⟦8ed7b93b4⟧ Wang Wps File

    Length: 2390 (0x956)
    Types: Wang Wps File
    Notes: MOM at SHAPE              , Missing sectors
    Names: »0976A «

Derivation

└─⟦d10d3ed68⟧ Bits:30006014 8" Wang WCS floppy, CR 0055A
    └─ ⟦this⟧ »0976A « 

WangText




…02…           

…02… KM/810521…02……02…#
MINUTES OF MEETING AT SHAPE 12-5-81
…02……02…CAMPS











                           
…02……02……02……02…         …02…81-05-12…02…   6. …02…SHAPE
                                       

         Minutes of Meeting at SHAPE - Tuesday 12/5-81


  …0f…SHAPE…0e…
  Col. Miller                          Mr. B̲jarne B̲erthold
  Mr. J. Herrinck          Mr. K̲urt M̲ikkelsen
  Mr. A. Earl                          
  Mr. B. Marsh   …02…     
  P̲A̲B̲                      
  Mr. A. Winther
  A̲R̲C̲
  Mr. Philip Becker
             
              
                
                
                    
       
            
           
          
…06…1…02…        …02…   …02…   …02…   …02…                …02…                          
               


         1.  H̲A̲R̲D̲W̲A̲R̲E̲ ̲P̲R̲E̲S̲E̲N̲T̲A̲T̲I̲O̲N̲

          Rack, IDF/Filter Box and PLF design was presented
          by BHB.


         2.  S̲I̲T̲E̲ ̲D̲E̲S̲I̲G̲N̲ ̲C̲O̲N̲C̲E̲P̲T̲

          A draft copy of CPS/TCN/023 with the comments per
          CAMPS Log 214 incorporated was reviewed and accepted
          except for para 1.1.  COMSEC will comment this para
          thursday 14/5. Item closed 14/5 with the incorporation
          of the DN2 of the CAMPS Log 214.

          CR gave a rationale for using flexible conduit between
          the two suites.  CR explained why metal conduit was
          required for power cabling;  this was accepted by
          COMSEC and para 3.1 and 3.2.b of the site design concept
          was changed accordingly.


         3.  G̲R̲O̲U̲N̲D̲I̲N̲G̲

             a)  The grounding concept was discussed
                 and it was decided to distribute the
                 secure ground in the CAMPS room either
                 as the third wire in the power cable
                 or within the power conduit as a separate
                 cable or wire.  A common busbar will
                 be provided in the CAMPS PDB and the
                 ground will be distributed to the
                 power outlets (3 wire) and equipment
                 racks in such a way that ground loops
                 are avoided.

         ACTION      KM to rewrite site design concept
                     to reflect this for the thursday
                     14/5 meeting.

                 Item closed 14/5, see draft site design
                 document attached.

             b)  Copper cables to maintenance position
                 (see 4.2c and sketch 4 of the site
                 design concept ). will require
                 the ground to be distributed via the
                 racks to the maintenance position
                 in order to avoid ground loops.

             c)  All terminals (both CAMPS room and
                 user terminals) will be supplied with
                 a 3 pin power plug, which will fit
                 the 3 pin power outlets provided by
                 H