DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦cca4a009a⟧ Wang Wps File

    Length: 44041 (0xac09)
    Types: Wang Wps File
    Notes: Progress Minutes no 18+19 
    Names: »1227A «

Derivation

└─⟦d04a935aa⟧ Bits:30006049 8" Wang WCS floppy, CR 0078A
    └─ ⟦this⟧ »1227A « 

WangText

…00……00……00……00…>…0a……00……00…>…0b…>…02…<…00…<…06…9…0d…4…0d…4…01…3…08…3…0d…3…02…3…05……86…1                                           …02…            …02…  …02…           


…02…           

…02…  KNN/830906…02……02…#
PROGRESS MINUTES OF MEETING NO. 19
…02……02…  CAMPS







                           
…02……02……02……02…          …02……0f……0f…83-09-06…02… 19.…02…CR A/S…0e……0e…
                                            


          Minutes of Meeting of the 19th Progress Meeting
          Between SHAPE and CHRISTIAN ROVSING A/S 6th
          September 1983

…0f……0f…SHAPE…0e……0e…
         
Commodore Elfrink          Mr. Gert Jensen
Ltc. H.Hofmann             Mr. K. Nybroe-Nielsen  
                             Mr. B. Strandtoft
Mr.  G. Reynolds           Mr. Uffe R. Holst      
                             Mr. Jan Lauridsen
Mrs. Michel                Mr. Ole Eskedal                       
Mr.  Lohisse          Mr. J. Holm                
Mr.  Wellekens             Mr. Bjarne Berthold   

GQAR K. Hahn


         1.  M̲a̲n̲p̲o̲w̲e̲r̲ ̲o̲n̲ ̲S̲W̲-̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲T̲e̲a̲m̲

             CR believe that sufficient manpower is
             left to complete the project within the
             existing schedule.

         2.  H̲W̲-̲F̲A̲T̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

             On SHAPE request CR stated that CR had
             confidence in the schedule for the Factory
             Acceptance Test. First of all because
             most of the HW has been delivered from
             subcontractors, secondly because firm
             agreements have been made for the remaining
             deliveries.

             CR stated that CR was confident in the
             present installation schedule.

         3.  S̲W̲-̲A̲s̲s̲e̲s̲s̲m̲e̲n̲t̲

             CR stated that all SW will be developed
             by the end of October and system integrated
             and verified.

         4.  C̲o̲n̲d̲i̲t̲i̲o̲n̲s̲ ̲f̲o̲r̲ ̲2̲4̲0̲ ̲H̲o̲u̲r̲s̲ ̲T̲e̲s̲t̲

             CR stated that if an error occurs during
             the 240 hours test, the procedure will
             be as follows:

             The clock will be stopped, the error will
             be corrected, CR will perform sufficient
             regression test to prove that the error
             has been solved. The clock will restart
             from that point in the 240 hours test
             where the regression test is started.

             CR stated that in its understanding this
             was in accordance with the wording in
             the contract: "Accummulated test time
             of 240 hours".



             SHAPE strongly reject and refute the above
             CR interpretation. The issue is left open
             and SHAPE will telex in the very near
             future reflecting SHAPE proposal tabled
             at the meeting.

         5.  S̲e̲c̲u̲r̲i̲t̲y̲ ̲A̲c̲c̲r̲e̲d̲i̲t̲a̲t̲i̲o̲n̲

             CR and SHAPE agreed in a memorandum of
             understanding concerning the security
             accreditation attached as annex A.

         6.  P̲a̲y̲m̲e̲n̲t̲ ̲o̲f̲ ̲I̲n̲v̲o̲i̲c̲e̲s̲ ̲o̲n̲ ̲C̲A̲M̲P̲S̲

             CR handed out an overview of all invoices
             forwarded on the CAMPS program from 1980
             to 31/8 1983.

             Payments remaining on some invoices are
             notified in the overview. SHAPE will go
             through the list and compare it
         SHAPE   with the books at SHAPE. SHAPE will
                 notify CR if their books are not in
                 accordance with CR books and provide
                 information and details of SHAPE Treasury
                 transfer to enable CR to reconcile
                 all grouped payment effected by SHAPE.

         7.  N/A

         8.  F̲A̲T̲ ̲8̲,̲ ̲1̲2̲ ̲a̲n̲d̲ ̲1̲4̲

             Ref.: a)                 CPS/101/TLX/0946

             1   Ref a, sect. 2 (Disk Head Alignment).

                 SHAPE accepted CR's explanation, but
                 wanted the following confirmed:

                 a)  CE maintenance disk is available
                     at site as being purchased under
                     the contract

                 b)  Procedure for alignement available
                     on site documentation.

                 c)  CR confirmed that training in
                     disk head adjustment was included
                     in Existing training course.

                 CR confirmed a) to c).

                 d)  Site level maintenance manual,
                     preventive actions shall list
                     the Disk head alignment with ref.
                     to appropriate manual.



                 e)  CR will provide SHAPE with a recommended
                     procedure to check the validity
                     of the site CE packet, by comparing
                     the site packet with the depot
                     CE packet.

             2   Ref a, sect. 3: VDU Failure Rate

                 SHAPE accepted CR's clarification
                 but asked for the following:

                 a)  CR to issue updated document CPS/TCN/042
                     (Reliability monitoring of DD
                     7260TC VDU).

                     The updated document shall include
                     OMDT-reliability, because VDU
                     as one peripheral includes the
                     OMDT.

         CR      b)  Quarterly issue of updated document.

             3   Ref a, Sect. 4: MSP Problems

                 SHAPE accepted CR's clarification
                 but asked for the following:

                 a)  Repair reports covering the two
                     defective printers shall be sent
                     to SHAPE, when available after
                     repair at TRACOR.

         CR      b)  When all retrofit of the boards
                     with excessive no. of straps on
                     solder side has been executed
                     and when the printers have been
                     tested successfully vitnessed
                     by HMAK, and confirmation report
                     signed by HMAK will be sent to
                     SHAPE.

                 c)  Problems observed in FAT 3 will
                     be analysed into close details
                     by CR.

             4   Ref a, Sect. 5 (STI-DMA Error)

                 CR explained ref a, Sect. 5 and SHAPE
                 accepted CR's explanation.

         CR      The ECO will be forwarded to SHAPE
                 for approval with justification as
                 agreed CR/SHAPE in July-Meeting (1983).

             On receipt of the above SHAPE will release
             payment to CR on the FATs.



         9.  S̲i̲t̲e̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲t̲o̲g̲e̲t̲h̲e̲r̲ ̲w̲i̲t̲h̲ ̲C̲O̲M̲S̲E̲C̲

             SHAPE request to combine installation
             of CR and of ACE COMSEC are due to unpredictable
             problems not acceptable by CR.

         10. C̲A̲M̲P̲S̲ ̲P̲r̲e̲s̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲f̲o̲r̲ ̲a̲l̲l̲ ̲s̲i̲t̲e̲s̲

             SHAPE is planning a CAMPS presentation
             trip to all sites to take place just before
             the SPA.

             CR marketing department (Axel Hvidtfeldt)
             agreed to supply viewgraphs to supplement
             scene 3 of the TV-spot, free of charge.

         11. S̲t̲a̲t̲u̲s̲ ̲a̲t̲ ̲E̲C̲P̲3̲7̲

         SHAPE   SHAPE confirms informally that ECP37
                 will be accepted (SHAPE acceptance
                 telex will follow).

             SHAPE explained that the only deviation
             from ECP37 is that these may be more than
             9 spaces proceeding the text in the text
             strings.

         12. S̲p̲a̲r̲e̲ ̲p̲a̲r̲t̲s̲ ̲l̲i̲s̲t̲s̲ ̲f̲o̲r̲ ̲s̲i̲t̲e̲ ̲a̲n̲d̲ ̲d̲e̲p̲o̲t̲

             ref CAMPS log 1345

             The following is the agreement reached
             on the references msg.

             1.  CR agrees to provide the final updating
                 of the ASPL's at the conclusion of
                 the H/W warranty period.

             2.  CR does not accept that SHAPE do not
                 effect payment for the codification
                 prior to completion of the task, since
                 this task may be required to last
                 up to an undefined date.

         SHAPE   3.  SHAPE will investigate if the
                     codification effort can be limited
                     to a defined period.

         13. M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲M̲a̲n̲u̲a̲l̲

             CR agreed to deliver to all sites, at
             no cost to NATO, a copy of Student Textbooks
             expanded to include for all CR modules
             (e.g. boards) a brief description together
             with block diagrams circuit schematics
             and signal name/pin assignment, which
             may be shown in one diagram.



             The student text book will include the
             system level signal distribution schematics
             showing the signal paths w̲i̲t̲h̲i̲n̲ the crates
             while system level signal distribution
             schematics for signal paths b̲e̲t̲w̲e̲e̲n̲ crates
             already are part of the Hardware Assembly
             breakdown manual.

             The pin assignments of the signal paths
             between crates are shown in the module
             schematics mentioned above.

             SHAPE agrees that above described documents,
             delivered to all sites will allow the
             required maintenance of the site.

             The Student Text Books will have the same
             outlook as other Site Documentation and
             will also be updated up to end of warranty.
             The draft documents will be forwarded
             to SHAPE for review.

             SHAPE's Technical remarks, forwarded to
             CR (see TX Log 1238, dated 3 June 83)
             were discussed during the Progress Meeting.
             Comments are given in attachment B.

             Based on above and the associated appendix,
             SHAPE agrees to approve the maintenance
             manual in accordance with the "critical
             document" approval cycle time and that
             SHAPE agrees that this will constitute
             the final and definitive review. CR agrees,
             however, to correct any errors pointed
             out by SHAPE as a result of the review/approval.

         14. C̲l̲a̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲o̲n̲ ̲D̲e̲l̲i̲v̲e̲r̲a̲b̲l̲e̲

         CR  CR agreed to deliver to SHAPE the source
             code of the application software according
             to the contract. In addition to this CR
             will at no costs submit the latest DAMOS
             source code. This will take place no later
             than at the end of November.

             SHAPE requested a clarification on deliverables
             for system software and support software.
             CR's response is shown in annex C.

             CR confirmed that the penetration test
             could be performed in January 84 with
             the current schedule at CR's plant.



         15. S̲i̲t̲e̲ ̲D̲a̲t̲a̲

             CR pointed out that many site data have
             been inconsistent. It is, therefore, urgent
             that valid and consistent data exist 4
             months before SPA.

             SHAPE stated that a print out containing
             all site data and inconsistencies have
             been promised by CR, but not yet been
             forwarded. CR stated that no manpower
             is available now to work out the site
             data.

             SHAPE will consider in which way they
             could give support to correct the situation.

             CR will support SHAPE in validation of
             the data, when CR has received the baselined
             site data.

             CR need to have the user profiles, terminal
             profiles, device profiles not contained
             in the present data submitted.

         16. Concerning the HW-reliability SHAPE accepted
             the explanation given by CR.






                     A̲N̲N̲E̲X̲ ̲B̲





A̲T̲T̲A̲C̲H̲M̲E̲N̲T̲ ̲T̲O̲ ̲P̲M̲O̲M̲ ̲N̲o̲.̲ ̲1̲9̲ ̲d̲a̲t̲e̲d̲ ̲A̲u̲g̲u̲s̲t̲ ̲3̲0̲t̲h̲ ̲1̲9̲8̲3̲.̲



             SHAPE's remarks from log 1238 have been
             reviewed during the meeting and commented
             as follows:




     para 3.a    CR is still developing SW error reports.

             CR states that all SW error reports will
             be interpreted and the results will be
             incorporated in the maintenance manual
             prior to SPA.

             HW reports are included in issue 1.1 of
             the Maintenance Manual to be sent to SH
             for review within a few weeks.


     para 3.b    In order to meet availability requirements
                 and SHAPE comments the maintenance
                 procedures have been changed:

             instead of closing down a TDX crate to
             test a single channel, the peripheral
             is now tested as the first step.

     SH comments of the following paragraphs have been
     inluded in new version of Maintenance Manual:

     para 4.1/4.2/4.3/4.4/4.5/4.7/4.8/4.20/4.21/4.26/4.27/4.30.


     para 4.6                     Site documentation
                                  will include crate
                                  lay-out and diagrams
                                  (step 1800 will refer
                                  to Student test book
                                    where lay-out is
                                  displayed)

     para 4.9                     CR states that according
                                  to requirements one
                                  of redundant items
                                  may be taken off-line
                                  for tests and maintenance
                                  (see SRS p. 257)

     para 4.10/11/16 CR states that only 2 channels
                     are lost. This is 1 group of external
                     lines (see SRS p.256).

     para 4.12                    One module short
                                  circuits I/O bus.
                                  CR states that the
                                  only way to isolate
                                  the fault is to remove
                                  the CU modules one
                                  by one.










     para 4.13                    CR states that first
                                  action is to check
                                  the access to the
                                  disc controller and
                                  not the drive.

     para 4.14/15                 CR states that a
                                  disk controller has
                                  been assigned to
                                  the off-line PU and
                                  the print-out should
                                  be valid.

     para 4.17                    CR states that system
                                  is not down at this
                                  time. Only a test
                                  on this module is
                                  being performed

     para 4.18                    CR states CAMPS will
                                  not cease operation,
                                  because power remains
                                  on during the replacement
                                  procedure. The temporary
                                  removal of a module
                                  causes a manually
                                  reset.

     para 4.19                    CR states that system
                                  will not go to unknown
                                  status , see Maintenance
                                  Manual, step 3000.
                                  Therefore the proposed
                                  tests are valid.


     para 4.22/24/25 CR states that for TDX the group
                     of user connecting points is 8,
                     and that a group of users may
                     loose  service during maintenance
                     by System Requirements Spec. (p.
                     255). However, if an error occurs
                     in only one channel then tests
                     on the specific peripheral are
                     performed prior to proceeding
                     to the TDX tests.








     para 4.23                    CR states that it
                                  is possible

     para 4.28                    CR states that this
                                  is performed to test
                                  an outlet. All groups
                                  of users of the specific
                                  TDX crate are down.
                                  The test set-up explained
                                  in the maintenance
                                  manual will be more
                                  clearly shown by
                                  means of a figure.

     4.29                         same as for 4.6

                     Step 4800 will refer to the student
                     text book page where lay-out is
                     displayed.

     4.31/32         CR states that the parameters
                     used in the tests indicate the
                     crate, module and channel (ref.
                     to appendix A: Identification
                     of error reporting H/W module.)

     para 5                       CR states that if
                                  an "unreported error
                                  situation" occurs,
                                  the entry points
                                  to the "Off-line
                                  troubleshooting tree"
                                  are given in and
                                  selected from appendix
                                  C to the manual.
                                  

                     For an LTU error the maintenance
                     manual covers fault tracing up
                     to the filterbox of the main site
                     and from the modem at the remote
                     site.


                     The modem test and crypto test
                     is not covered by the maintenance
                     manual, but fault in that part
                     can be confirmed by the M & D
                     test procedures.







                     A̲N̲N̲E̲X̲ ̲C̲


            T̲A̲B̲L̲E̲ ̲1̲…01……01…S̲Y̲S̲T̲E̲M̲ ̲S̲O̲F̲T̲W̲A̲R̲E̲


  S̲W̲ ̲I̲T̲E̲M̲                                           I̲T̲E̲M̲

              M̲M̲ ̲R̲e̲s̲i̲d̲e̲n̲t̲   R̲O̲M̲ ̲R̲e̲s̲i̲d̲e̲n̲t̲        Source       Object
                                                Listings     Code
1. KERNEL          D                                D        D

2. MEMORY MGMT              D                                D         D

3.            DEVICE DRIVERS:

 TDX (System)                     D                 X        D

 VDU (APP.LTUXFW)                 D                 D        D

 DISK CDC/Floppy   D                                X        D

 DMA               D                                X        D

 COMM LINES                        
 (LTU)                            D             D            D

 PRINTER                           
 LTUX APP                         D             D            D

 PAPER TAPE
 READER/PUNCH
 (LTUX)                           D             D            D

 OCR (LTUX
 APPL)                            D             D            D

4.            I/O SYST.
 (DAMOS)      D                                 D            D

5.            FILE
 MANAGEMENT
 SYSTEM       D                                 D            D






D = DELIVERABLE

X = NOT DELIVERABLE.






A̲N̲N̲E̲X̲ ̲C̲…01……01…T̲A̲B̲L̲E̲ ̲2̲…01……01……01…S̲U̲P̲P̲O̲R̲T̲ ̲S̲O̲F̲T̲W̲A̲R̲E̲ ̲D̲E̲L̲I̲V̲E̲R̲A̲B̲L̲E̲S̲ ̲I̲T̲E̲M̲


S̲W̲ ̲I̲T̲E̲M̲                     U̲S̲E̲R̲ ̲G̲U̲I̲D̲E̲S̲    S̲O̲U̲R̲C̲E̲         O̲B̲J̲E̲C̲T̲
                            CR DESIGN
                              DOC.

COMPILERS (SWELL, PASCAL)       D                            D

LINKERS                         D                            D

EDITORS                         D                            D

DEBUGGER                        D                            D

LIBRARY MAT.                    D                            D

M & D PROGRAMS                  D                            D

CROSS RERERENCE GENERATORS      D                            D

SYSTEM GENERATORS               D                            D







                           
…02……02……02……02…          …02……0f……0f…83-06-15…02… 18. …02…CR A/S…0e……0e…
                                            

          Minutes of Meeting of the 18th Progress Meeting
          Between SHAPE and CHRISTIAN ROVSING A/S 14.-15.
          June 1983

…0f……0f…SHAPE…0e……0e…
         
Commodore Elfrink          Mr. Gert Jensen
Ltc. H.Hofmann             Mr. K. Nybroe-Nielsen Mr.
                                                 L.S.
                                                 Nielsen
Ltc. Dlugos                Mr. Uffe R. Holst     Mr.
                                                 B.
                                                 Rinhart
Mrs. Michel                Mr. Ole Eskedal                       Mr.
                                                                 K.
                                                                 Hjort
Mr.  Lohisse          Mr. J. Holm                Mr.
                                                 J.
                                                 Larsen
Mr.  G. Reynolds           Mr. Jan Lauridsen
                           Mr. Bjarne Berthold



GQAR K. Hahn



         1.  W̲e̲e̲k̲l̲y̲ ̲S̲t̲a̲t̲u̲s̲ ̲R̲e̲p̲o̲r̲t̲ ̲o̲n̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲-̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲

             SHAPE requested that the weekly status
             report on software development should
             be expanded to contain the number of test
             cases executed and successfully completed
             together with the planned number of test
             cases for each software builds and associated
             package releases.

         CR  CR agreed to extend the weekly status
             report as requested and to include it
             as part of the progress reports too.

         2.  M̲a̲n̲p̲o̲w̲e̲r̲ ̲o̲n̲ ̲C̲A̲M̲P̲S̲ ̲P̲r̲o̲g̲r̲a̲m̲

             On SHAPE's enquiry CR stated that there
             are no planned changes in the CAMPS program
             management.


         3.  I̲n̲s̲u̲r̲a̲n̲c̲e̲ ̲o̲f̲ ̲C̲A̲M̲P̲S̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲

             On SHAPE's inquiry CR stated as follows:

             CR confirmed that items for which SHAPE
             has paid 100 per cent are free of all
             liens and encumberances. CR stated that
             all items completely or partly paid by
             SHAPE are insured for the benefit of SHAPE
             while on CR's premises or at sites prior
             to SPA. CR agreed that by contract. Risk
             of loss and damages to all items to be
             delivered to each site remains with CR
             until SPA, notwithstanding prior payment
             in full or in part for the items by SHAPE.
             All SHAPE equipment paid for in part or
             in full has been clearly identified as
             SHAPE property and CR's books have been
             adjusted accordingly to reflect SHAPE's
             interest.


             A letter from CR's insurance company will
             be forwarded to SHAPE stating that SHAPE
             is beneficiary for those items which are
             paid for by SHAPE in part or in full.
             A copy of the insurance policy covering
             plant or site equipment holding was handed
             over to the SHAPE contracting officer
             during the meeting.

         CR  A letter from CR's insurance company will
             be forwarded SHAPE explaining SHAPE's
             insurable interest for all items.

             A copy of the insurance policies covering
             plant equipment holding, transportation
             and installation was handed over to the
             SHAPE CAMPS contracting specialist during
             the meeting.


         4.  S̲p̲a̲r̲e̲s̲ ̲f̲o̲r̲ ̲S̲y̲n̲c̲.̲ ̲L̲o̲w̲ ̲S̲p̲e̲e̲d̲ ̲P̲o̲r̲t̲s̲

             The quotation is based on contract amendment
             7, instruction no. 5.2. 

             The detailed quotation is given in annex
             F.

             CR agreed to consider a reduction of this
             quotation up to a maximum of D.Kr. 300.000.
             This consideration is in respons to Commodore
             Elfrink's statement (Please refer annex
             E). This quotation is valid until 15th
             July 1983.


         5.  C̲A̲M̲P̲S̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲ ̲B̲a̲s̲e̲l̲i̲n̲e̲

             The issue was discussed based on the proposal
             made by SHAPE, see PMOM No. 17, item 12.

             SHAPE stated that by contract the hardware
             baseline occurred at DSMT. That baseline
             has not been kept, stated SHAPE, and there
             have been changes to hardware which have
             not been communicated to SHAPE and which
             have not been accomplished on the hardware
             for all sites. SHAPE stated the need to
             establish a valid baseline and to bring
             the CAMPS for each site to the same level.

             CR explained that all hardware module
             configuration changes have been communicated
             to SHAPE via HMAK. CR will in the future
             also notify SHAPE by telex of pending
             ECO's.



             Furthermore, CR pointed out that all system
             configuration changes have been forwarded
             to SHAPE for approval.

             SHAPE stated that any hardware configuration
             change affecting form, fit and function
             is considered by SHAPE as a system configuration
             change. CR must therefore also ask SHAPE
             for approval of these hardware configuration
             changes.

             CR stated that it had prepared a paper
             proposing how the baseline should be accomplished.
             SHAPE pointed out that the contract already
             established the DSMT as the hardware baseline
             and that from that point all changes were
             to be communicated to SHAPE for SHAPE
             approval. CR agreed, but stated that CR
             would now like to establish SPA for site
             1 as the hardware baseline.

             CR stated that CR would know the status
             of the systems for each site at FAT, SPA
             and at completion of the hardware warranty
             period and CR agreed that at each of those
             3 steps it would update the hardware at
             each site to the latest ECO level for
             all sites and all modules. SHAPE pointed
             out that hardware for different sites
             now have different levels of the same
             board and stated in its view that the
             same ECO level for each site ought to
             result in the same level boards for each
             site. SHAPE relied upon the pert chart
             from CR, the reliability and maintainability
             and the maintenance considerations of
             the contract in support of its position
             that hardware  configuration should be
             the same for the sites. Further SHAPE
             pointed out that the concept of definition
             of baseline at DSMT followed by approved
             changes only for the CAMPS, suggested
             that there would be the same hardware
             configurations for all sites. CR stated
             its position that there could be different
             boards for different sites, provided that
             form, fit and function were maintained.
             CR said that it would provide updated
             accurate documentation for each site,
             sufficient for CR to produce and repair
             the boards in their different configurations
             and suggested that such data should be
             sufficient for SHAPE to accept and repair
             boards of different configuration provided
             that form, fit and function were preserved.
             SHAPE pointed out that it has not even
             been informed of all changes to the boards.
             CR stated that there have been changes
             since DSMT for correction of bugs and
             that CR was not prepared to deliver all
             boards at the same level. It was agreed
             that this subject would be further discussed
             in detail at a subsequent meeting.


             It was mutually agreed that the baseline
             issue will be discussed during a meeting
             tentatively scheduled to week 27.

         6.  M̲e̲m̲o̲r̲y̲ ̲U̲p̲g̲r̲a̲d̲e̲ ̲f̲o̲r̲ ̲P̲U̲

             CR stated that it had decided to standardise
             the memory boards for all sites at 512k.

             Some sites would have 3 boards and some
             sites would have 2 boards and the mock
             up will have 2 boards.

             CR stated that this arrangement would
             require 14 boards in addition to the 88
             which CR planned. CR agreed to furnish
             an ECP defining this expansion. CR then
             referred to an understanding that SHAPE
             would consider sharing in some of the
             additional memory cost if CR were successful
             in achieving bi-level accreditation. SHAPE
             pointed out that the agreement was that
             there might be cost sharing up to the
             maximum previously stated amount if CR
             achieved bi-level security which was accredited.
             The previously stated amount would be
             the ceiling for CR's costs for the entire
             hardware and software effort related to
             the bi-level, which SHAPE would be requested
             to share in. SHAPE stated that cost sharing
             will be subject to NATO committee approval.
             CR agreed that in the event that CR achieves
             only system high and not bi-level, no
             additional costs will be requested from
             SHAPE. CR agreed to furnish an ECP setting
             forth these considerations.

             CR maintained that all costs related to
             expansion of the PU memory are subject
             to be paid by SHAPE in case of bi-level
             accreditation. For the 88 512 k ram boards
             these costs will not exceed Dkr. 6,787.375.

             Whenever more PU memory is added to the
             configuration, CR reserves the right to
             request SHAPE to pay the additional costs
             for memory boards if the system becomes
             accredited as bi-level.

             CR agreed not to present this claim for
             reimbursement until the system has passed
             a successful security accreditation.

             SHAPE expressed that they were willing
             to consider sharing to an amount of Dkr.
             6,787,375.- as the limit of their share
             in the bilevel effort, which is subject
             to NATO approval.


         7.  M̲e̲m̲o̲r̲y̲ ̲U̲p̲g̲r̲a̲d̲e̲ ̲f̲o̲r̲ ̲L̲T̲U̲,̲ ̲T̲a̲r̲e̲ ̲I̲n̲t̲e̲r̲f̲a̲c̲e̲

             The LTU is equipped with a 32 K RAM. The
             firmware supporting the TARE interface
             needs additional memory. CR propose to
             equip the LTUs for the TARE interface
             with 64K RAM.

         CR  CR will forward an ECP on the subject.
             SHAPE in principle agreed in the change,
             if the ECP was at no cost to SHAPE.


         8.  D̲e̲t̲a̲i̲l̲e̲d̲ ̲A̲s̲s̲e̲s̲s̲m̲e̲n̲t̲ ̲o̲f̲ ̲S̲W̲-̲S̲t̲a̲t̲u̲s̲

             As agreed in Progress Meeting No. 17.
             CR presented their assessment of the delay
             in software development.

             CR proposed the following new schedule
             for SW Development:

                           - 1st Sept.1983:                      All
                                                                 application
                                                                 SW
                                                                 integrated
                                                                 and
                                                                 test
                                                                 cases
                                                                 successfully
                                                                 completed
                                                                 except
                                                                 for
                                                                 the
                                                                 following
                                                                 functions:

                             -        OCR I/F
                             -        NICS-TARE I/F
                             -        Table and statistics
                                      print-outs
                             -        Preparation of
                                      service messages
                                      and local retrieval
                             -        Final version
                                      of predefined
                                      messages

                           - 1st Dec. 1983:                      The
                                                                 last
                                                                 of
                                                                 the
                                                                 functions,
                                                                 missing
                                                                 at
                                                                 1st
                                                                 Sept.
                                                                 integrated
                                                                 and
                                                                 test
                                                                 cases
                                                                 successfully
                                                                 completed.

         SHAPE agreed at CR's request that:

         -   The completion date of the 240 hours test would
             now be the 14th December under the assumption that
             this milestone delay has no impact on the final
             date of completion of the CAMPS program (1st Sep.
             84).

         -   The acceptance of the 240 hours test by SHAPE would
             be stated no later than two days after successful
             completion of the 240 hours test.

         -   The 240 hours test could start with the SW only
             partly completed, but SHAPE would only agree that
             the 240 hours test had been successfully completed
             when a total regression test of all functional
             test cases, after which para 2.1.1.2 and 2.1.1.3
             of CPS/TPR/007 will be performed.



         9.  C̲o̲n̲s̲i̲d̲e̲r̲a̲t̲i̲o̲n̲s̲ ̲f̲o̲r̲ ̲t̲h̲e̲ ̲S̲W̲-̲T̲e̲s̲t̲ ̲R̲e̲s̲c̲h̲e̲d̲u̲l̲i̲n̲g̲

             Appendix A and B gives a personnal statement
             from Commodore Elfrink on the subjects.

             Appendix A and B represents SHAPE's position
             and CR does not concur with all statements
             given there.

             SHAPE believed that the costs imposed
             on SHAPE due to the rescheduling had to
             be paid by CR. CR disagreed completely
             with this statement.

             CR refused to acknowledge responsibility
             for reimbursing costs incurred by SHAPE
             as a result of CR's delay in software
             development and integration testing.

             Concerning considerations for the rescheduling
             of the completion of the 240 hours test,
             CR referred to the contract for handling
             delays in the clause: liquidated damages.

             CR recognizes that SHAPE was caused problems
             in the training area, and CR is willing
             to compensate for the problem in the following
             manner:

             CR agreed to give additional training
             to the MTs and RSTs already trained. It
             will be given  as shown in paragraph 12.


         10. A̲d̲d̲i̲t̲i̲o̲n̲a̲l̲ ̲U̲s̲e̲ ̲o̲f̲ ̲C̲A̲M̲P̲S̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲a̲t̲ ̲S̲H̲A̲P̲E̲

             SHAPE expressed their concern about the
             additional use of CAMPS equipment due
             to the SW-delay. CR will avoid extensive
             use of parts of the equipment by rotating
             the equipment on the SW development systems.

         11. S̲e̲a̲l̲e̲d̲ ̲V̲D̲U̲s̲

             CR prefers not to seal the VDUs, but will
             return to the issue after experience from
             the first 3 sites installed.

         12. T̲r̲a̲i̲n̲i̲n̲g̲

             SHAPE raised the following problems:

             a)  Sufficient software shall be available
                 on the training system before training
                 is continued.

             b)  Some RST and MT students may have
                 left the program, when the sites are
                 ready for take over by the site personnel,
                 due to a delay in SPA.



             c)  The knowledge of the previous trained
                 MT/RST technicians logically decreases
                 due to the delay in SPA.

             CR has proposed a new schedule for the
             courses, see annex. Answers for the above
             mentioned problems are:

             a)  When the training starts according
                 to the proposed schedule, the software
                 for the training will be available
                 on the system assigned the training.

             b)  CR agrees to allowing additional RST
                 students on the next two RST courses,
                 provided the number of students never
                 is larger than 10, including possible
                 attendance by Depot Level Technicians
                 according to separate contract.

                 To accomodate additional MT students,
                 an additional MT course has been planned
                 (please refer to the schedule).

             c)  CR proposes, that 1 week practical
                 OJT training is repeated at the involved
                 sites by CR personnel present during
                 installation or integration. The personnel
                 doing the training shall have some
                 knowledge of how to conduct training.

             Additionally, the proposed schedule has
             the following advantage that all students
             are trained in time for SPAs.

         13. M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲M̲a̲n̲u̲a̲l̲

             SHAPE/CR reviewed SHAPE telex Camps Log
             No. 1238 with CR comments. SHAPE took
             CR comments back for review. The conclusion
             was that some items may have to be discussed
             at a special meeting between SHAPE/SSG,
             SHNMO and CR-ILS.

             CR proposed that SHAPE send an RST and
             an MT to CR to evaluate and validate site
             documentation and in particular trouble-shooting
             procedures. SHAPE will respond to this
             proposal.

             CR/SHAPE agreed to discuss telex 1238
             in detail during the special meeting.

         CR  CR will come up with a date in week 30
             for this special meeting.




         14. C̲A̲M̲P̲S̲ ̲V̲i̲d̲e̲o̲ ̲I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲

             CR presented an outline of the script
             for part 3 of the Video Introduction and
             a list of action items for SHAPE and CR.
             This has been included in the minutes
             of meeting as annex D.

             SHAPE commented on some of the points,
             which may have to be changed or deleted
             for security reasons. SHAPE also pointed
             out a need for help producing the actual
             script for the part 3 of the introduction,
             which all concerns the CAMPS system.

             SHAPE and CR agreed on the following course
             of actions:

             a)  SHAPE is presently working out the
                 script for part 1 and 2, and preparing
                 materials for recording

             b)  SHAPE will make recordings of part
                 1 and 2 during week 29 and 30, 1983.

             c)  Based on the outline presented during
                 this progress meeting and contact
                 between SHAPE and CR per letter, telex
                 or by telephone, SHAPE will work out
                 the first draft of the script for
                 part 3. This will take place in the
                 period, week 31 through 33, 1983.

                 In week 34, SHAPE will send a representative
                 to CR for discussing and refining
                 the script for part 3 together with
                 CR.

             d)  During week 34, CR will enable the
                 SHAPE representative to get familiar
                 with the operation of the CAMPS equipment
                 (mainly user functions), using the
                 training equipment. CR will introduce
                 the system and the applicable functions
                 to be used for the video-presentation.
                 During the same week, the SHAPE representative
                 can make the necessary preparations
                 for the coming RST course, starting
                 week 34, 1983.

             e)  During week 35 through 48, SHAPE will
                 finalize and finally approve the script,
                 and record the scenes not dependent
                 on the operation of the CAMPS.



             f)  In week 49, CR will send a representative
                 to SHAPE to discuss the results of
                 the already produced parts, and to
                 help making the scenes for the software
                 dependent parts of the introduction.
                 It should be noted, that this schedule
                 is linked to the dry-runs on the CAMPS
                 system at SHAPE, before the functional
                 test warning that the previous discussed
                 adjustment of the Master Schedule
                 will be approved by SHAPE + CR.

             Above timing is to be coordinated, and
             perhaps updated, with the SHNMO action
             officer for training.

             CR will pay the cost estimated in CAMPS
             log no: 1247, and provide the services
             mentioned above at no cost to SHAPE, provided
             the total Video Introduction is made unclassifed
             and may be used by CR for commercial purposes.

         16. P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲ ̲T̲e̲s̲t̲i̲n̲g̲

             CR and SHAPE agreed that if proper equipment
             is available penetration testing should
             take place at CR in Ballerup.

         SHAPE   SHAPE will investigate the requirement
                 for HW configuration and load generators.
                 CR pointed out that they are not responsible
                 for the availability of equipment
                 on which to perform the penetration
                 testing. 

         17. I̲n̲v̲o̲i̲c̲e̲ ̲R̲e̲l̲a̲t̲e̲d̲ ̲S̲u̲b̲j̲e̲c̲t̲s̲

             a)  On SHAPE's request CR agreed to keep
                 the number of invoices to a minimum.
                 Each months there shall only be one
                 invoice on each contract in each currency.
                 Continuation pages will be used instead.

             b)  Every time SHAPE does not pay the
                 full amount on an invoice, SHAPE will
                 forward an telex stating the exact
                 amount paid on each invoice.

         SHAPE   c)  SHAPE agreed to deliver within
                     a week a list of invoices due,
                     but not paid, and the reasons
                     for withhelding the payment.

         SHAPE   d)  Every half year starting 1st July
                     1983 SHAPE will forward a review
                     of invoices on CAMPS describing
                     what have been paid when and payments
                     due.



         CR/ e)  After 1st July CR and SHAPE will investigate
                 if
         SHAPE       another payment system on CAMPS
                     could be possible.

         SHAPE   f)  CR proposed that CR accounting
                     and SHAPE met at SHAPE and went
                     through all previous invoices
                     to see if all payments have been
                     accounted correctly during the
                     CAMPS program. SHAPE will respond
                     to that.


18.      C̲A̲M̲P̲S̲ ̲M̲a̲s̲t̲e̲r̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

             SHAPE stated that there is a desperate
             need for CAMPS to be installed in the
             ACE environment.

             CR and SHAPE did discuss the details of
             the update of the CAMPS Master Schedule.

             During the discussion CR stated that it
             is of utmost importance that no tests
             are delayed, but should be started as
             early as possible to accommodate the CAMPS
             schedule independant of holidays etc.
             Since SHAPE needs a fixed date to start
             and terminate the operational training,
             to accommodate ACE COMSEC equipment as
             well as communication lines and interfaces,
             and to provide manpower (operating users)
             for the operational test, it was agreed
             by CR and SHAPE to start the functional
             test by 3rd Jan. 84, and the operational
             test by 6th Feb. 84, to be finished by
             5th April 1984. To provide a buffer for
             reruns of tests, it was agreed to plan
             the PSA site 1 (SHAPE) for 24th April
             through 5th May 84. This means that all
             other 15 SPA have to be planned to be
             conducted within the period from 7th May
             through 31st August 84. SHAPE will investigate
             if this is possible and come back with
             a proposal for the SPA period.

             In addition, CR forwarded a proposal for
             the new HW installation schedule which
             generally represents a delay of 1 to 2
             months when compared with CR's previous
             proposal. CR confirmed that there will
             be no problems meeting this new installation
             schedule. SHAPE will investigate and try
             to coordinate SHAPE's various activities
             combined with HW installation.



19.      C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲.̲

             SHAPE feels the need to ascertain the
             progress relative to the performance of
             CR documentation.

             Notice was given, therefore, to CR that
             a visit of SHAPE representatives will
             take place for one week in July. Exact
             date will be coordinated with CR.


20.      N̲e̲x̲t̲ ̲P̲r̲o̲g̲r̲e̲s̲s̲ ̲M̲e̲e̲t̲i̲n̲g̲.̲

             SHAPE proposed to have the next Progress
             Meeting during week 34 using the month
             of July for additional meetings in specific
             items.













    A P P E N D I X   A…01…*********************




         C̲o̲m̲m̲o̲d̲o̲r̲e̲'̲s̲ ̲S̲t̲a̲t̲e̲m̲e̲n̲t̲ ̲R̲e̲g̲a̲r̲d̲i̲n̲g̲ ̲C̲R̲'̲s̲ ̲R̲e̲p̲o̲r̲t̲ ̲t̲h̲a̲t̲ ̲t̲h̲e̲
         ̲S̲o̲f̲t̲w̲a̲r̲e̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲ ̲C̲o̲m̲p̲l̲e̲t̲i̲o̲n̲ ̲w̲i̲l̲l̲ ̲b̲e̲ ̲D̲e̲l̲a̲y̲e̲d̲
         ̲f̲r̲o̲m̲ ̲J̲u̲l̲y̲ ̲8̲3̲ ̲t̲o̲ ̲S̲e̲p̲t̲.̲ ̲8̲3̲ ̲a̲n̲d̲ ̲t̲h̲a̲t̲ ̲a̲s̲ ̲o̲f̲ ̲S̲e̲p̲t̲.̲ ̲8̲3̲ ̲t̲h̲e̲
         ̲F̲o̲l̲l̲o̲w̲i̲n̲g̲ ̲F̲u̲n̲c̲t̲i̲o̲n̲s̲ ̲w̲i̲l̲l̲ ̲n̲o̲t̲ ̲b̲e̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲e̲d̲:̲

         -   OCR I/F
         -   NICS TARE I/F
         -   Table Statistics Printout
         -   Preparation of Service Messages and Local Retrieval
         -   Final Version of Predefined Messages.

         "I am flabbergasted and concerned about what I have
         been told today concerning delay to the schedule.

         I carefully delivered a statement to the NATO nations
         through the  P+P Committee a short time ago explaining
         an earlier delay that CR expected. I carefully wrapped
         it in a prepared statement so that CR would not be
         blamed and I coordinated that statement in advance
         with CR management. Now I am told of further delay
         of eight weeks to 5 months in the software integration
         and for several sites delay in SPA of five months.
         In between last January and now we have sent 4 or 5
         messages to CR indicating our concern about possible
         slippage to the schedule and one message I wrote myself
         to Mr. Christian Rovsing. I was always told that there
         would be no substantial delay. I am concerned and disappointed.

         I am not sure how to express this to NATO. There will
         be additional cost to SHAPE as a result of the slip
         for example we probably have trained the wrong people.
         Also, we have a contract with TRW to accomplish certification
         of the system. The delay to the schedule will be costly.
         It will delay completion of the training because of
         the non-availability of the software for training purposes.
         SHAPE's continued involvement in software development
         will be costly.

         You have given me cause to develop a lack of confidence
         in your ability to accomplish what you schedule - this
         is despite my efforts to support you during the last
         few months. I did all I could to improve the relationsship
         between CR and SHAPE since I took over from my predecessor.
         Now I see that I have been misled when I inquired about
         scheduled performance. The problem is I do not know
         what to believe from CR. 

         I would like a break in the meeting to discuss your
         report and to formulate a statement for the record."















        A P P E N D I X   B…01…*********************




         C̲o̲m̲m̲o̲d̲o̲r̲e̲'̲s̲ ̲S̲t̲a̲t̲e̲m̲e̲n̲t̲ ̲w̲h̲e̲n̲ ̲M̲e̲e̲t̲i̲n̲g̲ ̲R̲e̲s̲u̲m̲e̲d̲ ̲a̲f̲t̲e̲r̲ ̲B̲r̲e̲a̲k̲
         ̲t̲o̲ ̲c̲o̲n̲s̲i̲d̲e̲r̲ ̲C̲R̲ ̲R̲e̲p̲o̲r̲t̲ ̲o̲f̲ ̲S̲l̲i̲p̲p̲a̲g̲e̲ ̲i̲n̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲ ̲S̲y̲s̲t̲e̲m̲
         ̲T̲e̲s̲t̲ ̲a̲n̲d̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲.̲

         "I want you to know that the SHAPE team does have confidence
         in CR's ability to complete the contract. We know that
         you have taken steps on your own to minimize delay
         and in spite of problems which you have experienced
         you are maintaining quality. HMAK assures us of this.

         We do not have much choice, but to accept your announced
         delay in scheduled software integration and test. However,
         we would like to view what you have called delay as
         a slippage of five months in the scheduled completion
         of the 240 hours test, that the test shall include
         the five functions which you have projected would not
         be completed by September 1, 1983 as part of the basic
         integrated and tested software.

         This slippage in the scheduled completion of the 240
         hours test according to your report will not affect
         the September 1984 date for completion of the 16th
         Site (# 11).

         We propose that a schedule be prepared by CR for SHAPE
         approval reflecting the change to the completion date
         for the 240 hours test and leaving unchanged the scheduled
         final contract completion date for final site SPA.

         The schedule and milestones will have to be worked
         out while the SHAPE project manager is here this week.

         I would appreciate if the revised schedule would be
         confirmed by top CR management not because of any legal
         considerations but as a representation by Mr. Christian
         Rovsing that he is personnally committed to CR's meeting
         the schedule.

         Further I ask for concrete suggestions from CR on how
         to compensate SHAPE for the financial and other impact
         upon SHAPE as a result of the delay to the schedule.

         I also ask for any positive suggestions CR may have
         concerning how to express the schedule slippage to
         NATO in a cooperative way. Please do not send me back
         to NATO for a third time.



         As another point for your consideration it may be appropriate
         to omit a progress meeting in July so that you can
         concentrate on your performance.

         I recognize that I am asking you to do certain things
         and you may wish to discuss them.

         In response to Gert Jensen's inquiry concerning priority
         of functions which will not now be ready by September
         1983 and the rules for the start of the 240 hours test,
         the commodore stated:

         "It is up to you when you start the 240 hours test
         so that it is completed by December 1983 as you have
         announced. We wish to cooperate with you and we understand
         that the outstanding functions do not necessarily have
         to be completed at the time you start the 240 hours
         test, but those functions must be completed, integrated,
         and tested in order for you to complete the 240 hours
         test. When you start the test is up to you, I am talking
         about a revision to scheduled completion based on what
         you have reported at this meeting.

         CR agreed to the proposal, but asked that the 1 December
         1983 date be slipped to 16th December.














        A P P E N D I X   C…01…*********************













   A P P E N D I X   D…01…***********************












   A P P E N D I X   E…01…***********************



             C̲o̲m̲m̲o̲d̲o̲r̲e̲'̲s̲ ̲S̲t̲a̲t̲e̲m̲e̲n̲t̲ ̲o̲n̲ ̲R̲S̲P̲L̲ ̲(̲P̲i̲e̲c̲e̲ ̲P̲a̲r̲t̲s̲)̲

             This is probably the appropriate point
             for me to state that I am upset about
             an old item. That item concerns the question
             whether the contract required the preparation
             and maintenance of an RSPL down to the
             piece parts level or only to the replaceable
             module level. 

             There were discussions including one at
             Mr. Christian Rovsing's home one evening
             in which I personally participated, where
             we agreed to a compromise by which CR
             would complete the RSPL to the piece part
             level at no cost to NATO, and we promised
             to purchase the first years 270 day depot
             spare parts from CR at CR's cost plus
             overhead and reasonable profit. Despite
             that compromise, CR marked every item
             in the piece parts list with a price for
             the preparation and maintenance of the
             piece parts RSPL. We could do nothing,
             but agree on a compromise cost in order
             to avoid problems. It was probably a gentleman's
             agreement that we had, but I would like
             to go on record that I am disappointed
             with the company's failure to abide by
             that agreement. Before providing a price
             quotation for the additional spares I
             ask that you consider the agreement that
             we previously had.












   A P P E N D I X   F…01…***********************



   S̲P̲A̲R̲E̲S̲ ̲F̲O̲R̲ ̲S̲Y̲N̲C̲.̲ ̲L̲O̲W̲ ̲S̲P̲E̲E̲D̲ ̲P̲O̲R̲T̲S̲ ̲Q̲U̲O̲T̲A̲T̲I̲O̲N̲



             This quotation is in response to contract
             amendment 7, instruction 5.2.

             The total costs of this quotation are:

         D.Kr. 3,727,054…01…===============

             T̲a̲b̲l̲e̲ ̲o̲f̲ ̲C̲o̲n̲t̲e̲n̲t̲s̲

             1   Hardware
             2   Firmware
             3   Transportation and Installation
             4   Management
             5   Bidding Provisions



         1   H̲A̲R̲D̲W̲A̲R̲E̲

         1.1 E̲n̲g̲i̲n̲e̲e̲r̲i̲n̲g̲

             a)  Rework and upgrade of 17 Resync
                 modules already ordered          Dkr   
                                                        
                                                        313,283

             b)  Delivery of the following
                 HW as spares

                 b1) For 15 sites (Site 3 excluded):

                     1 LTUX-S, type 4        21,430
                     1 BP-8                   2,490
                     2 Resycn. Modules
                     (upgraded)              40,132
                     2 Cables, V24              589              1,580,415

                 b2) For site 3

                     1 LTUX-S, type 4        21,430              
                                                                 
                                                                 
                                                                 21,430

                 b3) For two depots

                     1 LTUX-S, type 4        21,430              
                                                                 
                                                                 
                                                                 42,860

                     b1 + b2 + b3:                Dkr.  1,644,705

             c)  1 LTUX-S, type 4 and 1 resync
                 module delivered as part of each
                 Mock-up (new crate required)     Dkr   
                                                        
                                                        541,166

             d)  Total cost, hardware

                 Total cost (equipment, a+b+c)    Dkr.  2,499,154

         1.2 H̲a̲r̲d̲w̲a̲r̲e̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲

             a)  Resync. Module, upgraded version

                 Development and qualification-
                 test (incl. materials)           Dkr.  
                                                        
                                                        475,000

             b)  LTUX-S, type 4
                 Documentation                    Dkr.  
                                                        
                                                        
                                                        65,000

             Total cost (hardware)                Dkr.  3,039,154



         2   F̲I̲R̲M̲W̲A̲R̲E̲

             Firmware Development and
             Qualifications                       Dkr.  
                                                        
                                                        364,000

             Documentation                        Dkr.  
                                                        
                                                        
                                                        68,900

             Total costs (firmware)               Dkr.  
                                                        
                                                        422,900


         3   T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲

             The existing (17) seventeen resynchronous
             modules already purchased by SHAPE will
             be shipped and installed independent of
             this proposal.

             When CR delivers the 32 additional resyncronous
             modules (new version) to the depots, it
             is up to the depots to exchange the 17
             resync. modules old version with the new
             versions:

             The depots will upon exchange send the
             17 resync. modules old version to CR to
             be retrofitted. Having retrofitted the
             modules, CR will return the modules to
             the depots.

             SHAPE will be responsible for all installation
             equipment in this proposal and of exchange
             of resync. modules delivered to the depots.

             The only costs related to this line item
             to be covered by CR is transportation
             of resync. modules between CR and the
             depots.

             Total cost (transport)               DKr.  
                                                        
                                                        
                                                        15,000


         4   M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲

             Total costs (management)             Dkr.  
                                                        
                                                        250,000




         5.  B̲I̲D̲D̲I̲N̲G̲ ̲P̲R̲O̲V̲I̲S̲I̲O̲N̲S̲

         a:  C̲o̲n̲t̲r̲o̲l̲ ̲T̲e̲r̲m̲s̲

             The proposal is assumed to be an extension
             to the CAMPS contract.

         b:  T̲y̲p̲e̲ ̲o̲f̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲

             Prices given are firm fixed prices.

         c:  S̲c̲h̲e̲d̲u̲l̲e̲

             All equipment will be shipped to the depots
             no later than March 84. The resync modules
             to be retrofitted shall be delivered to
             CR no later than April 84.

         d:  V̲a̲l̲i̲d̲i̲t̲y̲

             The price is valid until 15th of July
             1983.

         e:  S̲p̲a̲r̲e̲s̲

             No spares are included in the proposal.

         f:  P̲a̲y̲m̲e̲n̲t̲ ̲P̲l̲a̲n̲

             At acceptance of proposal    30 per cent
             overall costs
             At acceptance in factory     60 per cent
             overall costs
             At acceptance at site        10 per cent
             overall costs

             Payments shall take place in Danish Kroner
             (Dkr.)

         g:  A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲

             Equipment will be accepted as all other
             spares.