WangText
:…05…:…06…9…09…9…0b…9…0d……86…1
…02…
…02…
…02…
…02…CPS/PLN/004
…02…LP/810123…02……02…#
R & M
PROGRAM
PLAN
…02……02…CAMPS
T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
5 R & M ANALYSIS ...............................
2
5.1 INTRODUCTION ..............................
2
5 R̲ ̲&̲ ̲M̲ ̲A̲N̲A̲L̲Y̲S̲I̲S̲
5.1 I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
This section summarizes all activities which have to
be performed to realise the specific requirements mentioned
in sec. 3.1.2.
5.2 RELIABILITY REPORTS ........................
5.2.1 Introduction ...........................
4
5.2.2 Reliability Model (Parts Count) ........
5.2.3 TabularPresentation of Component
Failure Rates Under Required Conditions
5.2.5 MTBF Calculation Method ................
5.2.6 Mathematical Model .....................
5.2.7 Failure Analysis Reports (System
Level Only) ...........................
5.2.9 Reliability Test Report (For Specified
Modules Only) ..........................
5.2.10 Final Report .........................
…86…1 …02… …02… …02… …02…
5.2.1 I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲
These reports are conducted to verify and improve the
reliability on module level and system level as well.
The predicted values are compared with experienceby
test data and carefully calculated values using stress
parameter techniques and FMECA tools.
TA̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲
6 FAILURE REPORTING AND CONTROL ..................
6.1 INTRODUCTION ...............................
6
6.2 DESCRIPTION OF FAILURE REPORTING SYSTEM ...
6
6.3 COLLECTION OF FAILURE DATA .................
6
6.4 HANDLING OF FAILURE DATA ...................
…86…1 …02… …02… …02… …02…
6.1 I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
A deliberate failure reporting and control system is
of great importance during implementation of the project
and in the operational phase as well. This sectiondescribes
all action items to be taken to establish and run such
a system.
6.2 D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲ ̲O̲F̲ ̲F̲A̲I̲L̲U̲R̲E̲ ̲R̲E̲P̲O̲R̲T̲I̲N̲G̲ ̲S̲Y̲S̲T̲E̲M̲
For each CR80 module in CAMPS, a log book shall be
established. Together with a complete technical manual,
including reliablity analysis report, possibly FMECA
analyse report, and design analysis report, it shall
contain all facts considering the specific module.
All failures shall be registrated in time and the operating
or test conditions under which the module fai