    Notes: Minutes of Meeting No. 8  
    Names: »0978A «

Derivation

└─⟦3eaaffc64⟧ Bits:30006034 8" Wang WCS floppy, CR 0057A
    └─ ⟦this⟧ »0978A « 

WangText





…02…MEETING No. 8

…02… GJ/810521…02……02…#

…02……02…CAMPS











                           
…02……02……02……02…         …02…81-05-21…02…  8. …02…CR A/S
                                       

         …0e…Minutes of Meeting held at CR facility on 19 to 21
         of May 1981.…0f…

  …0f…SHAPE…0e…

  Mr. D.A. Gardiner      Mr. G. Jensen           
  Mr. J. Herrinck        Mr. B. Rinhart
  Mr. J. P. Lohisse      Mr. K. Nybroe-Nielsen
                 …02…     
                      
                                               …06…1  …02…      …02…   …02…
   …02…   …02…                …02…                          







         1.  H̲a̲r̲d̲w̲a̲r̲e̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲

          CHRISTIAN ROVSING stated that in accordance with the
          Contract special clauses 14.5 and 17.3 Hardware could
          be delivered to the sites prior to completion of the
          240 Hrs. In-Plant software verification.



         2.  R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

          A revised version of TCN/024 was presented. SHAPE
          commented on different aspects outlined in CAMPS Log
          No. 166, 239 which were approved for correction by
          CR.

          -  CR confirmed the following approval of this document.

          -  CR will provide a draft contract amendment including
             a CDRL.

          -  SHAPE confirmed that no independent V24 connections
             are needed for the MARARMED/SUBMED site. For this
             site there will be one VDU and MSP wired via a
             metalic V24/V28 connection.





  3.     Q̲A̲/̲Q̲C̲ ̲f̲o̲r̲ ̲m̲a̲j̲o̲r̲ ̲s̲u̲b̲c̲o̲n̲t̲r̲a̲c̲t̲

         CR inform SHAPE of the fact that a subcontract
         exist for the procurement of the tempest Racks,
         conclusive negotiations is also presently taking
         place. Therefore it is agreed that CR will forward
         a letter to SHAPE stating the address, the contract
         No., the QA/QC level and authority, and their
         willingness to provide the copy of the specification
         and contract to the National QA/QC authorities.

         SHAPE in his tasking instruction to DCASO shall
         specify that the use of DD250 is requested for
         each lot of equipment.



  4.     P̲l̲a̲n̲n̲i̲n̲g̲

         CR confirmed that a PERT-like activity diagram
         would be derived from the Master Schedule to
         represent the higher level activities and dependancies.
         This activity will be one of the first tasks
         for the newly appointed CAMPS Planner (Jan Holm
         1.7).

         The lower level schedules will be represented
         by means of milestone charts and controlled
         by means of dependancy/deliverables lists.



  5.     P̲r̲e̲l̲i̲m̲i̲n̲a̲r̲y̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲v̲i̲e̲w̲ ̲(̲P̲r̲o̲p̲o̲s̲a̲l̲)̲

         The PDR will consist of a series around 10 internal
         design reviews.

         CR is willing to accept the participation of
         SHAPE at CR during these reviews. The reviews
         will take place over a period of one month commencing
         the 22nd June.

         A diagram representing the PDR activity is shown
         in fig. 1.

         The SHAPE engineers will work in parallel with
         the CR internal review team and the SHAPE DN's
         will be taken along with the internally generated
         DN's at the internal review meeting.

         Subsequent to the PDR, a progress meeting will
         be held at which the results of the PDR will
         be presented.




  6.     During the first week of June CR will submit
         to SHAPE a proposal for the introduction of
         formal QA with respect to software.

         The proposal will be based on the understanding,
         that changes to CR's present procedures should
         be kept at a minimum and that full benefit in
         terms of cost and schedule should be derived
         from the formal QA inspection.