DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦8959719d9⟧ Wang Wps File

    Length: 53594 (0xd15a)
    Types: Wang Wps File
    Notes: CROSSFOX                  
    Names: »1708A «

Derivation

└─⟦e1d52bc1b⟧ Bits:30006228 8" Wang WCS floppy, CR 0137A
    └─ ⟦this⟧ »1708A « 

WangText

>…00……00……00……00…F…02……00……00…F
F F…06…D…0d……12……0d……12……0e……12……0f……12……00……12……06……11……0c……11……02……10……08……10……0e……10…
…10… …10……05……0f……08……0f……0c……0f……0f……0f…
…0e……09……0e……0b……0e……0f……0e……01……0e……06……0e……86…1         …02…   …02…   …02…   …02…                       …02…                   




VOLUME III     1982-02-16
CONTRACTUAL PART   Page No. #






























                          Part 1




                        CROSS FOX

                   CONTRACT INFORMATION



                  CHRISTIAN ROVSING A/S
                    BALLERUP, DENMARK



39a̲r̲t̲ ̲1̲.̲ ̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲ ̲I̲n̲f̲o̲r̲m̲a̲t̲i̲o̲n̲


                1̲.̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲u̲a̲l̲ ̲I̲n̲f̲o̲r̲m̲a̲t̲i̲o̲n̲


         Christian Rovsing A/S has studied the IFB Bidding Instructions
         and contract Provisions and have the below listed comments.


         Comment on PART II, 4 General Provisions

         A̲r̲t̲i̲c̲l̲e̲ ̲9̲: Patents and rights

         c)  The stipulations herein are not immediately acceptable
             to Christian Rovsing A/S. Clarification  of the
             purpose of the paragraph is needed.…86…1         …02… 
              …02…   …02…   …02…                                       
                




         P̲A̲R̲T̲ ̲I̲I̲ ̲2̲ ̲-̲ ̲S̲p̲e̲c̲i̲a̲l̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲s̲ ̲P̲r̲o̲v̲i̲s̲i̲o̲n̲s̲

         A̲r̲t̲i̲c̲l̲e̲ ̲2̲: Terms of Payment 
                    Refer to Price Proposal.

         A̲r̲t̲i̲c̲l̲e̲ ̲3̲: Terms of Delivery, Penalty

         3̲.̲6̲,̲ ̲3̲.̲9̲ ̲a̲n̲d̲ ̲3̲.̲1̲0̲: It does not seem reasonable to limit
         the consequences of delay on the part of NODECA to
         payment of storing cost. The limitation of such storing
         cost to 10% of the contract value of the stored items
         may unreasonably prevent the contractor from obtaining
         coverage of his cost. Changes and modifications due
         to delay in civil engineering work or due to any other
         delay on the part of NODECA should be covered by the
         standard change procedure under which the contractor
         submits change proposal and under an authorized change
         order is granted an equitable adjustment of the delivery
         time and/or price of deliverables.

         A̲r̲t̲i̲c̲l̲e̲ ̲4̲:̲  Performance Bond

         All prices in this proposal are based on the assumption
         that Christian Rovsing A/S will submit no guarantees.
         This statement covers the advance payment guarantee,
         the performance bond for the contractual period and
         the performance bonds for software and hardware warranty,
         respectively.

         A̲r̲t̲i̲c̲l̲e̲ ̲5̲:  Warranty

         5.2: The hardware warranty covers defects in deliveries
         due to faulty materials, errors in assembly or workmanship
         which may develop during normal and proper use within
         the (2) years from the date of completed SNT category
         iii.

         Repair or exchange of equipment with an expected failure
         rate that falls within the warranty period is not considered
         warranty repair but falls under normal maintenance
         repair.



         5.3: The principle of full new warranty periods for
         repaired or exchanged items is not immediately acceptable
         to Christian Rovsing A/S. Christian Rovsing A/S can
         agree to suspending the original warranty period while
         a hardware item is under repair/exchange. For software
         a one year warranty is included.

         5.6:  The prices quoted herein are based on a one year
         warranty after FSA.

         5.7:  The prices quoted herein are based on a software
         warranty principle according to which the warranty
         expires immediately if unauthorized modifications to
         Christian Rovsing A/S software are made. Further, under
         our standard software warranty the customer must produce
         a failure report and normally be able to reproduce
         the aledged error in the presence of representatives
         of Christian Rovsing A/S. Christian Rovsing A/S is
         prepared to discuss these principles but cannot immediately
         accept the wording of 5.7.

         5.10 and 5.11:  Please refer to the comment above on
         Article 4.2.

         Article 8:  Transfer of the contractors responsibility.

         8.1:  For hardware, transfer of title should take place
         at Factory Acceptance Test.
         For software, transfer of title should take place at
         FQT.

         A̲r̲t̲i̲c̲l̲e̲ ̲1̲7̲ - Governmental regulations

         17.1: Meeds clarifications.

         S̲e̲c̲t̲i̲o̲n̲ ̲3̲ ̲p̲a̲g̲e̲ ̲4̲6̲ ̲o̲f̲ ̲5̲5̲ ̲p̲a̲r̲a̲.̲ ̲7̲/̲1̲5̲ ̲s̲u̲b̲p̲a̲r̲a̲g̲r̲a̲p̲h̲ ̲h̲:

         Christian Rovsing A/S normally commits to supply spare
         parts for a period of maximum 10 years after commissioning.
         A guaranteed supply for 20 years from total system
         acceptance will have to be qualified by a statement
         to the effect that Christian Rovsing A/S may discontinue
         production/availability of an item but before doing
         so, the customer must be given a notice of 6 months
         within which additional orders shall be accepted by
         Christian Rovsing A/S.…86…1         …02…   …02…   …02…   …02…         
                                          




                          Part 2




                        CROSS FOX

                    COMPLIANCE SHEETS



                  CHRISTIAN ROVSING A/S
                    BALLERUP, DENMARK



               P̲a̲r̲t̲ ̲2̲.̲ ̲ ̲C̲o̲m̲p̲l̲i̲a̲n̲c̲e̲ ̲S̲h̲e̲e̲t̲s̲ ̲



         Not Applicable.













                          Part 3

         Preliminary Project Implementation Plan



                        CROSS FOX

               MESSAGE PROCESSING FACILITY



                  CHRISTIAN ROVSING A/S
                    BALLERUP, DENMARK


                    T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲

                        V̲O̲L̲U̲M̲E̲ ̲I̲I̲I̲

                     C̲O̲N̲T̲R̲A̲C̲T̲U̲A̲L̲ ̲P̲A̲R̲T̲


                 P̲a̲r̲t̲ ̲3̲:̲ ̲ ̲P̲r̲e̲l̲i̲m̲i̲n̲a̲r̲y̲ ̲P̲I̲P̲




     3.1  MANAGEMENT PLAN AND PROGRAM CONTROL .......
        4
       3.1.1  Overall MPF Project Approach ..........
          4
       3.1.2  MPF Project Management and Organization
          6
         3.1.2.1  Staffing ..........................
           10
         3.1.2.2  Curriculum Vitae ..................
           10

       3.1.3  Project Implementation Procedures .....
         21
         3.1.3.1  Work Breakdown Structure ..........
           23
         3.1.3.2  Operating Procedures ..............
           29
         3.1.3.3  Cost Control ......................
           32
         3.1.3.4  Contracts Management and
                  Administration ....................
                 33
         3.1.3.5  Problem Recognition and Resolution 
           34
           3.1.3.5.1  Problem Recognition ...........
             34
           3.1.3.5.2  Meetings ......................
             35
           3.1.3.5.3  Reporting .....................
             36
           3.1.3.5.4  Problem Resolution ............
             37
           3.1.3.5.5  Prime Contractor/Company
                      Coordination ..................
                     37

       3.1.4  Project Work Breakdown Structure and
              Schedule ..............................
               37
         3.1.4.1  Detailed WBS Structure ............
           41



     3.2  SYSTEM ENGINEERING PLAN ...................
       46
       3.2.1  Introduction ..........................
         46
       3.2.2  System Engineering ....................
         46
         3.2.2.1  Requirements/Design Specification..
           47
         3.2.2.2  Acceptance Tests ...................
          47
         3.2.2.3  Reliability Program ................
          48 
         3.2.2.4  Technical Coordination ............
           48
         3.2.2.5  Deliverable Items .................
           48

       3.2.3  Hardware Specification ................
         49
       3.2.4  Software Development ..................
         49
       3.2.5  System Integration ....................
         51

     3.3  SUPPORT REQUIREMENTS ......................
       51
       3.3.1  Installation ..........................
         52
       3.3.2  Training ..............................
         53
       3.3.3  Documentation .........................
         53
       3.3.4  Maintenance and Support ...............
         54

     3.4  QUALITY ASSURANCE AND CONFIGURATION
          MANAGEMENT ................................
           54
       3.4.1  Quality Assurance .....................
         55
       3.4.2  Configuration Management ..............
         58

     3.5  AVAILABILITY ..............................
       60
     3.6  TEST AND ACCEPTANCE .......................
       60
     3.7  TECHNICAL TRANSFER ........................
       62



3.1      M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲P̲L̲A̲N̲ ̲A̲N̲D̲ ̲P̲R̲O̲G̲R̲A̲M̲ ̲C̲O̲N̲T̲R̲O̲L̲

         Based upon experience gained as participant in significant
         aerospace and defense projects, a project procedure
         framework has been established at Christian Rovsing
         for management planning and program control.

         As evidenced by successful application in the past,
         these procedures will play an important rate in ensuring
         the successful development, installation, and operation
         of the Message Processing Facility and thus guarant
         performance of a key element of the Cross Fox Project.

         The following sub-sections present:

         o   Overall MPF Project Approach

         o   MPF Project Management and Organization

         o   Project Implementation Procedures (PIP) Introduction



3.1.1    O̲v̲e̲r̲a̲l̲l̲ ̲M̲P̲F̲ ̲P̲r̲o̲j̲e̲c̲t̲ ̲A̲p̲p̲r̲o̲a̲c̲h̲

         This section contains the project management and implementation
         approach for the proposed effort. The techniques to
         be employed have been refined on previous projects.
         The highlights of this approach include:

         o   Reliable, off-the-shelf equipment utilizing the
             latest in technology.

         o   Effective management controls and reporting procedures.

         o   A realistic implementation and support plan to
             ensure operational capability within schedule.



         In describing its management and implementation plan,
         Christian Rovsing has combined a total systems approach
         with advanced business and financial techniques. This
         approach ensures that the total scope of the effort
         has been identified, defined, and analyzed, and will
         be responded to in accordance with the requirements
         of the overall Cross Fox project. The coming effort
         is supported by the following facts:

         a.  Christian Rovsing management has identified the
             MPF as a project of major significance. As such,
             the company will dedicate all required resources
             toward the successful acquisition and completion
             of the contract.

         b.  Christian Rovsing has considerable industrial experience
             in the management, design, development, fabrication,
             and installation of advanced, online computer systems.

         c.  The work to be performed can be accomplished within
             the proposed cost and delivery schedules.

         d.  Highly qualified personnel are available for the
             conduct of the proposed effort.

         e.  Management and technical personnel continuity can
             be maintained through all phases of the project.

         f.  The company can and will take advantage of the
             management and technical skills, knowledge, and
             experience gained on other related projects.





3.1.2    M̲P̲F̲ ̲P̲R̲O̲J̲E̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲&̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲

         To ensure an orderly and timely project effort, our
         subcontractor management and engineering team will
         be assembled at Christian Rovsing's facilities located
         in Ballerup, Denmark. Opened in 1978, these modern
         facilities comprise 12,000 sq. metres - (128,500 sq.
         ft) of manufacturing, integration & test, laboratory
         and office space.

         A dedicated Project Office will be established within
         the Systems Division - see Fig. 3.1-1

         The MPF Project Office will have total system responsibility,
         cognizance, and control authority in order to coordinate
         in-house activities and provide close liaison with
         the prime contractor throughout the duration of the
         project.

         Overall direction for the MPF project is to be provided
         by an adiministratively distinct Project Office. It
         will operate under a Project Manager whose sole responsibility
         will be the management of the MPF project. The Project
         Manager will be the prime interface between Christian
         Rovsing and Prime Contractor.

         The Project Manager will be supported by an Engineering
         Manager, Operations Manager, and Logistics Manager.
         Fig 3.1-2 depicts the project management structure
         and Prime Contractor liaison which will be established
         at project start up.

         Within the supporting functional departments MPF activities
         will be assigned as project entities.



         Since the MPF project requires heavy technical emphasis,
         especially in the early stages, the  Engineering Manager
         will be assigned to coordinate all engineering activities
         and provide close liaison with the Prime Contractor
         on all technical aspects of the Project. The Systems
         Engineering Manager will direct the system hardware
         and software engineering efforts, hold design reviews
         and report on status and progress.

         The equipment procurement, integration and quality
         control will be planned and monitored by the Operation
         Manager. He will be supported by in-house technical
         staff.

         The site installations, provisioning, documentation,
         training and field support aspects of the MPF will
         be planned and coordinated by the Logistics Manager
         supported by the Logistics Support staff of Christian
         Rovsing.

         The Project Office will establish the baseline for
         work breakdowns, specifications, schedules and budgets;
         it will monitor variances and initiate corrective action.

         The management control provided internally and closely
         coordinated with the Prime Contractor will ensure a
         successful design and implementation of the Message
         Processing Facility.








































                        Fig. 3.1-1








































                        Fig. 3.1-2


3.1.2.1  S̲t̲a̲f̲f̲i̲n̲g̲

         The following is a list of staff for key positions
         on the MPF project:

         Program Manager:          

         System Engineering Manager:                     

         Software Manager:                     

         Logistics Manager:  Ole Eskedal

         Site Installation Manager:  Kurt Mikkelsen

         Documentation and Training Manager:  Ole Ren} Petersen



3.1.2.2  C̲u̲r̲r̲i̲c̲u̲l̲u̲m̲ ̲V̲i̲t̲a̲e̲

         Curriculum Vitae for those persons named in section
         3.1.2.1 follows.


         P̲R̲O̲J̲E̲C̲T̲:                      N̲A̲M̲E̲:

         TM CHAIN                      OLE ESKEDAL

         A̲S̲S̲I̲G̲N̲E̲D̲ ̲A̲S̲:

         LOGISTICS MANAGER

         E̲D̲U̲C̲A̲T̲I̲O̲N̲:

         1972    University of Santa Clara, California MSc.
                 EE

         E̲X̲P̲E̲R̲I̲E̲N̲C̲E̲:

         Mr. Eskedal joined Christian Rovsing A/S in 1974 and
         is currently Manager - Integrated Logistics Support
         (ILS) Department of the Systems Division

         1̲9̲7̲6̲ ̲-̲ ̲7̲9̲:

         Project Manager for the F-16 Fire Control Computer
         Co-production Program

         1̲9̲7̲4̲-̲7̲6̲:̲

         Christian Rovsing A/S, Ballerup, Denmark.
         Position: Project Leader.
         Designed and managed the development of micro computer
         based data collection- and control systems.  Author
         of several technical proposals for commercial and military
         porjects.

         1̲9̲6̲9̲-̲7̲4̲:̲

         Hewlett-Packard Cupertino, California.
         Position: Project Engineer.
         Developed controllers for computer peripherals.



         1̲9̲6̲7̲-̲6̲9̲:̲

         Raytheon Semiconductor Mountain View, California.
         Position: Project Engineer.
         Developed production test equipment for integrated
         circuits.

         1̲9̲6̲5̲-̲6̲7̲:̲

         General Electric Semiconductor Syracuse, New York.
         Position:  Project Engineer.
         Developed special purpose test equipment for analog
         integrated circuits.

         1̲9̲6̲4̲-̲6̲5̲

         Teleteknisk Forskningslab., Copenhagen, Denmark.
         Position: Project Engineer.
         Developed test equipment for push button telephones.

         Date of Birth:         4th September, 1939

         Languages:             Danish, English, German


         P̲R̲O̲J̲E̲C̲T̲:               N̲A̲M̲E̲:

         TM CHAIN               KURT MIKKELSEN

         A̲S̲S̲I̲G̲N̲E̲D̲ ̲A̲S̲:

         SITE INSTALLATION MANAGER

         E̲D̲U̲C̲A̲T̲I̲O̲N̲:

         1972    State Accredited Engineering College, Aarhus,
                 BSc.EE

         E̲X̲P̲E̲R̲I̲E̲N̲C̲E̲:

         Mr. Mikkelsen joined Christian Rovsing A/S in 1974.

         1̲9̲7̲4̲ ̲-̲ ̲p̲r̲e̲s̲e̲n̲t̲:̲

         Current responsibility at CR:

         From 1980 employed as installation manager in the integrated
         logistic support (ILS) department with responsibility
         for installation and transportation.  ILS is a function
         set up to support all projects within the System Division;
         current major projects are FIKS and CAMPS.

         CAMPS (Computer Aided Message Processing System) is
         a message preparation and data processing system to
         be installed at NATO sites in Western Europe.

         FIKS (Forsvarets Integrerede Kommunikations System)
         is a message preparation and data processing and routing
         system to be installed at military sites in Denmark.

         Past experience



         Experience has been gained in mechanical and electrical
         design, electronic design, test and production by participating
         in the following CR-projects.

         STRADOGRAF 1974-1975 with the responsibility for mechanical
         and electrical design.  Other tasks on the project
         encompassed electronic design of an analog multiplexer,
         participation in development of measurement methods
         and writing of micro programs.

         The STRADOGRAF is an equipment for measuring skid resistance
         and bumpiness of roads.  The equipment is installed
         in a bus at the Danish Road Research Institute.

         SERIAL CRATE CONTROLLER 1975-1976.  Tasks:  Development
         and electronic design.  Responsible for design, production
         and test.

         The SERIAL CRATE CONTROLLER (SCC) is a module which
         controls the data stream between a parallel bus and
         a serial bus in the CAMAC data aquisition system. 
         The CAMAC system of modula equipment is sued to connect
         on-line inputs and outputs to a computer.

         COMMUNICATION PROCESSOR 1976-1980.  Responsible for
         electrical and mechanical design.  Other areas of responsibility
         encompassed maintenance engineering, hardware assembly
         and accomplishment of qualification tests.

         1978-1980 furthermore responsible for hardwrae integration
         and test.



         The COMMUNICATION PROCESSOR is a subunit in the NICS/TARE
         system, which is a communication system for message
         and data processing and routing.

         Date of Birth:         19th February, 1944

         Languages:             Danish, English, German


         P̲R̲O̲J̲E̲C̲T̲:               N̲A̲M̲E̲:

         TM CHAIN               OLE RENE PETERSEN

         A̲S̲S̲I̲G̲N̲E̲D̲ ̲A̲S̲:

         DOCUMENTATION & TRAINING MANAGER

         E̲D̲U̲C̲A̲T̲I̲O̲N̲:

         Computer Technician

         E̲X̲P̲E̲R̲I̲E̲N̲C̲E̲:

         Mr. Petersen joined Christian Rovsing A/S in 1980 and
         is currently Documentation & Training Manager in the
         Integrated Logistics Support (ILS) Department.

         1̲9̲8̲0̲:̲

         Documentation & Training Manager.

         1̲9̲7̲7̲-̲8̲0̲:̲

         Burroughs A/S.  Trained in and maintained the B2700
         - B4800 Mainframe Computers.  Peripherals: Paper Tape
         R/P.  Magnetic Tape Stations, Disk Drives, Disk Pack
         Drives, Card Readers, Line Printers a.o.

         1̲9̲7̲3̲-̲7̲7̲:̲

         1976:
         Service Manager.
         1974:
         Instructor for the sales staff and customers, i.e.
         technicians, audiologist doctors and engineers
         1973:
         Service Documentation


         1̲9̲6̲6̲-̲7̲3̲:̲ ̲D̲a̲n̲i̲s̲h̲ ̲A̲i̲r̲.̲ ̲F̲o̲r̲c̲e̲.̲

         1970:
         Worked as an Electronic Technician.  Instructor in
         Basic Electronics and Computer Electronics at the Air
         Force Electronics School.
         1968:
         Maintenance Technician.
         1967:
         Trained in Ground Communication Electronics.
         1966:
         Trained in Basic Electronics.

         Date of Birth:         April 6th 1946.

         Languages:             Danish, English, German


3.1.3    P̲r̲o̲j̲e̲c̲t̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲ ̲(̲P̲I̲P̲)̲

         The Project Implementation Plan, PIP, will establish
         a firm baseline for all MPF activities against which
         status, progress and performance can be evaluated and
         controlled.

         PIP will be used as a management tool to provide visibility
         and control of the MPF project. It describes the schedule,
         performance control system, the detailed Work Breakdown
         Structure (WBS), the project administration, the interfaces
         with Prime Contractor, and other aspects of the project,
         Fig. 3.1-3 depicts the various aspects of the PIP.
         Each function addresses the unique requirements of
         the MPF project.

         The PIP will have a well defined structure. Each section
         will identify the activity, its organization and operating
         procedures. A Work Breakdown Statement, WBS, for the
         activity will be related to the schedule network consistent
         with the master schedule and correlated with the associated
         WBS elements of other activities. Documentation produced
         by the activity will be listed. Finally, a cross-reference
         with contractual items will be made for accountability
         of deliverable items and unique requirements.







































       Fig. 3.1-3 PROJECT IMPLEMENTATION PLAN (PIP)



3.1.3.1  T̲o̲p̲-̲L̲e̲v̲e̲l̲ ̲W̲o̲r̲k̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲ ̲S̲t̲r̲u̲c̲t̲u̲r̲e̲ ̲(̲W̲B̲S̲)̲

         The WBS will be the framework for establishing work
         packages, schedules and budgets for managing the MPF
         project and will provide the baseline for performance
         evaluation.

         The basic framework which will be used for integrating
         and reconciling all contractual requirements of MPF
         with the project implementation plan is the Work Breakdown
         Structure (WBS).

         A project tasks overview is shown in Fig. 3.1-4.

         For each of the major tasks a further breakdown has
         been generated detailing hardware, software, and support
         tasks. These WBS elements will become work packages
         for reporting, scheduling and cost control.

         Changes to the WBS will be under configuration management
         and require Project Office approval usually as a result
         of technical and contractual negotiations with Prime
         Contractor. Combined with the master schedule milestones
         for engineering, operations and logistics, the WBS
         will become the system-level plan from which budgets
         can be allocated.

         Project Management is the first task described by the
         tasks overview. The general management structure shown
         in figure 3.1-5 is further expanded in figure 3.1-6
         to show a more formal project organization. The key
         managers in the Project Office and the support functions
         are identified, and the principal tasks assigned to
         the Project Office Staff are delineated.



         The Project Office is responsible for the overall conduct
         of the MPF project under the direction of the Project
         Manager. The Project Office includes an Systems Engineering
         Manager, Operations Manager, and Logistics Manager
         supported by a Contracts Administrator. The principal
         responsibilities of the MPF project staff are briefly
         outlined.








































                       FIG. 3.1-4 

               MPF - PROJECT TASKS OVERVIEW











































                       Fig. 3.1-5 

           MPF-PROJECT MANAGEMENT ORGANISATION

















































                       FIG. 3.1-6  

            PROJECT MANAGEMENT TASKS OVERVIEW

















































                        FIG. 3.1-5

MPF-PROJECT MANAGEMENT ORGANISATION…86…1         …02…   …02…   …02…   …02…                           
                
         M̲P̲F̲ ̲P̲r̲o̲j̲e̲c̲t̲ ̲M̲a̲n̲a̲g̲e̲r̲.̲ As the executive responsible for
         successful execution of the project, the Project Manager
         has authority over and is responsible for budget allocation,
         cost, control, schedule and timely performance, technical
         cognizance of design and development, and control of
         production, test integration and support activities.
         The Project Manager will report directly to the senior
         management for prompt resolution of project issues.
         He is directly supported by the  Project Office staff
         and indirectly by the managers of all operating departments
         within Christian Rovsing.

         E̲n̲g̲i̲n̲e̲e̲r̲i̲n̲g̲ ̲M̲a̲n̲a̲g̲e̲r̲.̲ This senior systems engineer,
         with a complete understanding of the technical implications
         of the MPF top-level system specifications, will be
         responsible for the ultimate technical performance
         and compliance of the MPF installations. He provides
         the correct technical interpretation of Prime Contractor/Cross
         Fox requirements. He plans, directs, monitors, audits
         and controls the design, development, testing, installation
         and cut-over of the MPF with regard to all technical
         aspects. He provides the technical liaison with the
         prime contractor, with the in-house development and
         production groups, and with sub-contractors and suppliers.
         This position will be filled by a senior systems engineer
         experienced in computer systems design and data communications.

         O̲p̲e̲r̲a̲t̲i̲o̲n̲s̲ ̲M̲a̲n̲a̲g̲e̲r̲. This manager will provide the liaison
         between the Project Office and the procurement and
         production activities. Scheduling, cost control, configuration
         control, production status, and quality control are
         his major concerns. He is responsible for establishing
         and maintaining an up-to-date baseline configuration
         and to access the status and quality of MPF production
         during implementation.



         L̲o̲g̲i̲s̲t̲i̲c̲s̲ ̲M̲a̲n̲a̲g̲e̲r̲.̲ The installation and site support
         tasks will be combined under one manager. The Logistics
         Manager will be responsible for site surveys, delivery
         and installation, training, maintenance, spares, documentation
         and site support. Logistic support tasks will be carried
         out by staff from the integrated Logistics Support
         Department of Christian Rovsing.

         Quality Assurance and Contracts Administration are
         divisional staff functions carried on for all projects.
         Intensive support will be given during start up and
         critical phases and will continue throughout the duration
         of the project.



3.1.3.2  O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲

         Formal operating procedures and proven management methods
         will be used by the Project Office to control the MPF
         project.

         Management procedures define the methods used within
         Christian Rovsing for planning, work assignment, monitoring
         and coordination of activities within a project such
         as MPF.

         The Project Office and its staff operates within these
         well-established procedures and is responsible for:

         P̲l̲a̲n̲n̲i̲n̲g̲:̲       Evaluation of contract requirements
                         and allocation of work to the various
                         functional departments.

         Work
         A̲s̲s̲i̲g̲n̲m̲e̲n̲t̲s̲:̲    Assurance of work statements, specification,
                         budgets and schedules requirements.



         M̲o̲n̲i̲t̲o̲r̲i̲n̲g̲:̲     Periodic review of technical schedule
                         and cost performance applying programme
                         control through budget authorisation.

         C̲o̲-̲o̲r̲d̲i̲n̲a̲t̲i̲o̲n̲:̲  Co-ordination of all projects activities
                         between operating departments.

         Internal management procedures have been developed
         as a practical cost/schedule control system which produce
         valid, auditable and timely performance reports. Variances
         from budget and schedule are quickly identified and
         significant deviations are flagged for immediate project
         management attention and corrective action.

         Technical supervision and monitoring are effected through
         periodic design reviews with hardware and software
         engineering managers.

         The primary management controls are based on a well-planned
         WBS, master schedule and budget. Firm baselines established
         early in the project provide the basis for managing
         it. (see figure 3.1-7).

         The WBS consists of a family tree of hardware, software,
         services and tasks organized to define and geographically
         display the work to be accomplished for a successful
         implementation of the project. As a planning tool,
         it defines the work packages for planning, scheduling
         and cost control, negotiated and approved project changes
         are reflected in the baseline WBS.







































                       FIG. 3.1-7 

             WBS SCHEDULE & BUDGET BASELINES


         The master schedule incorporates customer-directed
         milestones and indicates the timing relationships of
         the WBS elements. Detailed plans derived from the master
         schedule establish work package milestones.

         The budget baseline allocates the resources between
         operating departments following contract award. Work
         authorisations are timephased based on schedule constraints.
         Internal budget allocations allow for the retainment
         of funds for contingencies and unforeseen effort.

         All detailed packages identified and assigned from
         the WBS are defined by a statement of work, schedule,
         and budget thus establishing a performance measurement
         baseline.



3.1.3.3  C̲o̲s̲t̲ ̲C̲o̲n̲t̲r̲o̲l̲

         The project Cost and Schedule Control System (CSCS)
         applied by Christian Rovsing to medium and large size
         projects is based upon a multi-level Work Breakdown
         Structure (WBS).

         o   Level 1 defines the Main WBS items within the responsibility
             of each functional manager.

         o   Intermediate levels define Summary Work Packages
             (SWP) within the responsibility of a single task
             manager.

         o   The lowest level defines the Work Packages (WP)
             constituting an SWP. WP's are the units of effort/tasks
             from which project schedule and cost performance
             are monitored. As a guideline each WP is defined
             not to exceed a 3 months duration from start to
             completion. The total effort is not to exceed 6
             man-months.



         Reporting by SWP-Managers on progress, i.e. degree
         of completion and effort spent on the WP-level, takes
         place monthly. These reports serve a dual purpose by
         giving early warnings of both schedule delays and cost
         overruns.

         The overall impact of a threatening delay in completion
         of a WP is judged from Tracking Forms which easily
         identify the interrelations between SWP's in terms
         of due dates for input necessary for the timely performance.

         The impact of a threatening cost overrun is judged
         from regular quarterly and ad hoc project budget revisions
         taking into account both cost-to-date and the latest
         estimates of effort needed for completion. The computerized
         processing of these data ensures up-to-date information.

         By constantly monitoring schedule and cost performance
         from a single source of information, i.e. the SWP-managers
         monthly reporting, the CSCS applied by Christian Rovsing
         ensures consistency in the information from which the
         Project Management identifies problem areas and takes
         subsequent corrective action.



3.1.3.4  C̲o̲n̲t̲r̲a̲c̲t̲s̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲ ̲&̲ ̲A̲d̲m̲i̲n̲i̲s̲t̲r̲a̲t̲i̲o̲n̲

         Contracts Management and Administration is a staff
         function within the division providing support services
         to the Project Manager.

         The function is responsible for the following:

         o   Contract terms and conditions in relation to the
             customer/prime contractor



         o   Contract terms and conditions for purchase orders
             on sub-contractors and suppliers of standard equipment
             and supplies

         o   Project budgets
         o   Invoicing
         o   Settlement of suppliers and sub-contractors
         o   Finance
         o   Cost control

         The function is required to keep such cost and accounting
         records as are required to perform audit consistent
         with Danish law and according to the terms and conditions
         of the contract.

         The function is responsible for the conversion of all
         capacity and other budgets and plans into economic
         terms permitting the safe establishment of rolling
         budgets and long range financial forecasts.



3.1.3.5  P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲c̲o̲g̲n̲i̲t̲i̲o̲n̲ ̲&̲ ̲R̲e̲s̲o̲l̲u̲t̲i̲o̲n̲



3.1.3.5.1    P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲c̲o̲g̲n̲i̲t̲i̲o̲n̲

         From project start to start of acceptance test the
         exchange of information between the Project Manager
         and the prime contractor is performed via:

         -   regular meetings
         -   progress reports, and
         -   telexes, letters, and telephone



         The information to be exchanged makes it possible for
         the prime contractor to monitor the project and continually
         to be kept informed about the status of the product
         and thus enables the customer to intervene if some
         deficiencies which might not be covered by the specification
         are foreseen.

         In case that such deficiencies should occur, these
         are handled as Change Requests, which are acted upon
         by the Project Manager specifying the cost and schedule
         impact that the change might create.

         However, in case that the Project Manager recognizes
         that a specific requirement cannot be fulfilled within
         the frame of the project he immediately informs the
         prime contractor and includes suggestions for the solution.



3.1.3.5.2    M̲e̲e̲t̲i̲n̲g̲s̲

         During the period of design, development, and implementaton,
         regular meetings are held between the prime contractor
         and the Project Manager. Discussions at these meetings
         deal with the concept of the equipment, the various
         solutions affecting the operation, and possible modificaitons
         and changes, which are requested during the period.

         In order to achieve a minimum response time in decision,
         the mutual agreeable changes and conclusions obtained
         during these meetings automatically form part of the
         work statement and the specification.





3.1.8.5.3    R̲e̲p̲o̲r̲t̲i̲n̲g̲

         The reporting by the Project Manager consists of:

         -   progress reports
         -   minutes of progress meetings with the Project Team
         -   minutes of other relevant meetings and 
         -   other documents associated with the control, the
             test and the delivery of the product.

         Progress Reports describing all activities regarding
         design, manufacturing and management are submitted
         at regular intervals according to negotiation between
         Christian Rovsing and the prime contractor.

         The contents of Progress Reports are typically as follows:

         o   Technical Status
             -   Technical Summary
             -   Assembly Level Progress Report

         o   Problems Outstanding 
         o   Quality Assurance Status
         o   Schedule Status & Report
         o   List of documents received and submitted within
             the reporting period
         o   Action Item List

         The scheme presented above has been used successfully
         on other projects including development efforts.





3.1.3.5.4    P̲r̲o̲b̲l̲e̲m̲ ̲R̲e̲s̲o̲l̲u̲t̲i̲o̲n̲

         Whenever internal problems and deviations are ascertained
         the Project Manager refers the matter to the responsible
         party.

         The Project Manager takes action if responsibility
         for the problem discovered is difficult to place.

         Questions relating to the financial and economic schedules
         of the project re-referred by the Project Manager to
         Contracts Management for consideration.

         QA problems within production are referred to the Project
         Manager.



3.1.3.5.5    P̲r̲i̲m̲e̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲/̲C̲o̲m̲p̲a̲n̲y̲ ̲C̲o̲o̲r̲d̲i̲n̲a̲t̲i̲o̲n̲

         Possible problems which may arise and which require
         prime contractor action are reported directly to the
         prime contractor by telex for necessary follow-up and
         action, whatever the case may be.



3.1.4    P̲r̲o̲j̲e̲c̲t̲ ̲W̲o̲r̲k̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲ ̲S̲t̲r̲u̲c̲t̲u̲r̲e̲ ̲a̲n̲d̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲ ̲

         The design, implementation, and installation of the
         CROSS FOX/MPF require the following Work Packages to
         be performed or produced by Christian Rovsing:

         o   System Engineering

         o.  Hardware Specification



         o.  Software Development

         o.  System Integration

         o   Support Requirements

             -   Installation

             -   Training

             -   Documentation

             -   Maintenance and Support

         o   Qualityh Assurance amd Configuration Management

         o   Availability

         o   Test and Acaceptance

         o   Technical Transfer

         A schedule showing deliverable item milestones is given
         in figure 3.1-8, and a planning network diagram showing
         task relationships is given in 3.1-9.






































                        Milestones
                        Fig. 3.1-8






































                        FIG. 3.1-9

                 PLANNING NETWORK DIAGRAM
…86…1         …02…   …02…   …02…   …02…                                           
3.1.4.1  D̲e̲t̲a̲i̲l̲e̲d̲ ̲W̲B̲S̲ ̲S̲t̲r̲u̲c̲t̲u̲r̲e̲

         The following list identifies each work package in
         the detailed WBS as envisaged.

         1.          P̲R̲O̲G̲R̲A̲M̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲

         1.1         Program Management

         1.2         Monthly Progress Reviews

         1.3         Project Implementation Plan

         2.          S̲Y̲S̲T̲E̲M̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲

         2.1         Systems Engineering Management/Technical
                     Coordination

         2.2         System Requirements Review

         2.3         System (Requirements/Design) Specification

         2.4         Preliminary Test Plan

         2.5         Final Test Plan

         2.6         Preliminary Test Procedures

         2.7         Final Test Procedures

         2.8         Preliminary Design Review

         2.9         Final Test Procedure Review

         2.10        Reliability Programme




         3.          H̲A̲R̲D̲W̲A̲R̲E̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         3.1         Equipment Specification (system level)

         3.2         Equipment Product Specification

         3.3         Equipment Logic and Wiring Diagrams


         4.          S̲O̲F̲T̲W̲A̲R̲E̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲

         4.1         Software Management

         4.2         Preliminary Software Design Specification
                     (packet level)

         4.3         Detailed Software Design Specification
                     (module level)

         4.4         Critical Design Review

         5.          S̲Y̲S̲T̲E̲M̲ ̲I̲N̲T̲E̲G̲R̲A̲T̲I̲O̲N̲

         5.1         "Site 101" Integration and Testing (in-factory)

         5.2         "Site 301" Integration and Testing (in-factory)

         6.          T̲E̲S̲T̲I̲N̲G̲

         6.1         FQT Pre-Test in Copenhagen

         6.2         FQT and FPPT in Copenhagen site 101

         6.3         PSAT site 101

         6.4         SNT (iii) site 101



         6.5         FPPT site 301 in Copenhagen

         6.6         PSAT 301

         6.7         SNT (iii) site 301

         6.8         SNT (iv)

         6.9         OSAT


         7.          I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         7.1         Management and Planning

         7.2         Site Preparation

         7.2.1       Site Survey

         7.2.2       Site Verification

         7.2.3       As-Built Doc.

         7.3         Transportation Site 101

         7.3.1       Planning

         7.3.2       Insurance

         7.3.3       Pack and Transp.

         7.4         Transportation Site 301

         7.4.1       Planning

         7.4.2       Insurance

         7.4.3       Pack and Transportation



         7.5         Installation Site 101

         7.5.1       Installation Procedure

         7.5.2       Installation and Checkout

         7.6         Installation Site 301

         7.6.1       Installation Procedure

         7.6.2       Installation and Checkout


         8.          T̲R̲A̲I̲N̲I̲N̲G̲

         8.1         Hareware Maintenance

         8.1.1       Planning & Management

         8.1.2       Course Development

         8.1.3       Course Material

         8.1.4       Course Conduct

         8.2         Software Maintenance

         8.2.1       Planning and Management

         8.2.2       Course Development

         8.2.3       Course Materials

         8.2.4       Course Conduct

         8.3         OJT Courses

         8.3.1       Planning and Management



         8.3.2       Development

         8.3.3       Materials

         8.3.4       Course Conduct


         9.          D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲

         9.1         Equipment Handbooks

         9.2         Maint.Manual (Draft input)

         9.3         System Handbook (Draft input)

         9.4         MC Operators Handbook (Draft input)


         10.         M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲&̲ ̲S̲U̲P̲P̲O̲R̲T̲

         10.1        Maint.Document

         10.2        HW Warranty (4R2)

             .1      Site 101

             .2      Site 301

         10.3        Codification

         10.4        Spares

         10.4.1      RSPL

         10.4.2      ASPL


3.2      S̲Y̲S̲T̲E̲M̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲ ̲P̲L̲A̲N̲



3.2.1    I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲

         The System Engineering Plan comprises the following:

             o   System Engineering

             o   Hardware Specification

             o   Software Development

             o   System Integration



3.2.2    SYSTEM ENGINEERING

         Christian Rovsing has management and technical responsability
         for delivery of the Message Processing Facility (MPF)
         to Prime Contractor and for interfacing the MPF to
         the CROSS FOX system.  As such, Christian Rovsing has
         full MPF system responsability for the following System
         Engineering Tasks:

         o   MPF Requirements/Design System Specification

         o   MPF Test Plan and Procedures

         o   MPF Reliability Program

         o   Technical Coordination



             -   Prime Contractor

             -   NODECA

             -   System Reviews

         In the following sub-sections, each of the above tasks
         is outlined, and deliverable items are enumerated.



3.2.2.1  R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲/̲D̲e̲s̲i̲g̲n̲ ̲S̲y̲s̲t̲e̲m̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ 

         The first task in the development of a system is to
         identify all the requirements to the sytem which then
         form the baseline for design procedures and acceptance
         test plans and procedures.  After approval - a System
         Requirements Review is to be held in Copenhagen - the
         Requirements/Design Specification is created, describing
         how requirements are to be implemented; it will show
         - point for point - where in the system each requirement
         is implemented.  The Requirements/Design Specification,
         approved at a preliminary design review in Copenhagen
         will form the technical baseline, allowing all agreed
         functional requirements to be traced through the design
         to the implemented system.



3.2.2.2  A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲s̲ 

         Subsequent to the System Specification a Test Plan
         and Procedure will be specified.  As described in System
         Integration and Testing, section 5, the following tests
         are envisaged:



         o   Factory Qualification Test (FQT)

         o   Factory Post Production Test (FPPT)

         o   Preliminary Site Acceptance Test (PSAT)

         o   Sub-Net Test-Category iii

         o   Sub-Net Test-Category iv

         o   Final Acceptance Test (FAT)

         Test procedures (and implicitly test plans) will be
         reviewed at a Final Test Procedure Review.



3.2.2.3  R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲ ̲P̲r̲o̲g̲r̲a̲m̲ 

         This task is carried out by conducting in-house reviews
         of all program items to guarantee that required levels
         of quality are met.



3.2.2.4  T̲e̲c̲h̲n̲i̲c̲a̲l̲ ̲C̲o̲o̲r̲d̲i̲n̲a̲t̲i̲o̲n̲ 

         Progress meetings will be held quarterly throughout
         the program, and Christian Rovsing will participate
         in each meeting in Oslo  along with Prime Contractor,
         to ensure effective communication and coordination.



3.2.2.5  D̲e̲l̲i̲v̲e̲r̲a̲b̲l̲e̲ ̲I̲t̲e̲m̲s̲ 

         The following deliverable items from System Engineering
         are envisaged.



         o   System Requirements/Design Specification

         o   Preliminary and Final Test Plan

         o   Preliminary and Final Test Procedures



3.2.3    H̲a̲r̲d̲w̲a̲r̲e̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ 

         All hardware items are off-the-shelf, NATO qualified
         units, and the task (and deliverables) will consist
         of:

         o   Equipment S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
                - System Level

         o   Equipment D̲a̲t̲a̲ ̲S̲h̲e̲e̲t̲s̲

         o   Equipment P̲r̲o̲d̲u̲c̲t̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲

         o   Equipment L̲o̲g̲i̲c̲ ̲D̲i̲a̲g̲r̲a̲m̲s̲

         o   Equipment W̲i̲r̲i̲n̲g̲ ̲D̲i̲a̲g̲r̲a̲m̲s̲



3.2.4    S̲o̲f̲t̲w̲a̲r̲e̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ 

         This task consists of:

         o   Creation of Specifications for the following software
             subsystems:

             -   System

             -   Applications

             -   Support



             -   Maintenance and Diagnostic

         o   Software Coding

         o   Software Unit Testing

         Software Design Specifications will be produced at
         level 2 and 3 in accordance with ACE Standard 007 amended
         and approved by SHAPE into a CAMPS Standard. A Preliminary
         Software Design Specification (packet level, i.e. level
         2) will be produced and subjected to an intermediate
         Christian Rovsing Design Review.  Following this, a
         Detailed Software Design Specification (module level,
         i.e. level 3) will be produced and subjected to a Critical
         Design Review in Copenhagen.

         All software coding will be contingent upon acceptance
         of the Detailed Software Design Specification.  Finally,
         each software module will be unit-tested before HW/SW
         integration is attempted.

         The following items are deliverable:

         o   Detailed Software Design Specification

         o   Documentation of system, maintenance, and support
             software

             -   software system specifications

             -   software product specifications

             -   software user specifications

             -   program listings

             -   linker listings,



         o   documentation of application software in accordance
             with the modified ACE-STD 007.

             -   system (reg./design) specificaton

             -   preliminary SW design spec. (packet level)

             -   detailed SW design spec. (module level)

             -   program listings

         o   Code

             -   System (with object program libraries)

             -   Applications (with source program libraries
                 and linker control statement files)

             -   Support (with object program libraries)

             -   Maintenance and Diagnostic (with object program
                 libraries)



3.2.5    S̲y̲s̲t̲e̲m̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲

         For each MPF (1 to site 101 and 1 to site 301), the
         hardware and software are integrated at the factory
         and pre-tested.

         The pre-tested equipment is then ready for formal acceptance
         testing.



3.3      S̲U̲P̲P̲O̲R̲T̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲



         In the following sub-sections support requirements
         are listed for:

             o   Installation

             o   Training

             o   Documentation

             o   Maintenance and Support

         All suppot items will be carried out by the Logistics
         Support and Services Department of Christian Rovsing
         A/S.



3.3.1    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ 

         Installation comprises the following items:

         -   Site Preparation and Verification

         -   Transportation and Installation

         -   Packaging Requirements

         The following installation tasks will be carried out:

         -   Site Survey 101

         -   Site Interface Specification Data (civil works
             requirements) 101

         -   Packaging and Shipping 101

         -   Site Installation 101



         -   Site Survey 301

         -   Site Interface Specification Data 301

         -   Packaging and shipping 301

         -   Site Installation 301

         A description of the tasks as they relate to CROSSFOX/MPF
         are to be found in the Technical Proposal.



3.3.2    T̲r̲a̲i̲n̲i̲n̲g̲ 

         The following training courses will be provided:

         1.  Operator Training

         2.  SW Maintenance Training

         3.  HW Maintenance Training

         A detailed description of the training courses is found
         in the technical proposal.



3.3.3    D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ 

         The following documentation items/tasks will be performed:

         Operators Handbook

         Hardware Maintenance Handbook

         Software Documentation As-built



         Technical Manuals Preparation

         Delivery of Documentation Site 101

            -     -      -         Site 301

         A more detailed description of the documentation is
         contained in the technical proposal.



3.3.4    M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲a̲n̲d̲ ̲S̲u̲p̲p̲o̲r̲t̲

         Maintenance and support comprise the following items:

         -   Maintenance

         -   Field Support

         -   Spares Management

         -   Codification of Supply Items

         -   Tools and Test Equipment

         -   Failure Reporting

         -   Warranty Repair

         Descriptions of these activities in greater detail
         are given in the technical proposal



3.4      Q̲U̲A̲L̲I̲T̲Y̲ ̲A̲S̲S̲U̲R̲A̲N̲C̲E̲ ̲A̲N̲D̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲





3.4.7    Q̲u̲a̲l̲i̲t̲y̲ ̲A̲s̲s̲u̲r̲a̲n̲c̲e̲ ̲(̲Q̲A̲)̲

         The Quality Assurance Manager (QAM) is responsible
         for all QA tasks within the division. This includes
         the establishment and control of general QA procedures
         and special QA procedures for dedicated projects.

         The Engineering Drawing Office and Secretariat operate
         in accordance with the procedures established and controlled
         by the QAM.

         The Quality Assurance Manager is, in particular, responsible
         for:



         1.  P̲a̲r̲t̲s̲ ̲a̲n̲d̲ ̲M̲a̲t̲e̲r̲i̲a̲l̲ ̲(̲P̲&̲M̲)̲

             P&M is responsible for procurement control, vendor
             evaluation & qualification, and performs a support
             function for receiving inspection and purchasing.



         2.  R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲

             This is a supervision function available for all
             projects. Reliability analysis, trade-offs, and
             tests are performed by the project team under the
             supervision and control of QA.

         3.  Q̲u̲a̲l̲i̲t̲y̲ ̲C̲o̲n̲t̲r̲o̲l̲ ̲(̲Q̲C̲)̲

             This includes the establishment and control of
             general QC procedures within the division and special
             QC procedures for dedicated projects, and the establishment
             and control of QC requirements relating to subcontractors
             and suppliers.



             The QC function is in particular responsible for:

             -   Evaluation of quality control plans
             -   Evaluation of inspection plans
             -   Incoming inspection of parts and materials
                 and subcontractual items
             -   In-process inspection
             -   End-item acceptance test
             -   Shop procedures
             -   Control of special procedures
             -   Methology and calibration relating to test
                 instrument and tools
             -   Electrical and environmental tests
             -   Entrance control and cleanliness control of
                 restricted clean room areas
             -   Control of packing & shipping
             -   Trend reporting
             -   Quality audits



         4.  Q̲A̲-̲P̲o̲l̲i̲c̲y̲

             The Quality Assurance Policy of the company is
             defined in "Quality Assurance Policy" which is
             an internal standard.

             Based on this policy, the company has implemented
             a standard QA-system which is fully compliant with
             "NATO Quality Control System Requirements for Industry",
             AQAP-1.





         5.  Q̲A̲-̲S̲y̲s̲t̲e̲m̲

         The standard QA system comprises a series of functions
         among which are:

         o   Q̲u̲a̲l̲i̲t̲y̲ ̲P̲l̲a̲n̲n̲i̲n̲g̲

             At an early point in the contract performance,
             the quality requirements are reviewed and a contract
             related Quality Plan is established. This plan
             is
             based on the standard QA system but may contain
             amendments or exemptions, if necessary. The plan
             contains detailed scheduling of QA participation
             in such activities like design reviews, factory
             test, acceptance test, etc.

         o   D̲e̲s̲i̲g̲n̲ ̲C̲o̲n̲t̲r̲o̲l̲

             The QA system provides strict control of all new
             designs of both hardware and software. Design Reviews
             are scheduled and performed and no design is released
             for production/programming without proper approval.

         o   C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲C̲h̲a̲n̲g̲e̲ ̲C̲o̲n̲t̲r̲o̲l̲

             A Configuration and Change Control system assures
             that all necessary documentation is established
             and baselined. Also software is placed under control
             after programming and development test. The Change
             Control is managed by a board with participation
             of a prime contractor representative, if required.



         o   W̲o̲r̲k̲ ̲I̲n̲s̲t̲r̲u̲c̲t̲i̲o̲n̲s̲

             In all areas where necessary for quality, work
             instructions and standards are established. Standards
             define the required quality level and instructions
             define processes needed to reach that level.

         o   I̲n̲s̲p̲e̲c̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲

             Detailed procedures are established for Inspection
             and Tests to be performed during development, production
             and upon completion of the contract (acceptance
             test).

         o   R̲e̲c̲o̲r̲d̲s̲

             All inspection and test results - as well as any
             other events significant for the documentation
             of the product quality - are recorded and kept
             in the QA files until completion of the contract.



3.4.2    C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲

         Configuration Management will benefit from the experience
         gained on other major projects.

         The Configuration Management function covers the following
         areas:

         o   Organization
         o   Items under configuration control
         o   Configuration identification
         o   Configuration Control
         o   Status accounting
         o   Configuration audit



         The Configuration Management function is part of the
         divisional configuration management section under Quality
         Assurance. This organizational arrangement ensures
         consistency in configuration management and documentation
         control, although each project follows its own Configuration
         Management Plan.

         Christian Rovsing Configuration Management acts as
         chairman of the Configuraton Control Board. All requests
         for changes go through the CCB.

         The following items are under Configuration Control:

         o   Specifications and Procedures
         o   Engineering Drawings
         o   Change Documentation
         o   Hardware and Software Items

         All items released as part of the baseline configuration
         as well as subsequent change documentation to these
         items are identified for the purpose of Configuration
         Control with one or more of the following numbers:

         o   Drawing or part number
         o   Revision number
         o   Serial number
         o   Specification description
         o   Change identification number

         Configuration Control is divided into three major tasks:

         o   Change analysis
         o   Change classification
         o   Approval of changes

         The Configuration Control Board (CCB) is involved in
         all areas.



         The Configuration Status Accounting function records
         and maintains the informaton and documentation required
         by configuration control management. It includes listings
         of approved engineering documentation, status reports
         of proposed changes, and implementation status of approved
         changes.

         The Physical Configuration Audit (PCA) is the formal
         examination of the as-built version of a configuration
         item against its technical documentation in order to
         establish the Configuration Item's product baseline.
         The Functional Configuration Audit (FCA) is the verification
         of the completion, or extent of completon, of all tests
         required by development specifications.

         The Configuration Management function gets involved
         in updating of the PIP and other plans of the project
         by the fact that DATA MANAGEMENT is handled by configuration
         control.

         The changes are normally initiated through the project
         office but controlled by Configuration Management.



3.5      A̲V̲A̲I̲L̲A̲B̲I̲L̲I̲T̲Y̲

         Availability is treated in the Technical Proposal,
         section on Availability.



3.6      T̲E̲S̲T̲I̲N̲G̲ ̲A̲N̲D̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲

         Following system integration and unit testing of each
         software module, a Factory Qualification Test (FQT)
         is performed.  Thereafter, each MPF system will be
         subjected to a Factory Post Production Test (FPPT)
         before shipment to site for installation.



         At the site, system integration is carried out, and
         a Preliminary Site Acceptance Test (PSAT) is performed.
          Following this, a Sub-Net-Test (SNT) - Category iii
         verifies that the MPF interfaces properly to the TARE
         Communication Processor Sub-System and to the Telegraph
         Message Sub-System.  Additionally, at the second site,
         a SNT - category iv verifies that the two MPF's communicate
         properly with each other, both already having been
         tested to SNT iii.

         Finally, an Official System Acceptance Tesat (OSAT)
         is performed, and succesful completion of the OSAT
         constitutes final acceptance of the MPF by NODECA.

         The following is a list of formal tests:

         FQT Pre-Test in Copenhagen

         FQT and FPPT in Copenhagen for site 101 equipment

         PSAT site 101

         SNT (iii) site 101

         FPPT in Copenhagen for site 301 equipment

         PSAT 301

         SNT (iii) site 301

         SNT (iv)

         OSAT






3.7      T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲T̲R̲A̲N̲S̲F̲E̲R̲ ̲