 
       10
     4.4 RECOVERY AND CORRECTIVE ACTIONS ........... 
       10

5  APPLICAPLE STANDARDS ............................ 
     11




                         1̲ ̲ ̲S̲C̲O̲P̲E̲



         The purpose of this plan is to provide a description
         of the methods to be used in the development of the
         CAMPS Remote Terminals, and the division of the project
         in phases and define major milestones where reviews
         will be held.
         The project will be carried out as a subcontract to
         the CAMPS project.









                 2̲ ̲ ̲A̲P̲P̲L̲P̲I̲C̲A̲P̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲



         1)  CPS/QAP/OO1
             CAMPS QUALITY ASSURANCE PLAN

         2)  SD/PLN/006
             CONFIGURATION MANAGEMENT PLAN









                     3̲ ̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



         The CAMPS Remote Terminals project will be implemented
         by a project team in the System Division.  The project
         team is headed by a project manager and includes a
         system-, a hardware- and a test software group.



         Below the key personel and their responsibilities are
         further described.



3.1      R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲

         R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲ ̲P̲r̲o̲j̲e̲c̲t̲ ̲M̲a̲n̲a̲g̲e̲r̲:

         The project manager has the full responsibility and
         the necessary authority for the achievement of the
         project objectives:

         -   ensure that all contractual requirements for technical
             performance and schedule are fulfilled within planned
             costs,

         -   identify the resources necessary to fulfill the
             project requirements,

         -   utilize optimally the resources made available,

         -   ensure that the project is implemented in accordance
             with the applicaple plans,

         -   assist QAD in performing audits and reviews including
             informing QAD of all activities in order to enable
             scheduling of audits, and to

         -   react by proper corrective actions upon all non
             conformance reports issued by QAD.

         The project manager reports to the CAMPS Program Manager
         and is responsible to him that these objectives are
         met.



         C̲A̲M̲P̲S̲ ̲P̲r̲o̲g̲r̲a̲m̲ ̲M̲a̲n̲a̲g̲e̲r̲:̲

         The CAMPS Program Manager is responsible for allocating
         the resources to the projest on the basis of the requirements
         from the project manager. This includes technical facilities
         as development tools and laboratories as well as manpower.



         Furthermore the department manager is responsible for
         the availability of general plans and procedures which
         are necessary in order that the project can be implemented
         successfully within the organization.

         The CAMPS Program Manager also establishes the interface
         to SHAPE on all contractual and tectnical matters.

         The department manager reports to the division manager.



         Q̲u̲a̲l̲i̲t̲y̲ ̲A̲s̲s̲u̲r̲a̲n̲c̲e̲:̲

         All authority and responsibility regarding quality
         assurance questions within the Systems Division are
         placed in an independent Quality Assurance Department
         (QAD).

         The QAD responsibilities are to:

         -   assist projects managements in establishment of
             QA system and define QA system in QA plan,

         -   perform quality control on sample basis,

         -   convey previous experience in quality aspects to
             project personnel.

         The QAD is responsible to the System Division Manager.



         P̲r̲o̲d̲u̲c̲t̲i̲o̲n̲ ̲D̲e̲p̲a̲r̲t̲m̲e̲n̲t̲,̲ ̲E̲l̲e̲c̲t̲r̲o̲n̲i̲c̲s̲ ̲D̲i̲v̲i̲s̲i̲o̲n̲:̲ (K.J.
         Larsen)

         The production of CRA equipment takes place in the
         Production Department in the Electronics Division.



3.2      C̲O̲M̲M̲U̲N̲I̲C̲A̲T̲I̲O̲N̲S̲

         In order to allow control of the project, all communications
         should include the project manager of the Remote Terminals
         project as well as the CAMPS Program Manager.



         The following rules should be followed:

         Technical maters:

         Attention: Mrs. Gunvor Tind, Remote Terminals Project
         Manager.

         Copy:    : Mr. Gert Jensen, CAMPS Program Manager.

         Contractual matters:

         Attention: Mr. Gert Jensen, CAMPS Program Manager.

         Copy     : Mrs Gunvor Tind

         Concerning QA the communication should normally be
         adressed to the project manager of Remote Terimnals
         with copy to the CAMPS Program Manager. It may also
         include a copy to the relevant QA Department Manager



3.3      I̲N̲T̲E̲R̲F̲A̲C̲E̲ ̲W̲I̲T̲H̲ ̲P̲U̲R̲C̲H̲A̲S̲E̲R̲S̲ ̲Q̲U̲A̲L̲I̲T̲Y̲ ̲A̲S̲S̲U̲R̲A̲N̲C̲E̲ ̲R̲E̲P̲R̲E̲S̲E̲N̲T̲A̲T̲I̲V̲E̲.

         The purchasers Quality Assurance Representative (QAR)
         will at all times have free access to all materials
         pertinent to the project.

         The normal interface for the QAR will be the project
         manager. In case of conflicts the interface may be
         extendet upwards in the organization in accordance
         with the organization diagram.











                4̲ ̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲



4.1      P̲R̲O̲J̲E̲C̲T̲ ̲P̲H̲A̲S̲E̲S̲

         The project is divided in several phases to assure
         that the project conforms to its requirements. This
         division is illustrated in the Work Package Summary.
         (Fig. 4-1)

4.1.1    P̲r̲o̲j̲e̲c̲t̲ ̲P̲l̲a̲n̲n̲i̲n̲g̲

         In the project planning phase, the project is divided
         in seperate workpackages and a description is made
         for each. Furthermore, the Project Implementation Plan
         is established.



4.1.2    G̲e̲n̲e̲r̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ 

         During the general specification phase the requirements
         are analyzed, and a System Requirement Specification
         is established.

         The analysis shall also lead to system design, and
         detailed specification of all equipment to be purchased.

         A Test Plan will also be established during this phase.

         The System Requirement Specification and the Test Plan
         are external baselines and the detailed specifications
         are internal baselines.

4.1.3    D̲e̲s̲i̲g̲n̲

         During the design phase all development is performed
         and and a prelimirary documentation is made. Also a
         Test Driver System is defined and designed during this
         phase.

         Besides a Factory Test Procedure and a procedure for
         Incomming inspection of Terminal equipment will be
         established.

         The Factory Test Procedure represents an external baseline.





4.1.4    P̲r̲o̲d̲u̲c̲t̲i̲o̲n̲

         During this phase production, Incoming Inspection,
         and Integration will take place.



4.1.5    F̲a̲c̲t̲o̲r̲y̲ ̲T̲e̲s̲t̲

         In the Factory Test phase the factory acceptance test
         will take place.

         The Factory Test is an official test, the purpose of
         which is to demonstrate that all equipment fulfills
         its requirements as specified in the System Requirement
         Specification. In the same phase the documentation
         will be finalized.



4.2      R̲E̲V̲I̲E̲W̲S̲

         Different reviews are scheduled during the project
         life time. Their relation to the project phases is
         illustrated in the Work Package Summary. (Fig.4-1)



4.2.1    P̲r̲o̲j̲e̲c̲t̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲R̲e̲a̲d̲i̲n̲e̲s̲s̲ ̲I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲

         At the conclusion of the project planning phase a project
         implementation readiness inspection shall take place.

         This is an internal review where schedule, workpackages
         and the Implementation Plan is examined.



4.2.2    S̲y̲s̲t̲e̲m̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲ ̲R̲e̲v̲i̲e̲w̲

         At the conclusion of the general specification phase,
         a system requirement review shall take place.

         This is to assure that the specified product conforms
         to its requirements.





4.2.3    C̲r̲i̲t̲i̲c̲a̲l̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲v̲i̲e̲w̲

         At the end of the design phase, a critical design review
         will take place. At this review it is verified that
         the product designed makes it possible to meet the
         requirements.



4.2.4    V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲R̲e̲a̲d̲i̲n̲e̲s̲s̲ ̲I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲

         Prior to the factory test, a verification readiness
         inspection is held to review the availability of equipment
         to be tested, of a test system and of a Factory Test
         Procedure.

         The Factory Test Procedure will be investigated to
         check that the requirement to the product will be verified
         by the test.



4.2.5    F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲R̲e̲v̲i̲e̲w̲

         At the conclusion of the factory acceptance test a
         factory acceptance review will be held. Test Reports
         and comments from all the tests will be examined.

         It shall be verified that the product has been subject
         to all necessary tests. The succesfull completion of
         these tests implies acceptance of the product.



4.3      S̲C̲H̲E̲D̲U̲L̲E̲ ̲C̲O̲N̲T̲R̲O̲L̲

         A Progress Report will be issued when found necessary,
         to describe the project status. The progres Report
         will contain information on "Tasks performed","Tasks
         to be performed during the next period" and "Problems
         areas".



4.4      R̲E̲C̲O̲V̲E̲R̲Y̲ ̲A̲N̲D̲ ̲C̲O̲R̲R̲E̲C̲T̲I̲V̲E̲ ̲A̲C̲T̲I̲O̲N̲S̲

         During the Factory Test the equipment will be subject
         to a number of tests in accordance with the Test Plan
         and the Test Procedure.



         Each step of these tests are carried out and approved
         seperately for each sub system. In case of a failure
         in one of the tests, the test will be interrupted and
         the failure will be analyzed to discover whether the
         test was performed correctly or not and whether the
         failure was an external error or due to an error in
         the test object.

         In case of a failure in the test object the error will
         be further analyzed. The result of this analysis and
         a corrective action will be presented to the QAD before
         it is performed.

         When the corrective ction is performed, the failed
         test will be repeated.









                 5̲ ̲ ̲A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲S̲T̲A̲N̲D̲A̲R̲D̲S̲

         CAMPS STANDARD MANUAL

         CPS/STM/001