DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦d26605e47⟧ Wang Wps File

    Length: 33975 (0x84b7)
    Types: Wang Wps File
    Notes: SD/PRC/001                
    Names: »4499A «

Derivation

└─⟦61f87be83⟧ Bits:30006024 8" Wang WCS floppy, CR 0420A
    └─ ⟦this⟧ »4499A « 

WangText

…00……00……00……00……00……13……02……00……00……13…
…12……0c……12……0f……12… …11……08……11……0a……11……00……11……01……11……05……10……0c……10…
…10……06……0f……09……0f……0c……0f……00……0f……01……0f……06……0f……07……0e……08……0e……0d……0e……0e……0e……86…1                                             …02…           …02…   …02…        

…02…SD/PRC/001

…02…JHO/840130…02……02…#
INTERNAL STATUS REPORTS
…02……02…SYS.DIV.








                    T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲






   1 SCOPE ..........................................
        4

   2 STRUCTURE OF THE STATUS REPORT .................
        5

   3 DESCRIPTION AND EXAMPLES OF SHEETS .............
        6

     3.1 PROJECT STATUS .............................
            6
       3.1.1 Accomplishments ........................
                6
       3.1.2 Near Term Activities ...................
                6
       3.1.3 Problems/Issues ........................
                7
       3.1.4 Master Schedule ........................
                8
       3.1.5 Contractual Value ......................
               10
       3.1.6 Quotations or Extensions ...............
               11
       3.1.7 Budget and Account .....................
               11
       3.1.8 Manpower and Organization List .........
               13
       3.1.9 Used Manpower Resources ................
               14
       3.1.10  Contract Deliverables Status .........
                 16

     3.2 FINANCIAL STATUS ...........................
           18
       3.2.1 Accumulated Invoiced Sales .............
               18
       3.2.2 Overdue Payments .......................
               18

     3.3 HARDWARE DEVELOPMENT AND FABRICATION .......
           21
       3.3.1 Development of Hardware Items ..........
               21
       3.3.2 Order Hardware Items ...................
               23
       3.3.3 Hardware Integration Status ............
               25
       3.3.4 Update of HW-baselines .................
               27

     3.4 SW DEVELOPMENT STATUS ......................
           29
       3.4.1 SW Development - Preliminary and 
             Detailed Design ........................
               29
       3.4.2 SW Development - Code and Unit Test and
             Package Test ...........................
               29 

     3.5 SYSTEM INTEGRATION AND TEST ................
           34

     3.6 ILS STATUS .................................
           37
       3.6.1 ILS-Installation .......................
               37
       3.6.2 ILS-Training ...........................
               40
       3.6.2 ILS-Documentation ......................
               42
       3.6.3 ILS-Maintenance ........................
               44
       3.6.4 ILS-Repair .............................
               44


                         1̲ ̲ ̲S̲C̲O̲P̲E̲


         The purpose of this procedure is to state the mandatory
         requirements to the content and the layout for company
         internal project status reports.

         It is only acceptable to omit status report sheets,
         when these are not applicable to the project concerned.

         Additional report sheets may be used, when necessary
         to describe essential subjects of the project status.

         The project manager is responsible for preparation
         of the status report. The status report shall be submitted
         to the systems division manager on his request as part
         of a formal monthly status report on the project.





            2̲ ̲ ̲S̲T̲R̲U̲C̲T̲U̲R̲E̲ ̲O̲F̲ ̲T̲H̲E̲ ̲S̲T̲A̲T̲U̲S̲ ̲R̲E̲P̲O̲R̲T̲


         The status report is structured into three parts:

         -   a verbal introduction with highlights of accomplishments
             and near term activities

         -   a project status related to the project as a whole
             concerning contract, finance and schedule

         -   a detailed status report concerning each of the
             major items in the project: hardware, software,
             system integration and integrated logistics support.

         The purpose with this structure is to give a top-down
         description of the status and to avoid too many details
         in the beginning of the report.

         The layout of the status report is fitted for a wordprocessor-system.
         A monthly status report can be created from the last
         one by an update of the wordprocessor-file. Only few
         additional sheets with graphic status presentation
         have to be updated by other means.

         Appendix A includes a status report with blank sheets
         to use f.i. for the first status report.



          3̲ ̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲E̲X̲A̲M̲P̲L̲E̲S̲ ̲O̲F̲ ̲S̲H̲E̲E̲T̲S̲



3.1      P̲R̲O̲J̲E̲C̲T̲ ̲S̲T̲A̲T̲U̲S̲

         A verbal introduction to the project status shall give
         the highlights of 

         -   accomplishments
         -   near term activities
         -   problems/issues.



3.1.1    A̲c̲c̲o̲m̲p̲l̲i̲s̲h̲m̲e̲n̲t̲s̲

         The accomplishment sheet shall describe the items accomplished
         together with the dates. Only items related to the
         contractual  deliveries or to the customer should be
         included and only, if they are accomplished in the
         period covered by the status report.

         An example of an accomplishment sheet is given in figure
         3.1-1.



3.1.2    N̲e̲a̲r̲ ̲T̲e̲r̲m̲ ̲A̲c̲t̲i̲v̲i̲t̲i̲e̲s̲

         The "near term activities"-sheet shall include the
         activities related to the contract or the customer
         1-2 months ahead.

         The scheduled date for the completion of the activity
         shall be included and - of course - be in accordance
         with the detailed status.




                     A̲C̲C̲O̲M̲P̲L̲I̲S̲H̲M̲E̲N̲T̲S̲




























    Figure 3.1.1-1 Example of an accomplishment-sheet

         described later on.

         An example of a "near-term-activities-sheet" is given
         in figure 3.1.2-1.



3.1.3    P̲r̲o̲b̲l̲e̲m̲s̲/̲I̲s̲s̲u̲e̲s̲

         Major problems or issues having a considerable effect
         on the progress of the project may be brought up, if
         the decision has to be taken on or supported at a higher
         level than the project manager level.





                   N̲E̲A̲R̲ ̲T̲E̲R̲M̲ ̲A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲

















  Figure 3.1.3-1  Example of near-term-activities-sheet.

         The problem/issue brought up shall be accompanied by
         one or more suggestions to solve the problem.

         The decisions made on the problems/issues listed are
         the most important results of the status meetings.
         They shall be covered in the minutes-of-meeting.



3.1.4    M̲a̲s̲t̲e̲r̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲

         The Master Schedule for the project shall describe
         only the items defined in the contract, f.i. deliveries
         or milestones for which the schedule only can be moved
         by an update to the contract.

         The schedule shall cover the entire period, the project
         is running. The schedule shall reflect the contractual
         agreed schedule. Updates not reflected in the contract
         shall only be added as pen-and-ink changes to the schedule
         with a different marking.

         In appendix A a form for program schedules is shown:
         It is not mandatory, that this form is used, if another
         layout has the same content.

         The schedule shown in the status report shall be updated
         to the date of the status report. A comment to the
         updates of the master schedule may be appropriate.

         An example of the status report is shown in figure
         3.1.4-1.




















































Figure 3.1.4  Example on a master schedule for a project.



3.1.5    C̲o̲n̲t̲r̲a̲c̲t̲u̲a̲l̲ ̲V̲a̲l̲u̲e̲

         In order to keep track of the contract value, the different
         amendments or letter-of-intents shall be listed together
         with the acceptance dates and the contract value (preferably
         in D.kr.).

         If several contracts are running together in the department,
         the total of all contracts should be given.

         The purpose of the list is to evaluate the sales activity
         in form of amendments and extensions to existing contracts.
         Furthermore the contract value is used in the calculation
         of work-in-progress.

         An example of a status sheet for the contractual value
         is given in figure 3.1.5-1.




























   Figure 3.1.5-1  Example on contractual status sheet.



3.1.6    Q̲u̲o̲t̲a̲t̲i̲o̲n̲s̲ ̲o̲r̲ ̲E̲x̲t̲e̲n̲s̲i̲o̲n̲s̲

         For each project a list of submitted or requested quotations,
         options in the contract together with possible extensions
         should be listed.

         If the subject is a submitted quotation or an option
         in the contract the validity date should be stated.

         The purpose of the list is to estimate the future sales
         and to support the activities of the marketing department.

         An example of a "quotation or extension"-list is given
         in figure 3.1.6-1.


         Q̲u̲o̲t̲a̲t̲i̲o̲n̲s̲ ̲o̲r̲ ̲p̲o̲s̲s̲i̲b̲l̲e̲ ̲e̲x̲t̲e̲n̲s̲i̲o̲n̲s̲:

         Relay Function                           3,727,054
         SW Development System                    7,553,757
         Test Drive System                       14,120,925
         In Circuit Test Programs                 1,396,736
         MSPs for SW dev.                         ̲3̲,̲5̲0̲0̲,̲0̲0̲0̲
         Total                                   30,298,472


Figure 3.1.6-1  Example on a "Quotations or extension"-list.



3.1.7    B̲u̲d̲g̲e̲t̲ ̲a̲n̲d̲ ̲A̲c̲c̲o̲u̲n̲t̲

         For each project the financial status of the project
         should be presented.

         The output from the CRAS' finance system has to be
         included directly. Major deviations between accounts
         and budgets has to be commented.

         Two tables have to be presented and commented:

         First the budget and the accounts for the project from
         start of year until now. Each of the 8 keyfigures in
         the budget should be compared and commented.The purpose
         of the table is to evaluate if the performance during
         the financial year is in accordance with the budgetted
         values.

         The second table presents the total financial project
         status from the beginning of the project with revised
         cost-to-complete until end-of-project.



         The purpose of the second table is to evaluate the
         overall project performance. The effect of dispositions
         this year may first occur next year.

         All deviations between last budget and the new budget
         have to be explained.

         Examples of the two tables are given in figure 3.1.7-1
         and figure 3.1.7-2.

                                        Budget     Account    Comment
             Period: xx.xx - xx.xx      1000 Dkr.  1000 Dkr.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
           Net Sales
         - D̲i̲r̲e̲c̲t̲ ̲P̲r̲o̲d̲u̲c̲t̲i̲o̲n̲ ̲C̲o̲s̲t̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         = M̲a̲r̲g̲i̲n̲a̲l̲ ̲C̲o̲n̲t̲r̲i̲b̲u̲t̲i̲o̲n̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         - Sales & Distribution Costs
         - G̲e̲n̲e̲r̲a̲l̲ ̲&̲ ̲A̲d̲m̲i̲n̲i̲s̲t̲r̲a̲t̲i̲v̲e̲ ̲C̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         = N̲e̲t̲ ̲O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲R̲e̲s̲u̲l̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
           C̲a̲p̲i̲t̲a̲l̲ ̲C̲o̲s̲t̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
           N̲e̲t̲ ̲I̲n̲c̲o̲m̲e̲ ̲b̲e̲f̲o̲r̲e̲ ̲T̲a̲x̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
           Comments:


                     Figure 3.1.7-1  Budget and Account cumulated this year

                                     Period:  Total Project
                                                   Revised
                                        Budget     Budget     Comment
                                        1000 Dkr.  1000 Dkr.
          ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
           Net Sales
         - D̲i̲r̲e̲c̲t̲ ̲P̲r̲o̲d̲u̲c̲t̲i̲o̲n̲ ̲C̲o̲s̲t̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         = M̲a̲r̲g̲i̲n̲a̲l̲ ̲C̲o̲n̲t̲r̲i̲b̲u̲t̲i̲o̲n̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         - Sales & Distribution Costs
         - G̲e̲n̲e̲r̲a̲l̲ ̲&̲ ̲A̲d̲m̲i̲n̲i̲s̲t̲r̲a̲t̲i̲v̲e̲ ̲C̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         = N̲e̲t̲ ̲O̲p̲e̲r̲a̲t̲i̲n̲g̲ ̲R̲e̲s̲u̲l̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         - C̲a̲p̲i̲t̲a̲l̲ ̲C̲o̲s̲t̲s̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
         = N̲e̲t̲ ̲I̲n̲c̲o̲m̲e̲ ̲b̲e̲f̲o̲r̲e̲ ̲T̲a̲x̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


                        Figure 3.1.7-2  Revision of Total Project Budget


3.1.8    M̲a̲n̲p̲o̲w̲e̲r̲ ̲a̲n̲d̲ ̲O̲r̲g̲a̲n̲i̲z̲a̲t̲i̲o̲n̲ ̲L̲i̲s̲t̲

         The purpose of the list is to define the persons assigned
         to the project and their responsibilities in the organization
         of the project. Especially should the different managers
         in the project be clearly defined. The managers f.i.
         as in the example figure 3.1.8-1 be marked by underlining.

         If the persons only are working parttime or on consultancy
         basis on the project in the period concerned, the monthly
         workload should be stated by a percentage.





































 Figure 3.1.8-1  Example on Manpower & Organization List.


3.1.9    U̲s̲e̲d̲ ̲M̲a̲n̲p̲o̲w̲e̲r̲ ̲R̲e̲s̲o̲u̲r̲c̲e̲s̲

         The use of manpower resources should be followed every
         month for each of the line items at the highest level.

         The use of manpower resources every year until now
         should be stated too.

         The use of manpower resources this year "until now"
         should be compared with the budget for use of manpower
         resources this year until now.

         The purpose of the table is to evaluate if a delay
         in schedule is caused by missing manpower. An example
         of the report is shown in figure 3.1.9-1.
































  Figure 3.1.9-1  Example on "used manpower resources".



         For the system engineering manpower and software development
         manpower a split in the different phases is appropriate.

         The table with "planned and actual resources used to
         establish functional baselines and software development"
         is in accordance with the estimation process used in
         software development. Based on  experience the estimation
         of cost-to-
         complete can be done more accurate for this especially
         risky part of a project.

         An example of a table with actual resources is given
         in figure 3.1.9-2.































                      Figure 3.1.9-2

Example on "Actual resources used to establish baselines."



3.1.10   C̲o̲n̲t̲r̲a̲c̲t̲ ̲D̲e̲l̲i̲v̲e̲r̲a̲b̲l̲e̲s̲ ̲S̲t̲a̲t̲u̲s̲

         The purpose with the list of contract deliverables
         is to give the status of each deliverable defined in
         the contract. The table should state

         -   the line item, 
         -   the subject and the dates for 
         -   scheduled delivery
         -   actual delivery
         -   submittal to customer
         -   for approval by customer, and
         -   invoice forwarded. 

         Comments to the status could be added. Only deliverables
         where the customer is contractual involved by some
         sort of approval or by a payment should be included
         in the list.

         If approval is not applicable to a delivery before
         invoicing or if a payment is not connected to the delivery,
         these facts should be marked on the list.

         An example on a list is given in figure 3.1.10-1.

















































                     Figure 3.1.10-1
     Example on a contract deliverables status list.


3.2      F̲I̲N̲A̲N̲C̲I̲A̲L̲ ̲S̲T̲A̲T̲U̲S̲

         A more detailed description concerning the financial
         status shall be submitted. The status reports should
         be based on the reports from the CRAS' finance system,
         but at least two tables are mandatory:

         -   accumulated invoiced sales and
         -   overdue payments.



3.2.1    A̲c̲c̲u̲m̲u̲l̲a̲t̲e̲d̲ ̲I̲n̲v̲o̲i̲c̲e̲d̲ ̲S̲a̲l̲e̲s̲ 

         In a graphic presentation the accumulated invoiced
         sales (the actual cash flow) shall be plotted for the
         actual year. For each month the following accumulated
         values for the project shall be plotted:

         -   budgetted invoiced sales
         -   actual invoiced sales
         -   actual paid amounts.

         The purpose with the figure is to control that the
         actual invoicing follows the budget and to control
         that the payment follows the invoicing.

         An example is shown in figure 3.2.1-1.



3.2.2    O̲v̲e̲r̲d̲u̲e̲ ̲P̲a̲y̲m̲e̲n̲t̲s̲

         A list of o̲v̲e̲r̲d̲u̲e̲ payments from the customer shall
         be submitted. The list shall contain 

         -   invoice number
         -   invoice date
         -   due date
         -   unpaid amount
         -   items covered by the invoice.

         Comments concerning customer arguments for withholding
         payment may be added.

         An example is shown in figure 3.2.2-1.

















































                      FIGURE 3.2.1-1
             Budgetted and actual cash flow.




















































                     Figure 3.2.2-1.
                     Overdue Payments


3.3      H̲A̲R̲D̲W̲A̲R̲E̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲ ̲A̲N̲D̲ ̲F̲A̲B̲R̲I̲C̲A̲T̲I̲O̲N̲

         The hardware part of a project has different phases:

         -   develop new items or systems
         -   order hardware items
         -   integrate and test the hardware
         -   update of baselines (engineering change orders).

         For each of these phases one or more status sheets
         shall be used.



3.3.1    D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲o̲f̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲ ̲I̲t̲e̲m̲s̲

         For all HW items where the development is controlled
         by the project, a status list should be submitted.
         The standard phases to be controlled are:

         -   product specification
         -   technical manual
         -   reliability report
         -   critical design review
         -   test procedures
         -   test report
         -   factory qualification test procedure
         -   factory test report
         -   serie 0 release
         -   functional test release 0
         -   release for production.

         Completion or scheduled completion should be marked
         on the list. If a more detailed report is necessary
         to describe the actual status, other subjects may be
         added to the list. 

         An example of a status report for development of HW
         is given in figure 3.3.1-1.






















































 Figure 3.3.1-1  Example on status on development of HW.


3.3.2    O̲r̲d̲e̲r̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲ ̲I̲t̲e̲m̲s̲

         For all HW-items ordered at subcontractor a status
         list shall be submitted. A̲l̲l̲ items with a lead time
         on more than 1 month or with a unit price on more than
         1500 Kr. shall be included in the list. Even if the
         items are not yet ordered at the subcontractor, they
         shall be included too.

         The list shall cover the following subjects:

         -   name on subcontractor
         -   name of item
         -   number ordered by the customer under the contract
         -   number ordered at subcontractor
         -   number received by the project
         -   number accepted by incoming inspection and - if
             applicable - certificate of conformance by QA
         -   number invoiced to the customer.

         The purpose of the list is to give the status of the
         hardware deliveries before the hardware is integrated
         and tested.

         A comment sheet may be attached to the order status.

         An example is given in figure 3.3.2-1.



















































       Figure 3.3.2-1  Example on HW order status.



3.3.3    H̲a̲r̲d̲w̲a̲r̲e̲ ̲I̲n̲t̲e̲g̲r̲a̲t̲i̲o̲n̲ ̲S̲t̲a̲t̲u̲s̲

         The hardware integration status for all systems gives
         an overview for each system of 

         -   hardware delivered to integration (yes or no) perhaps
             with comments on missing hardware
         -   total no. of test cases in the integration and
             acceptance testing
         -   number of test cases completed successfully
         -   scheduled date for factory acceptance testing
         -   completion date for factory acceptance testing
         -   date for submittal of FAT report
         -   date for approval of FAT report by the customer.

         This sheet will give an overview over all systems to
         be integrated.

         If only the integration status of one system is to
         be described, a graphic presentation as shown in figure
         3.3.3-1 may be used.






















































                      Figure 3.3.3-1



3.3.4    U̲p̲d̲a̲t̲e̲ ̲o̲f̲ ̲H̲W̲-̲b̲a̲s̲e̲l̲i̲n̲e̲s̲

         During incoming inspection or factory acceptance test
         the hardware is tested according to a certain baseline.
         If, at a later point in time, an error is detected
         causing an engineering change order (eco) the baseline
         has to be changed for all items.

         The purpose with this report is to present the status
         of the update process for the hardware items.

         The list shall cover only those hardware items, which
         are 

         -   not yet baselined, 

         -   erroneous i.e. with a pending eco, 

         -   with an eco submitted, 

         -   or in an update process.

         For each item the list shall contain:

         -   the date for issue of eco
         -   the date for update of internal documentation
         -   submittal date of ecp to customer
         -   date of approval of ecp by customer
         -   submittal date of the updated version of the system
             design to the customer
         -   number of modules affected by the eco
         -   number of modules already updated.

         An example is given in figure 3.3.4-1.



















































   Figure 3.3.4-1  Example of an update of HW-baselines


3.4      S̲W̲ ̲D̲E̲V̲E̲L̲O̲P̲M̲E̲N̲T̲ ̲S̲T̲A̲T̲U̲S̲

         The software development is divided into several phases:

         -   preliminary design
         -   detailed design
         -   code and unit test
         -   package test

         For each of these phases one or more status sheets
         shall be used.



3.4.1    S̲W̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲-̲ ̲P̲r̲e̲l̲i̲m̲i̲n̲a̲r̲y̲ ̲a̲n̲d̲ ̲D̲e̲t̲a̲i̲l̲e̲d̲ ̲D̲e̲s̲i̲g̲n̲

         The status sheets for the preliminary and the detailed
         design phases may be the same. For each workpackage
         (WP) the size of the work, f.i. in number of typed
         pages shall be described. The following shall be described:

         -   the original plan
         -   the latest plan
         -   the status of the draft
         -   the status of typing
         -   no. of pages reviewed in critical design reviews
         -   no. of pages updated and completed in design.

         All items shall be added to a total.



3.4.2    S̲W̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲-̲ ̲C̲o̲d̲e̲ ̲a̲n̲d̲ ̲U̲n̲i̲t̲ ̲T̲e̲s̲t̲ ̲a̲n̲d̲ ̲P̲a̲c̲k̲a̲g̲e̲ ̲T̲e̲s̲t̲

         The code and unit test may be followed in the same
         way through the different working phases.

         Each workpackage may be described in the unit kilo-lines-
         of-code (kloc) under the headlines:

         -   originally planned
         -   latest plan
         -   coded
         -   tested
         -   subpackage integrated and tested
         -   package integrated and tested
         -   system integrated and tested.

         A total of all workpackages should be calculated for
         each column.



         An example is shown in figure 3.4.2-1.

         A graphic presentation of the same information showing
         the development over the time shall be added too. See
         example figure 3.4.2-2.

         To support the status of the testing the SW development
         status shall be described in number of test cases too.
         For each workpackage the number of test cases

         -   originally planned
         -   latest planned
         -   completed successfully

         shall be described in each of the phases:

         -   subpackage integration and test 
         -   package integration and test 
         -   system integration and test.

         A total for each column shall be calculated too.

         The status of the update of the SW documentation may
         be described as in the example figure 3.4.2-3.





















































     Figure 3.4.2-1  Example on SW Development Status




















































Figure 3.4.2-2  Example on SW Development Status Graphics






















































                      Figure 3.4.2-3

      Example on Update of SW As-Built Documentation



3.5      S̲Y̲S̲T̲E̲M̲ ̲I̲N̲T̲E̲G̲R̲A̲T̲I̲O̲N̲ ̲A̲N̲D̲ ̲T̲E̲S̲T̲

         The phase:  System Integration and Test shall be followed
         by the status of the test cases and on the error statistics.

         For each testgroup the total number of test cases shall
         be defined together with the number of test cases executed
         successfully.

         A total shall be given of all test cases.

         An example of this table is given in figure 3.5-1.

         The error statistics shall include only the software
         under configuration control and submitted to system
         integration and test.

         The table shall be given for a defined period (a week,
         a month, etc.).

         For each package the following shall be reported:

         -   the no. of errors detected 
         -   the no. of errors correcting
         -   the no. of errors outstanding at the end of the
             period 
         -   the accumulated no. of errors.

         A total shall be calculated, as an acceptance test
         may be connected to a limit on this number.

         A graphic presentation may be as in figure 3.5-2.





















































                       Figure 3.5-1

      Example of System Integration and Test Status





















































                       Figure 3.5-2

              Example on SW Error Statistics



3.6      I̲L̲S̲ ̲S̲T̲A̲T̲U̲S̲

         Integrated Logistics Support will submit status reports
         for each of the contract line items

         -   installation
         -   training
         -   documentation
         -   maintenance
         -   repair.



3.6.1    I̲L̲S̲-̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲

         The status report shall for each site describe the
         scheduled dates for 

         -   submittal of civil work requirements
         -   as-to-be-built drawings
         -   delivery of cables etc.
         -   site verification before site installation
         -   site installation start
         -   site acceptance test start.

         A special signature shall be given, if the item has
         been submitted and, if it has been accomplished and
         accepted.

         Comments may be added to the list.

         An example is shown in figure 3.6.1-1.

         If not covered by the master schedule a schedule for
         the installation shall be included too.

         An example is shown in figure 3.6.1-2.




















































                     Figure 3.6.1-1.
        Example on Site Implementation Milestones.




















































                      Figure 3.6.1-2
             Example on Installation Schedule


3.6.2    I̲L̲S̲-̲T̲r̲a̲i̲n̲i̲n̲g̲

         The status report of Training shall be divided into
         two sheets.

         The first one shall for each course given the status
         of all training material necessary before start of
         training. The second one is the schedule of all courses
         shown together.

         The first sheet shall describe the scheduled dates
         of:

         -   preliminary version (PV) submitted
         -   customer comments on PV
         -   final version (FV) submitted
         -   FV approved
         -   FV printed.

         A special signature shall be used if the item has been
         accomplished.

         An example on a training schedule is shown in figure
         3.6.2-1.





















































                      Figure 3.6.2-1

                    Training Schedule



3.6.2    I̲L̲S̲-̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲

         The status report shall for each documentation item
         describe the scheduled dates for

         -   submittal of preliminary version (PV)
         -   comments from customer on PV
         -   submittal of final version (FV)
         -   FV approved
         -   FV printed.

         A special signature shall be given, if the item has
         been accomplished.

         An example of another version of the documentation
         status report is given in figure 3.6.2-1.

         On overdue items a remark shall be made.























































                      Figure 3.6.2-1

            Example on Status of Documentation


3.6.3    I̲L̲S̲-̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲

         For maintenance documentation the same status sheet
         shall be used as for documentation, i.e. scheduled
         dates for:

         -   submittal of PV
         -   comments from customer on PV
         -   submittal of FV
         -   FV approved
         -   FV printed,

         and a special signature, if the item has been accomplished.



3.6.4    I̲L̲S̲-̲R̲e̲p̲a̲i̲r̲

         The status of the Repair function shall be divided
         into two sheets:

         -   repair before customer warranty
         -   repair under customer warranty.

         The report submitted shall cover a defined period.
         For each HW item the status of no. of items

         -   incoming to repair
         -   repaired
         -   on stock unrepaired ultimo
         -   out-of-house for repair, 

         shall be given.





















                         APPENDIX


                   Draft Status Report













                      STATUS REPORT




          ............................ (project)




                           FOR




          ............................. (period)













                                                Date:
                          
                                           Issued by:








                     A̲C̲C̲O̲M̲P̲L̲I̲S̲H̲M̲E̲N̲T̲S̲

Item:                                                     Date:







                     P̲R̲O̲B̲L̲E̲M̲S̲/̲I̲S̲S̲U̲E̲S̲


Problem/Issue:                             Suggested Actions:





                   N̲E̲A̲R̲ ̲T̲E̲R̲M̲ ̲A̲C̲T̲I̲V̲I̲T̲I̲E̲S̲

Activity:                                              Date:



















                            PROJECT STATUS


                              including


                     o   Master Schedule

                     o   Contract Status

                     o   Quotations or Extentions

                     o   Budget Status this year

                     o   Man-power List


















































                           PROGRAM SCHEDULE



                             CONTRACTUAL
                                VALUE
                                 FOR

                             ...........



 ̲ ̲ ̲A̲m̲e̲n̲d̲m̲e̲n̲t̲ ̲o̲r̲ ̲l̲e̲t̲t̲e̲r̲-̲o̲f̲-̲i̲n̲t̲e̲n̲t̲ ̲ ̲ ̲ ̲ ̲ ̲D̲a̲t̲e̲ ̲ ̲ ̲ ̲ ̲ ̲C̲o̲n̲t̲r̲a̲c̲t̲ ̲V̲a̲l̲u̲e̲ ̲ ̲ ̲ ̲ ̲


Orig. contract






































 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Total contract
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲




                       Q̲u̲o̲t̲a̲t̲i̲o̲n̲s̲ ̲o̲r̲ ̲E̲x̲t̲e̲n̲s̲i̲o̲n̲s̲

 ̲ ̲S̲u̲b̲j̲e̲c̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲V̲a̲l̲i̲d̲i̲t̲y̲ ̲D̲a̲t̲e̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲A̲p̲p̲r̲.̲ ̲V̲a̲l̲u̲e̲ ̲













































 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

Total Value
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲




                          B̲u̲d̲g̲e̲t̲ ̲a̲n̲d̲ ̲A̲c̲c̲o̲u̲n̲t̲


                          D̲a̲t̲e̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                         P̲r̲o̲j̲e̲c̲t̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                          P̲e̲r̲i̲o̲d̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


                              Budget          Account      Comment
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲1̲0̲0̲0̲ ̲D̲k̲r̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲1̲0̲0̲0̲ ̲D̲k̲r̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                     Net Sales
-                    Direct Production Costs
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

=                    Marginal Contribution
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

-                    Sales & Distr. Costs
-                    General & Adm. Costs

 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

=                    Net Operating Result
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
-                    Capital Cost
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
= Net Income before Tax
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
C̲o̲m̲m̲e̲n̲t̲s̲:̲





                            B̲u̲d̲g̲e̲t̲ ̲S̲t̲a̲t̲u̲s̲


                         D̲a̲t̲e̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                                                                 P̲r̲o̲j̲e̲c̲t̲:̲
                                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                                 ̲ ̲ ̲ ̲ ̲ ̲ ̲
                                                                 ̲ ̲ ̲ ̲ ̲ ̲

                         P̲e̲r̲i̲o̲d̲:̲ ̲T̲o̲t̲a̲l̲ ̲P̲r̲o̲j̲e̲c̲t̲

                                              Revised
                              Budget          Budget       Comment
                                                                    dated           dated
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲1̲0̲0̲0̲ ̲D̲k̲r̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲1̲0̲0̲0̲ ̲D̲k̲r̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                     Net Sales
-                    Direct Production Costs
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

=                    Marginal Contribution
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

-                    Sales & Distr. Costs
-                    General & Adm. Costs
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

=                    Net Operating Result
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
-                    Capital Cost
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
= Net Income before Tax
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
C̲o̲m̲m̲e̲n̲t̲s̲:̲




                                     M̲a̲n̲p̲o̲w̲e̲r̲ ̲L̲i̲s̲t̲

                         P̲r̲o̲j̲e̲c̲t̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

                         D̲a̲t̲e̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


            P̲R̲O̲J̲E̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲R̲:̲


            S̲E̲C̲R̲E̲T̲A̲R̲I̲A̲T̲


            H̲A̲R̲D̲W̲A̲R̲E̲



            S̲Y̲S̲T̲E̲M̲ ̲E̲N̲G̲I̲N̲E̲E̲R̲I̲N̲G̲



            S̲O̲F̲T̲W̲A̲R̲E̲



            I̲L̲S̲-̲T̲R̲A̲I̲N̲I̲N̲G̲


            I̲L̲S̲-̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲


            I̲L̲S̲-̲M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲


            I̲L̲S̲-̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲




                                   U̲S̲E̲D̲ ̲M̲A̲N̲P̲O̲W̲E̲R̲ ̲R̲E̲S̲O̲U̲R̲C̲E̲S̲ ̲(̲M̲M̲)̲

                     P̲r̲o̲j̲e̲c̲t̲:̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


                                              Used this      Budget this
                                              year until     year until
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲Y̲e̲a̲r̲/̲P̲e̲r̲i̲o̲d̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲n̲o̲w̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲n̲o̲w̲ ̲ ̲ ̲

Program Management
Systems Engineering
H/W Development
S/W Development
Fabrication
Installation
Acceptance
Logistics
Documentation
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
      Total
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
      Accumulated
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲




                                        P̲L̲A̲N̲N̲E̲D̲
                                          A̲N̲D̲
                                        A̲C̲T̲U̲A̲L̲
                                       R̲E̲S̲O̲U̲R̲C̲E̲S̲


       used to establish Functional Baselines and Software Development.



 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲               
                         Planned      %     Actual use
                                        (pr.      )        (pr.      )
            Requirements Baseline
            Systems Design Baseline
            Preliminary Design
            Detailed Design
            Code and Unit Test
            Package Integration
            System Integration
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

            Total                                             100%
 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲




                             C̲o̲n̲t̲r̲a̲c̲t̲ ̲D̲e̲l̲i̲v̲e̲r̲a̲b̲l̲e̲s̲ ̲S̲t̲a̲t̲u̲s̲

                     Date                                       Comments
 ̲L̲I̲ ̲ ̲S̲u̲b̲j̲e̲c̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲d̲ ̲ ̲ ̲S̲u̲b̲m̲i̲t̲t̲e̲d̲ ̲ ̲ ̲A̲p̲p̲r̲o̲v̲e̲d̲ ̲ ̲ ̲I̲n̲v̲o̲i̲c̲e̲d̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲


























 ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲

       C̲o̲m̲m̲e̲n̲t̲s̲: