top - download
⟦bfe92e9a7⟧ Wang Wps File
Length: 34172 (0x857c)
Types: Wang Wps File
Notes: ISCC Kontrakt
Names: »4188A «
Derivation
└─⟦e9ca1be93⟧ Bits:30006183 8" Wang WCS floppy, CR 0382A
└─ ⟦this⟧ »4188A «
WangText
…00……00……00……00……00……17……0a……00……00……17……0b……17……0d……17……05……16……0b……16……01……15……09……15……0e……15… …86…1 …02… …02… …02… …02…
CAMPS ISSC, CONTRACT 1983-10-24
PART II Page #
C O N T R A C T…01……01……01…between…01……01……01…Supreme Headquarters Allied Powers Europe…01……01…(in the following referred to as SHAPE)…01……01……01…and…01……01……01…Christian Rovsing A/S…01…2, Lautrupvang…01…DK-2750 Ballerup…01…Denmark…01……01……01…(in
the following referred to as CR)…01……01……01…on…01……01……01……01…ISSC Development and Test
Drive System
P̲A̲R̲T̲ ̲I̲I̲
T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
1 CAMPS DEVELOPMENT SYSTEM ......................
3
1.1 EQUIPMENT PURPOSE ..........................
3
1.2 EQUIPMENT CONFIGURATION AND CONNECTIVITY ...
3
1.3 SOFTWARE CONFIGURATION .....................
4
1.4 DOCUMENTATION ..............................
4
1.4.1 Hardware ...............................
4
1.4.2 Software ...............................
4
1.5 ACCEPTANCE TEST ............................
4
1.5.1 Factory Acceptance Test ................
5
1.5.2 In Plant System Acceptance Test ........
5
1.5.3 Site Provisional Acceptance Tests ......
5
1.5.4 Test Procedures ........................
5
2 CAMPS TEST DRIVE SYSTEM .......................
6
2.1 EQUIPMENT PURCHASE .........................
6
2.2 EQUIPMENT CONFIGURATIONB AND CONNECTIVITY ..
6
2.3 SOFTWARE CONFIGURAION ......................
7
2.4 DOCUMENTATION ..............................
7
2.4.1 Hardware ...............................
7
2.4.2 Software ...............................
7
2.5 ACCEPTANCE TESTS ...........................
8
2.5.1 Factory Acceptance Test (FAT) ..........
8
2.5.2 In Plant System Acceptance Test ........
8
2.5.3 Site Provisional Acceptance Tests ......
8
2.5.4 Test Procedures ........................
8
3 PROTOCOL CONVERTER SYSTEM (PC SYSTEM) .........
9
4 SITE PROVISIONAL ACCEPTANCE (SPA) .............
10
5 INSTALLATION ..................................
11
6 TRAINING ......................................
15
7 LOGISTICS SUPPORT .............................
16
8 ACE COMSEC REQUIREMENTS AND CLEARANCE .........
17
1̲ ̲ ̲C̲A̲M̲P̲S̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲ ̲S̲Y̲S̲T̲E̲M̲
1.1 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲P̲U̲R̲P̲O̲S̲E̲
This is provided for the following activities:
a) Unit and Module code corrections
b) Recompilation and unit and module tests
c) Package Integration and Test
d) System Generation
e) Configuration Management and SW Library Support
f) Production of disks/floppies for corrections
g) Data Base Configuration management and generation
It forms an integral part of the ISSC and shall be
capable of producing complete CAMPS systems on disc
suitable for loading on site or on the CAMPS Reference
System for system level tasks.
1.2 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲V̲I̲T̲Y̲
The equipment consists of non-dualized equipment in
TEMPEST racks with termination units and adaptors provided
to connect the required number of peripheral.
The outline configuration of the equipment is given
in Appendix A-1, and the number and connectivity of
the peripherals is given in Appendix A-2. The detailed
central equipment quantities are given in the equipment
list Appendix A-3.
The equipment shall be constructed and/or retrofitted
to conform with the actual or pending change status
of the similarly designed and constructed hardware
of the SHAPE CAMPS at the end of the warranty period
of that site.
1.3 S̲O̲F̲T̲W̲A̲R̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
All CAMPS system and off-line software and all DAMOS
software utilities will be installed forming a software
configuration control and development environment capable
of performing the tasks defined in paragraph 1.1.
Additional package integration test utilities and related
package test input, output, and result files will be
delivered.
Improvements and extensions to the System Generation
tools deliverable under the CAMPS contract will be
made to cover Data Base generation, capabilities entries,
boot module generation to enable new and consistant
systems to be generated efficiently.
The list of software items to be supplied is included
at Appendix A-4.
1.4 D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
1.4.1 H̲a̲r̲d̲w̲a̲r̲e̲
All documentation related to hardware items not deliverable
under any other CAMPS related contract will be delivered
as commercial off-the-shelf documentation. The hardware
assembly breakdown shall be provided.
1.4.2 S̲o̲f̲t̲w̲a̲r̲e̲
Userguides, design documentation and source listings
will be provided for all package integration test utilities.
CR will provide magnetic media (disk pack) of the package
test cases, input and expected output for stimulation
and test command interpreter.
1.5 A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲T̲E̲S̲T̲
CR will deliver a Stimulator and Test Command Interpreter
Manual. This manual will be able to be used by a qualified
ADP person unfamilar with the CAMPS System.
This manual will enable the person to setup and run
system level software tests of all software modules
and packages in isolation. The manual will provide
step by step instructions for all aspects of this testing.
1.5.1 F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲
When the CAMPS development system has been integrated
in the factory and a successful run of the test has
been witnessed and reported by the SHAPE appointed
QAR, the factory acceptance test shall be carried out
to verify that the hardware is functioning according
to requirements.
1.5.2 I̲n̲ ̲P̲l̲a̲n̲t̲ ̲S̲y̲s̲t̲e̲m̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲
The test shall demonstrate the use of the development
system to perform the tasks a through g of paragraph
1.1. This shall include but not be limited to a demonstration
of the complete generation of a system from source
files and the successful load and test on a representative
CAMPS system. Successful creation and load of system
software, application software and system database
updates separately and together using disc packs and
floppy disks shall be shown.
1.5.3 S̲i̲t̲e̲ ̲P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲s̲
This test shall demonstrate that the system as delivered
to site is capable of operating together with the CAMPS
Reference System in the Integrated System Support Centre
(ISSC) environment. The in-plant system acceptance
tests shall be repeated on site to give SHAPE assurance
of such capability.
1.5.4 T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
Test procedures will be delivered as follows:
- Factory Acceptance Test Procedures
- In Plant System Acceptance Test Procedures
- Site Provisional Acceptance Test Procedures
The procedures shall be delivered for SHAPE review
and approval no later than 60 days prior to each test.
2̲ ̲ ̲C̲A̲M̲P̲S̲ ̲T̲E̲S̲T̲ ̲D̲R̲I̲V̲E̲ ̲S̲Y̲S̲T̲E̲M̲ ̲(̲T̲D̲S̲)̲
2.1 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲P̲U̲R̲C̲H̲A̲S̲E̲
This system drives the external circuits and terminal
(VDU) interfaces of the CAMPS Reference system to achieve
the following main tasks:
a) Stress test of the software and hardware of the
reference system
b) Functionally test SW in the reference system
c) Perform automated regression tests on new SW releases
d) Assist in fault analysis in the reference system.
It contains facilities for test transmission data creation
and control as well as test output data compression
and analysis.
The Test Drive System Description (CSP/SDS/042) shall
be updated to reflect the features, and functions of
the actual TDS.
2.2 E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲B̲ ̲A̲N̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲V̲I̲T̲Y̲
The equipment consists of Message Traffic and VDU test
drive hardware systems in TEMPEST racks, with appropriate
terminations and adaptors provided to connect the required
number of peripherals.
The outline configuration of the equipment is given
in Appendix B-1.
The number and connectivity of the peripherals are
as given in Appendix B-2.
The detailed central equipment quantities are given
in the equipment list in Appendix B-3.
The equipment shall be constructed and/or retrofitted
to conform with the actual or pending change status
of the similarly designed and constructed hardware
of the SHAPE CAMPS at the end of the warranty period
of that site.
2.3 S̲O̲F̲T̲W̲A̲R̲E̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲I̲O̲N̲
The software to handle the functions mentioned in para
2.1 shall be installed in the Test Drive System.
Provided in addition to the CAMPS System software will
be all software to enable the TDS to drive the reference
system CAMPS with defined messages and terminal transactions
in a defined manner (timings, message contents, etc.)
The software to enable creation of the transaction
sequence and contents prior to a test run and to analyse,
compares and present data from the run shall also be
included.
The baseline test sequences for the CAMPS 240 hour
test shall be delivered.
The list of deliverables is included in appendix B-4.
2.4 D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
2.4.1 H̲a̲r̲d̲w̲a̲r̲e̲
N/A.
2.4.2 S̲o̲f̲t̲w̲a̲r̲e̲
Test Drive System Users Guide, design documentation
one paper copy and one magnetic media copy and source
listings shall be provided.
The documentation shall be to the same level of detail
and standard as the application software deliverables
under the main CAMPS contract.
Any firmware developed specifically for the Test Drive
System shall be described and design documents source
listings and source files provided.
The CAMPS 240 hours test message and transmission sequence
files shall be documented.
2.5 A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲T̲E̲S̲T̲S̲
2.5.1 F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲ ̲(̲F̲A̲T̲)̲
When the Test Drive System has been integrated in the
factory and a successful run of the test has been witnessed
and reported by the SHAPE appointed QAR, the factory
acceptance test shall be carried out to verify that
the hardware is functioning according to requirements.
The FAT shall be based on the FAT for CAMPS system
under the main CAMPS contract.
2.5.2 I̲n̲ ̲P̲l̲a̲n̲t̲ ̲S̲y̲s̲t̲e̲m̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲
The test shall demonstrate the use of the test drive
system to perform the tasks paragraph 2.1. This shall
include but not be limited to a demonstration of the
test script generation, test of software on the reference
or equivalent CAMPS system, configuration mangement
of test scripts and cases, regression testing and load
testing.
2.5.3 S̲i̲t̲e̲ ̲P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲s̲
This test shall demonstrate that the system as delivered
to site is capable of operating together with the CAMPS
Reference System in the ISSC environment. The in-plant
system acceptance tests shall be repeated on site to
give SHAPE assurance of such capability.
2.5.4 T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
(As for 1.5.4).
3̲ ̲ ̲P̲R̲O̲T̲O̲C̲O̲L̲ ̲C̲O̲N̲V̲E̲R̲T̲E̲R̲ ̲S̲Y̲S̲T̲E̲M̲ ̲(̲P̲C̲ ̲S̲Y̲S̲T̲E̲M̲)̲
N/A.
4̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲(̲S̲P̲A̲)̲
a) Site provisional acceptance is the act whereby
SHAPE will acknowledge by protocol that CR has
fully demonstrated that a site is complete and
ready for initial operation and will take place
when the following requirements have been met:
- Completion of an agreed on-site acceptance
test
- Verification of the site inventory
- Availability of a certificate proving compliance
with national safety regulations
- If applicable, availability of a mutually agreed
discrepancy list showing the agreed date for
clearance of each listed discrepancy
b) SHAPE will either sign a SPA Acceptance Protocol
or deliver to CR in writing a "Notice of Defects"
listing the defects which prevented provisional
acceptance of the site.
c) The date of signature of the SPA Acceptance Protocol
marks the date of the SPA.
d) If SHAPE delivers a "Notice of Defects" then the
date on which SHAPE signs "Correction of Defects
Notice" shall be the date of the SPA.
e) "Defects", as referred to above, means any non-compliance
with this contract by CR which prevents the normal
operation of the site. "Discrepancies" shall mean
a non-compliance which does not prevent completion
of site provisional acceptance. However, any discrepanices
existing at the time of signing the Site Provisional
Acceptance Protocol will be listed in the protocol
and dates for correction of each will also be included.
f) The date of the SPA marks the time at which SHAPE
takes over the responsibility of a site and the
operation of the site can commence. Prior to SPA,
all operation by SHAPE of the site shall be approved
by CR.
5̲ ̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲
5.1 S̲I̲T̲E̲ ̲N̲O̲M̲I̲N̲A̲T̲I̲O̲N̲
SHAPE will have the right to nominate a site within
the Kingdom of Belgium no later than SPA CAMPS site
1 plus 3 months. At this time SHAPE and Christian Rovsing
agree that the price indicated in the Contract Schedule
Item would be reopened for negotiation if SHAPE elects
to globalize the site installation work package for
all CAMPS related ISSC equipment which would be written
in the contract on that date.
5.2 Site Preparation and Installation Responsibilities.
5.2.1 General. Site preparation and installation shall be
carried out as follows:
5.2.2 SHAPE will be responsible for site preparation.
5.2.3 The contractor shall be responsible for providing one
set of site Civil Works drawings. These drawings will
contain all the information needed to prepare the site
for equipment installation.
In addition to the preparation and delivery of the
above Civil Works drawings the contractor shall be
responsible for preparing the As-To-Be-Built drawing
package. These drawings will contain all details of
how all major assemblies off the equipment will be
physically installed, powered and laid down and electrically/opto
inter-connected.
5.2.4 The contractor is responsible for determining site
readiness and agrees that the site preparation meets
the requirement as laid down in the ATBB drawing.
5.3 S̲I̲T̲E̲ ̲P̲R̲E̲P̲A̲R̲A̲T̲I̲O̲N̲
5.3.1 All site civil works drawings must be forwarded to
SHAPE no later than 4 1/2 months prior to SPA
5.3.2 All ATBB drawings must be delivered to SHAPE no later
than two months prior to the start of installation.
Within 21 days of delivery SHAPE will notify Christian
Rovsing that the drawings reflect installation within
the restriction of AMSG-719B.
5.4 C̲U̲S̲T̲O̲M̲E̲R̲'̲S̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲Y̲
a) To perform all work necessary and pay all associated
costs to make the site ready for installation of
contractor's equipment according to contractor's
site civil work drawings as modified by SHAPE or
the territorial host nation, if appropriate, to
meet territorial host nation laws and regulations.
b) Customer will remain responsivle for all site preparations
until site has been verified and accepted as ready
for installation by CR.
c) If CR is prevented from commencing or performing
installation work according to schedule due to
sites being unfinished or if, having arrived at
the siete, the contractor's staff and/or supplies
are denied access to the site, a claim will be
submitted by the contractor. This claim will be
resolved under Clause 37 of SHAPE's General Provisions
"SHAPE delay of work".
d) Customer will notify contractor of a site's readiness
no less than 30 calender days prior to the anticipated
date the site will be ready. Once SHAPE certifies
that a site is ready for installation, the Contractor
will be required to verify that the site is acceptable
within fourteen calender days of a formal request
by SHAPE to accomplish the verification. This inspection
date may be modified by mutual agreement of SHAPE
and CR.
5.5 S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
5.5.1 C̲o̲n̲t̲r̲a̲c̲t̲o̲r̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
Subject to SHAPE authorization of shipment, contractor
may move equipment onto site subsequent to approval
of site readiness. The installation of equipment will
be done in accordance with the following:
At the site contractor will:
a) Deliver and install CAMPS central equipment.
b) Deliver the proposed number of supervisors positions
and a maintenance position and connect them with
secure cables to the central equipment.
c) Deliver the proposed number of user terminals and
connect them with secure cables to the central
equipment.
d) Connect the propsed number of SCARS, CCIS and TARE
interface cables (secure) to the CAMPS Test Drive
equipment furnished by SHAPE.
e) Connect the remote CAMPS rack to the central equipment
with secure cables.
5.5.2 C̲u̲s̲t̲o̲m̲e̲r̲'̲s̲ ̲R̲e̲s̲p̲o̲n̲s̲i̲b̲i̲l̲i̲t̲y̲
Customer's responsiblities are set forth below:
Customer will perform the following civil works according
to contractor's specifications:
a) Perform all light and mainpower installations to
feed and maintain the proposed equipment (power
cabling, circuit breakers, fuses, light armatures,
distribution to outlets, and outlets), except within
the confines of the shielded enclosure.
b) Provide and install raised floors if required and
all cable ducts including ducts under raised floors
if applicable to run the cables.
c) Run all signal cables (supplied by contractor),
except cabling within the confinbes of the CAMPS
room.
d) Perform all installation required to maintain the
environmental conditions (temperature, humudity)
specified. Customer will install ventilation ducts,
if required, according to civil works drawings.
Contractor will perform all installations directly
to the shielded enclosure.
e) Perform all other installations not directly related
to the CAMPS equipment, if any (alarms, voice activated,
intercom. o.e.)
6̲ ̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲
Training for aspects of operation of the systems controlled
within this contract is described in the contract for
the CAMPS reference system for the ISSC.
7̲ ̲ ̲L̲O̲G̲I̲S̲T̲I̲C̲ ̲S̲U̲P̲P̲O̲R̲T̲
7.1 W̲A̲R̲R̲A̲N̲T̲Y̲
a) The hardware shall be warranted for a period of
90 days following SPA. After the completion of
the warranty period, the system will be brought
to the same Equipment Change Status (implemented
or pending) as pertains to the following sites
of the completion of their warranty:
DEVELOPMENT SYSTEM - SHAPE CAMPS HARDWARE
TEST DRIVE SYSTEM - SHAPE CAMPS HARDWARE
7.2 S̲P̲A̲R̲E̲ ̲P̲A̲R̲T̲S̲
As an option, SHAPE will purchase spare parts for the
systems. SHAPE will have the right to select part from
within the list of recommended spare parts.
7.3 Q̲U̲A̲L̲I̲T̲Y̲ ̲A̲S̲S̲U̲R̲A̲N̲C̲E̲
CR will deliver new, unused except with SHAPE approval
Hardware/Software equipment for the CAMPS Reference
system of the same quality and standard as those agreed
by SHAP/CR and applicable under SHAPE Contract CE 80-9009/INF.
8̲ ̲ ̲A̲C̲E̲ ̲C̲O̲M̲S̲E̲C̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲ ̲A̲N̲D̲ ̲C̲L̲E̲A̲R̲A̲N̲C̲E̲
8.1 The CAMPS computer equipment processing classified
information will be placed in EMI racks. The EMI Racks
will provide the attenuation specified within the TEMPEST
requirements for all this equipment.
8.2 To obtain ACE COMSEC approval, the computer equipment
will be operated within the EMI Racks, and test measurements
will be made outside of the rack to ensure that the
attenuation provided by the rack is adequate to meet
the TEMPEST requirements.
8.3 All other equipment which process classified information
in a clear electrical form, shall meet the NATO COMSEC
Tempest requirements as laid down in AMSG 720-A.
8.4 Certificates from national COMSEC Authorities for equipments
which have been tested and approved by them will be
accepted by ACE COMSEC. SHAPE will, however, accept
that the certification to be provided for peripheral
equipment (i.e. VDUs, Medium Speed Printers, Paper
Tape Punchers, Paper Tape Reader and Line Printers),
will apply to the standard version of the equipment.
Where modifications are required, supplementary test
data will be provided to confirm that the "Tempest"
integrity has been maintained. However, SHAPE, reserves
the right to test and reject either at factory or on
site, any equipment that does not come within the limits
laid down in AMSG 720-A.
8.5 Uncertified equipment cannot be accepted and many equipment
which has not received certification must be submitted
to a qualified national COMSEC authority for testing
and certification. ACE COMSEC is not an approving or
testing authority for TEMPEST certification.
A̲p̲p̲e̲n̲d̲i̲x̲ ̲A̲-̲1̲
* Line printer not provided under this contract
CAMPS DEVELOPMENT SYSTEM
Figure 3.1
A̲p̲p̲e̲n̲d̲i̲x̲ ̲A̲-̲2̲
D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲s̲y̲s̲t̲e̲m̲ ̲-̲ ̲T̲Y̲P̲E̲ ̲A̲N̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲V̲I̲T̲Y̲ ̲O̲F̲ ̲P̲E̲R̲I̲P̲H̲E̲R̲A̲L̲S̲.̲
T̲y̲p̲e̲ Number of Number of C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲ ̲t̲y̲p̲e̲
D̲e̲v̲i̲c̲e̲s̲ C̲o̲n̲n̲e̲c̲t̲.̲
VDU 5 5 Metallic
MSP - 3 Metallic - Serial
LP - 1 Metallic - Parallel
Dual Floppy 1 N/A -
SMD 3 N/A -
APPENDIX A-3
-------------
HARDWARE DELIVERABLES
Temp.
CR-Number. Name Unit T. Total OEM
Price Sys Price
Dkr. ea. Dkr.
--------------------------------------------------------------
2 CR80 PROCESSOR UNIT
MODULES
------------------------------
21 CR8003M/040PC/00 CPU/CACHE 116,059
1 116,059
25 CR8020M/000PC/00 MAP
89,181
1
89,181
26 CR8071M/010--/00 MIA
40,486
1
40,486
29 CR8016M/512PC/00 512
K RAM 162,840 3 488,520
3 CR80 CHANNEL UNIT MODULES
----------------------------
31 CR8081M/010A-/00 CIA-A
25,020
2
50,040
33 CR8044M/041AB/00 DISC
CTL/32K 64,194 2 128,388
34 CR8084M/010--/00 DCA
10,465
2
20,930
35 CR8047M/040AB/00 ST
FD CTLR 38,742 1
38,742
36 CR8087M/010--/00 SFA
5,124
1
5,124
37 CR8066M/010AB/00 LTU,SYNC/16K
34,688
2
69,376
38 CR8082M/010--/00 LIA-N
3,731
2
7,462
3A CR8046M/040AB/00 PAR
CTRL 37,796 1
37,796
3D CR8086M/010--/XX PCA
10,877
1
10,877
5 TDX SYSTEM MODULES
---------------------
5A CR80109/000--/00 V28
ADAP 4C 26,511 1
26,511 X
5B CR80110/000--/00 V28L
ADAP 1C 29,428 5 147,140 X
5E CR8105S/010--/00 FAN
UNIT,CTX 5,190
1
5,190
5F CR1104S/000--/00 ADAP
CRATE 15,656 2
31,312
5G CR1102S/000--/00 ADAP POW SUP 28,104 2
56,208 X
5L CR1100S/000--/00 BP-8
2,771
3
̲
̲
̲
̲8̲,̲3̲1̲3̲
1,377,655
Temp.
CR-Number. Name Unit T. Total OEM
Price SYS Price
Dkr. ea. Dkr.
---------------------------------------------------------------
7 CR80 RACK, CRATES, ACCESSORIE
--------------------------------
73 RACK,EMI,1,(LE,RH)
)
74 RACK,EMI,1,(LE,LH)
)
75 RACK,EMI,2,(RE,RH)
) 121,021 )3 363,063 X
76 RACK,EMI,2,(RE,LH)
)
77 RACK,EMI,3,( I,RH)
)
78 RACK,EMI,3,( I,LH)
)
7B CR8108-/220--/00 MAINS
SWITCH 7,885 3
23,655
7D CR8107-/010--/00 POW
DIST PAN 3,114
4
12,456
7E CR8050M/010--/00 POW
SUPPLY 20,350 2
40,700
7G CR8125M/225PC/00 PU
CRATE 58,081 1
58,081
7H CR8125M/425AB/00 CU
CRATE 68,077 1
68,077
7J CR8105M/020--/00 FAN
UNIT 16,118 2
32,236
7K CR8055M/020--/00 MBT(PU)
3,250
5
16,250
7L CR8211M/738--DATA CHAN
TERM 3,483 1
3,483
RACK 19" 0
0 X
7P FILTER BOX 55,920
1
55,920 X
7Q POWER LINE FILTER 7,631
1
7,631 X
8 CR80 CABLES
--------------
81 CR8201D DATA CHAN CABLE
1,682
1
1,682
86 CABLE, FLOPPY DISK
631
1
631
8A CR8201S POW CABLE 0,5M )
)
8D CR8201S POW CABLE 2,5M )
)
8E CR8201S POW CABLE 3,5M )
542
)
9
4,878
8F CR8201D POW CABLE 0,5M )
)
8G CR8201D POW CABLE l,0M )
)
8H CR8201D POW CABLE 1,5M )
)
8W POWER CABLE l,0MM l,0M
)
8X POWER CABLE l,0MM l,5M
542
4
2,168
8Y POWER CABLE l,0MM 2,5M
)
CABLE, LINE PRINTER 625 1 ̲ ̲
̲ ̲6̲2̲5̲
691,530
Temp.
CR-Number. Name Unit T. Total OEM
Price SYS Price
Dkr. ea. Dkr.
-----------------------------------------------------------------------
9 V24 SIGNAL CABLES
--------------------
91 V24 CABLE 9A/240
92 V24 CABLE 9A/270
93 V24 CABLE 9A/300
94 V24 CABLE 9A/330
95 V24 CABLE 10A/360
96 V24 CABLE 9A/390
97 V24 CABLE 17A/270
656 27 17,712
98 V24 CABLE 17A/300
99 V24 CABLE 17A/330
9A V24 CABLE 17A/360
9B V24 CABLE 10B/240
9C V24 CABLE 10E/150
9U FILTERED CONN 10 POL
2,464
8 19,712 X
G MECHANICS
------------
GW LUMP SUM PER RACK 1,947
3
5,841
H PERIPHERAL EQUIPMENT
-----------------------
H1 VDU, TEMPEST
179,426 5 897.130 X
J MASS STORAGES
----------------
J1 CR8300-/080--/00
DISK DRV SMD 175,780 3 527,340 X
J6 CR8308-/216--/00
FD ST 2xSGL 28,522 1 ̲ ̲ ̲2̲8̲,̲5̲2̲2̲ X
1,496,257
691,536
̲ ̲ ̲1̲,̲3̲7̲7̲,̲6̲5̲5̲
Total (App. A) 3,565,448
A̲p̲p̲e̲n̲d̲i̲x̲ ̲A̲-̲3̲
SOFTWARE DELIVERABLES
o STIMULATOR (Package System Test Utility)
o TEST COMMAND INTERPRETER (Module Test Utility)
A̲p̲p̲e̲n̲d̲i̲x̲ ̲B̲-̲1̲
CAMPS VDU TEST DRIVE SYSTEM
Figure 3.1
A̲p̲p̲e̲n̲d̲i̲x̲ ̲B̲-̲1̲
CAMPS MESSAGE TRAFFIC TEST DRIVE SYSTEM
Figure 3.2
A̲p̲p̲e̲n̲d̲i̲x̲ ̲B̲-̲2̲
T̲E̲S̲T̲ ̲D̲R̲I̲V̲E̲ ̲S̲Y̲S̲T̲E̲M̲ ̲-̲ ̲N̲U̲M̲B̲E̲R̲ ̲A̲N̲D̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲V̲I̲T̲Y̲ ̲O̲F̲ ̲P̲E̲R̲I̲P̲H̲E̲R̲A̲L̲S̲
A. V̲D̲U̲ ̲T̲E̲S̲T̲ ̲D̲R̲I̲V̲E̲ ̲S̲Y̲S̲T̲E̲M̲
PORTS ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲O̲N̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Peripheral Wired Equipped DEVICES SLAVE OPTO METALLIC CAMPS OPTO METALLIC
REF
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
VDU 23 23 3 - - 3 20
-
20
MSP 1 1 1* 1 - 1 -
-
-
SMD 1 1 1 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ N/A ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Dual
Floppy 1 1 1 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ N/A ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
B. M̲E̲S̲S̲A̲G̲E̲ ̲T̲R̲A̲F̲F̲I̲C̲ ̲T̲E̲S̲T̲ ̲D̲R̲I̲V̲E̲ ̲S̲Y̲S̲T̲E̲M̲
PORTS ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲C̲O̲N̲N̲E̲C̲T̲I̲O̲N̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Peripheral Wired Equipped DEVICES SLAVE OPTO METALLIC CAMPS OPTO METALLIC
REF
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
VDU 6 6 6 - - 6 -
-
-
MSP 5 5 6* 1 - 5 -
-
-
TARE 4 4 - - - - 4
-
4
Low
Speed 24 24 - - - - 24
-
24
SCARS 1 1 - - - - 1
-
1
CCIT 1 1 - - - - 1
-
1
SMD 1 1 1 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ N/A ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Dual
Floppy 1 1 1 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ N/A ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
* CR equipment shall support this number of devices. Devices
not purchased under this contract.
A̲p̲p̲e̲n̲d̲i̲x̲ ̲B̲-̲3̲
VDU
Test Mes.
CR-Number. Name Unit Drv. Trf. To-
Total OEM
Price Sys TDS tal
Price
Dkr. ea. ea. ea.
Dkr.
--------------------------------------------------------------------------
2 CR80 PROCESSOR UNIT
MODULES
------------------------------
21 CR8003M/040PC/00 CPU/CACHE 116,059
3 3 6
696,354
25 CR8020M/000PC/00 MAP
89,181
1 1 2
178,362
26 CR8071M/010--/00 MIA
40,486
1 1 2
80,972
27 CR8021M/010-C/01 STI
81,976
1 1 2
163,952
28 CR8073M/010--/00 TIA
22,169
1 1 2
44,338
29 CR8016M/512PC/00 512
K RAM 162,840
3 3 6
̲
̲
̲9̲7̲7̲,̲0̲4̲0̲
2,141,018
3 CR80 CHANNEL UNIT MODULES
----------------------------
31 CR8081M/010A-/00 CIA-A
25,020
1 1 2
50,040
33 CR8044M/041AB/00 DISC
CTL/32K 64,194
1 1 2
128,388
34 CR8084M/010--/00 DCA
10,465
1 1 2
20,930
35 CR8047M/040AB/00 ST
FD CTLR 38,742
1 1 2
77,484
36 CR8087M/010--/00 SFA
5,124
1 1 2
10,248
37 CR8066M/010AB/00 LTU,SYNC/16K
34,688
1 2 3
104,064
38 CR8082M/010--/00 LIA-N
3,731
1 5 6
22,386
39 CR8066/020AB/00 LTU,
SYNC/32K 43,688
- 2 2
̲
̲
̲8̲7̲,̲3̲7̲6̲
500,916
5 TDX SYSTEM MODULES
---------------------
51 CR1070S/000--/00 TDX
CONTL'R 23,799
1 1 2
47,598
52 CR2501 X-NET CABLE TERMINATION
499
4 4 8
3,992
53 CR2500 (100M) X-NET
CABLE 1,405
1 1 2
2,810
54 CR2510-/000--/00 X-NET
OUTLET 1,127
5 7 12
13,524
55 CR1074S/000--/00 BSM-X
15,712)
3 5 8
125,696
56 CR1066-/000--/00 BSM-X
PANEL )
57 CR1060S/000--/00 LTUX
TYPE1 23,855 - 2 2
47,710
58 CR1060S/000--/00 LTUX,TYPE2 23,855 - 2 2
47,710
59 CR1060S/000--/00 LTUXS
TYPE3 23,855 - 6 6
143,130
60 CR1060S/000--/00 LTUXS
TYPE4 23,855
5 - 5
119,275
5A CR80109/000--/00 V28
ADAP 4C 26,511
6
10
16
424,176 X
5B CR80110/000--/00 V28L
ADAP 1C 29,428
6
6
176,568 X
5C CR1053S/000--/00 5U
CTX-CRATE 15,656
3 5 8
125,248
5D CR8022S/000--/00 POWER
SUPPLY 36,597
3 5 8
292,776
5E CR8105S/010--/00 FAN
UNIT,CTX 5,190
3 4 7
36,330
5F CR1104S/000--/00 ADAP
CRATE 15,656
1 2 3
46,968
5G CR1102S/000--/00 ADAP POW SUP 28,104
4 7
11
309,144 X
5L CR1100S/000--/00 BP-8
2,771
1 4 5
̲
̲
̲1̲3̲,̲8̲5̲5̲
1,976,510
4,618,444
VDU
Test Mes.
CR-Number. Name Unit Drv. Trf. To-
Total OEM
Price Sys TDS tal
Price
Dkr. ea. ea. ea.
Dkr.
--------------------------------------------------------------------------
6 CR80 SPECIAL MODULES
-----------------------
7 CR80 RACK, CRATES, ACCESSORIE
--------------------------------
73 RACK,EMI,1,(LE,RH)
) )
74 RACK,EMI,1,(LE,LH)
) )
75 RACK,EMI,2,(RE,RH)
) 121,021 )3 4 7
847,147 X
76 RACK,EMI,2,(RE,LH)
) )
77 RACK,EMI,3,( I,RH)
) )
78 RACK,EMI,3,( I,LH)
) )
7B CR8108-/220--/00 MAINS
SWITCH 7,885
3 4 7
55,195
7D CR8107-/010--/00 POW
DIST PAN 3,114
4 5 9
28,026
7E CR8050M/010--/00 POW
SUPPLY 20,350
3 3 6
122,100
7G CR8125M/225PC/00 PU
CRATE 58,081
1 1 2
116,162
7H CR8125M/425AB/00 CU
CRATE 68,077
1 1 2
136,154
7J CR8105M/020--/00 FAN
UNIT 16,118
2 2 4
64,472
7K CR8055M/020--/00 MBT(PU)
3,250
4 6
10
32,500
7L CR8211M/738--DATA CHAN
TERM 3,483
1 1 2
6,966
7M CR8055M/020AB/00 MBT
(CU) 3,250
2 - 2
6,500
7P FILTER BOX 55,920
1 1 2
111,840 X
7Q POWER LINE FILTER
7,631
1 2 3
22,893 X
7R RACK TROLLIES 1,000
18
̲
̲
̲1̲8̲,̲0̲0̲0̲
1,567,955
8 CR80 CABLES
--------------
81 CR8201D DATA CHAN CABLE
1,682
1 1 2
3,364
82 CABLE,BSM-X-X-NET OUTL
625
3 5 8
5,000
83 CABLE,TIA-X-NET OUTL
878
1 1 2
1,756
84 CABLE,TDXCTRL-X-NET
OUTL 565
1 1 2
1,130
86 CABLE, FLOPPY DISK
631
1 1 2
1,262
8A CR8201S POW CABLE 0,5M )
)
8D CR8201S POW CABLE 2,5M )
)
8E CR8201S POW CABLE 3,5M )
542
)
18
23
41
22,222
8F CR8201D POW CABLE 0,5M )
)
8G CR8201D POW CABLE l,0M )
)
8H CR8201D POW CABLE 1,5M )
)
8J Ground Wire for BP-8
158
1 3 4
̲
̲
̲
̲
̲
̲6̲3̲2̲
35,366
1,603,321
VDU
Test Mes.
CR-Number. Name Unit Drv. Trf. To-
Total OEM
Price Sys TDS tal
Price
Dkr. ea. ea. ea.
Dkr.
--------------------------------------------------------------------------
8M Ground Wire 158 15
18
33
5,214
8W POWER CABLE l,0MM l,0M
)
8X POWER CABLE l,0MM l,5M
542
)
5 6
11
5,962
8Y POWER CABLE l,0MM 2,5M
)
A1 Internal Cable type
1 394
1 3 4
1,576
A2 BSM to TDX Cable
293
1 1 2
̲
̲
̲
̲
̲5̲8̲6̲
13,328
9 V24 SIGNAL CABLES
--------------------
91 V24 CABLE 9A/240
92 V24 CABLE 9A/270
93 V24 CABLE 9A/300
94 V24 CABLE 9A/330
95 V24 CABLE 10A/360
96 V24 CABLE 9A/390
97 V24 CABLE 17A/270
656
8
40
48
31,488
98 V24 CABLE 17A/300
99 V24 CABLE 17A/330
9A V24 CABLE 17A/360
9B V24 CABLE 10B/240
9C V24 CABLE 10E/150
9U FILTERED CONN 10 POL
2,464
-
24
24
59,136 X
9V FILTERED CONN 18 POL
3,114
- 8 8
24,912 X
9W V24 CABLE TO PERIPH.
( 25M) INCL. TERMI-
NATION 1,580 24 44 68
̲
̲1̲0̲7̲,̲4̲4̲0̲
222,976
G MECHANICS
------------
GW LUMP SUM PER RACK
1,947
3 4 7
13,629
H PERIPHERAL EQUIPMENT
-----------------------
H1 VDU, TEMPEST
130,000
3 6 9 1,170,000 X
H3 MOUNTING TABLE 11,329
3 6 9
101,961 X
J MASS STORAGES
----------------
J1 CR8300-/080--/00
DISK DRV SMD 175,780 1 1 2
351,560 X
J2 CR8319-/080--/00
DISK PACK, 80MB 5,428 4 4 8
43,424 X
J6 CR8308-/216--/00
FD ST 2xSGL 28,522 1 1 2
̲
̲
̲5̲7̲,̲0̲4̲4̲ X
1,737,618
1,973,932
Total (App. B) 8,195,697
A̲P̲P̲E̲N̲D̲I̲X̲ ̲B̲-̲4̲
TEST DRIVE SYSTEM - SOFTWARE items to be supplied
o VDU SIMULATOR
o TRAFFIC GENERATOR SOFTWARE CONSISTING OF
o STIMULATOR
o CAMPS SOFTWARE
o TEST SCRIPT PREPARATION TOOLS
o DAMOS
o TOS
o EDITOR