DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦aedac5d93⟧ Wang Wps File

    Length: 33544 (0x8308)
    Types: Wang Wps File
    Notes: CAMPS INST. PLAN          
    Names: »0569A «

Derivation

└─⟦c36200119⟧ Bits:30006003 8" Wang WCS floppy, CR 0038A
    └─ ⟦this⟧ »0569A « 

WangText

                                  …00……00……00……00…%…0a……00……00…%…0b…%
%…07…$…0c…$…01…$…02…#…09…#…0e……86…1                                              …02…           …02…   …02…         

…02…CPS/PLN/005

…02…KM/810826…02……02…#
CAMPS INSTALLATION PLAN
…02…Issue 3…02…CAMPS








                 T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



   1   SCOPE AND PURPOSE ............................
        5 

   2   ORGANIZATION .................................
        5 
     2.1 INSTALLATION SECTION........................
          5 
       2.1.1 CAMPS Site Preparation .................
              6 
       2.1.2 CAMPS Site Installation ................
              8 
       2.1.3 CAMPS Site Transportation ..............
              9 

   3   CR/SHAPE RESPONSIBILITIES ....................
        9 
     3.1 SITE PREPARATION AND VERIFICATION ..........
         10 
       3.1.1 Site Surveys ...........................
             10 
       3.1.2 Civil Works Requirements ...............
             10 
       3.1.3 As-To-Be-Built Drawings ................
             11 
       3.1.4 Delivery of Signal Cables ..............
             12 
       3.1.5 As-Built Drawings ......................
             12 
       3.1.6 Site Verification ......................
             12

     3.2 INSTALLATION ...............................
         13 
       3.2.1 Main Sites .............................
             13 
       3.2.2 Remote Tares ...........................
             14 
       3.2.3 Remote Terminals .......................
             15 

   4   SITE IMPLEMENTATION MILESTONES ...............
       20 
     4.1 SITE SURVEYS ...............................
         20 
     4.2 CIVIL WORKS REQUIREMENTS (CWR) .............
         20
     4.3 AS-TO-BE-BUILT DRAWINGS ....................
         20 
     4.4 DELIVERY OF SIGNAL CABLES ..................
         22
     4.5 SITE VERIFICATION ..........................
         22
     4.6 SITE INSTALLATION ..........................
         22

   5  SITE PREPARATION AND INSTALLATION TASKS .......
   22
     5.1 SITE PREPARATION ...........................
         23
       5.1.1 SITE SURVEYS AND SITE VISITS ...........
             23
       5.1.2 CIVIL WORKS REQUIREMENTS (CWR) .........
             24
       5.1.3 AS-TO-BE-BUILT DRAWINGS ................
             25
       5.1.4 DELIVERY OF SIGNAL CABLES ..............
             27
       5.1.5 AS-BUILT DRAWINGS ......................
             27
     5.2 SITE VERIFICATION ..........................
         27




     5.3 INSTALLATION ...............................
         29 
       5.3.1 Preparation of Installation ............
             29 
       5.3.2 Shipment of Equipment ..................
             29 
       5.3.3 Installation at Remote Locations .......
             30 
       5.3.4 Installation Phase Activities ..........
             30 



                  L̲I̲S̲T̲ ̲O̲F̲ ̲F̲I̲G̲U̲R̲E̲S̲



     2.1 CAMPS INSTALLATION ORGANIZATION AND TASKS...
          7 

     3.1 TYPICAL CAMPS ROOM LAYOUT ..................
         16 
     3.2 CABLE CONNECTIONS AT A TYPICAL MAIN SITE ...
         17 
     3.3 COLLOCATED TARE, TYPICAL COMMUNICATION
         LINK .......................................
         18 
     3.4 REMOTE TARE, TYPICAL COMMUNICATION LINK ....
         19 

     4.1 SITE IMPLEMENTATION MILESTONES .............
         21 

     6.1 INSTALLATION PHASE ACTIVITY AT A 
         TYPICAL SITE ...............................
         33 



                   1̲ ̲ ̲S̲C̲O̲P̲E̲ ̲A̲N̲D̲ ̲P̲U̲R̲P̲O̲S̲E̲



         This plan outlines the various tasks to be accomplished
         concerning site preparation and installation.  It describes
         how CR intends to manage and perform the job and outlines
         the responsibilities of CR and SHAPE/host nation concerning
         installation.  Milestones of the site implementation
         schedule have been identified and an analysis of the
         site installation task is performed.









                     2̲ ̲ ̲O̲R̲G̲A̲N̲I̲Z̲A̲T̲I̲O̲N̲



2.1      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲E̲C̲T̲I̲O̲N̲

         a)  The Installation Section is the section within
             the Logistic Department responsible for CAMPS site
             preparation and installation.  The Installation
             Section Manager will report directly to the Logistic
             Department Manager.  The Logistic Department Manager
             will coordinate the Installation Section activities
             with the CAMPS Project Office.  See Figure 2.1.

         b)  The Installation Section is responsible for the
             interface between PAB and the CAMPS Site Installation
             Subsection.





2.1.1    C̲A̲M̲P̲S̲ ̲S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲

         a)  The Systems Division has contracted with a Norwegian
             company, Ingeni]r P.A. Bakkejord A/S (PAB) to perform
             the following tasks on the CAMPS program:

             1.  Perform Site Survey
             2.  Prepare Site Civil Works Requirements
             3.  Prepare As-To-Be-Built Drawings
             4.  Perform Site Verification
             5.  Prepare As-Built Drawings

         b)  PAB is the contractor representative for CR and
             should be treated as such by SHAPE when performing
             the above tasks.  CR will maintain overall responsibility
             for completion of these tasks and will review PAB's
             work prior to its submission to SHAPE.

             PAB will perform the work under supervision and
             control of the installation section.

         c)  Communication between PAB-CR-SHAPE will be as follows:

             1)  PAB will transmit all documentation and correspondance
                 intended for SHAPE to CR for approval.  CR
                 will, by return telex, issue approval to PAB.
                  PAB will then transmit documentation or correspondance
                 to SHAPE.

             2)  SHAPE will transmit documentation and correspondance
                 to CR.  Only if CR explicitly express so SHAPE
                 will transmit to PAB directly.




















































   Figure 2.1…01…CAMPS INSTALLATION ORGANIZATION AND TASKS



2.1.2    C̲A̲M̲P̲S̲ ̲S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         a)  This subsection is responsible for CAMPS site installation
             planning and CAMPS equipment installation.  An
             important area in this respect is site design performed
             in conjunction with PAB. 

         b)  The installation of CAMPS equipment will be performed
             by 2 teams.  Each team will be composed of a team
             leader and 2 installation technicians. As a back
             up 2 technicians will be available at CR's plant
             to relieve a team member in case of sickness, vacation
             etc.  The back-up will also be used for the installation
             of some of the main sites where more than one remote
             terminal site is connected, and for some of the
             remote TARE sites located far  from the main sites.
              The team leaders will report to the manager of
             the CAMPS site Installation subsection.

         c)  The team will install a complete site and be organized
             so that each member will be responsible for specific
             tasks, within the installation program.  All members,
             however, will be trained in all tasks of the program
             so they can substitute for each other if necessary.

         d)  The team leaders will be experienced in the installation
             of electronic data processing Systems and will
             be capable of working without close supervision.

         e)  The technicians will be experienced in the installation
             of computer equipment.  They will be trained in
             CAMPS installation by participating in all stages
             of integration and test at CR's plant up to factory
             acceptance of systems.

         f)  The installation team will be specially trained
             in optical fibre technics and will be familiar
             with the use of maintenance and diagnostic software.





2.1.3    C̲A̲M̲P̲S̲ ̲S̲i̲t̲e̲ ̲T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲

         a)  This subsection will contract with a transportation
             company to perform all tasks associated with the
             shipment of CAMPS equipment from CR factory to
             each sites.

         b)  This subsection will plan and coordinate the shipments
             with the transportation company and will issue
             the procedures and instructions to be followed
             concerning packing, marking, and documentation.

         c)  Invoicing, insurance, and notice of shipment will
             be the responsibility of the CAMPS project office.

         d)  Packing, marking, and documentation will be performed
             by the CAMPS Transportation subsection and controlled
             by the Quality Assurance Department of the Systems
             Division, (see figure 2.1).  This department will
             also approve the procedures per b) above.









               3̲ ̲ ̲C̲R̲/̲S̲H̲A̲P̲E̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲



         The following outlines CR's and SHAPE's/Host Nations
         responsibilities concerning site preparation and installation.
          It translates the requirements of the contract into
         specific responsibilities to be performed by each organization.





3.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



3.1.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲

         a)  Prior to the site survey, SHAPE will furnish all
             available site documentation to the contractor
             to support his pre-survey planning.  If additional
             documentation (i.e. other than that furnished prior
             to the survey) is available at the site during
             the survey, SHAPE will insure that it is furnished
             to the contractor.

         b)  CR will perform site surveys in conjunction with
             SHAPE.  SHAPE will assist CR in collecting relevant
             information and site documentation during the surveys
             for the preparation of civil works requirements
             (CWR) and as-to-be-built drawings.

         c)  At least one of SHAPE representatives on each site
             survey team will be authorized to make decisions
             and to sign a survey protocol on behalf of SHAPE.

         d)  During the site survey, the contractor will gather
             all information needed for preparation of Civil
             Works Requirements, As-To-Be-Built Drawings, and
             As-Built Drawings.  The contractor will also provide
             general CAMPS system information to the Host Nation
             to support the Host Nation's preliminary design
             of site preparation works.



3.1.2    C̲i̲v̲i̲l̲ ̲W̲o̲r̲k̲s̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲

         a)  CR will deliver civil works requirements (CWR)
             not later than 12 months prior to the installation
             start date for each site for SHAPE's approval.
              SHAPE will issue approval or a list of deficiencies
             within 15 work days of receipt.  The CWR will be
             used by host nation to prepare the CAMPS designated
             space for CR to install the equipment.



         b)  The contractor's planning baseline for preparation
             of Civil Works Requirements is the site survey.
              If SHAPE advises the contractor of site modifications
             accomplished after the site survey, the contractor
             will incorporate these changes into his Civil Works
             Requirements provided that he is notified of the
             changes no later than 3 months prior to either
             the contractually specified submission date or
             the actual submission date, whichever is later.

         c)  If available, SHAPE will deliver additional site
             documentation, requested by CR and updates to the
             site documentation supplied during the site surveys.
              Last submittal of data from SHAPE/Host Nation
             is 3 months prior to CR's submittal of CWR.

         d)  A detailed description of the contents of the CWR
             is contained in Chapter 5.



3.1.3.   A̲s̲-̲T̲o̲-̲B̲e̲-̲B̲u̲i̲l̲t̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  CR will deliver As-To-Be-Built Drawings to SHAPE
             for approval not later than 9 months prior to the
             installation start date for each site.  SHAPE will
             issue approval or a list of deficiencies within
             15 work days of receipt.  The approved drawings
             will be used for installation of the CAMPS equipment.

         b)  The approved Civil Works Requirements and the equipment
             characteristics are the Contractor's planning baseline
             for his preparation of As-To-Be-Built drawings.
              SHAPE is responsible of ensuring that any site
             modifications made after Civil Works Requirements
             approval are identified to the contractor for his
             incorporation into the As-To-Be-Built Drawings.
              The contractor shall so incorporate these changes
             in the As-To-Be-Built Drawings provided the changes
             are identified to him not later than 2 1/2 month
             prior to either the contractually specified submission
             date or the actual submission date, whichever is
             later.

         c)  A detailed description of the contents of As-To-Be-Built
             Drawings are contained in Chapter 5.





3.1.4    D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲S̲i̲g̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲

         CR will deliver, 6 months prior to start of installation,
         fiber optical cables for user terminals to be run by
         Host Nation, with the necessary installation documentation.



3.1.5    A̲s̲-̲B̲u̲i̲l̲t̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  During site installation, a copy of the As-To-Be-Built
             Drawings will be marked up to reflect any deviations,
             and a copy submitted to SHAPE for approval by ACE
             COMSEC.  The approved marked up drawings will be
             delivered as preliminary as built drawings at time
             of SPA.

         b)  Final As-Built drawings will be delivered 3 months
             after preliminary.



3.1.6    S̲i̲t̲e̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲

         a)  CR will perform a verification of each site's readiness
             for installation.  SHAPE will participate.

         b)  SHAPE will notify CR of a site's readiness no less
             than 30 calendar days prior to the anticipated
             date the site will be ready.  Once SHAPE certifies
             that a site is ready for installation, CR will
             be required to verify that the site is acceptable
             within fourteen calendar days of a formal request
             by SHAPE to accomplish the verification.  This
             inspection date may be modified by mutual agreement
             of SHAPE and CR.





3.2      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



3.2.1    M̲a̲i̲n̲ ̲S̲i̲t̲e̲s̲

         a)  CR will provide and install the contractual number
             of computer racks, frequency stabilizers, supervisor
             positions and maintenance positions in the room
             designated as the CAMPS equipment room.  (Refer
             to Figure 3.1).

         b)  CR will provide and install all signal cables between
             racks, between racks and maintenance position and
             between racks and supervisor positions.  (Refer
             to Figure 3.2). Host Nation will install all signal
             cable ducts in the CAMPS Equipment room identified
             in the CWR.

         c)  Host Nation will be responsible for power and ground
             installations.  The CWR will contain CR's requirements
             to these installations.

         d)  CR will connect the above equipment to power outlets
             and ground connection points installed by Host
             Nation.

         e)  CR will provide and install the user terminals
             in the rooms specified by Host Nation; connect
             the signal cables to the terminals and connect
             the terminals to the power outlets and ground connection
             points installed by Host Nation. These power outlets
             and ground connections will be specified in the
             CWR.

         f)  Host Nation will install the cable ducts and run
             the cables from the CAMPS equipment room to each
             user terminal.  CR will supply the signal cables
             (OPTO) and installation instructions.



         g)  Host Nation will provide and install cables for
             low speed lines CCIS, SCARS and collocated TARE
             connections.  Collocated TARES, (see fig. 3.3.)
              Low speed lines, CCIS and SCARS cables will be
             terminated at the IDF by Host Nation (the IDF is
             located in rack F).  Host Nation will also provide
             and install cable ducting.  



3.2.2    R̲e̲m̲o̲t̲e̲ ̲T̲a̲r̲e̲s̲  (see figure 3.4).



3.2.2.1  M̲a̲i̲n̲ ̲C̲A̲M̲P̲S̲ ̲S̲i̲t̲e̲

         a)  CR will provide and install a rack with modem(s)
             and black patch jack field (BPJF) in a room specified
             by Host Nation.  Host Nation will provide and install
             crypto equipment, crypto rack and red patch jack
             field (RPJF) in a crypto room.

         b)  Signal cables from the IDF (rack F) to the BPJF
             will be provided and installed by Host Nation.
              CR will provide and install signal cables from
             BPJF to MODEM and Host Nation will provide and
             install signal cable from MODEM rack to TCF.

         c)  Host Nation wil install power and ground as specified
             in CWR.  CR will connect MODEM rack to power and
             ground provided.



3.2.2.2  R̲e̲m̲o̲t̲e̲ ̲T̲a̲r̲e̲ ̲S̲i̲t̲e̲

         a)  CR will provide and install a rack with Modem(s)
             and BPJF in a room specified by the Host Nation.
              Host Nation will provide and install crypto equipment,
             crypto rack and RPJF in a crypto room.



         b)  Signal cables from the Tare MDF to the BPJF in
             the Modem rack will be provided and installed by
             Host Nation.  Signal cables from the BPJF to the
             Modem will be provided and installed by CR.  Signal
             cable from the Modem rack to the TCF will be provided
             and installed by Host Nation.

         c)  Host Nation will install power and ground as specified
             in the CWR.  CR will connect Modem rack to the
             power and ground provided.



3.2.3    R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

         T.B.S.
















































                        Figure 3.1



















































                        Figure 3.2



















































                        Figure 3.3


















































                        Figure 3.4


            4̲.̲ ̲S̲I̲T̲E̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲M̲I̲L̲E̲S̲T̲O̲N̲E̲S̲



         a)  Figure 4.1 shows the milestones of the efforts
             to be accomplished during the site preparation
             and installation phase, related to each site.

         b)  Each milestone is represented by a dot and reference
             number.  The referenced efforts are listed at the
             bottom of the figure.

         c)  A discussion of each effort follows.



4.1      S̲I̲T̲E̲ ̲S̲U̲R̲V̲E̲Y̲S̲

         The date each site survey is completed is shown.



4.2      C̲I̲V̲I̲L̲ ̲W̲O̲R̲K̲S̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲ ̲(̲C̲W̲R̲)̲

         The contractual due date is shown.



4.3      A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲

         The contractual due date is shown.


















































        Figure 4.1…01…SITE IMPLEMENTATION MILESTONES



4.4      D̲E̲L̲I̲V̲E̲R̲Y̲ ̲O̲F̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲

         The due date for CR delivery of signal cables (6 months
         prior to start of installation) is shown.



4.5      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         A Site Verification by CR will be performed, when the
         preparation works are completed by the Host Nation.
          One month is scheduled between completion of Site
         Preparation works and start of installation.  The Site
         Verification will take place within this 30 days. 
         The dates shown is the latest time CR would like to
         conduct their site verification.



4.6      S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

         The date scheduled for start of site installation is
         shown.









       5̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲T̲A̲S̲K̲S̲ ̲



         This section describes CR's tasks in connection with
         site preparation and installation.





5.1      S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲

         The site preparation phase can be defined as the time
         span from contract award to completion of site verification.
          During this phase CR's main activities concerning
         site preparation are the development of Civil Works
         Requirements and as-to-be built drawings for each site.
          During the same phase Host Nation's main activities
         are concentrated on completion of the design and construction
         or reconstruction of each site, and preparing the site
         area for installation.



5.1.1    S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲ ̲a̲n̲d̲ ̲S̲i̲t̲e̲ ̲V̲i̲s̲i̲t̲s̲

         a)  CR will perform site surveys in conjunction with
             SHAPE at each site as required.  Refer to section
             3.1.1 for an identification of responsibilities.

         b)  A site survey report will be prepared by CR and
             agreed to by SHAPE and the local command.  This
             report will identify equipment location, equipment
             entry routes, existing and planned power, grounding
             and air conditioning, local facility support etc.
              Action items for outstanding information will
             be included.  A detailed description of this report
             can be found in the CAMPS Project Site Survey Procedure
             and Checklist.

         c)  The information collected during the site survey
             will form the Data Baseline for that site.  Information
             needed by CR for this Data Baseline but not available
             during the site survey will be identified by CR
             and agreed by SHAPE.  SHAPE/Host Nation will forward
             this information to CR to complete this baseline.
              Information collected as part of the Data Baseline
             that subsequently changes must be forwarded to
             CR at least 3 months prior to CR's delivery of
             CWR if it is to be incorporated in this document.

         d)  Revisit to some sites prior to site verification
             may be requested by CR.  Upon notification by CR
             and agreement by SHAPE, such visits will be arranged
             with the local commands by SHAPE.





5.1.2    C̲i̲v̲i̲l̲ ̲W̲o̲r̲k̲s̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲(̲C̲W̲R̲)̲.̲

         a)  CR will provide CWR for each site as identified
             in paragraph 3.1.2.

         b)  The CWR will contain all information needed to
             clearly identify to the Host Nation what civil
             works are required to prepare the site for the
             contractor to install his equipment.

         c)  The CWR will be based on the following information:

             1)  Host Nation drawings/documents handed over
                 to CR during the site surveys or submitted
                 to CR as agreed to during the survey meetings.
                  If available, the drawings/documents should
                 include cable runs outside CAMPS-room and location
                 of user terminals and other equipment which
                 has to be connected to CAMPS.  When this information
                 is not available to CR in time for its inclusion
                 in their CWR and/or  As-To-Be-Built drawings,
                 CR will provide a "typical layout" of a user
                 terminal position specifying space, power and
                 cabling requirements.  SHAPE will attach the
                 final terminal locations within each room and
                 the cable routing information to the CWR and
                 as-to-be-built drawings when it becomes available.

             2)  The information gathered during the surveys
                 and contained in the survey report including
                 the proposed site layouts or an amended site
                 layout if received by CR within 3 months of
                 the CWR delivery date.

             3)  Physical characteristics of the CAMPS equipment,
                 concerning power requirements, air conditioning,
                 power and signal and grounding interface, weight,
                 floor load, envelope dimensions etc.

             4)  The site design concept (CPS/TCN/023) and AMSG
                 719B.

             5)  National regulations and other applicable engineering
                 standards.



         d)  The CWR will cover the following:

             1)  Physical layout of major equipment.

             2)  All cable ducts and conduits in the CAMPS room.

             3)  Record of Host Nation/ACE COMSEC cable runs
                 outside the CAMPS room, if available.

             4)  Requirement of power and grounding systems
                 including number of required power outlets
                 and grounding connection points in conjunction
                 with major equipment.

             5)  Airconditioning requirements.

             6)  Other civil works requirements, if any.



5.1.3    A̲s̲-̲T̲o̲-̲B̲e̲-̲B̲u̲i̲l̲t̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  CR will provide as-to-be-built drawings for each
             site as identified in paragraph 3.1.3.
             These drawings will be used for the installation
             of CAMPS equipment on each site and will be based
             on the following information:

             1)  The site survey report

             2)  The equipment configuration and equipment interface
                 data.

             3)  The CWR.

             4)  The site design concept (CPS/TCN/023) and AMSG
                 719B.

             5)  National regulations and other applicable engineering
                 standards.…86…1         …02…   …02…   …02…   …02…             
                                              


         b)  The A-T-B-B drawings will be prepared to cover
             the following:

             1)  Floor and wall plans showing cable runs within
                 the CAMPS equipment room.  Cable runs must
                 be CAMPS related or have COMSEC implications.
                  Signal cable runs from CAMPS equipment room
                 to user terminals shall be incorporated in
                 the as-to-be-built and as-built documentation.
                  (Information on the routing of the cable-runs
                 will be provided by customer).

             2)  Plan showing grounding system related to CAMPS
                 with description of conductors, electrodes,
                 and joints.  Drawings and specifications to
                 be provided by customer.

             3)  Cable racking and cable runs with cable numbers
                 and cable functions to include as appropriate
                 all terminating point, connections, connectors,
                 and sockets.  The functions of all conductors
                 shall be shown.

             4)  Physical layout (plan and elevation) of all
                 major equipments.

             5)  Ventilation and environmental control systems
                 that impact on COMSEC.  Drawings and specifications
                 to be supplied by customer if installed or
                 modified after site survey.

             6)  Cross-connection frames and patch panel details.

             7)  Power distribution boards, cabling, wiring,
                 and distribution schemes showing position of
                 filters if fitted.  Drawings and specifications
                 to be supplied by customer.

             8)  Ancillary equipment that have COMSEC implications.
                  Drawings and specifications to be provided
                 by customer if installed or modified after
                 site surveys.

             9)  Layout and cable runs of all intercomm equipment
                 having a COMSEC impact relative to CAMPS equipment.
                  Drawings and specifications to be supplied
                 by customer if installed after site surveys.…86…1
                         …02…   …02…   …02…   …02…                         
                                  


             10) All other information necessary for the Purchaser
                 to operate, maintain, and expand or modify
                 the installation.



5.1.4    D̲e̲l̲i̲v̲e̲r̲y̲ ̲o̲f̲ ̲S̲i̲g̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲

         a)  The signal cables to be run by Host Nation from
             IDF (Rack F) to user terminals will be delivered
             at least 6 months prior to site installation  together
             with necessary installation documentation.  The
             signal cables will be supplied on spools.  Host
             Nation will run the cables and cut them in accordance
             with the instructions provided by CR with the spools
             and the information contained in the CWR.

         b)  The correct installation of these cables will be
             verified during site verification.



5.1.5    A̲s̲-̲B̲u̲i̲l̲t̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲

         a)  CR will provide as-built drawings for each site
             as identified in paragraph 3.1.5

         b)  The as-built drawings will be based on the As-To-Be-Built
             Drawings marked up during installation and SPA.
              The contents will be as specified above for As-To-Be-Built
             Drawings.



5.2      S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲

         a)  CR will perform a site verification at each site
             in accordance with paragraph 3.1.6.  It is planned
             that a main CAMPS site with its associated remote
             terminal site(s) and remote TARE site(s) will be
             verified at the same visit.…86…1         …02…   …02…   …02…   …02…
                                                       


         b)  The vereification shall certify that all requirements
             in the CWR have been accomplished and that the
             site is ready for installation of the CAMPS equipment.
              This verification will consist of inspections
             and tests according to a site verification procedure
             to be delivered to SHAPE one month prior to the
             first site verification.  The provisions of AMSG
             719B relative to site preparation should be verified
             by SHAPE/COMSEC prior to or during the site verification.
              The procedure prepared by CR will include:

             1.  An introduction and description of how CR intends
                 to perform the verification.

             2.  A check of the power and grounding (cabling,
                 distribution, outlets) required in the CWR.

             3.  Verification of the access and space required
                 in the CWR.

             4.  Verification of the signal cables run by Host
                 Nation required in the CWR.  Site verification
                 can be accomplished without all user terminal
                 cables installed.  However, when this occurs,
                 SHAPE will be responsible for terminating and
                 connecting those terminals cables not installed
                 prior to CAMPS equipment installation.

             5.  Verification of cable ducting and conduits
                 required in the CWR for the CAMPS room.

             6.  Verification and update of the site support
                 and logistic data (storage, liaison, facilities
                 for the installation team) recorded during
                 the site survey.

         c)  The procedure is to be signed by the participants
             from SHAPE and CR and then issued as a site verification
             report.

             
         d)  Discrepancies found during the verification will
             be recorded together with corrective actions required
             and completion date of action taken.  The site
             is ready for equipment installation upon successful
             completion of the verification.





5.3      I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲



5.3.1    P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         a)  Site representatives will receive information in
             an Installation Procedure on how CR intends to
             install the CAMPS equipment.  This Installation
             Procedure will be prepared by CR and submitted
             to SHAPE for review and forwarding to the site
             two to three months prior to start of installation.
              The information contained in the Installation
             Procedure will be checked during the site verification
             or one month prior to start of installation whichever
             is later.

         b)  Also included in the Installation Procedure will
             be a detailed task schedule which will itemize
             work functions to be performed by CR installation
             personnel at each site.  It will contain descriptions
             of each installation item, the responsible individual
             for each item and when each item should be completed.



5.3.2    S̲h̲i̲p̲m̲e̲n̲t̲ ̲o̲f̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲

         a)  All equipment will be shipped from CR's plant in
             Copenhagen, Denmark.  CR will contract with a transportation
             company to provide the transportation to the sites.
              Generally the equipment will be shipped from Copenhagen
             to a main CAMPS site by truck.

         b)  Equipment destinated for Remote TARES or Remote
             Terminal sites will be transported as part of their
             main CAMPS site shipment.

         c)  CR intends to schedule the shipments so that the
             installation team will be present at the site to
             receive the equipment.

         d)  In order to reduce the effect of slippages of the
             schedule caused by a delay in the installation
             at a previous site, arrangements for local site
             personnel to handle the receipt of the equipment
             will be coordinated with SHAPE as part of the Installation
             Procedure.



         e)  Shipments of signal cables to be run by the Host
             Nation will be sent to the main CAMPS sites.  The
             Host Nation will arrange for further distribution
             to the Remote Terminal Sites.  CR will so mark
             the spools.

         f)  Details on transportation are described in the
             CAMPS Transportation Plan.



5.3.3    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲a̲t̲ ̲R̲e̲m̲o̲t̲e̲ ̲L̲o̲c̲a̲t̲i̲o̲n̲s̲

         T.B.S



5.3.4    I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲h̲a̲s̲e̲ ̲A̲c̲t̲i̲v̲i̲t̲i̲e̲s̲

         Figure 6.1 is an analysis of the installation effort
         to be carried out at a typical site.  A similar analysis
         will be made for each site, when the site configurations
         are finalized and will be a part of CR's installation
         planning.

         A step by step description of figure 6.1 follows:

         Step 1      One week…08…s buffer between sites is planned
                     to allow for the distance between sites,
                     for possible delays in the installation
                     of the previous site and possible delays
                     in the shipment of equipment.  The necessary
                     buffer actually required will be calculated
                     when the final installation sequence is
                     decided. 

         Step 2,3,4  The first 2 days on site will be used to
                     contact site officials, make all necessary
                     arrangements, inspect the installation
                     areas and move in.

         Step 5      Before equipment is brought into the CAMPS
                     room CR will install all signal cables.
                      Cable ducts will already have been installed
                     by Host Nation.



         Step 6      The team leader will spend one or two days
                     to contact site officials, make all necessary
                     arrangements and inspect the installation
                     areas at remote terminal and remote TARE
                     locations.

         Step 7      Racks, terminal equipment and furniture
                     is unpacked, and moved to the CAMPS and
                     CRYPTO-room.  The availability of equipment
                     and manpower at the site has been investigated
                     during the site surveys and recorded in
                     the site survey report.

         Step 8      The signal cables will be terminated and
                     connected.  

         Step 9,10   The user terminals (up to 24) will be installed
                     in the rooms specified by the local commands.
                      The cables (optical fibres) should already
                     have been installed by the Host Nation.
                      The cables will be terminated and connected
                     to the user terminals.  Each terminal will
                     be connected to the power and ground outlet
                     installed by the Host Nation.

         Step 11,12  Both the Remote Terminal installations
                     and Remote Tares are considered here. 
                     Remote terminal installation information
                     will be provided after contract award.
                      The installation task at a Remote TARE
                     location will consist of the installation
                     of 1 modem rack.  The considerable distance
                     to some of the Remote TARE location might
                     require use of extra manpower for their
                     installation.  At each location equipment
                     will be installed and the hardware tested.
                      Final check out test cannot be performed
                     until the main CAMPS site equipment is
                     functioning.  (Step 11, 12 can also be
                     performed after completion of Step 15).
                      Both the installation of remote tares
                     and remote terminals will be further described
                     in the installation procedure.  (See paragraph
                     5.3.1).



         step 13, 14 The equipment in the CAMPS room is
         15          connected to power, modules are unpacked
                     and mounted, and an installation checkout
                     test of hardware is started.  This test
                     is completed at step 18.

         step 16     When the hardware at the Main CAMPS site
                     is functioning a final hardware check out
                     test is performed at the remote location.

         step 17     An inventory check is carried out at the
                     completion of installation with representatives
                     from the site and/or SHAPE.  The inventory
                     check will verify that the equipment is
                     delivered in accordance with the Properity
                     Equipment List.  The inventory check will
                     be further described in the Installation
                     Procedure.

         step 18     A nucleus test is performed to verify that
                     all hardware is functioning.  A test procedure
                     for this nucleus test will be prepared.
                      It will be a subset of the factory acceptance
                     test and will verify that the processor
                     units, the channel unit and TDX units are
                     correctly installed.  Correct installation
                     of terminal connections is also verified.
                      The test is regarded as an informal test
                     to demonstrate that installation is completed,
                     and that the site is ready to be taken
                     over by CR's test team.  This test team
                     will arrive on site when installation is
                     completed to install the site software
                     and conduct the SPA.



















































                         Fig. 6.1