I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
This statement of work (SOW) for delivery of the NEC CCIS
com- munication subsystem (CDIMS) identifies the Work Packages
which constitute Christian Rovsing A/S (CRAS) deliveries.
CRAS deliveries group in three major tasks:
a. Development and delivery from CRAS plant of CDIMS
subsystems which fulfill the appropriate requirements
as identified in this SOW.
b. Support of CDIMS systems delivered to Burroughs
FSSG in Paoli, Pa. (4 systems) and McLean, Va (1
system).
c. Logistics support including site survey and installation
support.
All schedules given in this document are relative to award
of CDIMS order by Burroughs Corporation to Christian Rovsing
A/S
W̲P̲ ̲D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲
WP 1…02…Hardware
WP 1.1.9…02…Other Equipment
WP 2.1.1…02…Operating System
WP 2.1.5…02…Diagnostics
WP 2.2.1…02…Communications Processing
WP 4.1.3…02…Test Procedures
WP 4.1.4…02…Test Reports
WP 4.2.1…02…Hardware CI Test
WP 4.2.2…02…Software CPCI Test
WP 4.2.5…02…System Test and Support
WP 5.1.2…02…System Analysis
WP 5.1.3…02…System Integration
WP 5.1.4…02…RMA Programme
WP 5.1.5…02…EMI/EMC Programme
WP 5.1.7…02…Hardware New Design
WP 5.2.1…02…Programme Office
WP 5.2.2/3/4…02…Config Man/QA/Inspec/Travel
WP 6…02…Documentation
WP 7.1.…02…ILS Management Organization
WP 7.2.1…02…Site Spares
WP 7.3.2…02…Provisioning Conference
WP 7.5.1…02…Site Survey
WP 7.5.2…02…Facility Design Criteria
WP 7.5.4…02…Transportation
WP 7.5.5…02…Packing/Packaging
WP 7.6.1…02…Training Burroughs FEs
WP 7.6.3.1…02…CRAS Site Facility Cost
WP 7.6.3.2/3…02…SDC/GVL Sites
WP 7.6.4…02…Installation/C-O and Maintenance Support
W̲P̲ ̲1̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the manufacturing, integration,and factory
acceptance of the hardware of the 19 NEC CCIS CDIMS
subsystems. It consists of the CR80D modules and equipment
as described in the Burroughs proposal II/3/4 and II/3/5
B̲l̲o̲c̲k̲ ̲D̲i̲a̲g̲r̲a̲m̲
Refer Burroughs Proposal Figure II/3-4-1.
E̲q̲u̲i̲p̲m̲e̲n̲t̲/̲I̲t̲e̲m̲ ̲L̲i̲s̲t̲
Refer Burroughs Proposal Table II/1-2-3
Table II/1-2-6
Table II/1-2-9
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
CRAS may delay production provided the required site
de- livery is not missed. CRAS will provide storage
for integrated CDIMS systems for the period between
factory acceptance test (considered f.o.b. delivery)
and scheduled site delivery (refer Burroughs proposal
Figure III-1-10).
E̲x̲c̲l̲u̲s̲i̲o̲n̲s̲
Burroughs will provide required paper tape readers.
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 4.2.1 and 4.2.2 CI/CPCI Test
- WP 7.5.4 and 7.5.5 Transportation and Packaging
R̲e̲l̲a̲t̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
N/A.
…02…S̲c̲h̲e̲d̲u̲l̲e̲
The hardware deliveries are as follows:
a. At the end of the 14th month shipment from CRAS
of 3 CR80D systems with limited CDIMS capability
in form of interface capability to B 5900 as well
as to Aydin Controller. Two of the systems will
be shipped to Burroughs FSSG, Paoli, Pa. while
the third will be shipped to SDC, McLean, Va. One
of the systems will be equipped with disks.
b. At the completion of the CDIMS CI/CPCI tests (end
of month 19) shipment from CRAS of those additional
CR80D modules which are required to upgrade the
three previously shipped systems to respectively
the ACBA SWHQ, NORCCIS PSC/CRC and RSSC CDIMS configurations.
…02…c. Shipment at the end of the 22nd month to Burroughs
FSSG, Paoli of the second NORCCIS PSC as well as a
CRC configuration.
…02…d Delivery f.o.b. CRAS, Ballerup of the remaining 14
CDIMS configurations as follows:
Configuration Factory Scheduled
Acceptance Site
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲T̲e̲s̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲
̲ ̲
AFNORTH (CRAS dev system) - 38
CRC (2) 22 37/44
Air Station (3) 24 29/37/39
ACBA Air Base (3) 26 30/31/32
ACBA Air Base (3) 28 33/34/35
Air Station (2) 30 39/44
W̲P̲ ̲1̲.̲1̲.̲9̲ ̲ ̲O̲t̲h̲e̲r̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the delivery of cables between the CR80D
and other equipment as follows:
a. C̲o̲m̲m̲u̲n̲i̲c̲a̲t̲i̲o̲n̲ ̲e̲q̲u̲i̲p̲m̲e̲n̲t̲
Not included
b. D̲i̲s̲p̲l̲a̲y̲ ̲c̲o̲n̲t̲r̲o̲l̲l̲e̲r̲s̲
Optical fibre to 142 Aydin controllers inclusive
associated transceivers/transmitters in both ends
as specified in the Burroughs proposal.
128 connections each below 500 m
14 connections each below 4 km
S̲c̲h̲e̲d̲u̲l̲e̲
Available f.o.b. CRAS, Ballerup 1 month prior to scheduled
site delivery (refer Burroughs proposal Figure III-1-10).
WP 2.1.1 O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲S̲y̲s̲t̲e̲m̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the delivery of a DAMOS operating system
with each of the CDIMS subsystems. It includes the
delivery of CDIMS DAMOS development utilities only
as part of the RSSC delivery as described in the Burroughs
Proposal II/4/3.1 respectively II/4/3.3.
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 2.2.1
S̲c̲h̲e̲d̲u̲l̲e̲
Delivered with CDIMS hardware deliveries.
WP 2.1.5 D̲i̲a̲g̲n̲o̲s̲t̲i̲c̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the delivery of the diagnostic package
of the following CR80D modules of the CDIMS:
- CPU/CACHE
- RAM
- STI/SBA
- MAP/MIA
- CIA-A/B
- LTU
- Disk Ctl'r/DCA
- Burroughs CTL'r/BCA
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 1 Hardware
S̲c̲h̲e̲d̲u̲l̲e̲
Delivered with CDIMS hardware deliveries.
WP 2.2.1 C̲o̲m̲m̲u̲n̲i̲c̲a̲t̲i̲o̲n̲s̲ ̲P̲r̲o̲c̲e̲s̲s̲i̲n̲g̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the detailed design, coding, test and
in- tegration of software and LTU-firmware for the
CDIMS sub- system as described in the Burroughs proposal:
- II/1/2.3.4.1.2.1 - Bootstrap Loader
- II/2.3.4.2.6 - Communication Software
- II/1/2.7.4 - Communication Interface
Modules
- II/4/3.2 - Communication Software
…02…E̲q̲u̲i̲p̲m̲e̲n̲t̲/̲I̲t̲e̲m̲ ̲L̲i̲s̲t̲ ̲(̲C̲P̲C̲s̲)̲
Communication Software
o Protocol Drivers (LTU-firmware)
- X25/2 SCCIWG
- X25/2 NDDN
- LINK-1
- TOSCA
- PTR/PTP
- CAMPS VDU
- CRYPTO Monitoring/Control
o Conversion Handlers
- Comm Line ITA-5 Conversion
- ITA-2 Conversion
- Display Data Conversion
- Link-1 Data Conversion
o Control/Dispatch (Basic Transport Service)
- Message Dispatch Control
- Replication of Data Stream
- Overall Monitoring and Status
o Burroughs Interface Driver
o Bootstrap Loader
- Bootstraploader
- Basic Maintenance Utilities
o Backup Programs
- ACBA SWHQ Msg. Prep. Back-up
- Air Base Back-up
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
In order to fulfil the schedule Burroughs shall supply
specifications and equipment as follows:
3̲r̲d̲ ̲m̲o̲n̲t̲h̲
o Front-end Interface Specification Burroughs/CR80D
interface as outlined in Burroughs Memo 52211-JPG-0218
from J.Gibson dated 29.Sep.80.
o External Interface Protocol Specifications,
i.e.
- X25 SCCIWG
- X25 NDDN
- TOSCA
- LINK-1
- PTR/PTP
- Crypto
including electrical and protocol specification
4̲t̲h̲ ̲m̲o̲n̲t̲h̲
o Definition of data format for Aydin (EBCDIC
con- version)
6̲t̲h̲ ̲m̲o̲n̲t̲h̲
o Final Functional Display Operation Specification
(to enable implementation of ITD to VDU conversion)
9̲t̲h̲ ̲m̲o̲n̲t̲h̲
o Burroughs B 5900 running at CRAS, Ballerup
by start of 9th month
o Burroughs provide Paper Tape Reader
1̲0̲t̲h̲ ̲m̲o̲n̲t̲h̲:̲
o Aydin controller with ITD and IGD as a minimum
running at CRAS, Ballerup by start of 10th
month
1̲4̲t̲h̲ ̲m̲o̲n̲t̲h̲
o At least two Aydin Controllers connected to
one of each display type up and running at
CRAS by start of month 14
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 2.1.1 Operating System (DAMOS)
- WP 5.1.3 System Integration (CDIMS Dev. Spec.)
- WP 4.2.2 Software CPCI Test
S̲c̲h̲e̲d̲u̲l̲e̲
The communication Processing is partioned in two separate
tasks, the Bootstrap-loader and the operational Communication
Processing; the latter consists of two phases of which
the first phase consists of providing a single path
from the B 5900 through the CDIMS to an Aydin Controller
while the second consists of the upgrades required
for the final CDIMS operational program.
…02…a̲.̲ ̲B̲o̲o̲t̲s̲t̲r̲a̲p̲-̲l̲o̲a̲d̲e̲r̲ ̲(̲C̲P̲C̲)̲
4 start of detailed design
6-7 preliminary Product Spec (Dev. Spec.)
10 start test versus B 5900 controller prototype
12 CPC complete
b̲.̲ ̲O̲p̲e̲r̲a̲t̲i̲o̲n̲a̲l̲
b.1. P̲h̲a̲s̲e̲ ̲1̲
7 Availability of CDIMS development spec
10 Product Specification
14 Integration Complete
b.2 P̲h̲a̲s̲e̲ ̲2̲
18 CDIMS Integration Complete…86…1 …02… …02… …02…
WP 4.1.3 T̲e̲s̲t̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the preparation based upon the Burroughs
Requirements Specifications of the test procedures
ap- plicable to the CDIMS subsystem with respect to
vali- dation of the performance of the following
- CDIMS Hardware (CI Test)
- CDIMS Software (CPCI Test)
E̲q̲u̲i̲p̲m̲e̲n̲t̲/̲I̲t̲e̲m̲ ̲
- CI test procedure
- CPCI test test procedure
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Specifications available as defined in WP 2.2.1
and WP 5.1.7
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 2.2.1 Communications Processing
- WP 5.1.7 Hardware New Development
R̲e̲l̲a̲t̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
o Burroughs Proposal
o Burroughs Interface Specifications
- electrical
- logical interface
o External Interfaces
S̲c̲h̲e̲d̲u̲l̲e̲
The test procedure will be available 4 months and shall
be agreed upon 3 months prior to conduct of the associated
tests.
WP 4.1.4 T̲e̲s̲t̲ ̲R̲e̲p̲o̲r̲t̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the manpower required to finalize the
CI/CPCI test reports of the CDIMS subsystem.
E̲q̲u̲i̲p̲m̲e̲n̲t̲/̲I̲t̲e̲m̲ ̲L̲i̲s̲t̲
- CI test report
- CPCI test report
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- 4.2.1 CI Test
- 4.2.2 CPCI Test
S̲c̲h̲e̲d̲u̲l̲e̲
The Test Report is due for delivery one month after
the completion of CI/CPCI test .
WP 4.2.1 H̲a̲r̲d̲w̲a̲r̲e̲ ̲C̲I̲ ̲T̲e̲s̲t̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the conduction at CRAS, Ballerup of
the hardware CI test of the CDIMS in accordance with
the as- sociated test procedure .
It includes development of special test software antici-
pated for the CI Test.
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 5.1.7 Hardware New Design
R̲e̲l̲a̲t̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
- WP 4.1.3 Test Procedure (CI)
S̲c̲h̲e̲d̲u̲l̲e̲ ̲
This WP is scheduled as the first two weeks of month
19.
WP 4.2.2 S̲o̲f̲t̲w̲a̲r̲e̲ ̲C̲P̲C̲I̲ ̲T̲e̲s̲t̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This item covers the conduction at CRAS, Ballerup of
the software CPCI test of the CDIMS in accordance with
the associated test procedure .
It includes development of special test software antici-
pated for the CPCI Test.
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 4.1.3 Test Procedure (CPCI)
- WP 1 Hardware (item b)
S̲c̲h̲e̲d̲u̲l̲e̲
This WP is scheduled at the end of the hardware CI
test as the later two weeks of month 19.
WP 4.2.5 S̲y̲s̲t̲e̲m̲ ̲T̲e̲s̲t̲ ̲a̲n̲d̲ ̲S̲u̲p̲p̲o̲r̲t̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the on-site CRAS system/hardware/software
engineering support at field site required for the
CDIMS hardware and software.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Burroughs shall provide the recommended tools and test
equipment required for the CR80D system.
S̲c̲h̲e̲d̲u̲l̲e̲
A major part of this support is expected to take place
during the LOC at ACBA SWHQ.
WP 5.1.2 S̲y̲s̲t̲e̲m̲ ̲A̲n̲a̲l̲y̲s̲i̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS services with CDIMS related items
of the following areas:
o system overall design (front-end trade-offs)
o update of system specification
o prepare material for design reviews (SDR,
PDR, and CDR) for CDIMS CI/CPCI at CRAS, Ballerup
o conduct design reviews at CRAS, Ballerup of
hardware/software items for which CRAS is
responsible
o participate in major design reviews
o limited participation in working groups con-
cerned with external interfaces
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Burroughs shall provide CRAS with the following in-
formation
m̲o̲n̲t̲h̲ ̲0̲
hardware spec on Burroughs/CR80D interface (relevant
version of SDS 2323-7472 and SDS 1947-5011 specifications)
otherwise as for WP 2.2.1
S̲c̲h̲e̲d̲u̲l̲e̲
The front-end trade-offs and System Design part is
anticipated to take place in US while the remaining
takes plase as the CRAS plant, Ballerup..
WP 5.1.3 S̲y̲s̲t̲e̲m̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS contribution to level B-spec (de-
velopment design specification) for the CDIMS.
It includes the conduction of preliminary and critical
design reviews at CRAS, Ballerup.
It includes the engineering input required with respect
to documentation and review of same.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
In order to meet the schedule Burroughs shall provide
specifications to CRAS as specified in WP 2.2.1 and
5.1.7
Timely delivery of this and dependant Work Packages
depends upon acceptance of System Design (WP 5.1.2)
by end of month 3.
S̲c̲h̲e̲d̲u̲l̲e̲ ̲
Development Specification complete at end of month
7.
WP 5.1.4 R̲M̲A̲ ̲P̲r̲o̲g̲r̲a̲m̲m̲e̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲
This WP covers CRAS support to Burroughs as follows:
o reliability: provide Burroughs with failure rates
for supplied CR80D modules in accordance with
MIL-HDBK-217C
o maintainability: provide Burroughs with values
of MTTR's of applicable modules
o provide information as requested by Burroughs
on maintainability plan and demonstration
S̲c̲h̲e̲d̲u̲l̲e̲ ̲
Data on MTBF and MTTR on all but specially developed
modules will be provided by month 6.
Values related to specially developed modules will
be available at CI Test.
WP 5.1.5 E̲M̲I̲/̲E̲M̲C̲ ̲P̲r̲o̲g̲r̲a̲m̲m̲e̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers a CRAS report to Burroughs with EMI/EMC
data related to the CDIMS processor equipment.
WP 5.1.7 H̲a̲r̲d̲w̲a̲r̲e̲ ̲N̲e̲w̲ ̲D̲e̲s̲i̲g̲n̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the following hardware development:
- B 5900 if controller…02… - optical
transceivers
Included are the associated hardware module development
as well as product specification.
The diagnostic software related to the B 5900 controller
is included in this WP.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
This WP is dependant on a timely delivery by Burroughs
of specifications for the
- electrical interface (day 0)
- front-end interface protocol spec (month 3)
It is dependant on timely availability of running B
5900 (refer WP 2.2.1)
R̲e̲l̲a̲t̲e̲d̲ ̲W̲o̲r̲k̲ ̲P̲a̲c̲k̲a̲g̲e̲s̲
- WP 4.2.1 Hardware CI test
S̲c̲h̲e̲d̲u̲l̲e̲
The Development Spec will be available at end of 4th
month (PDR) while the Product Spec will be available
at end of 8th month.(CDR)
WP 5.2.1 P̲r̲o̲g̲r̲a̲m̲ ̲O̲f̲f̲i̲c̲e̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the manpower required to run the CDIMS
program office and includes monthly status reports.
WP 5.2.2/3/4 C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲M̲a̲n̲/̲Q̲A̲ ̲I̲n̲s̲p̲e̲c̲/̲T̲r̲a̲v̲e̲l̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
These WPs cover the manpower and costs associated with
the following tasks:
o Configuration management - includes baseline
management of all specifications and drawings,
site inventory list as well as participation
in configuration Control Board
o conduct QA program and inspection of hardware
and software, including the cost of factory
acceptance test
o Travel expenses
which are related to the CDIMS development at CRAS.
WP 6 D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the technical writing,publication and
reproduction costs of CDIMS documentation.
R̲e̲l̲a̲t̲e̲d̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
o Engineering Data Qty
- HW Dev Spec 10 copies
- HW Product Spec 10 copies
- CDIMS Software Dev Spec 10 copies
- CDIMS Product Spec 10 copies
- Test Procedures 10 copies
- Test Reports 10 copies
o Management Data
- Design Review Data 20 copies
o Technical Publication Data
- Maintenance Manual 100 copies
- Supply Manual (CRAS reorder
procedures) 50 copies
- Program Maintenance Manual 20 copies
- SW Installation Procedures 20 copies
- Programmer User Manuals 20 copies
- Operator User Manuals 20 copies
- Source Code Listings of
CDIMS appl SW 2 + 1 hardcopy
- Software Support Manuals 20 copies
WP 7.1.1 I̲L̲S̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲ ̲O̲r̲g̲a̲n̲i̲z̲a̲t̲i̲o̲n̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers ILS management costs associated with
the CRAS ILS support on the NEC CCIS program.
It includes liaison with Burroughs and sites on ILS
areas where CRAS contributes directly.
WP 7.2.1 S̲i̲t̲e̲ ̲S̲p̲a̲r̲e̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This item covers provision of information to Burroughs
with respect to:
- installed quantity
- failure rate
- unit price
on a line replaceable unit basis and per site.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Dependant on configurations (WP 1)
E̲x̲c̲l̲u̲s̲i̲o̲n̲s̲
No spare parts are provided
NATO codification is not included.
S̲c̲h̲e̲d̲u̲l̲e̲
Due 3rd month.
WP 7.3.2 P̲r̲o̲v̲i̲s̲i̲o̲n̲i̲n̲g̲ ̲C̲o̲n̲f̲e̲r̲e̲n̲c̲e̲ ̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS support to Burroughs prior to and
during spare parts provisioning conference in either
CPH or at Kolsaas.
S̲c̲h̲e̲d̲u̲l̲e̲
The provisioning conference is anticipated to be in
month 4.
WP 7.4.1 S̲i̲t̲e̲ ̲T̲o̲o̲l̲s̲/̲T̲e̲s̲t̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
This WP covers the tools and test equipment required
by CRAS.
E̲x̲c̲l̲u̲s̲i̲o̲n̲s̲
No tools and test equipment will be provided by CRAS.
WP 7.5.1 S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS participation and carry out of
the initial site survey. CRAS will cover the areas
of which CRAS holds the installation responsibility:
- CR80D equipment
- optical fibres between CR80D and Aydin Controller
E̲x̲c̲l̲u̲s̲i̲o̲n̲s̲
Secure cabling between CR80D and customer provided
com- munication termination equipment and CAMPS is
not in- cluded as customer responsibility.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲ ̲
Burroughs has responsibility for the site survey as
well as for finalization of site survey report.
S̲c̲h̲e̲d̲u̲l̲e̲ ̲
CRAS will provide Burroughs with draft report covering
CRAS areas within one month from end of final initial
site survey.
WP 7.5.2 F̲a̲c̲i̲l̲i̲t̲y̲ ̲D̲e̲s̲i̲g̲n̲ ̲C̲r̲i̲t̲e̲r̲i̲a̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS support to Burroughs with respect
to Facility Design Criteria, e.g. floor loading, floor
cut- outs, physical dimensions, weight, power consumption.
S̲c̲h̲e̲d̲u̲l̲e̲
The required information will be provided in report
prior to month 11.
WP 7.5.4 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the shipment, insurance cost associated
with the total of 5 CDIMS systems which are to be delivered
to US.
Burroughs is responsible for site delivery whether
of 5 US-based system or the remaining 14 systems which
are delivered f.o.b. CRAS, Ballerup.
S̲c̲h̲e̲d̲u̲l̲e̲
Refer WP 1.
WP 7.5.5 P̲a̲c̲k̲i̲n̲g̲/̲P̲a̲c̲k̲a̲g̲i̲n̲g̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the packing/packaging costs for all
systems delivered as part of the NEC CCIS program.
In total 13 dual and 6 single configurations.
Packaging will for all systems be for air transportation.
S̲c̲h̲e̲d̲u̲l̲e̲
Refer WP 1
WP 7.6.1 T̲r̲a̲i̲n̲i̲n̲g̲ ̲B̲u̲r̲r̲o̲u̲g̲h̲s̲ ̲F̲E̲'̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the conduction of two 3-week training
courses at CRAS, Ballerup.
The first course will be for 2 US instructors and 6
Tech. Personnel (FEs) from BKurroughs, DK. The last
course will be for 6 Tech Personnel (FEs) from Burroughs,
N.
Courses will be conducted in English and as described
in the Burroughs Proposal.
The WP covers preparation, conduction, materials, fa-
cilities during the length of the course. The level
will be
hardware - pull and replacement basis
software - to the extent required to modify software
by e.g. incorporation of patches and
re-compilation.
S̲c̲h̲e̲d̲u̲l̲e̲
First course month 26-30
Second course month 32-36
WP 7.6.3.1 C̲R̲A̲S̲ ̲S̲i̲t̲e̲ ̲F̲a̲c̲i̲l̲i̲t̲y̲ ̲C̲o̲s̲t̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers the facility costs associated with the
CRAS site until month 38. Facilities will be provided
for
- B 5900 installation with peripherals such as
disks, line printers, mag tape
- a limited number of Aydin controllers and dis-
plays
- dual CDIMS communications front-end with disks,
development VDUs and matrix printer
The WP includes maintenance of CRAS produced equipment.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Burroughs shall be responsible for installation, operation
and maintenance and later refurbishment of B 5900 as
well as Aydin supplied equipment.
S̲c̲h̲e̲d̲u̲l̲e̲
The facilities will be available for installation from
month 8 and until end of month 38.
WP 7.6.3.2/3 S̲D̲C̲/̲G̲V̲L̲ ̲S̲i̲t̲e̲s̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲
This WP covers CRAS hardware and software support of
the five CDIMS communication front-ends installed with
one at SDC, McLean and four at Burroughs, Paoli.
Included is support in form of spare parts as required
to maintain above sites in US. Faulty modules to be
shipped by Burroughs to CRAS, Ballerup for repair.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
Burroughs shall provide at least one TTY-compatible
VDU on each system, which can interface with the CR80D
for software development purposes.
S̲c̲h̲e̲d̲u̲l̲e̲ ̲
US-based support is included for the first 6 months
of the period, as well as the support required for
installation, US of the five systems in question:
o Paoli Sites
- ACBA SWHQ 14-22
- NORCCIS PSC/CRC 14-29
- NORCCIS PSC 29-44
- CRC 22-49
o SDC
- RSSC 14-38
WP 7.6.4 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲/̲C̲h̲e̲c̲k̲-̲o̲u̲t̲ ̲a̲n̲d̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲S̲u̲p̲p̲o̲r̲t̲ ̲
D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲
This WP covers CRAS Technical FE-support during site
in- stallation of the 19 NEC CCIS installations in
Denmark and Norway. CRAS FE participation will cover
installation and Check-out on the site with respect
to the CR80D com- munications front-end and associated
optical fibre cable runs to display controllers.
It includes maintenance support during the warranty
period.
A̲s̲s̲u̲m̲p̲t̲i̲o̲n̲s̲/̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲ ̲
Burroughs has overall installation responsibility.
Cable runs, cableducts, piping etc. is provided by
the customer and is ready before CRAS installation
can take place. It will be the full responsibility
of Burroughs to ensure that site readiness on CRAS
items is ensured through a site verification prior
to installation.
E̲x̲c̲l̲u̲s̲i̲o̲n̲s̲
Secure cabling between CR80D and customer provided
com- munication termination equipment is not included.
S̲c̲h̲e̲d̲u̲l̲e̲
The installation is scheduled as described in Burroughs
proposal III/1.2.3.