DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦9a00e57fa⟧ Wang Wps File

    Length: 745 (0x2e9)
    Types: Wang Wps File
    Notes: Spelunked
    Names: »~ORPHAN37.12«

Derivation

└─⟦9bafbe04c⟧ Bits:30006092 8" Wang WCS floppy, CR 0144A
    └─ ⟦this⟧ »~ORPHAN37.12« 

WangText

ordination of all project ac-
               tivities between operating de-
               partments.


 Internal management cost/schedule procedures produce valid, auditable and timely
 performance reports. Variances from budget and schedule are quckly identified, and
 significant deviations are flagged for immediate project management attention and
 corrective action.

 Technical supervision and monitoring are effected by periodic design reviews with
 hardware and software engineering managers


         The primary management controls are based on a well-planned
         WBS, master schedule and budget. Firm baselines established
         early in the project provide the basis for management.

         Th