⟦901258f1a⟧ Wang Wps File

    Length: 8844 (0x228c)
    Types: Wang Wps File
    Notes: CAMPS SITE DESIGN SPEC.   
    Names: »0802A «

Derivation

└─⟦872f87e0f⟧ Bits:30006013 8" Wang WCS floppy, CR 0052A
    └─ ⟦this⟧ »0802A « 

WangText




…02…CPS/TCN/023   

…02…KM/810810…02……02…#
CAMPS SITE DESIGN CONCEPT
…02…KM/810612…02…CAMPS







                    T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



         1  SCOPE...................................   4
             1.1  GENERAL REQUIREMENTS..............   4

         2  EQUIPMENT AND SITE DATA.................   4
             2.1  EQUIPMENT.........................   4
             2.2  POWER.............................   4
             2.3  EMP PROTECTION....................   5
             2.4  RED CONCEPT.......................   5

         3  POWER CABLING...........................   5
             3.1  GENERAL DESIGN SPECIFICATIONS.....   5
             3.2  CAMPS ROOM........................   5
             3.3  USER TERMINALS....................   6

         4  SIGNAL CABLING.........................    7
             4.1  GENERAL DESIGN SPECIFICATIONS....    7
             4.2  CAMPS ROOM.......................    7
             4.3  USER TERMINALS...................    8

         5  GROUNDING..............................    9
             5.1  GENERAL DESIGN SPECIFICATIONS....    9
             5.2  CAMPS ROOM.......................    9
             5.3  USER TERMINALS...................    9



                        …01…1̲ ̲ ̲S̲C̲O̲P̲E̲



         This document outlines the ACE COMSEC Requirements
         for the CAMPS Equipment Installation and specifies
         the overall site design criteria, to be reflected in
         the CWR and A-T-B-B drawings.



1.1      G̲E̲N̲E̲R̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The CAMPS Equipment is to be installed in accordance
         with relevant paragraphs of AMSG 719B, including:

         ADP-INSTALLATION Paragraphs 330, 331, with references:
         305b-c, 240
         OPTO-Systems     Paragraphs 370, 371



                2̲ ̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲A̲N̲D̲ ̲S̲I̲T̲E̲ ̲D̲A̲T̲A̲



2.1      E̲Q̲U̲I̲P̲M̲E̲N̲T̲

         Racks, VDU's, printers and PTR/PTP are EMI shielded
         and therefore equipped with power line filters and
         signal line filters or optical interface (except for
         the frequency stabilizer rack). Sketch No. 1 shows
         a typical CAMPS room layout.



2.2      P̲O̲W̲E̲R̲

         All power in the CAMPS room is filtered (pink power)
         The filter is located prior to the PDB (see sketch
         no 2).
         The user terminals will be supplied with black or pink
         power.





2.3      E̲M̲P̲ ̲P̲R̲O̲T̲E̲C̲T̲I̲O̲N̲

         At most sites the CAMPS room is located within an EMP
         area i.e. power is filtered, all signal lines are filtered
         etc.



2.4      R̲E̲D̲ ̲C̲O̲N̲C̲E̲P̲T̲

         At all sites the CAMPS room is located within a red
         area or class I area. Some user terminals are also
         located in a red area and some are n̲o̲t̲.



                     3̲ ̲ ̲P̲O̲W̲E̲R̲ ̲C̲A̲B̲L̲I̲N̲G̲



3.1      G̲E̲N̲E̲R̲A̲L̲ ̲D̲E̲S̲I̲G̲N̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲S̲

         Standard power cables laid in unperforated sheet metal
         ducts with lids or conduits (fixed or flexible), below
         raised floors, on the wall or below the ceiling are
         to be specified since a pick up within the nearfield
         of each piece of equipment could cause reradiation
         of line emission within the CAMPS room.  The filter
         at the entrance to the CAMPS Room will prevent line
         emission detectable outside the CAMPS room.



3.2      C̲A̲M̲P̲S̲ ̲R̲O̲O̲M̲

         a)  Sketch no. 3 shows a typical cable duct layout
             concerning power distribution. A discussion of
             the layout follows.

         b)  Metal power cable ducts (not inside ceiling) shall
             be connected to the EMI rack only and isolated
             at the PDB by an insulated bush.

         c)  The separation between power and signal cables
             and power and other cables or metalwork follows
             the AMSG719B paragraph 305b separation criteria:
                 Power - Signal (Opto, copper) in Parallel:
                 15 cm
                 Power - other cables or metalwork in Parallel:
                 15 cm


             Crossing of other cables (red/black) or metalwork
             must be done at right angles with a minimum separation
             of 1,5 cm.
             On the walls standoff insulators must be provided,
             so that the cable is at least 1,5 cm from the wall
             at any point.

         d)  The EMI racks are provided with power line filters
             at which the power cables terminate. Either bottom
             or top cable entrance to the racks will be provided.
             At sites with raised floor the cables are to enter
             from bottom and at sites not provided with computer
             floor the entrance is from the top

         e)  The frequency stabilizer rack is treated as a black
             piece of equipment by COMSEC. It must therefore
             be placed, so that a 1 m separation from red equipment
             can be maintained (racks, VDU etc.).
             Note that there might be Host Nation provided black
             equipment or cables in the CAMPS room. If so, it
             must be specified in the site documentation received
             from SHAPE. 

         f)  Power outlets near each piece of equipment are
             to be specified. The power outlets shall be a 3
             wire type (line + neutral + GND) with break of
             line only. 
             The power outlets can be mounted in the false floor,
             on the wall or on the ceiling depending on the
             facility in question.



3.3      U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲

         a)  A power outlet near each piece of equipment is
             to be specified. The power outlet shall be a 3wire
             type (Line + neutral + GND) with break of line
             only.

         b)  The user terminals will either be supplied with
             black or pink power. In both cases the separation
             criteria are to be maintained.


                    4̲ ̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲I̲N̲G̲



4.1      G̲E̲N̲E̲R̲A̲L̲ ̲D̲E̲S̲I̲G̲N̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲S̲

         a)  OPTO-cables in plastic ducts, since only physical
             protection is required, below raised floors, on
             the wall or below the ceiling (not inside false
             ceiling) are to be specified.

         b)  Coppercables in plastic ducts require 1m separation
             to black cables or metalwork and 15 cm to power
             or other pink cables. Coppercables in ferrous shield
             (waterpipe, or ferrous metal duct) requires 15
             cm separation to metalwork or black cables.



4.2      C̲A̲M̲P̲S̲ ̲R̲O̲O̲M̲

         a)  Sketch No 4 shows a typical cable duct layout concerning
             signal cable distribution. A discussion of the
             layout follows:

         b)  OPTO-cables to supervisor positions are run in
             plastic ducts below raised floors and in case false
             floors are not provided on the walls or below the
             ceilings. Only physical protection against damage
             is to be specified where OPTO cables leave the
             duct (rack, supervisor position)

         c)  Coppercables to the maintenance position are run
             in a separate ferrous duct or pipe, which can be
             placed next to the OPTO-duct. A termination (junction
             box o.e) of the duct or pipe is to be specified
             where the coppercable leaves the shield. CR will
             install flexible conduit from this point if necessary
             (rack, maintenance position).

         d)  Ducting for the coppercables to low speed teleprinters,
             SCARS, CCIS and TARE are not to be specified by
             CR, but must be taken into consideration with regard
             to space and entrance to rack F in the CWR. CR
             will specify the electrical and mechanical interface
             to the racks in the CWR and As-To-Be-Built Drawings.





         e)  Either bottom or top cable entrance will be provided
             to the EMI racks as specified in paragraph 3.2.d.
              The connection between the two bays of racks (processor
             and line termination racks) will be installed by
             CR as a flexible ferrous conduit, which is to be
             considered as a part of the EMI shield. 




4.3      U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲

         a)  OPTO-cables to user terminals are to be run in
             metal ducts or pipes outside the CAMPS room. Pull-boxes
             for every 20m must be specified and ducts must
             not be welded or otherwise locked (sealed) until
             CR has completed the CAMPS installation. When leaving
             the CAMPS room the wall penetration must be at
             right angles.
             Inside the CAMPS room plastic ducts are to be specified.

         b)  The OPTO cable will be terminated at the user terminal
             by CR's installation team.
             The OPTO-cable is installed by Host Nation up to
             the location of the terminal and precut to a certain
             length. (to be specified)





                       5̲ ̲ ̲G̲R̲O̲U̲N̲D̲I̲N̲G̲



5.1      G̲E̲N̲E̲R̲A̲L̲ ̲D̲E̲S̲I̲G̲N̲ ̲S̲P̲E̲C̲I̲F̲I̲C̲A̲T̲I̲O̲N̲S̲

         a)  A common secure ground connection point (Copper
             or similar) will be provided in the CAMPS room
             in order to achieve a star point configuration.The
             secure ground will also act as safety ground and
             must therefore comply to national regulations.

         b)  User terminals will either be connected to a secure
             ground or to a safety ground.

         c)  The secure ground will be connected primarily to
             PLF case and to the grounding point of each piece
             of equipment.



5.2      C̲A̲M̲P̲S̲ ̲R̲O̲O̲M̲

         SHAPE or Host Nation will provide a common secure ground
         terminal (copperbar, o.e. in the CAMPS room PDB), and
         distribute it to power outlets and equipment racks
         either as the third wire of a 3wire power cable or
         as a separate wire run within the same conduit.


5.3      U̲S̲E̲R̲ ̲T̲E̲R̲M̲I̲N̲A̲L̲S̲

         Host Nation will provide 3 pin power outlets for user
         terminals, the third wire of which will provide either
         a secure or safety ground. The ground wire may be the
         third wire of a 3 wire power-cable from the PDB to
         the power outlet or a separate wire run within the
         same conduit.