The Configuration Status Accounting function records
and maintains the informaton and documentation required
by configuration control management. It includes listings
of approved ngineering documentation, status reports
of proposed changes, and implementation status of approved
changes.
The Physical Configuration Audit (PCA) is the formal
examination of the as-built version of a configuration
item against its technical doumentation in order to
establish the Configuration Item's product baseline.
The Functional Configuration Audit (FCA) is the verification
of the completion, or extent of completon, of all tests
required by development specifications.
The Configuraion Management function gets involved
in updating of the PIP and other plans of the project
by the fact that DATA MANAGEMENT is handled by configuration
control.
The changes are normally initiated through the project
office but controlled by Confguration Management.
3.5 A̲V̲A̲I̲L̲A̲B̲I̲L̲I̲T̲Y̲
Availability is treated in the Technical Proposal,
section on Availability.
3.6 T̲E̲S̲T̲I̲N̲G̲ ̲A̲N̲D̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲
Following system integration and unit testing of each
software module, a Factory Qualification Tet (FQT)
is performed. Thereafter, each MPF system will be
subjected to a Factory Post Production Test (FPPT)
before shipment to site for installation.
At the site, system integration is carried out, and
a Preliminary Site Acceptance Test (PSAT) is performed.
Following this, a Sub-Net-Test (SNT) - Category iii
verifies that the PF interfaces properly to the TARE
Communication Processor Sub-System and to the Telegraph
Message Sub-System. Additionally, at the second site,
a SNT - category iv verifies that the two MPF's communicate
properly with each other, both already havng been tested
to SNT iii.
Finally, an Official System Acceptance Tesat (OSAT)
is performed, and succesful completion of the OSAT
constitutes final acceptance of the MPF by NODECA.
The following is a list of formal tests:
FQT Pre-Test in Copehagen
FQT and FPPT in Copenhagen for site 101 equipment
PSAT site 101
SNT (iii) site 101
FPPT in Copenhagen for site 301 equipment
PSAT 301
SNT (iii) site 301
SNT (iv)
OSAT
3.7 T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲T̲R̲A̲N̲S̲F̲E̲R̲