⟦98de8ff8a⟧ Wang Wps File

    Length: 5822 (0x16be)
    Types: Wang Wps File
    Notes: CPS/ECP/014 (telex)       
    Names: »1319A «

Derivation

└─⟦3d850f1a5⟧ Bits:30006054 8" Wang WCS floppy, CR 0085A
    └─ ⟦this⟧ »1319A « 

WangText





                     1981-10-16    GJ/am]

to:  shnmo division
     att.: mr. paul f. shey, contracting officer

cc.: lt. col. manfred stoltz, camps program manager
 

fm:  christian rovsing a/s, denmark
     gert jensen

our ref: cps/101/tlx/0357

subject: CPS/ECP/014 revision 1 - Quotation for the
 SHAPE CAMPS Expansion
-----------------------------------------------------------------

1.   Introduction
 ------------
 In reply to the request from SHAPE dated 16. september
 1981, CR hereby submit a proposal covering the expansion
 of the SHAPE site in order to facilitate the NAEW.

2.   Price Quotation
 ---------------
 The cost related to the change is a non-recurring cost.
 The cost is devided into:

 a)  Change of documentation
 b)  Hardware cost
 c)  Testing
 d)  Transportation
 e)  Installation

 The total cost of the change is:…01……01…D. Kr.   884,118,-
               --------------------

2.1  Documentation cost
     ------------------
     This item covers the cost of updating/writing the
     needed ECO's, the Systems Requirements Specification,
     the System Design Specification, and the CR internal
     Assembly Breakdown:…01…D. Kr. 74,400,-…01…-----------------

2.2  The hardware cost
     -----------------
     In order to support the requested extension of
     the SHAPE-site with 1 rack, 2 VDU's, 1 MSP and
     5 spare links the equipment listed below is needed.

     The implementation is based on the assumption that
     the rack is added to the line termination racks
     (rack D,E F) as rack G to form a four-bay rack
     assembly.

1 EMI-rack,                unit price dkr 80,413.00
 total    80,413
2 TDX outlets,             unit price dkr    955.00
 total     1,910
2 cables for outlets,      unit price dkr    530.00
 total     1,060
1 TDX crate,               unit price dkr 16,227.00
 total    16,227
1 TDX power supply         unit price dkr 19,880.00
 total    19,880
1 Adaptor power supply     unit price dkr 19,880.00
 total    19,880
1 BSM-X panel              unit price dkr  4,020.00
 total     4,020
1 BSM-X                    unit price dkr  7,830.00
 total     7,830
2 LTUX-S                   unit price dkr 23,317.00
 total    46,634
1 Fan                      unit price dkr  3,887.00
 total     3,887
1 Power distribution panel unit price dkr  2,295.00
 total     2,296
2 Power cables per site    unit price dkr    656.00
 total     1,312
1 Main switch              unit price dkr  7,247.00
 total     7,247
8 OMDT's CAMAC             unit price dkr 15,499.00
 total   123,992
2000 opto cable            price/m    dkr     53.40
 total   106,800
2 VDU(equipped)Delta 7260C unit price dkr 94,352.00
 total   188,704
1 MSP(equipped)TRACOR
  8000 T                   unit price dkr 84,346.00
 total    84,346
1 Cable Channel assy.      unit price dkr    280.00
 total       280
-------------------------------------------------------------------
Subtotal - H/W                                     
         716,718

2.3  Transportation
     --------------
     Additional Cost                               
     dkr     6,000

2.4  Installation
     ------------
     Additonal cost to change the CWR and the As-to-be-built
     drawing for the SHAPE site                    
     dkr    60,000
     Installation and coordination                 
     dkr    27,000
     ------------------------------------------------------------
     Subtotal                                      
     dkr    87,000

3.       Schedule Impact
     ---------------
     The implementation of the change has the following
     impact on the following line items:

     a)  Site Fabrication and Test, 5.4.4, 5.5.4, 5.6.4,
         5.7.4, 5.8.4, 5.9.4, 5.10.4, 5.11.4, 5.12.4,
         5.13.4, 5.14.4, 5.15.4, 5.16,4 will all be
         delayed 1 month.

     b)  Civil Works Requirements 6.4. (5th - 9th delivery)
         will be delayed 2 -4 weeks,

     c)  Site ATTB drawings 6.5 (2nd - 5th delivery)
         will be delayed 2 -4 weeks).

4.   Bidding Provisions
 ------------------

4.1  Validity
     --------
     The cost and schedule impact stated in 2 and 3
     above are under the assumptions that the order
     is given to CR no later than 1. nov. 1981.

4.2  Delivery
     --------
     The change will be delivered as part of the SHAPE
     site.

4.3  Acceptance Criteria
     -------------------
     The change has no impact on the present acceptance
     baseline. It shall be noted that the total current
     connectivity has been increased by 8.

4.4  Type of proposal
     ----------------
     Firm fixed price proposal.

4.5  Payment Plan
     ------------
     30 percent at approval of proposal
     70 percent of OEM equipment at CR receival
     60 percent of CR equipment at factory acceptance
     10% of CR equipment at site acceptance.

4.6  Of the quoted price Dkr. 350,000 represent cost
     incurred in US dllrs, therefore Dkr 350,000 will
     be payable in US dllrs applying the exchange rate
     valid on 1981-10-13.

5.   Engineering change description
 ------------------------------
 The change consists of adding 1 rack of the type intermediate
 to the SHAPE site. In the rack equipment will be placed
 to support 8 fibre optic links to terminal positions
 in the NAEW building. Here, only 3 of the links will
 be connected to 2 VDU's and 1 MSP. The remaining 5
 links will be left unterminated.

6.   Main Memory
 -----------

 Please be aware that the addition causes an extra consumption
 of memory. Therefore it is important that the main
 memory in the two PUs is expanded by two extra module
 (128K each) in order to maintain performance. This
 memory was quoted in the telex CPS/101/tlx/0352.

7.   Comments
 --------

7.1  Pls. observe that the devaluation of the BFR should
     be taken into account when considering the budget
     constraints.

7.2  In order to further reduce the cost we suggest
     that you reconsider your request for 8 OMDT-CAMAC
     in view of only 3 peripherals being added and therefore
     only 3 OMDT-CAMAC are strictly needed.

Kind regards,

CHRISTIAN ROVSING A/S

Gert Jensen