top - download
⟦aff910e0e⟧ Wang Wps File
Length: 18560 (0x4880)
Types: Wang Wps File
Notes: CPS/TCN/070
Names: »3806A «
Derivation
└─⟦f44499b45⟧ Bits:30006204 8" Wang WCS floppy, CR 0303A
└─ ⟦this⟧ »3806A «
WangText
…0a……00……00……00……00……0c……0a……00……00……0c……0b……0c……0e……0a……09……0a……0e……0a……02……86…1 …02… …02… …02…
3806A/rt…02…CPS/TCN/070
…02…NPP/830815…02……02… #
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02…Issue 1…02…CAMPS
…0f…
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP
CPS/TCN/070
Niels Peder Pedersen
Kurt Nybroe-Nielsen
SHAPE (5), KNN, KM, BHB, HAU, NPP, KLA,
CLA, SPN, PLN, QA, Config. Mgr., Library (5)
Install. Mgr. 830815
Issue 1.1
830815
…0e… Conf.Mgmt. 830815
…0f… 3806A/rt …02…CPS/TCN/070
…02…NPP/830815…02……02…ii
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02…Issue 1…02… CAMPS…0e…
1 830610 All Issue 1 of Document
1.1 830815 2, 5, Update according to
7, 11 CAMPS Log No. 1278 and
13 Mock Up Site Survey
MOM
83-07-05.
3806A/rt …02… CPS/TCN/070
…02… NPP/830610…02……02…iii
TYPICAL EQUIPMENT DATA AND REQUIREMENTS
FOR THE CAMPS MOCK UP…02……02… CAMPS
T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
1 INTRODUCTION .................................
1
2 GENERAL DESCRIPTION ..........................
1
2.1 CONFIGURATION ............................
1
2.2 SITE PREPARATION AND INSTALLATION PLANNING
4
2.2.1 Installation Schedule ................
4
3 SITE PREPARATION AND INSTALLATION REQUIREMENTS
4
3.1 RESPONSIBILITIES .........................
4
3.2 EQUIPMENT TO BE INSTALLED ................
5
3.3 FACILITY REQUIREMENTS ....................
6
3.3.1 Access and Dimensions ................
6
3.3.2 Air Cooling .......................... 12
3.3.3 Power ................................ 12
3.3.4 Environmental Specifications ......... 14
APPENDIX A
1̲ ̲ ̲I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
This document contains typical equipment data and requirements
which should support territorial host nations preliminary
site design of the Depot Maintenance Equipment and
Training for CAMPS, hereafter called CAMPS MOCK UP
System.
…01…2̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲
2.1 C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
The CAMPS MOCK UP System Configuration is shown on
figure 2.1-1.
The CAMPS MOCK UP consists of a 3-bay rack containing
both the processor and the line termination units.
The CAMPS MOCK UP has a number of work stations connected.
Each work station is dedicated to a specific repair
or test purpose. The system is managed from the maintenance
position.
The 3-bay rack configuration is shown on figure 2.1-2.
Legend: Notes:
Opto Signal Cables 1 Opto
cables
provided,
installed,
and
terminated
by
CR
Metallic Signal Cables 2 Metallic cables
(Max. length 50 feet) provided, installed,
and terminated by
CR
Flat Cables 3 Metallic cables
(max. length 50 feet) provided, installed,
and terminated by
SHAPE/THN
S Equipment by SHAPE/THN 4 Flat Cables provided,
installed, and
CR Equipment by CAMPS Contractor terminated by CR
Figure 2.1-1…01…CAMPS MOCK UP System…01…Configuration
FIGURE 2.1-2…01…3-Bay Rack Configuration
2.2 S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲N̲I̲N̲G̲
2.2.1 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲
a) The CAMPS MOCK UP will be installed by CR installation
team. The CAMPS Resident Site technician will participate
in the installation.
b) CR will submit Site preparation requirements (SPR)
to SHAPE based on the data obtained during a Site
survey and the equipment characteristics contained
in this document. The SPR will contain requirements
to space, power, access etc.
The Site preparation requirements will be given
to SHAPE as early as possible no later than 5 months
prior to commencement of Site installation. SHAPE
shall issue approval or a list of deficiencies
of the documents within 15 days after receipt.
c) CR will perform a Site readiness inspection at
the start of the installation.
3̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.1 R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲
The Site Preparation and Installation responsibilities
of CR and SHAPE are described in the contract and are
attached as appendix A for information.
3.2 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲T̲O̲ ̲B̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲E̲D̲
a) At each depot CR will provide and install (see
figure 2.1-1 or 3.1-1):
Pos. 1 One CAMPS MOCK UP Computer contained within
three 19" standard racks.
Pos.2-3 One maintenance position consisting of
one VDU and one MSP and one table.
Pos.4-9 Five Work Stations for VDU, DISC, MUX,
PTP/R and V28 L/L adaptor test and repair.
Pos 12 One supervisor position consisting of one
VDU.
b) At each depot SHAPE/THN will provide and install:
Pos.10 One position consisting of one VDU and
one table.
Pos.11 One position consisting of one PTP/R and
one table.
Pos. 12 One table for Supervisor VDU.
Pos.13 One position consisting of one MSP and
one table.
Pos.4-8 Five tables for the Fd, MMD, SMD, MUX and
Crate workstations.
c) The signal cables from CAMPS racks to the maintenance
position and the workstations will be provided,
installed and terminated with connectors as specified
on figure 2.1-1.
d) Power and Power outlets will be provided by SHAPE/THN
as specified in appendix A.
3.3 F̲A̲C̲I̲L̲I̲T̲Y̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
3.3.1 A̲c̲c̲e̲s̲s̲ ̲a̲n̲d̲ ̲D̲i̲m̲e̲n̲s̲i̲o̲n̲s̲
a) The typical equipment layout (fig. 3.1-1) reflects
the floor spare required by cabinets and operator
positions. The access dimensions for racks and
terminal equipment are shown on figure 3.3.1-1
and 3.3.1-2. The racks are positioned such that
sufficient clearance is maintained for access to
the front and rear of the equipment. Otherwise,
only few constraints as to the placement of the
equipment exist. The final layouts will take into
account human factors, segregation of functional
activities, access for maintenance and other considerations
or preferences of the operative personnel.
Figure 3.1-1…01…TYPICAL EQUIPMENT LAYOUT - CAMPS MOCK UP
FIGURE 3.3.1-1…01…PHYSICAL DIMENSIONS OF RACKS
FIGURE 3.3.1-2…01…USER TERMINALS…01…TYPICAL LAYOUT AND ACCESS REQUIREMENTS
One of the tasks to be performed at the Site Survey
is to work out the optimal layout in conjunction
with SHAPE/THN.
b) The floor load of the Computer equipment rack is
well within the Standard floor load limit of 1000
kg/m…0e…2…0f… for Computer floors as can be seen from the
following calculation:
Floor Load of heaviest rack:
̲ ̲W̲E̲I̲G̲H̲T̲ ̲ ̲ ̲ ̲ ̲ ̲3̲3̲0̲ ̲k̲g̲ ̲ ̲ ̲ ̲
= = 522 kg/sq metres
FLOOR SPACE 0.6 x 1.05 sq metres
Since the rack is provided with access space at front
and rear, the distributed floor load is considerable
smaller. Equipment weight and dimensions are given
in table 3.3.1-1.
EQUIPMENT UNIT SIZE CM ACCESS
CM
UNIT ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
POS WEIGHT
NO ITEM KG WIDTH DEPTH HEIGHT FRONT REAR
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
1 RACK A 270 60 105 206 120 100
RACK B 330 60 105 206 120 100
RACK C 240 60 105 206 120 100
2-10-12 VDU 35 48 76 43 100
15
3-13 MSP 27 60 55 25 100
15
4 80 MB SMD 77 48
80
26 120 100
5 80 MB MMD 57 43
67
26 120 100
6 FD STATION 20 48
51
14 100
15
7 STAT MUX 5 48
28
8 100
15
8 CRATE 15 48 53
22 100
15
9 OPTO TABLE 50 70
55
90 100
15
2, 3 Table 52 120 80 70 100
15
Table 3.3.1-1…01…EQUIPMENT WEIGHT AND DIMENSIONS
3.3.2 A̲i̲r̲ ̲C̲o̲o̲l̲i̲n̲g̲
The equipment is cooled by fans with intake at the
front and exhaust at the top. The heat dissipation
figures are given in Table 3.3.2-1.
3.3.3 P̲o̲w̲e̲r̲
a) Power to equipment is fed from individual fuse
protected 220 vac outlets. The required power supply
for the equipment is given in table 3.3.2-1.
b) The CAMPS MOCK UP equipment is designed to comply
with the following power characteristics.
PHASE: Single- or 3-phase, and
ground
VOLTAGE: Nominel Value: 380/220
VAC
Tolerances: + 10%/-10%
FREQUENCY: Nominal Value: 50 Hz
Tolerances: +10%/-10%
HARMONIC DISTORTION: Max 5%
TRANSIENTS: Non-Repetive impulsive
interference with a magnitude
not to exceed 500 volts,
pulse rise and fall times
not faster than 10 microseconds
and a total duration of
maximum 1 millisecond.
The available impulse energy
at the equipment power
inlet shall not exceed
5J.
Note:
The Disk Drives in rack A and B will not operate within
the tolerances of section b) above, but require.
Voltage: Nominal Value: 380/220V AC
Tolerances: + 6%/-10%
Frequency: Nominal Value: 50 Hz
Tolerances: + 0.5 Hz/-1.0 Hz
Per Per
U̲n̲i̲t̲ T̲o̲t̲a̲l̲ Unit Total
Pos.
Kcal/ Kcal/
N̲o̲.̲ ̲ ̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲Q̲t̲y̲.̲ ̲ ̲V̲o̲l̲t̲s̲ ̲ ̲ ̲W̲i̲r̲e̲s̲ ̲ ̲P̲h̲a̲s̲e̲ ̲ ̲ ̲W̲ ̲ ̲ ̲ ̲K̲W̲
̲ ̲ ̲h̲o̲u̲r̲ ̲ ̲h̲o̲u̲r̲ ̲ ̲
1 RACK A 1 220 2x3 2 1200 1.20 1030 1030
RACK B 1 220 2x3 2 2180 2.18 1870 1870
RACK C 1 220 2x3 2 1870 1.87 1600 1600
2-10-12
VDU 3 220 3 1 250 0.75
220
660
3-13 MSP 2 220 3 1 370 0.74
320
640
4 80 MB SMD 1 220 3 1 950 0.95
820
820
5 80 MB MMD 1 220 3 1 400 0.40
350
350
6 FD STATION 1 220 3 1 110 0.11
100
100
7 STAT MUX 1 220 3 1 50 0.05
50
50
8 CRATE 1 220 3 1 400 0.40
350
350
9 OPTO TABLE 1 220 3 1 400 0.40
350
350
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
TOTAL 9̲.̲0̲5̲ 7̲8̲2̲0̲
Table 3.3.2-1
3.3.4 E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲
The CR 80 equipment is designed to operate/comply with
the following:
D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲s̲
o Operating: These limits apply to equipment
installed as specified and
operating in a normal office
or computer roon environment.
o Storage: The limits apply to equipment
properly packed and protected
against dust, moisture, condensed
water etc.
o Transportation: These limits apply to equipment
properly packed for shipment.
T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲
o Operating: 15…0e…o…0f… to 32…0e…o…0f…
Maximum rate of change
6…0e…o…0f…C per hour
o Storage/Trans- -40…0e…o…0f… to 70…0e…o…0f…
portation:
H̲u̲m̲i̲d̲i̲t̲y̲
o Operating: 20 per cent to 80 per cent
RH non condensing. Maximum
rate of change 10 per cent
RH per hour.
Absolute water content in
the room air shall be limited
to 22g water per cubic meter
of air.
o Storage/Trans- 10 per cent to 90 per cent
portation: non condensing
A̲l̲t̲i̲t̲u̲d̲e̲
o Operating: 0 to 2000 m
o Storage/Trans- 0 to 10.000 m
portation
V̲i̲b̲r̲a̲t̲i̲o̲n̲
o Operating and 5 Hz to 50 Hz constant
Storage: displacement of 0.02 mm
50 Hz smooth crossover
50 Hz-350 Hz constant acceleration
0.2 g
o Transportation 5Hz to 350Hz constant acceleration
1.5 g
S̲h̲o̲c̲k̲
o Operating and 1g, half sine wave, 10 ms
Storage: duration. Not to be repeated
more often than one per 10
seconds.
o Transportation 25g, half sine wave, 10 ms
duration.
A̲P̲P̲E̲N̲D̲I̲X̲ ̲A̲
S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
1.1 G̲E̲N̲E̲R̲A̲L̲
Site preparation and Installation will be carried out
according to the following g̲e̲n̲e̲r̲a̲l̲ ̲r̲u̲l̲e̲s̲:̲
1.1.1 SHAPE will be responsible for site preparation, and
CR will generate the site depot data base, in co-ordination
with depot personnel.
1.1.2 CR will be responsible for providing SHAPE with requirements
for the preparation of the site for equipment installation.
CR will issue a site questionnaire stating the minimum
installation requirements, not later than 60 days from
date of contract.
1.1.3 CR will have the right to conduct site readiness verification
at a site. When site readiness has been established,
CR will be responsible for equipment installation.
1.2 S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲
1.2.1 CR reserves the right to perform a site survey at the
depot. The purpose of the site survey is to determine
the equipment room layout and ensure that CR can generate
site preparation requirements.
1.2.2 SHAPE will provide CR with the appropriate civil engineering
drawings of equipment rooms during the site survey.
SHAPE will be responsible for all relevant drawings
to be furnished to the Contractor.
1.2.3 CR's planning baseline for preparation of requirements
is the result of the site survey. If SHAPE advises
CR of site modifications accomplished after the site
survey, CR will incorporate these changes into his
Site Preparation Requirements provided that he is notified
of the changes no later than 3 months prior to the
submission date.
1.3 S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲
1.3.1 C̲R̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
All site preparation requirements will be given to
SHAPE as early as possible no later than 5 months prior
to commencement of site installation. SHAPE will issue
approval or a list of deficiencies of the documents
within 21 days after receipt.
1.3.2 S̲H̲A̲P̲E̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
1.3.2.1 SHAPE will be responsible for all work necessary to
make the site ready for installation of CR's equipment,
in compliance with CR's site preparation requirements.
1.3.2.2 SHAPE will notify the Contractor of a site's readiness
and an inspection date, no later than 30 days prior
to start of installation, will then be mutually agreed.
1.3.2.3 Customer will remain responsible for all site preparation
until site has been verified and accepted as ready
for installation by CR.
1.3.2.4 If CR is prevented from commencing or performing installation
work according to schedule due to the sites being unfinished
or if, having arrived at the site, the contractor's
staff and/or supplies are denied access to the site,
a c̲l̲a̲i̲m̲ will be submitted by the contractor. This claim
will be resolved under Clause 37 of SHAPE's General
Provisions "SHAPE Delay of Work."
1.4 S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
1.4.1 C̲R̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
In co-ordination with SHAPE, CR will move equipment
onto site subsequent to the acceptance of site readiness.
The installation of equipment is to be carried out
in accordance with the following:
At each site, contractor will:
1.4.1.1 Deliver and install the contractual number of equipment
racks and engineering terminals in the locations prepared
by SHAPE, and interconnect them with cables.
1.4.1.2 Deliver and install the contractual number of workstations
in the room(s) and location(s) specified by SHAPE,
with cables to equipment racks.
1.4.1.3 Terminals and other peripheral devices will be located
within a cable distance of 15 m from the equipment
racks, if connected via a metallic V24 cable and not
connected to one of the 7 units of the CR 80109/000
modules provided under contract.
1.4.1.4 CR accept that, during site installation and site acceptance
testing, SHAPE shall have the right to appoint a trained
Resident Site Technician /RST) who will participate
in the equipment installation under CR supervision.
CR is obliged to provide the RST with guidance and
additional knowledge of the system installation and
test procedure, to enable the RST to identify possible
faults.
1.4.1.2 S̲H̲A̲P̲E̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
1.4.2.1 SHAPE will prepare the site accorlding to CR's site
preparation requirements:
Provide for space, primary and stand-by power, if required,
power distribution and cabling, illuminations, flooring,
cable ducting, airconditioning and related civil works.
1.4.2.2 Each depot will ensure that at least 1 CR trained technician
(RST) will assist CR in the installation of the MOCK-UP.
The terms of references of the RST shall be agreed
by the parties within 3 (three) months from contract
signature.
1.4.3 M̲a̲i̲n̲s̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲i̲e̲s̲
SHAPE will arrange for mains power supply as follows:
1. Three phase and single phase 380/220VAC 50 HZ power
supplies.
2. Protective devices for the mains power installation
according to national standard.
3. Circuit breakers which operate to make or break
A.C. power lines shall make or break all conductors
at the same time. The neutral wire shall not pass
through any fuse.