⟦98832b764⟧ Wang Wps File

    Length: 21666 (0x54a2)
    Types: Wang Wps File
    Notes: Supp. by ILS to FIKS      
    Names: »0210A «

Derivation

└─⟦26e1ab804⟧ Bits:30005814 8" Wang WCS floppy, CR 0001A
    └─ ⟦this⟧ »0210A « 

WangText





…02…OE/801030…02……02…#

…02……02……02…ILS












                    STATEMENT OF WORK


            Support by ILS to the FIKS Project



                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



   1  SCOPE.......................................   4

   2  SITE PREPARATION, TRANSPORTATION
        AND INSTALLATION............................ 
  5 to 16

…02……02…2.1  SCOPE...................................   5
…02……02…2.2  DELIVERY SCHEDULE.......................   5
…02……02…2.3  WORK BREAK DOWN.........................   5
…02……02…2.4  SITE SURVEYS............................   6
…02……02……02…2.4.1  Survey Planning.....................   6
…02……02……02…2.4.2  Accomplishment of Site Surveys......   6
         2.4.2.1  ILS Responsibilities Concerning
                  Site Surveys ...................   6
         2.4.2.2  FIKS Responsibilities Concerning
                  Site Surveys ...................   7

…02……02……02…2.4.3  Preparation of Site Surveys.........   8
         2.4.3.1  ILS Responsibilities ...........   8
         2.4.3.2  FIKS Responsibilities ..........   9

…02……02…2.5  INSTALLATION PLANS......................  10
…02……02……02…2.5.1  General.............................  10
…02……02……02…2.5.2  Delivery of Data to ILS.............  10
         2.5.2.1  Delivery of Data From FIKS .....  10
         2.5.2.2  Delivery of Data from AMC ......  11
         2.5.2.3  Changes to Data Delivered ......  11
         2.5.2.4  Preparation of Installation
                  Plans ..........................  11

…02……02…2.6  ACTIVITIES DURING THE SITE PREPARATION
            PERIOD.................................. 
 12
…02……02…2.7  SITE VERIFICATION.......................  13
…02……02……02…2.7.1  Effort Break Down...................  14

…02……02…2.8  AS-INSTALLED DOCUMENTATION..............  14
…02……02……02…2.8.1  Drawings/Documents to be prepared...  14

…02……02…2.9  TRANSPORTATION..........................  14
…02……02……02…2.9.1  Packing.............................  15
…02……02……02…2.9.2  Shipping Documents..................  15

…02……02…2.10 SITE INSTALLATION.......................  15
…02……02……02…2.10.1 General.............................  15
…02……02……02…2.10.2 Hardware Test.......................  16
…02……02……02…2.10.3 FIKS Support concerning installation  16



   3  MANUALS AND HANDBOOKS ......................  17

   4  TRAINING ...................................  18

   5  MANUALS AND HANDBOOKS (N/A) ................  19

   Appendix A:  Schedule of Deliverables .........  20
   to 24



                         1̲ ̲ ̲S̲C̲O̲P̲E̲



         This document defines the work performed by ILS in
         support of the FIKS project.  Change in the scope of
         work may be made in the future with appropriate change
         of statement of work as well as budget.


           2̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



2.1      S̲C̲O̲P̲E̲

         ILS will deliver material and services to FIKS concerning
         site preparation and site installation in accordance
         with the requirements stated in this section

         Definitions/abbreviations:

         ILS         Integrated Logistic Support.
         FIKS        FIKS Project Group.
         Contractor  CR.
         Customer    AMC.



2.2      D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲

         The schedule of deliveries from ILS as well as FIKS
         are contained in Appendix A.



2.3      W̲O̲R̲K̲ ̲B̲R̲E̲A̲K̲ ̲D̲O̲W̲N̲

         a)  The effort is divided into the following work packages:

             1)  Site surveys

             2)  Installation plans

             3)  Activities during the site preparation period.

             4)  Site verification

             5)  As-installed documentation

             6)  Transportation

             7)  Site Installation





2.4      S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲



2.4.1    S̲u̲r̲v̲e̲y̲ ̲P̲l̲a̲n̲n̲i̲n̲g̲

         a)  A visit to each site is planned to take place As
             stated in appendix A.

         b)  Details concerning each visit and sequence of sites
             will be subject to coordination between ILS/FIKS
             and AMC.



2.4.2    A̲c̲c̲o̲m̲p̲l̲i̲s̲h̲m̲e̲n̲t̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         The purpose of site surveys is to gather information
         necessary to prepare the installation plans and to
         verify AMC delivered documents/drawings.



2.4.2.1  I̲L̲S̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲i̲e̲s̲ ̲C̲o̲n̲c̲e̲r̲n̲i̲n̲g̲ ̲S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         ILS responsibilities will comprise the following tasks:

         1)  To determine/verify the physical location of each
             piece of equipment in cooperation with customer.

         2)  To determine runs of all interface cables to AMC
             equipment and runs of all interconnecting cables
             between FIKS equipments. It will be decided whether
             or not the cables is to be runned in cable ducts.
              The contractors and customers responsibilities
             concerning the cabling will be discussed and clarified.

         3)  To investigate existing or planned environmental
             control facilities.

         4)  To investigate requirements to power installations.
              The quantity, type and location of utility outlets
             in conjunction with major equipment locations will
             be considered.



         5)  To investigate requiremens to grounding sytems.
              A terminal or jack near to each piece of major
             equipment is to be provided by AMC.  The survey
             team will investigate location and type of this
             terminal or jack.

         6)  To verify the access routes, along which major
             equipments have to be moved from entrance to installation
             area.  The smallest dimension is to be measured
             and compared with the largest piece of equipment.

         7)  To verify EMI/RFI and other requirements to the
             installations and to determine restrictions or
             limitations, if any, to the installation work to
             be performed.

         8)  To establish an interface to the FIKS responsible
             site personnel and to get an agreement on site
             facilities and support required for ILS and FIKS
             to perform work on site, such as:  receiving of
             equipment and spares, handling support, temporary
             storage, access and on site facilities and services
             for ISL/FIKS personnel, on site laison etc.

         9)  To discuss and clarify the on site responsibilities
             of contractor and customer.

         10) To complete the site survey questionnaire developed
             by ILS.



2.4.2.2  F̲I̲K̲S̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲i̲e̲s̲ ̲c̲o̲n̲c̲e̲r̲n̲i̲n̲g̲ ̲S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         FIKS will participate in the surveys with one representative
         who is confident with all details of the FIKS system
         concept and hardware configuration.  The respresentative
         will participate in the tasks outlined in para 2.4.2.1
         above.





2.4.3    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲



2.4.3.1  I̲L̲S̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲i̲e̲s̲

         The following task/documents shall be accomplished
         by ILS prior to site survey:

         1)  A site survey questionnaire and checklist which:

             -   Identifies all inspections, examinations and
                 verifications to be carried out during the
                 survey.  It shall further describe all areas
                 of decisions to be taken during the visits
                 (location of major equipment, runs of cables,
                 power, logistic support etc.).

             -   Lists all questions concerning transport, access
                 to site, access to rooms allocated for FIKS,
                 physical characteristics of FIKS rooms, data
                 concerning installation etc.

             This document shall be reviewed by FIKS.

         2)  A set of facility drawings for each site will be
             provided by FIKS/AMC prior to each site survey.
              The facility drawings shall contain all informations
             which have impact on FIKS equipment installation
             with regard to:  Access routes, corridors and passage
             ways between FIKS equipment rooms, room dimensions,
             customer installed equipment, power and power installations,
             ventilation, environmental data, EMI/RFI requirement
             to FIKS equipment installations (including ground
             and ground installations), mounting requirements,
             if any.

             The adequacy of these facility drawings will be
             verified during the site survey.  The drawings
             will be reviewed prior to site survey and if necessary
             supplementary drawings must be requested by ILS
             at each site visit.

         3)  Based upon the facility drawings and the data delivered
             by FIKS (described in para 2.4.3.2 below) ILS will
             work out preliminary requirements to sites concerning
             site preparation.



             Final site preparation requirement will be delivered
             after site survey as part of the installation plans.



2.4.3.2  F̲I̲K̲S̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲i̲e̲s̲

         The following task/documents will be accomplished by
         FIKS prior to site surveys:

         1)  Physical characteristics of equipment to be installed.
              The data will cover the following items:  equipment
             type, QTY, dimensions, weight, power consumption/heating
             (KVA/KW), floor space, floor load, clearance dimensions,
             mounting requirements, grounding requirements,
             power and signal interface (types of plugs and
             jackets), including EMI/RFI equipment data and
             shock/vibration data.  (Equipment will include
             furniture and test equipment).

         2)  Hardware configurations for each main site (node/mede)
             with associated comcenters, SCC's and remote terminals/centers.
              The approximate distance between centers shall
             be included together with all customer furnished
             equipment connected to FIKS equipment at these
             centers.  Type and quantity of all external interface
             cables and interconnecting cables between equipment
             shall be given.

         3)  Special requirements to site or other pertinant
             data to be discussed or questioned during the site
             surveys and, therefore, to be incorporated in the
             site survey questionnaire.

             ILS will accept that the above data are preliminary.
              Final data will be delivered in time for preparation
             of the installation plans.





2.5      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲S̲



2.5.1    G̲e̲n̲e̲r̲a̲l̲

         a)  The installation plans will comprise site preparation
             requirements and hardware installation drawings.
              The plans are to be delivered in accordance with
             Appendix A.

         b)  The plans will be reviewed and approved by FIKS/AMC.

         c)  The site preparation requirements should describe
             all works that need to be accomplished by AMC to
             prepare the site for contractors equipment installation.

         d)  The hardware installation drawings shall show how
             all major equipment at each location are to be
             installed and integrated.



2.5.2    D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲t̲o̲ ̲I̲L̲S̲



2.5.2.1  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲F̲I̲K̲S̲

         a)  Preliminary equipment characteristics and hardware
             configuration will be delivered by FIKS prior to
             site surveys as described in para 2.4.3.2.

         b)  Final equipment characteristics and hardware configuration
             will be delivered by FIKS 3 months prior to scheduled
             submission of installation plans.  This delivery
             will further include:

             -   cable inter connection diagrams showing cable
                 numbers, reference designators of plugs and
                 jackets.

             -   wire list for all power and signal cables,
                 if applicable.

             -   cross connection frames and patch panels details,
                 if applicable.



         c)  The data described above might be changed by the
             EMI/RFI measurements performed by AMC prior to
             site installation.  FIKS will incorporate such
             changes before final delivery of above data.



2.5.2.2  D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲D̲a̲t̲a̲ ̲f̲r̲o̲m̲ ̲A̲M̲C̲

         FIKS will ensure that final data will be delivered
         to ILS as scheduled in Appendix A for the preparation
         of installation plans.  The data will include:

         a)  Additional data requested by ILS during or after
             site survey.  (An earlier delivery date might be
             negotiated during the survey).

         b)  EMI/RFI site design data.

         c)  A set of final facility drawings updated with the
             changes caused by the EMI/RFI measurements performed
             by AMC.

         d)  Interface characteristics including type of mating
             connector and cable for all customer furnished
             equipment to be interconnected to FIKS.



2.5.2.3  C̲h̲a̲n̲g̲e̲s̲ ̲t̲o̲ ̲D̲a̲t̲a̲ ̲D̲e̲l̲i̲v̲e̲r̲e̲d̲

         Until the final delivery of data from FIKS and AMC,
         ILS will incorporate the changes in his documentation
         with no impact on cost and schedule.



2.5.2.4  P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲l̲a̲n̲s̲

         a)  The following data will form the basis for preparing
             the installation plans:

             1)  The facility drawings

             2)  The site survey report



             3)  The equipment characteristics and hardware
                 configuration

             4)  Additional information obtained after site
                 survey.

         b)  The documentation to be prepared will include:

             1)  Site layout with major equipment (racks, VDU,
                 printers etc.)

             2)  Cable runs of all interface cables and interconnecting
                 cables to be installed and cable ducts if applicable.
                  Cable number, and reference designator of
                 connectors shall be shown.

             3)  Air conditioning requirements

             4)  Power installation requirements and interfacing

             5)  Grounding requirements and interfacing

             6)  Wire lists of all power and signal cables,
                 if applicable

             7)  Cross connection frames and patch panel details,
                 if applicable

             8)  Equipment layout of each piece of major equipment
                 with all interface connectors, weight, clearance
                 dimensions, power consumption, mounting details
                 etc., if applicable.



2.6      A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲ ̲D̲U̲R̲I̲N̲G̲ ̲T̲H̲E̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲P̲E̲R̲I̲O̲D̲

         a)  The site preparation period will commence with
             ILS delivery of installation plans for the first
             site.

         b)  During this period, efforts is on final coordination
             and liason in connection with site preparation
             in addition to delivery of installation plans and
             installation at sites.



         c)  FIKS/AMC will issue approval or a list of deficiences
             of the drawings within 15 days after receipt.

         d)  All changes submitted by AMC resulting from the
             site preparation as well as design modification
             to FIKS equipment will be recorded by ILS for later
             update of the master documentation file at time
             of delivery of as-installed documentation.



2.7      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         a)  The verification of each site is scheduled to take
             place as stated in Appendix A.

         b)  The verification shall prove if the site is ready
             for installation of the FIKS equipment.

         c)  The proving will consist of inspections and tests
             according to a site verification procedure.

         d)  The procedure will be prepared on the basis of
             the installation plans, AMC provided facility drawings
             and equipment description.

         e)  Test reports proving correct functioning of the
             AMC installed equipment and lines shall be reveiwed
             during the verification and incorporated in the
             verification report.  FIKS will ensure that AMC
             is informed of this task.

         f)  The procedure is to be signed off by the participants
             and issued as a site verification report.

         g)  Discrepancies found during the verification will
             be recorded together with corrective actions to
             be taken and completion date of action taken.

         h)  The site is first to be considered ready for installation
             after successfull completion of the verification,
             i.e. major discrepancies may result in a second
             verification.





2.7.1    E̲f̲f̲o̲r̲t̲ ̲B̲r̲e̲a̲k̲ ̲D̲o̲w̲n̲

         a)  The following will participate in each site verification:

             -   One ILS representative
             -   One FIKS      -       
             -   One AMC       -       

         b)  Preparation of a site verification procedure to
             be approved by FIKS.



2.8      A̲S̲-̲I̲N̲S̲T̲A̲L̲L̲E̲D̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲

         a)  As-installed documentation for each site is to
             be delivered in accordance with appendix A.

         b)  The documentation shall show how all major equipment
             at each location have been installed and integrated.

         c)  During site installation a copy of the installation
             plans will be marked up to reflect any deviations.
              The marked up drawings will be reviewed by AMC
             who will ensure approval within 15 days of receipt.



2.8.1    D̲r̲a̲w̲i̲n̲g̲s̲/̲D̲o̲c̲u̲m̲e̲n̲t̲s̲ ̲t̲o̲ ̲b̲e̲ ̲p̲r̲e̲p̲a̲r̲e̲d̲

         The as-installed documentation will comprise up-dated
         installation plans.



2.9      T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲

         a)  FIKS will demount and pack the equipment according
             to a transportation plan to be approved by FIKS.

         b)  FIKS will start demounting and packing one day
             after factory acceptance test is completed.  At
             the same time spares, furnitures, tools and test
             equipment will be ready for packing.  The equipment
             will be transported to each site by truck.





2.9.1    P̲a̲c̲k̲i̲n̲g̲

         The equipment will be packed as follows:

         a)  2 or 3-bay racks are separated and crated on a
             wooden pallet.  Crates, fans, main filters and
             in-rack cabling will remain mounted in the rack.

         b)  Modules and power supplies are demounted and packed
             individually.



2.9.2    S̲h̲i̲p̲p̲i̲n̲g̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲

         Requirements to shipping documentation, if any, wil
         be provided by FIKS in time to be included in the transportation
         plan.



2.10     S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



2.10.1   G̲e̲n̲e̲r̲a̲l̲

         a)  ILS will install the equipment at each site in
             accordance with an installation plan to be approved
             by AMC.

         b)  The installation plan will be prepared after site
             surveys and will discuss the following items:

             1)  ILS organisation to be set up for FIKS installation

             2)  Responsibilities of contractor and customer
                 concerning installation

             3)  Installation tasks to be performed.

         c)  This installation plan shall be incorporated in
             the system integration plan to be prepared and
             submitted by FIKS.

         d)  The installation schedule is listed in Appendix
             A.





2.10.2   H̲a̲r̲d̲w̲a̲r̲e̲ ̲T̲e̲s̲t̲

         a)  The installed hardware will be tested at the completion
             of each site installation.  The test will be carried
             out with M&D software developed by FIKS in accordance
             with a test procedure prepared by FIKS.  The test
             shall verify that the hardware is functioning as
             at time of factory acceptance.  ILS responsibility
             concerning site installation is considered completed
             by this hardware test.  If the hardware test shows
             failures which cannot be solved by ILS within reasonable
             time FIKS will take over and solve the problem.

         b)  The M&D software and test procedure will be delivered
             to ILS for approval at least 4 months prior to
             scheduled installation of the first site.



2.10.3   F̲I̲K̲S̲ ̲s̲u̲p̲p̲o̲r̲t̲ ̲c̲o̲n̲c̲e̲r̲n̲i̲n̲g̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         Installation technicians from ILS shall be trained
         in integration and test of the FIKS equipment by participation
         in all stages of system integration and test at factory.


                      3̲ ̲ ̲M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲



         Not applicable.

         Experienced in-house labor which can be transferred
         to the maintenance section in the warranty period is
         not available. The maintenance function will then require
         a training period commencing March 80. This has proved
         unacceptable to the FIKS project which will consequently
         perform maintenance themselves.



                    4̲ ̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲ ̲(̲N̲/̲A̲)̲



         No training will be performed by ILS under this agreement.



              5̲ ̲ ̲M̲A̲N̲U̲A̲L̲S̲ ̲A̲N̲D̲ ̲H̲A̲N̲D̲B̲O̲O̲K̲S̲ ̲(̲N̲/̲A̲



         No effort in the area of manuals and handbooks will
         be spent by ILS under this agreement.













                        APPENDIX A

                 SCHEDULE OF DELIVERABLES


                          APPENDIX A

                   SCHEDULE OF DELIVERABLES







S̲O̲W̲ ̲R̲E̲F̲      D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲       R̲E̲S̲P̲O̲N̲S̲I̲B̲L̲E̲     D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲

2.4          1̲.̲S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲:                   1980

2.4.3.1(2)   Facility Drawings
             from AMC          FIKS            Week 42

2.4.3.2      Prelim.Equipment
             Data              FIKS            Week 43

2.4.3.1(1)   Site Survey
             Questionaire      ILS             Week 44

2.4.3.1(3)   Prelim.Site Pre-
             paration Require-
             ments             ILS             Week 44

2.4.2        Accomplishment 
             of Site Surveys   ILS/FIKS        Week 4&

2.4.2.1(10)  Site Survey Re-
             ports             ILS             Week 46




S̲O̲W̲ ̲R̲E̲F̲.̲     D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲       R̲E̲S̲P̲O̲N̲S̲I̲B̲L̲E̲     D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲

2.5          2̲.̲I̲n̲s̲t̲a̲l̲l̲.̲P̲l̲a̲n̲s̲                   1980

2.5.2.2(a)   Additional Data
             from AMC          AMC/FIKS        Week 49

2.5.2.2(d)   Interface Cha-
             racteristics      "    "          Week 49

                                               1981

2.5.2.2(b)   EMI/RFI Site
             Design Data       AMC/FIKS        Week 1

2.5.2.2(c)   Final Facility
             Drawings          "    "          Week 1

2.5.2.1(b)   Final Equipment
             Data              FIKS            Week 1

2.5.1(c)     Site Preparation
             Requirements                      1981

             Site No 4         ILS             Week 2

             Site No 5         ILS             Week 2

             Site No 8         ILS             Week 5

             Site No 1         ILS             Week 7

             Site No 6         ILS             Week 9

             Site No 3         ILS             Week 12

             Site No 7         ILS             Week 12

             Site No 2         ILS             Week 16


S̲O̲W̲ ̲R̲E̲F̲      D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲       R̲E̲S̲P̲O̲N̲S̲I̲B̲L̲E̲     D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲


2.5.1(d)     Installation
             Drawings:                         1981

             Site No 4         ILS             Week 9

             Site No 5         ILS             Week 9

             Site No 8         ILS             Week 13

             Site No 1         ILS             Week 15

             Site No 6         ILS             Week 17

             Site No 3         ILS             Week 20

             Site No 7         ILS             Week 20

             Site No 2         ILS             Week 24


2.6          3̲.̲A̲c̲t̲i̲v̲i̲t̲i̲e̲s̲ ̲D̲u̲-                  1981
             r̲i̲n̲g̲ ̲t̲h̲e̲ ̲S̲i̲t̲e̲ ̲P̲r̲e̲-                Week 4 through
             p̲a̲r̲a̲t̲i̲o̲n̲ ̲p̲e̲r̲i̲o̲d̲   ILS             Week 45


2.7          4̲.̲S̲i̲t̲e̲ ̲V̲e̲r̲i̲f̲i̲-                    2 Weeks
             f̲i̲c̲a̲t̲i̲o̲n̲

             All Sites         ILS/FIKS        Prior to
                                               each in-
                                               stall.


2.7(c)       Site Verifica-
             tion Procedure

             All Sites         ILS             Week 7

2.7(f)       Site Verifica-
             tion Reports                      1 Week after 

             All Sites         ILS             Each Verification



S̲O̲W̲ ̲R̲E̲F̲      D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲       R̲E̲S̲P̲O̲N̲S̲I̲B̲L̲E̲     D̲E̲L̲I̲V̲E̲R̲Y̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲


2.8          5̲.̲A̲s̲-̲I̲n̲s̲t̲a̲l̲l̲e̲d̲
             D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲:
                                               1981

2.8(c)       Marked up Draw.   ILS             2 Weeks after
                                               each install.
                                               is completed

2.8.1        Updated Drawings  ILS             8 Weeks after
                                               each install.
                                               is completed


2.9          6̲.̲T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲                  1981

             All Sites         ILS             1-2 Day prior
                                               to start of
                                               each install.

2.9(a)       Transportation
             Plan              ILS             1981
                                               Week 6


2.10         7̲.̲S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲
                                               1980
                               ILS             Week 49

             Hardware Test                     1981
             and M&D Software  FIKS            Week 1

2.10.1(d)    Site Install.   

             Site No 4,Start
             of                FIKS            Week 14
             "    "  5   "     ILS             Week 14
             "    "  8   "     ILS             Week 18
             "    "  1   "     FIKS            Week 20
             "    "  6   "     ILS             Week 22
             "    "  3   "     FIKS            Week 25
             "    "  7   "     ILS             Week 25
             "    "  2   "     ILS             Week 29