DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦9830bec09⟧ Wang Wps File

    Length: 2913 (0xb61)
    Types: Wang Wps File
    Notes: Telex SHAPE               
    Names: »0455A «

Derivation

└─⟦0cbd6095b⟧ Bits:30006077 8" Wang WCS floppy, CR 0034A
    └─ ⟦this⟧ »0455A « 

WangText





                     1980-12-23    gj/amo

to:  shnmo division
     att.: mr. paul f. shey, contracting officer

cc.: lt. col. manfred stoltz, camps program manager 

fm:  christian rovsing a/s, denmark
     gert jensen

our ref: cps/101/tlx/0151

subject: review and comments to document package on camps-tare
 interface
-----------------------------------------------------------------

ref.: a) your document 3103.3.15/SHCEPA/80
      b) minutes of Progress Meeting No. 5 para 7.

1.       The shape letter 3103.3.15/SHCEPA/80 refers
         to five enclosure. The following were received
         by CR A/S:

  a.     nicsma/sped/stb (80) 601.1/171. Only enclosure
         2, 3 and 5 were received.

  b.     Performance spec. for the TARE synchonous channel
         protocol. Appendix 30 were received as shape
         camps doc. no. 027. Appendix 40 were not received
         (and is not relevant to CAMPS).

         The received appendix 30 was a handcorrected
         draft version of document no. 177000-600 with
         revision identification F dated 29 june 1979
         and revised with DCN G5 of 26. sept. 1980.

  c.     An amplification of the TARE protocols were
         not received.

  d.     A source code listing of the latest TARE front
         end programming were received for information
         only as SHAPE document no. 32.

  e.     Appendix 10 to TARE spec. entitled command,
         report and rejection message format data were
         not received by CR A/S.

2.       The cover letter on ref. a) para 5 indicates
         that CR should be in possession of the relevant
         documentation.

  We like to correct this incorrect statement.

  CR has for a long period worked as a subcontractor
  to Litton performing the EDC protocol. Cr has, however,
  not been involved in the decission taking around the
  changes to the protocol.

  Now the changes are no longer performed by CR. CR therefore
  has no knowledge about the status of the EDC protocol.
  Therefore the agreed decision in Progress Minutes of
  Meeting no. 2 para 13. As far as the contractual situation
  goes we like to point out that CR has the contract
  with SHAPE and not with Litton.

  If the changes to the EDC protocol shall be properly
  implemented by CR (if any) we can only recommend that
  the proper configuration management procedures are
  followed.

3.       It was further established at the contract negotiation
         and revised in minutes of the 2nd CAMPS Progress
         Meeting 19/20 June para 13, that the contractual
         baseline for the NICS TARE I/F was the documents
         handed over to CR on or before 30 august 1980.
         The baseline document is therefore: 177000-600
         revision identification F and further revised
         by DCN G2 of 15 february 1980.

4.       The latest version of the TARE EDC protocol
         (Appendix 30) therefore represents a change
         to requirements baseline and we request SHAPE
         to submit a request for change proposal in accordance
         with the procedures set forth in the CAMPS contract.


kind regards,

CHRISTIAN ROVSING A/S

gert jensen