WangText
4.6.7
- LI 7.2-7.8 Site Provisional Acceptance will be officially executed immediately after
SPA 1.
- LI 7.9-7.16 SPA for system 9 to 16 will be performed in accordance with the installation
schedule given in ref 1).
L̲I̲ ̲8̲ ̲L̲o̲g̲i̲s̲t̲i̲c̲s̲ ̲S̲u̲p̲p̲o̲r̲t̲
- L 8.1 SW Warranty is rescheduled in accordance with the rescheduling of 1st SPA
- LI 8.2.4.2 Development of courses is completed by conduction of the first MT/RST
course.
- LI 8.2.5 Conduction of courses has started as planned at the beginning ofJanuary
1983.
- LI 8.4.2 Issue 1 of the Piece Parts RSPL has been forwarded to SHAPE December 1982.
- LI 8.4.4 Official Spare Parts Delivery to sites will take place together with the
SPA's. The site spare parts will be shipped together with the hipment of
CAMPS system. These dates are shown on the schedule.
- LI 9.3 Manuals and handbooks will be delivered
as site spare parts LI 8.4.4.
- LI 9.4 The As-built documentation will be
delivered together with the SPA's.