⟦bbe43c1e2⟧ Wang Wps File

    Length: 6936 (0x1b18)
    Types: Wang Wps File
    Notes: sd/std/017 App. I         
    Names: »0767A «

Derivation

└─⟦4bcf3d88d⟧ Bits:30005999 8" Wang WCS floppy, CR 0048A
    └─ ⟦this⟧ »0767A « 

WangText




…02…APPENDIX I TO SD/STD/017

…02…EV /810303…02……02…#
INCOMING INSPECTION STANDARD FOR VDU'S
…02……02…GENERAL








                T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



…02…1  PURPOSE  ...........................................
  4

…02…2  SURVEY  ............................................
  5

…02……02…2.1  FLOW CHART  ....................................
  5

…02…3  PACKAGED INSPECTION  ...............................
  7

…02……02…3.1  GENERAL  .......................................
  7
…02……02…3.2  DETAILED  ......................................
  7

…02…4  SPECIAL INSPECTION  ................................
  8
…02……02…4.1  GENERAL  .......................................
  8
…02……02…4.2  DETAILED  ......................................
  8

…02…5  RETURN TO VENDOR  ..................................
  9

…02……02…5.1  GENERAL  .......................................
  9
…02……02…5.2  DETAILED  ......................................
  9

…02…6  INSPECTION OF CONTENTS  ............................
 10

…02……02…6.1  GENERAL  .......................................
 10
…02……02…6.2  DETAILED  ......................................
 10

…02…7  SPECIAL INSPECTION  ................................
 12

…02……02…7.1  GENERAL  .......................................
 12
…02……02…7.2  DETAILED  ......................................
 12

…02…8  FUNCTIONAL TEST  ...................................
 13
…02……02…8.2  DETAILED  ......................................
 13

…02…9  SPECIAL FUNCTIONAL TEST  ...........................
 14

…02……02…9.1  GENERAL  .......................................
 14

…02…10 REPACKING  .........................................
 15

…02……02…10.2 DETAILED  ......................................
 15


                        1̲ ̲ ̲P̲U̲R̲P̲O̲S̲E̲



1.1…02…P̲U̲R̲P̲O̲S̲E̲

         The purpose of the standard is to define the general
         lines for incoming inspection of Video Display Units
         (VDU's). The standard is especially directed towards
         equipment purchased from other suppliers as mainly
         "off the shelf" equipment.


                        2̲ ̲ ̲S̲U̲R̲V̲E̲Y̲



2.1…02…F̲L̲O̲W̲ ̲C̲H̲A̲R̲T̲

         The  flow chart fig. 2.1.1 outlines the flow from the
         reception to stock. The following chapters will chronologically
         define the requirements to every single step in the
         diagram.




                  3̲ ̲ ̲P̲A̲C̲K̲A̲G̲E̲D̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲



3.1      G̲E̲N̲E̲R̲A̲L̲

         The "Packaged Inspection", point 1, is being performed
         to:

         a)  Ensure that the external packaging does not show
             any sign of  transportation damaging.

         b)  Ensure that the packaging is according to the requirements
             specified for the supplier.



3.2      D̲E̲T̲A̲I̲L̲E̲D̲

         a)  The package shall be opened by the use of relevant
             tools and the contents is separated and checked
             in according to SD/STD/017 

         b)  In case of abnormalities a Non-Conformance Report
             shall be filled in and the unit shall pass by to
             "Special Inspection", point 2.


                  4̲.̲ ̲ ̲S̲P̲E̲C̲I̲A̲L̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲



4.1      G̲E̲N̲E̲R̲A̲L̲

         The "Special Inspection", point 2, is being performed
         when the packaging shows signs of transportation damaging.



4.2      D̲E̲T̲A̲I̲L̲E̲D̲

         The package shall be opened very carefully to prevent
         any further damaging to the contents.

         a)  The VDU shall be examined in details and all remarks
             shall be stated in the Non-Conformance Report.

         b)  In case of destructive damaging and that no repair
             seems possible the unit shall be returned to the
             vendor (Point 3)

         c)  In case of minor repairable defects the unit passes
             by to "Functional Test" (Point 6).


                   5.  R̲E̲T̲U̲R̲N̲ ̲T̲O̲ ̲V̲E̲N̲D̲O̲R̲



5.1      G̲E̲N̲E̲R̲A̲L̲

         The "Return to Vendor", point 3, is being performed
         when unrepairable defects or electrical malfunctions
         are found in "Special Inspection", point 2 and 4 or
         "Special Functional Test", point 7.



5.2      D̲E̲T̲A̲I̲L̲E̲D̲

         Defect items can only be returned to the vendor by
         a MRB-decision.


                6. I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲



6.1      G̲E̲N̲E̲R̲A̲L̲

         The "Inspection of Contents", point 4, is being performed
         to assume that the presented hardware is according
         to the specified requirements.



6.2      D̲E̲T̲A̲I̲L̲E̲D̲

         a)  The VDU shall be examined in details to assume
             that no internal or external parts have been damaged
             during transportation and handling.

         b)  The workmanship shall be in accordance to the stated
             and accepted requirements.



         c)  In case of abnormalities a Non-Conformance Report
             shall be filled in and the unit shall pass by to
             the "Special Inspection", point 5.


                  7̲ ̲ ̲S̲P̲E̲C̲I̲A̲L̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲



7.1      G̲E̲N̲E̲R̲A̲L̲

         The "Special Inspection", point 5, is being performed
         when non-conforming remarks are found during "Inspection
         of Contents", point 4.



7.2      D̲E̲T̲A̲I̲L̲E̲D̲

         a)  The VDU shall be examined in details and all abnormalities
             shall be filled in the Non-Conformance Report.

         b)  In case of destructive demaging and no repair seems
             possible, the unit shall be returned to the vendor
             (Point 3)

         c)  In case of minor repairable defects the unit passes
             by to "Functional Test" (Point 6).


                    8. F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲T̲E̲S̲T̲



8.1      G̲E̲N̲E̲R̲A̲L̲
         The "Functional Test", point 6, is being performed
         to assume that all electrical and electronic functions
         fulfil the requirements.



8.2      D̲E̲T̲A̲I̲L̲E̲D̲

         a)  In case of a separated keyboard it shall be connected
             to the unit.

         b)  All functional keyboard functions shall be verified
             according to the presented Operators Manual and
             Maintenance Manual.

         c)  In case of remarks a Non-Conformance Report shall
             be filled in and the concerned unit shall pass
             by to the "Special Functional Test", point 7.


                9. S̲P̲E̲C̲I̲A̲L̲ ̲F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲T̲E̲S̲T̲



9.1      G̲E̲N̲E̲R̲A̲L̲

         The "Special Functional Test", point 7, is being performed
         when non-conforming remarks are found during "Functional
         Test", point 6.

         D̲E̲T̲A̲I̲L̲E̲D̲

         a)  All functions shall be tested carefully according
             to the presented manuals to locate failure(s)

         b)  In case of non-repairable failure the unit shall
             be returned to the vendor (Point 3).

         c)  In case of minor repairable defects i.e. change
             of a module the unit after repair passes by to
             "Repacking", point 8.


                      1̲0̲ ̲ ̲R̲E̲P̲A̲C̲K̲I̲N̲G̲



10.1     G̲E̲N̲E̲R̲A̲L̲

         The "Repacking", point 8, is performed after acceptance
         of the unit.



10.2     D̲E̲T̲A̲I̲L̲E̲D̲

         a)  The repacking is performed to assume that the packaging
             is according to the transportation environments
             stated in the requirements for the concerned equipment.

         b)  After repacking the units are kept in the stock
             until transportation.