top - download
⟦d950f45da⟧ Wang Wps File
Length: 101575 (0x18cc7)
Types: Wang Wps File
Notes: ASC - GREECE; TECHNICAL
Names: »4678A «
Derivation
└─⟦4ac6f2002⟧ Bits:30006023 8" Wang WCS floppy, CR 0438A
└─ ⟦this⟧ »4678A «
WangText
=…07…<…0a…<…0e…<…05…;…0c…;…01…:…08…:…0e…:…05…9…0b…9…01…9…06…8…09…8…0f…8…05…7…0a…7…0f…7…07…6…0a…6…00…6…02…5…86…1
…02…
…02…
…02…
…02…
ASC
GREECE
-
PART
II
SYS/84-03-10
TECHNICAL
PROPOSAL
Page
5̲ ̲ ̲A̲S̲C̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
5.1 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲A̲N̲A̲L̲Y̲S̲I̲S̲
5.1.1 R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲ ̲A̲n̲a̲l̲y̲s̲i̲s̲
a) Christian Rovsing A/S (contractor) shall make the
following major deliveries to Hellenic Civil Aviation
Authority (customer):
o Installation Plan
o Site Preparation Requirement
o Equipment Installation Drawings
o Delivery and Installation of Equipment.
b) The Installation Plan shall describe contractors
planning of site cabling and equipment installation
furthermore the plan specifies the division of
responsibilities between customer and contractor
concerning site preparation and installation.
c) Site Preparation Requirements (SPR) shall specify
the extent of site preparation regarding structural
and Ambient requirements customer must undertake
before equipment is installed. In order to generate
the SPR and the installation plan, contractor will
conduct a site survey at the site.
d) Equipment Installation Drawings (EID) shall show
how the proposed equipment is installed and interconnected.
e) Delivery and installation of equipment will be
performed in accordance with the master schedule
after Contractor has verified that the sites has
been prepared in accordance with the Site Preparation
Requirements.
Separate prices for delivery F.O.B. contractors
factory and CIF customer-site in Athens has been
given.
f) Preparation of the site for installation as well
as the actual equipment installation shall be carried
out either by contractor or by customer supervised
by contractor.
5.1.2 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲C̲o̲s̲t̲ ̲A̲n̲a̲l̲y̲s̲i̲s̲
a) Installation effort is divided in three main areas:
1. Installation planning and preparation of Installation
documentation (Installation Plan, SPR, EID)
2. Installation of power cables and outlets and
installation of signal cables and ducts.
3. Installation and checkout of computer equipment.
b) The price for preparation of SPR and EID's are
included in the documentation costs. The cable
installation costs are based on the following:
- installation of 30 m cable ducts
- installation of appr. 1000 m signal cable (63
x 15 m standard V24 cable)
c) Please note, that above points a.2 and a.3 are
priced as options and, as such, not included in
the Basic System Price.
During proposal factfinding or at time of negotiation
customer should decide on level of customer participation.
5.2 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲E̲R̲V̲I̲C̲E̲
In connection with the customer participation in the
installation of the ASC equipment outlined above contractor
can provide assistance as follows:
Cost for a specialist will consist of a start fee and
a cost per day. The start fee will contain the travel
and start expenses, while the cost per day will cover
the man power and subsistence allowences.
Start fee: Dkr. 22,000
Cost per day: Dkr. 5,800.
5.3 C̲H̲A̲N̲G̲E̲ ̲O̲V̲E̲R̲
The CR system will be installed in such a way that
it can gradually take over the ASC functions without
affecting the normal traffic flow.
This will be accomplished by dualizing the in/outgoing
lines during the installation and implementation period,
enabling the two systems to run in parallel until the
CR system has proven its capability of completely taking
over the ASC functions.
5.4 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲
A detailed breakdown of the installation of the UPS
system, the Computer H/W and the associated cabling
is provided in figure 5.4-1.
WORKING DAYS
1 3 5 7 9 11 13 15 17 19 21
23 25
2 4 6 8 10 12 14 16 18 20
22 24
Installation team
arrival at site '1'
Preparations for
installation '2 '
Signal cable
installations ' 7 '
Unpacking and inven-
tory check '1'
No break power physi-
cal integration '2 '
No break power elec-
trical installation '2 '
No break power up/
test '2 '
Power and ground in-
stallation for ASC ' 5 '
ASC equipment physi-
cal integration ' 2 '
ASC equipment elec-
trical installation ' 2 '
ASC equipment power
up/test '1 '
Test by maint. and
diagn. programs ' 2 '
Connection of exter-
nal signal cables ' 2
'
Figure 5.4-1
5.5.1 S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲l̲a̲n̲n̲i̲n̲g̲
a) The planning of the installation starts immediately
after contract award. The time span from contract
award to completion of installation can be divided
into two major steps:
1. Site Preparation
2. Site Installation.
b) The main activities in step 1 are proposed as follows:
1. Site survey, eight months prior to start of
site installation.
2. Preparation and delivery of an Installation
Plan, 5 months prior to start of installation.
3. Preparation and delivery of site preparation
requirements, 5 months prior to on-site installation.
4. Preparation and delivery of equipment installation
drawings, two months prior to on-site installation.
5. Site readiness verification, one month prior
to start of equipment installation.
The main activities in step 2 are proposed as follows:
6. Transportation to site.
7. On-site installation.
c) A more detailed description of the step 1 and 2
activities is presented in the following sections.
5.5.1.1 S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲
Contractor will perform a site survey with customer
participation. The purpose of the survey is to gather
information for the preparation of site preparation
requirements and plans for on-site integration and
installation.
An important task to be performed with the customer
during the survey meetings is to determine the equipment
room layout.
Building Schematics and civil engineering drawings
are to be used for the survey and should be handed
over to contractor at start of the survey.
5.5.1.2 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲P̲l̲a̲n̲
Contractor will prepare an installation plan, which
specifies the activities to be performed during steps
1 and 2.
The plan will cover the following areas:
a. Delivery of Site Preparation Requirements and Equipment
Installation Drawings.
b. Site readiness verification.
c. Packing, shipment, customs clearance and transportation
to site.
d. A specification of the division of responsibilities
between customer and contractor concerning transportation
and installation.
e. On-site integration and installation.
The plan will be delivered to Customer for approval
5 months prior to start of installation.
5.5.1.3 S̲i̲t̲e̲ ̲P̲r̲e̲p̲a̲r̲a̲t̲i̲o̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
a) Contractor will prepare a site preparation requirements
(SPR) concerning the preparation of the site for
installation of the proposed equipment. The SPR
will be submitted to Customer for approval three
months after completion of the Site Survey.
b) Besides the facility data given in the Technical
Specification of the RFP the SPR will be based
on the physical characteristics of the proposed
equipment, the equipment rooms layouts, the surveyed
cable routing and other pertinent data collected
during the site survey.
c) The SPR will specify equipment related requirements,
to customers facilities concerning access, space,
power supply, grounding, cooling capacity etc.
The SPR will contain floor plans showing the layout
of all major assemblies of the proposal equipment.
5.5.1.4 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲D̲r̲a̲w̲i̲n̲g̲s̲
a) Contractor will deliver equipment installation
drawings to Customer for approval 2 months prior
to start of installation.
b) The approved installation drawings will be used
by Contractor for power and signal cable installation
as well as for installation of the proposed equipment.
c) The installation drawings will be based on the
approved site preparation requirements, the hardware
configuration and the equipment characteristics.
d) The drawings will show how the proposed equipment
is to be installed and interconnected.
The drawings will be prepared to contain:
- Equipment layouts, showing physical location
of contractor provided equipment
- Power distribution and power cable connections
to contractor provided equipment
- Signal cabling and signal cable connections
to contractor provided equipment including
signal cable connections between contractors
equipment
- Power requirements and environmental conditions
of the provided equipment
- Procedures for unpacking, mounting and checkout.
e) Provisional drawings will be delivered two months
prior to start of installation as indicated above.
The drawings will be marked up during installation
to reflect the as built situation and corrected
drawings will be delivered 3 months after Provisional
Site Acceptance.
5.5.1.5 S̲i̲t̲e̲ ̲R̲e̲a̲d̲i̲n̲e̲s̲s̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
a) Cotractor and Customer will jointly perform a site
verification. The verification will take place
30 days prior to the scheduled installation date.
b) The purpose is to verify that the site is ready
for installation, i.e. that the site is prepared
in accordance with the preparation requirements.
c) Final arrangements concerning transportation to
site and Contractors presence at site during installation
and test are also to be made at time of site verification.
5.5.2 A̲S̲C̲ ̲F̲a̲c̲i̲l̲i̲t̲i̲e̲s̲
The following describes the Installation and Operating
Environment required by the System.
5.5.2.1 F̲a̲c̲i̲l̲i̲t̲y̲ ̲L̲a̲y̲o̲u̲t̲s̲
The Equipment Layouts (Figure 5.5.2.1-1 and 5.5.2.1-2)
reflect the floor space required by cabinets and operator
position.
The Access Dimension for racks and terminal equipment
is shown in figure 5.5.2.1-3 and 5.5.2.1-4.
The Racks are positioned such that sufficient clearance
is maintained for access to the front and rear of the
equipment, otherwise, only few constraints as to the
placement of the equipment exist. The final layout
will take into account human factors, segregation of
functional activities, access for maintenance and other
considerations or preferences of the customer.
One of the tasks to be performed at the site survey
is to work out optimal layouts in conjunction with
customer.
5.5.2.1.1 A̲S̲C̲ ̲R̲o̲o̲m̲
The Equipment Layout of the ASC room is shown in Figure
5.5.2.1-1.
The Equipment consists of:
Pos. 1-4: Dualized Computer System mounted in 19"
racks.
Pos. 5-6: Delta Data VDUs
Pos. 7: High Speed Printer
Pos. 8: Telex Station.
5.5.2.1.2 U̲P̲S̲ ̲R̲o̲o̲m̲
The Equipment Layout of the UPS room is shown on Figure
5.5.2.1-2.
The Equipment consists of:
Pos. 1: Charger
Pos. 2: Batteries
Pos. 3: Inverter.
For a further description of the UPS system, refer
to section 3.7.
Figure 5.5.2.1-1
AFTN ASC Installation Typical Layout
Figure 5.5.2.1-2
AFTN UPS-System Typical Layout
Figure 5.5.2.1-3
VDU Terminal Typical Layout and Access Requirements
Figure 5.5.2.1-4
Typical Equipment Layout and Access Requirements
5.5.2.2 F̲a̲c̲i̲l̲i̲t̲y̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
5.5.2.2.1 A̲c̲c̲e̲s̲s̲ ̲a̲n̲d̲ ̲D̲i̲m̲e̲n̲s̲i̲o̲n̲s̲
a) Weight and dimensions of each piece of equipment
in the ASC and UPS area are listed in the table
Figure 5.5.2.2-1.
All dimensions are within customer's stated requirements
concerning the access route.
b) The heaviest rack is well within the floor load
limit of 625 kilograms per square meter as can
be seen from the follwing calculation:
Floor load of heaviest rack:
̲ ̲ ̲ ̲ ̲W̲e̲i̲g̲h̲t̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲4̲5̲0̲ ̲ ̲ ̲ ̲ ̲ ̲
= 2 = 625 kg/m…0e…2…0f…
…0e… Floor Space 0.6 x 1.2 m…0f…
Since the rack is provided with Access space at
front and rear, the distributed floor load is considerably
smaller.
E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲A̲S̲C̲ ̲R̲O̲O̲M̲
P̲O̲S̲.̲ ̲N̲O̲ ̲ ̲ ̲ ̲ ̲I̲T̲E̲M̲ ̲ ̲ ̲ ̲ ̲ ̲W̲E̲I̲G̲H̲T̲ ̲ ̲ ̲ ̲W̲I̲D̲T̲H̲ ̲ ̲ ̲ ̲D̲E̲P̲T̲H̲ ̲ ̲ ̲ ̲H̲E̲I̲G̲H̲T̲
1 Rack 1 450 60 120 180
2 Rack 2 420 60 120 180
3 Rack 3 350 60 120 180
4 Rack 4 380 60 120 180
5-6 VDU 48 48 76 43
7 HSP 159 87 75,5 113
8 PTP/R 43 52 55 46
E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲U̲P̲S̲ ̲R̲O̲O̲M̲
P̲O̲S̲.̲ ̲N̲O̲ ̲ ̲ ̲ ̲ ̲I̲T̲E̲M̲ ̲ ̲ ̲ ̲ ̲ ̲W̲E̲I̲G̲H̲T̲ ̲ ̲ ̲ ̲W̲I̲D̲T̲H̲ ̲ ̲ ̲ ̲D̲E̲P̲T̲H̲ ̲ ̲ ̲ ̲H̲E̲I̲G̲H̲T̲
1 CHARGE 700 72 80 180
2 BATTERIES 1000
3-4 INVERTER 300 72 80 180
All weight in kg. and width, depth, height in cm.
Figure 5.5.2.2-1
Equipment Weight and Dimensions
5.5.2.2.2 E̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲P̲o̲w̲e̲r̲ ̲a̲n̲d̲ ̲G̲r̲o̲u̲n̲d̲i̲n̲g̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
a) In order to ensure that power for the system can
be maintained for at least 6 hours, regardless
of the mains supply, CR proposes an Uninterruptable
Power Supply (UPS) as described in section 3.7
of this proposal.
The UPS will enable the ASC to operate regardless
of +̲ 10% variation of the mains frequency and +̲
20% variation of the mains voltage. In addition
the system will be immune against transients.
b) The grounding concept of the proposed CR equipment
is the same as used for military equipment which
meets the appropriate Mil spec. All equipment frames
will be connected to the ground provided by customer.
Each piece of equipment will be connected to the
ground bus at one point only, in order to prevent
ground loops.
All signal cables shall contain a logic ground,
separated from the frame ground, and have an overall
shield connected to the frame ground at the CR
equipment end only.
5.5.2.2.3 A̲i̲r̲ ̲C̲o̲o̲l̲i̲n̲g̲
As all rack mounted equipment have internal blowers
using ambient room air for forced ventilation, the
equipment does not require any direct cooling.
Ambient room air is drawn into the racks through the
filters of the front doors and deflected upwards through
the top panel grills.
Refer to Figure 5.5.2.2-2.
The heat dissipation figures for the equipment in the
ASC Area are shown in the table Figure 5.5.2.2-3.
Figure 5.5.2.2-2
Equipment Dimensions and Air Flow
E̲L̲E̲C̲T̲R̲I̲C̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲ A̲I̲R̲
̲C̲O̲O̲L̲I̲N̲G̲
UNIT TOTAL UNIT
TOTAL
̲ ̲ ̲P̲O̲S̲ ̲ ̲ ̲ ̲I̲T̲E̲M̲ ̲ ̲ ̲ ̲Q̲T̲Y̲ ̲V̲O̲L̲T̲S̲ ̲W̲I̲R̲E̲S̲ ̲P̲H̲A̲S̲E̲ ̲ ̲ ̲ ̲W̲ ̲ ̲ ̲ ̲ ̲ ̲K̲W̲ ̲ ̲ ̲ ̲ ̲K̲C̲A̲L̲/̲H̲
̲ ̲K̲C̲A̲L̲/̲H̲
1 RACK 1 1 220 3 1 1,8 1548
2 RACK 2 1 220 3 1 1,8 1548
3 RACK 3 1 220 3 1 1,5 1320
4 RACK 4 1 220 3 1 1,0 880
5-6 VDU 2 220 3 1 250 0,5 220 440
7 HSP 1 220 3 1 0,7 616
8 PTP/R 1 220 3 1 0,36 315
Figure 5.5.2.2-3
Equipment Facility Requirements ASC Area
5.5.2.2.4 E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲C̲o̲n̲d̲i̲t̲i̲o̲n̲s̲
The CR80 equipment is designed to operate/comply with
the following:
D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲s̲
o Operating: These limits apply to equipment
installed as specified
and operating in a normal
air cooled computer room
environment.
o Storage: The limits apply to equipment
properly packed and protected
against dust, moisture,
condensed water etc.
o Transportation: These limits apply to equipment
properly packed for shipment.
T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲
o Operating: 10…0e…o…0f… to 40…0e…o…0f…
Maximum rate of change
6…0e…o…0f… per hour
o Storage/
Transportation: -40…0e…o…0f… to 70…0e…o…0f…
H̲u̲m̲i̲d̲i̲t̲y̲
o Operating: 20 per cent to 80 per cent
RH non condensing. Maximum
rate of change 10 per cent
RH per hour.
Absolute water content
in the room air shall be
limited to 22g water per
cubic meter of air.
o Storage/
Transportation: 10 per cent to 90 per cent
non condensing
A̲l̲t̲i̲t̲u̲d̲e̲
o Operating: 0 to 2000m
o Storage/
Transportation: 0 to 10.000m
V̲i̲b̲r̲a̲t̲i̲o̲n̲
o Operating and
Storage: 5 Hz to 50 Hz constant
displacement of 0.02mm
50 Hz smooth crossover
50 Hz-350 Hz constant acceleration
0.2 G
o Transportation: 5 Hz to 350 Hz constant
acceleration 1.5 G
S̲h̲o̲c̲k̲
o Operating and
Storage: 1G, half sine wave, 10
ms duration. Not to be
repeated more often than
one per 10 seconds
o Transportation: 25G, half sine wave, 10
ms duration.
E̲M̲I̲ ̲L̲e̲v̲e̲l̲s̲
The equipment will be installed in EMI Racks which
will provide for adequate screening against the electromagnetic
Radiation/Interference specified for the installation
site.
Without screening the CR80 equipment is in conformance
with the specifications of FCC and VDE 0871 as follows:
The conducted emission is up to 14 dB above limit B
and up to 2 dB above limit A of VDE 0871. The FCC limit
A is met.
The radiated magnetic field is above VDE limit B in
the frequency range 6-30 MHz.
The radiated electromagnetic field is above VDE limit
A and FCC limit A in the frequency range up to 88 MHz.
The radiation is above limit B of VDE in the frequency
range 30-350 MHz.
5.6 S̲I̲T̲E̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
5.6.1 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲t̲h̲e̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
The delivery of equipment follows the master schedule.
Actual shipping dates are selected in accordance with
the readiness of the site and the time for transportation.
The equipment is shipped by air and truck and packed
accordingly. Christian Rovsing A/S will arrange the
transportation so that the company's installation team
or installation supervisor, depending on option chosen,
will be present at the site for receipt and unpacking
of the equipment.
The packing and marking are proposed as in accordance
with Christian Rovsing A/S's standard procedures for
CR80 equipment. The following is a brief discussion
of that method.
The computer equipment is constructed in a modular
fashion, i.e. 19" racks containing crate assemblies
with plug-in modules. This is reflected in the packaging
as follows:
a. Modules are packed in styrofoam containers designed
to fit each module size. A number of modules are
put into a cardboard box or similar of Europe pallet
standard size.
b. Crates are packed with styrofoam corners so that
they fit into a cardboard box of Europe pallet
standard size.
c. Each rack or cabinet bay is separately packed on
a wooden pallet, protected with styrofoam corners,
and wrapped in plastic sheets. A skeleton of timber
protects the five free surfaces.
Packing lists are forwarded with every shipping container.
One copy of the packing list is enclosed in the container;
one copy is attached to the exterior of the container
in an envelope clearly marked "packing list".
Each container is to be clearly marked on the exterior
surface with at least:
- purchaser identification
- manufacturer's name and address
- shipping address.
In addition, each container is clearly labeled with
the identification and number of pieces in the shipment
and with precautionary labelling applicable to handling.
5.6.2 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲C̲a̲b̲l̲i̲n̲g̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
a) Optionally, contractor will install the ASC equipment
in accordance with the Customer approved Equipment
Installation Drawings.
b) Customer will prepare the facilities in accordance
with the approved site preparation requirements.
This includes installation of a power distribution
panel with circuitbreakers, air conditioning and
other related civil works required to prepare the
rooms for equipment installation.
c) Customer shall provide 3 phases, neutral and an
isolated ground in the appropriate room terminated
in a power distributing panel with circuitbreakers.
Optionally, contractor will provide and install
metal ducts for signal cabling; provide, run and
terminate signal cables in both ends. Customer
will provide connectors for connection to equipment
not provided by CR. It is anticipated that the
appropriate room(s) are provided with raised floors.
The UPS equipment, i.e. generator, batteries and
associated racks, can be installed remote from
the ASC. It is anticipated that the generator is
installed close to an outer wall.
2.6.2.1 C̲a̲b̲l̲i̲n̲g̲
All signal cables connected to the equipment provided
by CR, will be installed by the contractor (optionally).
Signal cables which are interconnecting CR provided
equipment are delivered as part of the equipment. Signal
cables that are connecting CR provided equipment to
equipment not provided by CR, will be run and terminated
in both ends by CR (optionally). Connectors which shall
connect the signal cables to the CR provided equipment
are delivered by CR, while connectors which shall connect
the signal cables to equipment not provided by CR shall
be delivered by customer.
All cables shall be clearly identified in both ends
by means of "cable idents".
5.6.6.2 G̲e̲n̲e̲r̲a̲l̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲R̲u̲l̲e̲s̲
The equipment will be contained in 19" EMI protective
racks. For maintenance and free ventilation purposes,
the equipment should be installed with the access area,
illustrated in sect. 5.5.2.
The racks will be installed on appropriate schock-
absorbers. The power and signal cables will enter the
racks through the bottom, or through the top, as required.
The installation shall comply to the Greek safety regulations.
6̲ ̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
6.1 G̲E̲N̲E̲R̲A̲L̲
The documentation proposed by Christian Rovsing A/S
is based on the information stated in the RFP and experience
from similar projects.
The following provides an overview of the content and
arrangement of the offered documentation.
The type of documentation proposed is listed below:
a) Program management documentation - 1
b) Study report - 1
c) Installation documentation (see chapter 5) - 2
d) Quality assurance documentation - 1
e) Training documentation (see chapter 7) - Nos. of
students
f) System description - 10
g) Provisional technical handbooks - 2
h) Final handbooks - 2
i) Maintenance check lists - 2
j) Maintenance reports (proposal) - 2.
6.1.1 R̲i̲g̲h̲t̲ ̲t̲o̲ ̲D̲u̲b̲l̲i̲c̲a̲t̲e̲
HCAA will have the right to dublicate the supplied
documentation, manuals and training documentation.
6.1.2 S̲t̲a̲n̲d̲a̲r̲d̲s̲
Standardized international technical terms and nomeclature
will be used in the supplied documentation (e.g. the
IEC standard).
The contents of the documentation will be structured
in a logical and functional way.
The proposed documentation will generally correspond
with the actual equipment supplied (including subcontractors).
Special attention will be given to the correspondance
between circuit diagrams and the actual parts. Generally,
documentation of no reference to the actual equipment
will be crossed out or removed.
The international SI measurement system will be used
in the documentation.
6.1.3 A̲m̲e̲n̲d̲m̲e̲n̲t̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
All delivered documentation will be checked by the
HCAA prior to final acceptance. The two parties coordinate
their points of view on the documentation and changes/correction
agreed upon will be incorporated without extra cost,
provided they emerge from errors in the basic documents,
or from lack of compliance with the contractual technical
specifications.
6.2 D̲E̲T̲A̲I̲L̲E̲D̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲ ̲A̲N̲A̲L̲Y̲S̲I̲S̲
Generally, Christian Rovsing A/S will deliver documentation
according to good commercial standard procedures.
6.2.1 P̲r̲o̲g̲r̲a̲m̲ ̲M̲a̲n̲a̲g̲e̲m̲e̲n̲t̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
The program management documentation will include:
a) Progress chart (PERT diagram, bar chart, etc.)
which will be updated when necessary.
b) Minutes of meeting (MOM) from progress review meetings
c) Engineering Change Proposal ECP (technical order),
if applicable, which describe the reasons and consequences
related to proposed modifications.
d) Summary of delivered documents (Documentation List)
including date and revision status.
e) Design standards (referred in the RFP as project
coordination documents) which determines the Contractor
Design Standard for this project.
6.2.2 D̲e̲s̲i̲g̲n̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲s̲ ̲a̲n̲d̲ ̲R̲e̲p̲o̲r̲t̲s̲
a) S̲y̲s̲t̲e̲m̲ ̲D̲e̲s̲i̲g̲n̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲ ̲(̲S̲D̲S̲)̲
The SDS will include a complete description of
the system including non-standard parts and relevant
interfaces.
b) R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲ ̲R̲e̲p̲o̲r̲t̲s̲
The Reliability Reports includes the necessary
information to prove that the availability of the
system meets or exceed the requirements.
c) D̲e̲t̲a̲i̲l̲e̲d̲ ̲D̲e̲s̲i̲g̲n̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
This document will be the functional specification
for the system and will relate directly to the
contractual specification.
6.2.3 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
Christian Rovsing A/S will deliver final and provisional
drawings, and installation procedures according to
chapter 5 of this proposal.
6.2.4 Q̲u̲a̲l̲i̲t̲y̲ ̲C̲o̲n̲t̲r̲o̲l̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
a) F̲i̲n̲a̲l̲ ̲F̲a̲c̲t̲o̲r̲y̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲T̲e̲s̲t̲ ̲S̲p̲e̲c̲i̲f̲i̲c̲a̲t̲i̲o̲n̲:
The manufacturer will submit a proposed factory
acceptance schedule for each part of the equipment
to the HCAA at the time specified in the time-schedule.
The FAT test specification will include a description
of all the tests necessary for checking that the
equipment is operating satisfactorily, a list in
tabular form of the operation to be performed and
a list of realistic faults which may occur in the
system.
b) S̲i̲t̲e̲ ̲P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲(̲S̲P̲A̲)̲ ̲S̲c̲h̲e̲d̲u̲l̲e̲:
This shall include a description of the whole of
the test procedures involved in checking the satisfactory
operation of the system and its guaranteed performance.
CHRISTIAN ROVSING A/S will submit the SPA schedule
to HCAA; The HCAA reserves the right to modify
all or part of the proposed tests and to have other
tests performed which conform to the standards
in force in Greece. Such additional tests shall
in no circumstances justify any postponement of
acceptance dates.
6.2.5 P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲H̲a̲n̲d̲b̲o̲o̲k̲s̲
a) System Description Manual
b) S/W Documentation
c) Maintenance Manual
d) Operation Manual
e) Operator's/User's Manual
f) Drawings
g) H/W Assembly Breakdown
h) Spare Parts List
i) Test Documentation
j) Maintenance Check List
k) Maintenance Check Reports.
6.2.5.1 S̲y̲s̲t̲e̲m̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲M̲a̲n̲u̲a̲l̲
The manual gives a general description of the system
function and use. It includes the system block diagram.
It gives an overview of the hardware/software interaction.
The manual describes the interfaces of the equipment
and its relation with external equipment including
a list of input/output signals of the interfaces to
adjacent equipment.
6.2.5.2 S̲/̲W̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
The software documentation will be divided into the
following groups:
1. P̲r̲o̲g̲r̲a̲m̲m̲i̲n̲g̲ ̲D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲ ̲T̲o̲o̲l̲s̲
a) Operating System
b) Utilities
c) Compilers
d) Linkers
e) SWELL & PASCAL Reference Manuals
2. A̲p̲p̲l̲i̲c̲a̲t̲i̲o̲n̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲ ̲A̲s̲-̲b̲u̲i̲l̲t̲ ̲S̲y̲s̲t̲e̲m̲ ̲D̲e̲s̲i̲g̲n̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
3. S̲y̲s̲t̲e̲m̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
For further details related to paragraphs 2 and 3 above,
see Software Implementation.
6.2.5.3 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲M̲a̲n̲u̲a̲l̲
Chapter 4 in the proposal describes the maintenance
philosophy.
A component level maintenance manual is only needed
if a development system and automatic testequipment
are required. Refer to chapter 8 - Accessories of this
proposal.
6.2.5.4 O̲p̲e̲r̲a̲t̲i̲o̲n̲ ̲M̲a̲n̲u̲a̲l̲
This manual comprises instructions for
- Job initiation
- Program Loading.
Unpacking instructions, transport data etc. will be
given in the Installation Documentation, see chapter
5 in this proposal.
6.2.5.5 O̲p̲e̲r̲a̲t̲o̲r̲'̲s̲/̲U̲s̲e̲r̲'̲s̲ ̲M̲a̲n̲u̲a̲l̲
This manual will give the necessary instructions concerning
how to operate the system. The content and format of
the operator's/User's Manual will meet the User's need.
The manual will describe the use of the various commands
to give the user/operator the knowledge required to
use the system, use the editing facilities, correct
messages, send messages, and receive messages.
6.2.5.6 D̲r̲a̲w̲i̲n̲g̲s̲
A set of drawings will be provided in the form of reproducible
copies. Reproduction of good quality will be possible.
The drawings shall contain the following:
a) Drawing Title
b) Drawing Number
c) Number of sheets
d) Revision status, Issue and Date
e) Drawing Date.
Christian Rovsing A/S will assure that OEM supplier's
drawings meet the above requirements. A list will specify
each set of drawings.
The drawings such as Circuit Diagrams and Blocked Schematics
are included in the Technical Manuals (TCM) for modules
and crates.
The TCMs will only be needed if HCAA requires a development
system and component level maintenance.
6.2.5.7 H̲a̲r̲d̲w̲a̲r̲e̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲ ̲B̲r̲e̲a̲k̲d̲o̲w̲n̲
The Hardware Assembly Breakdown describes and illustrates
the assembly breakdown of the hardware tree in order
to help the personnel towards the installation and
maintenance tasks, i.e. in identification of the replaceable
parts and the interconnection between the modules,
units, crates and racks.
The H/W Assy Breakdown will provide the following information
about each Equipment, its major assemblies, sub-assemblies,
and modules:
- Manufactors P/N
- Nomenclature
- Quantity.
6.2.5.8 S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲C̲a̲t̲a̲l̲o̲g̲/̲L̲i̲s̲t̲
Refer to chapter 4 here of this proposal.
6.2.5.9 A̲u̲x̲i̲l̲i̲a̲r̲y̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲a̲n̲d̲ ̲B̲u̲i̲l̲t̲-̲I̲n̲ ̲T̲e̲s̲t̲ ̲(̲B̲I̲T̲)̲
BIT information is described in the Annex A to Chapter
4 here of this proposal, M&D Requirements.
6.2.5.10 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲h̲e̲c̲k̲-̲L̲i̲s̲t̲,̲ ̲T̲e̲s̲t̲ ̲R̲e̲c̲o̲r̲d̲s̲
See section 4.1.1.2(b) here of this proposal.
6.2.5.11 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲R̲e̲p̲o̲r̲t̲s̲
See section 4.1.2.1 here of this proposal.
6.2.6 F̲i̲n̲a̲l̲ ̲H̲a̲n̲d̲b̲o̲o̲k̲s̲
Final version of the manuals and handbooks will be
based on the comments and descrepancies described in
section 6.1.3 Amendment Documentation.
6.3 D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲U̲P̲D̲A̲T̲E̲
Christian Rovsing A/S will update the documentation
for a period of 5 years from the date of final acceptance.
7̲ ̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲ ̲
7.1 G̲E̲N̲E̲R̲A̲L̲
This proposal based on the RFP discribes courses necessary
for the HCAA staff to operate, maintain and develop
the ASC system. The courses will range from a general
system course up to advanced and detailed level.
The following courses are proposed:
1. General Introduction Course.
2. Technical Course Hardware - Type 1 and 2. (Component
level).
3. Technical Course Software - Type 1 and 2. (S/W
Development and S/W Maintenance).
4. Hardware Maintenance Course - Type 3. (Module Level).
5. Operator's/User's Course - Type 3.
6. Soldering Course (Optional)
The courses will consist of theoretical, practical
and On-the-Job Training.
The following three types of courses are defined:
Type 1: Special training of staff who will be responsible
for the further development of the ASC both
on the hardware and software standpoints (system
engineers or system anslysts).
This special training is of particular importance
for:
- specially developed equipment
- software development (system software,
application software, assembler, compiler,
etc....).
Type 2: Training courses for hardware and software
maintenance specialists with:
2.1. theoretical classroom instruction
2.2. practical training
Type 3: Training courses forseen in the Greece ranging
from standard to detailed training (for hardware
maintenance personnel and operators) with:
3.1. theoretical classroom instruction
3.2. practical training
3.3. on-the-job training
The General Introduction Course will be given as a
lead to the other types of courses.
One course-week consists of 30 lessons of 45 minutes.
7.2 T̲R̲A̲I̲N̲I̲N̲G̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲ ̲
For training courses preliminary documentation will
be used where the final documentation is not available.
Each participant will at least obtain a complete set
of documentation when the course starts and keep these
documents at the end of the course. An extra copy of
the documentation including material to be used by
the instructor during training will be submitted to
the HCAA after each course. All documents will be written
in the English Language.
7.3 T̲r̲a̲i̲n̲i̲n̲g̲ ̲F̲a̲c̲i̲l̲i̲t̲i̲e̲s̲ ̲f̲o̲r̲ ̲O̲n̲-̲S̲i̲t̲e̲ ̲C̲o̲u̲s̲e̲s̲ ̲(̲O̲p̲t̲i̲o̲n̲a̲l̲)̲
Training facilities are offered as an option as required
in the RFP:
- White/Black board - 1.
- Screen - 1.
- Overhead Projector - 1.
- Tables and Chairs - 8/13.
- Shelfs - 1.
- Acessories.
These facilities shall as a minimum be available before
start and during the courses.
7.4 L̲A̲N̲G̲U̲A̲G̲E̲
The courses will be conducted in English.
7.5 C̲O̲U̲R̲S̲E̲ ̲S̲U̲P̲E̲R̲V̲I̲S̲I̲O̲N̲/̲C̲O̲O̲R̲D̲I̲N̲A̲T̲I̲O̲N̲
The progress and effectiveness of each of the proposed
training courses can be supervised/coordinated in cooperation
with the competent personnel of CHRISTIAN ROVSING A/S
and HCAA.
7.6 C̲O̲U̲R̲S̲E̲ ̲E̲X̲A̲M̲I̲N̲A̲T̲I̲O̲N̲
The students will not be "screened" before course entrance,
but examinations shall be held during the training
courses.
7.7 P̲R̲E̲P̲A̲R̲A̲T̲O̲R̲Y̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲
If preparatory courses are necessary for students the
training will be given by the HCAA instructors.
CHRISTIAN ROVSING A/S will coorporate with HCAA in
order to define the level of this training.
7.8 F̲I̲N̲A̲L̲ ̲T̲R̲A̲I̲N̲I̲N̲G̲ ̲P̲R̲O̲G̲R̲A̲M̲S̲
The proposed training program will be finalized upon
agreement between the two parties.
7.9 D̲E̲T̲A̲I̲L̲E̲D̲ ̲C̲O̲U̲R̲S̲E̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲
7.9.1 G̲e̲n̲e̲r̲a̲l̲ ̲I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲ ̲C̲o̲u̲r̲s̲e̲
7.9.1.1 O̲b̲j̲e̲c̲t̲i̲v̲e̲
The objective of the course is to give the participants
a general knowledge of the equipment, its extent, design,
functional principles, use, capacity, utility, operational
reliability, its need for maintenance, and the interaction
between software and hardware.
7.9.1.2 C̲o̲n̲t̲e̲n̲t̲s̲
The contents will include a presentation of the system,
its utility field and performance data, a system oriented
description of the equipment and its functioning by
use of block diagrams and figures showing the interaction
between software and hardware.
A summary of steps to be taken by the user for various
operational modes will also be given.
7.9.1.3 T̲a̲r̲g̲e̲t̲ ̲G̲r̲o̲u̲p̲
The course is intended for participants with general
technical education, holding positions where general
knowledge of the equipment is required.
The course is also inteded to serve as a lead for the
students participation the other courses.
7.9.1.4 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 12 per class.
7.9.1.5 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
To be negotiate.
7.9.1.6 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲C̲l̲a̲s̲s̲e̲s̲
To be negotiate.
7.9.1.7 L̲o̲c̲a̲t̲i̲o̲n̲ ̲
To be negotiated.
7.9.1.8 C̲o̲u̲r̲s̲e̲ ̲P̲r̲o̲f̲i̲l̲e̲
Mainly theoretically
7.9.1.9 F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲
With reference to the RFP section 7.9.3 the said training
programs will be finalized either upon the signature
of the contract or at a later stage to be agreed upon
by both parties concerned.
7.9.2 T̲e̲c̲h̲n̲i̲c̲a̲l̲ ̲C̲o̲u̲r̲s̲e̲,̲ ̲H̲a̲r̲d̲w̲a̲r̲e̲ ̲-̲ ̲T̲y̲p̲e̲ ̲1̲ ̲a̲n̲d̲ ̲2̲ ̲
O̲b̲j̲e̲c̲t̲i̲v̲e̲
The objective of the course is to give the participants
a good knowledge of the composition of the equipment,
the various constituent units and the design and function
of the more important units. After completion of the
course the participants will be well suited to accept
responsibility for operation and maintenance. They
will also be able to use the maintenance equipment
necessary.
This course may contain - for maintenance - necessary
knowledge of existing software.
7.9.2.1 C̲o̲n̲t̲e̲n̲t̲s̲ ̲
The equipment will be described in such a way, that
a fault can be localized down to the component level
by using the Zentell automatic test equipment.
The participants of the course will be trained in the
use of the Zentall tester for component level troubleshooting.
In addition, a complete account of the test philosophy
shall be given.
For modules in which the Zentell tester can not be
used the training will include a functional survey
based on figures and logic diagrams, as well as a detailed
description of the design and function with respect
to separate and cooperating units. Reference will be
made to figures, block diagrams, and other diagrams.
It will be possible to follow important circuits and
paths through the various units of the system. In-
and output functions and test (measurement) points
required for the maintenance of the equipment will
be thoroughly explained.
Applicable signal waveforms and transfer characteristics
of the interfaces and the equipment will be demonstrated.
The cabling between the units of the system will be
meticulously described.
The course shall comprise of theoretical as well as
practical training and on-the-job training.
7.9.2.2 T̲a̲r̲g̲e̲t̲ ̲G̲r̲o̲u̲p̲
The course is intended for technical personnel who
will be responsible for the operation, maintenance
and development of the equipment and future instructors
(hardware specialists).
7.9.2.3 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 6 per class.
7.9.2.4 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲ ̲
To be negotiated.
7.9.2.5 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲C̲l̲a̲s̲s̲e̲s̲
To be negotiated.
7.9.2.6 L̲o̲c̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.2.7 F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲
With reference to the RFP section 7.9.3 the said training
programs will be finalized either upon the signature
of the contract or at a later stage to be agreed upon
by both parties concerned.
7.9.3 Technical course, software - type 1 and 2 (S/W D̲e̲v̲e̲l̲o̲p̲m̲e̲n̲t̲
̲a̲n̲d̲ ̲S̲/̲W̲ ̲m̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
7.9.3.1 O̲b̲j̲e̲c̲t̲i̲v̲e̲
The objective of the course is to give the participants
a general knowledge of the extent and use of the equipment,
and also a general knowledge of the hardware to be
used. The student will be given a thorough knowledge
of existing programs down to the programming flow level,
and the programming languages that are used. After
completion of the training the participants will be
able to use and maintain the programs in question,
and to develop new programs.
7.9.3.2 C̲o̲n̲t̲e̲n̲t̲s̲
The course may contain the following sections:
Part 1: - Pascal, Swell and the operating system
- application software
- system software and utilities
- test programs
Knowledge of the programs down to the programming flow
level.
Part 2: - general techniques for software development
The course may contain theoretical as well as practical
training.
7.9.3.3 T̲a̲r̲g̲e̲t̲ ̲G̲r̲o̲u̲p̲
The course is intended for S/W specialists who will
be responsible for the operation, maintenance and development
of the equipment, the graduated will be employed as
instructors in these activities, programmers and amendments
in delivered programs.
7.9.3.4 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 10 students per class.
7.9.3.4 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.3.6 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲C̲l̲a̲s̲s̲e̲s̲
To be negotiated.
7.9.3.7 L̲o̲c̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.3.8 F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲
With reference to the RFP section 7.9.3 the said training
programs will be finalized either upon the signature
of the contract or at a later stage to be agreed upon
by both parties concerned.…86…1 …02… …02… …02… …02…
7.9.4 H̲/̲W̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲C̲o̲u̲r̲s̲e̲ ̲-̲ ̲T̲y̲p̲e̲ ̲3̲ ̲(̲M̲o̲d̲u̲l̲e̲ ̲L̲e̲v̲e̲l̲)̲ ̲
7.9.4.1 O̲b̲j̲e̲c̲t̲i̲v̲e̲
The goal of the couse will be to provide the hardware
maintenance technicians with the knowledge required
for procedures and measurements to perform the integration
phase of the sub-systems following installation, to
verify the proper function of the system to perform
the dayly maintenance of the system and to keep it
in operational state.
7.9.4.2 C̲o̲n̲t̲e̲n̲t̲s̲
The course will be developed to provide hardware maintenance
personnel with the knowledge required to:
a) Perform all procedures necessary during the integration
of the separate sub-system following installation.
The extent of instruments and special test equipment
and tools required for the integration shall also
be covered by this course.
b) Maintain the system in normal operational state.
The maintenance personnel shall be able to run
test programms, to identify faulty modules and
to replace them.
c) Perform system-level performance test following
installation, integration of new hardware and maintenance
operation. The extent of instruments, special test
equipment, built-in test (BIT) and tools required
for these test shall also be covered by this course.
d) Perform all alignments and adjustments normally
required to place a system in operation (commissioning)
following the installation, integration of new
hardware, and maintenance operation.
Training will consist of both lectures and practical
work experience session. Great emphasis will be given
to practical work experience sessions used to demonstrate
and perform the specified adjustments and tests and
to identify and replace faulty modules.
7.9.4.3 T̲a̲r̲g̲e̲t̲ ̲G̲r̲o̲u̲p̲
Technical personnel to be responsible for the maintenance
and setting-up of the equipment.
7.9.4.4 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 6 students.
7.9.4.5 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.4.6 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲C̲l̲a̲s̲s̲e̲s̲
To be negotiated.
7.9.4.7 L̲o̲c̲a̲t̲i̲o̲n̲ ̲
To be negotiated.
7.9.4.8 F̲i̲n̲a̲l̲i̲z̲e̲d̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲
With reference to the RFP section 7.9.3 the said training
programs will be finalized either upon the signature
of the contract or at a later stage to be agreed upon
by both parties concerned.…86…1 …02… …02… …02… …02…
7.9.5 O̲p̲e̲r̲a̲t̲o̲r̲'̲s̲/̲U̲s̲e̲r̲'̲s̲ ̲C̲o̲u̲r̲s̲e̲
7.9.5.1 O̲b̲j̲e̲c̲t̲i̲v̲e̲s̲
The objective of the course will be to provide operators
with the knowledge required to operate the system.
7.9.5.2 C̲o̲n̲t̲e̲n̲t̲s̲ ̲
The course will include a presentation of the system,
the description and the use of the various commands
in order to provide the operators with the knowledge
required to:
a) Use the system.
b) Perform configuration modification (open/close
input/output channels etc...).
c) Use editing facilities to correct corrupted messages
and to send messages over the associated networks.
Training will mainly consist of practical work sessions
where the functions and the use of operator peripherals
will be demonstrated and tested.
7.9.5.3 T̲a̲r̲g̲e̲t̲ ̲G̲r̲o̲u̲p̲
Personnel to be responsible for the operation of the
system.
7.9.5.4 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲P̲a̲r̲t̲i̲c̲i̲p̲a̲n̲t̲s̲
Up to 10.
7.9.5.5 C̲o̲u̲r̲s̲e̲ ̲D̲u̲r̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.5.6 N̲u̲m̲b̲e̲r̲ ̲o̲f̲ ̲C̲l̲a̲s̲s̲e̲s̲
To be negotiated.
7.9.5.7 L̲o̲c̲a̲t̲i̲o̲n̲
To be negotiated.
7.9.6 S̲o̲l̲d̲e̲r̲i̲n̲g̲ ̲C̲o̲u̲r̲s̲e̲ (Optional)
Soldering course will be given to the maintenance technicians
participating the hardware maintenance courses in order
to make proper soldering/desoldering of the multi-layer
PC-boards used in the system.
7.10 T̲R̲A̲I̲N̲I̲N̲G̲ ̲I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲ ̲P̲H̲A̲S̲E̲ ̲2̲ ̲A̲N̲D̲ ̲3̲
3 days per course type will be needed for training
in phase 2 and 3. The training program and cost for
implementation phase 2 and 3 will be defined upon agreement
between both parties conserned.
The total duration of conduct of this training is 30
days.
7.11 W̲i̲t̲h̲ ̲r̲e̲f̲e̲r̲e̲n̲c̲e̲ ̲t̲o̲ ̲t̲h̲e̲ ̲R̲F̲P̲ ̲s̲e̲c̲t̲i̲o̲n̲ ̲7̲.̲9̲.̲3̲
With reference to the RFP section 7.9.3 the said training
programs will be finalized either upon the signature
of the contract or at a later stage to be agreed upon
by both parties concerned.…86…1 …02… …02… …02… …02…
7.12 C̲O̲U̲R̲S̲E̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲S̲
Project Warranty
S̲t̲a̲r̲t̲ ̲ ̲ ̲ ̲ ̲I̲n̲s̲t̲a̲l̲l̲ ̲ ̲I̲X̲T̲
̲ ̲S̲t̲a̲r̲t̲ ̲ ̲ ̲
1. General Intro Course
2. Techn. Course H/W
3. Techn. Course S/W2
S/W1
4. H/W Maintenance
5. Operator's/User's Course
I & T: Integration & Test
W: Week
D: Day
Figure 7.11-1
8̲ ̲ ̲A̲C̲C̲E̲S̲S̲O̲R̲I̲E̲S̲ ̲-̲ ̲L̲A̲B̲O̲R̲A̲T̲O̲R̲Y̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲
This chapter describes the laboratory equipment necessary
to perform board and unit repair. In accordance with
chapter 4.2.1.2 and the RFP all repair of boards and
units will be CR responsibility. The need for a workshop
will not be necessary and is not prices in this proposal.
The only tools and test equipment needed to perform
on site maintenance will be rather few and consist
of standard electronic repair tools which CR expect
HCAA to have.
The following section give the requirements for a local
repair center.
8.1 W̲O̲R̲K̲S̲H̲O̲P̲ ̲R̲E̲P̲A̲I̲R̲ ̲F̲A̲C̲I̲L̲I̲T̲I̲E̲S̲
In order to meet the requirement for the repair facility
following main equipment are offered:
o A "stripped down" version of the ASC system
(Mock-Up)
o A subset of ASC system software
o Online/Offline M&D programs
o Workbench for CR80 modules
o Workbenches for all peripherals delivered
o ATE for board repair
o Tools & Test Equipment.
8.2 F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
It shall be possible to perform following activities
on the laboratory "stripped down" system:
o System trouble shooting on hardware and software
modules
o Manual troubleshooting
o Verification of defective modules and units
o Test of repaired modules and units
o Implementation and test of software and hardware
changes
o In-depth training of the maintenance staff enabling
them to perform the maintenance described in chapter
4 of this proposal.
8.3 T̲R̲A̲I̲N̲I̲N̲G̲ ̲A̲N̲D̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
The training of the Hardware Specialist Group working
in the Workshop is described in chapter 7 of this proposal.
The documentation needed to perform fault finding down
to component level is described in chapter 6 of this
proposal.
8.4 H̲A̲R̲D̲W̲A̲R̲E̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲
8.4.1 M̲o̲c̲k̲ ̲U̲p̲ ̲S̲y̲s̲t̲e̲m̲
The Mock-Up System will consist of modules similar
to the ASC system build up as a none dualized system
without the Watchdog.
8.4.2 W̲o̲r̲k̲b̲e̲n̲c̲h̲ ̲f̲o̲r̲ ̲C̲R̲8̲0̲ ̲M̲o̲d̲u̲l̲e̲s̲
This workbench consists of a stand alone combicrate
with CR80 modules.
The purpose of this workbench is to be able to perform
manual troubleshooting on CR80 modules.
8.4.3 W̲o̲r̲k̲b̲e̲n̲c̲h̲e̲s̲ ̲f̲o̲r̲ ̲P̲e̲r̲i̲p̲h̲e̲r̲a̲l̲s̲
There will be 6 different workbenches covering all
peripherals and CR80 power supply.
All benches will be original peripheral equipment rebuilt
to ease manual troubleshooting.
8.4.4 A̲u̲t̲o̲m̲a̲t̲i̲c̲ ̲T̲e̲s̲t̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
Automatic Test Equipment (ATE) will be used to trouble
shoot most of the CR80 modules.
The ATE proposed is a "Zentel 802" In Circuit Tester.
Included are Test Fixtures and test programs.
8.4.5 T̲o̲o̲l̲s̲ ̲&̲ ̲T̲e̲s̲t̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
A list of recommended Tools & Test Equipment will be
submitted.
8.4.6 M̲o̲c̲k̲-̲U̲p̲ ̲F̲a̲c̲i̲l̲i̲t̲i̲e̲s̲
The following describes the Installation and Operating
environment required by the system.
8.4.6.1 A̲S̲C̲ ̲M̲o̲c̲k̲-̲U̲p̲ ̲R̲o̲o̲m̲
The equipment layout of the ASC Mock-Up room is shown
in Figure 8.4.6-1.
The equipment consists of:
Pos. 1 Computer System mounted in 19" rack.
Pos. 2 Delta Data VDU.
The Rack is positioned such that sufficient clearance
is maintained for access to the front and rear of the
equipment. The final layout will take into account
human factors, segregation of functional activities,
access for maintenance and other considerations or
preferences of the customer.
One of the tasks to be performed at the site survey
is to work out optimal layouts in conjunction with
customer.
Typical Access Dimension for rack and terminal equipment
is shown in Figure 5.5.2.1-3 and 4.
The rack is well within the floor load limit of 598
kilogram per square meter as can be seen from the following
calculation:
floor load of rack:
̲ ̲ ̲w̲e̲i̲g̲h̲t̲ ̲ ̲ ̲4̲3̲0̲ ̲ ̲ ̲ ̲k̲g̲ ̲
floor space …0e…=…0f… 0,6 x 1,2 m…0e…2 = 598 kg/m…0e…2…0f…
Since the rack is provided with Access Space at front
and rear, the distributed floor load is considerably
smaller.
8.4.6.2 A̲i̲r̲ ̲C̲o̲o̲l̲i̲n̲g̲
As all rack mounted equipment have internal blowers
using ambient room air for forced ventilation, the
equipment does not require any direct cooling.
Ambient room air is drawn into the rack through the
filters on the front door and deflected upwards through
the top grills. Refer to Figure 5.5.2.2-2.
The heat dissipation figures for the equipment in the
ASC Mock-Up room is shown in the table below:
Electrical Requirements air cooling
v̲o̲l̲t̲s̲ w̲i̲r̲e̲s̲ p̲h̲a̲s̲e̲ t̲o̲t̲a̲l̲ ̲k̲w̲ t̲o̲t̲a̲l̲ ̲K̲C̲A̲L̲/̲H̲
Computer Rack 220 3 1 1,30 1118
Maintenance VDU 220 3 1 0,25
220
8.4.6.3 E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲C̲o̲n̲d̲i̲t̲i̲o̲n̲s̲
The CR80 equipment placed in the ASC room and ASC Mock-Up
room is the same type of equipment. Typical environmental
conditions of the CR80 equipment are described in section
5.5.2.2.4.
Figure 8.4.6-1
ASC Mock-Up Installation
Typical Layout
9̲ ̲ ̲I̲N̲I̲T̲I̲A̲L̲ ̲S̲P̲A̲R̲E̲S̲
9.1 G̲E̲N̲E̲R̲A̲L̲
The initial spares quoted in this proposal are CR's
best estimate at the time of bid.
Depending of the configuration of the ASC and the agreed
maintenance philosophy, CR will prepare "Recommended
Spare Part Lists" (RSPL's) on modules and piece parts.
The RSPL's shall be discussed at a Provisioning Conference
between HCAA and CR in order to establish the Approved
Spare Part Lists (ASPL).
The following sections describe the requirements for
spares in case of a local set up of board repair facilities.
This is not priced in this proposal.
9.2 S̲P̲A̲R̲E̲S̲ ̲C̲A̲T̲E̲G̲O̲R̲I̲E̲S̲
9.2.1 C̲o̲n̲s̲u̲m̲a̲b̲l̲e̲s̲
Consumables will be listed in the RSPL but will not
be included in this bid, and are not covered by warranty.
9.2.2 C̲o̲m̲p̲o̲n̲e̲n̲t̲s̲ ̲(̲P̲i̲e̲c̲e̲ ̲P̲a̲r̲t̲s̲)̲
A recommended list of piece parts will be prepared
accordingly to the agreed hardware configuration. The
standard lay-out for this list is shown in figure 9.2.2-1.
9.2.3 M̲o̲d̲u̲l̲e̲s̲
A recommended list of initial spare part modules is
shown in figure 9.2.3-1. This list represent
Figure 9.2.2-1
Typical lay-out for piece part lists
Figure 9.2.3-1
Recommended Spare Part List
the amount of spares calculated on the offered hardware
configuration. The list will be updated in relation
to the agreed hardware configuration.
9.3 S̲P̲A̲R̲E̲S̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
In accordance with the agreed maintenance philosophy,
spare part lists will be prepared for the workshop
and for the site.
9.4 O̲P̲T̲I̲M̲U̲M̲ ̲S̲P̲A̲R̲E̲S̲ ̲S̲U̲P̲P̲O̲R̲T̲ ̲S̲T̲R̲A̲T̲E̲G̲Y̲
9.4.1 The calculation of numbers of piece parts will be done
by use of Poissons distribution probability with a
minimum of one of each.
9.4.2 In order to determine the number of spare modules it
is assumed that the failure rate of each module (circuit
board) has an exponential distribution. This approximation
holds true for electronic equipment throughout its
useful life, i.e. wear-out phenomena can be ignored.
Thus the probability mass function for each module
is:
p(t) = (1/MTBF) x exp(-t/MTBF)
where MTBF is the Mean Time Between Failure for that
module.
It can be shown that the probability of observing exactly
i failures over a period of t operating hours is given
by the Poisson distribution:
i
p (i) = (̲t̲/̲M̲T̲B̲F̲)̲ ̲ ̲ ̲x̲ ̲e̲x̲p̲(̲-̲ ̲t̲/̲M̲T̲B̲F̲)̲
i!
The Period t corresponds to the accumulated operating
period for the involved modules.
Therefore, the probability of observing r or less failures
during a period t is determined by the cumulative Poisson
distribution:
r i
(̲t̲/̲M̲T̲B̲F̲)̲ ̲ ̲x̲ ̲e̲x̲p̲(̲-̲t̲/̲M̲T̲B̲F̲)̲
P (failures r) =
i!
i = 0
To determine the number of spares r required to obtain
an 80% confidence level for a period of 90 days is
equivalent to determining the minimal r for which the
probability of having more than r failures during the
period covered is less than 20%.
The following equation has to be solved for r:
i =
i
m̲ ̲ ̲ ̲x̲ ̲e̲x̲p̲ ̲(̲-̲m̲)̲
max
i ! .20
r i = r+1
r = number of spares required to obtain
the
required confidence level
m = N x ̲T̲ ̲
MTBF
N = total installed parts population. The
total installed population for a depot is determined
by the number installed items at the sites
involved.
T = length of period for which stock is
required
i.e 90 days for sites and 270 days
for the
central depot(s).
MTBF = Mean Time Between Failure (MTBF = 10…0e…6…0f…/
)
= failure rate per million hours.
Alternatively determine smallest integer r for which
r i
m
.80 exp (-m) x ̲ ̲ ̲
i!
i = 0
9.4.3 The spare parts for the peripheral equipment is the
spare part list recommended by the manufactors.
9.5 S̲P̲A̲R̲E̲S̲ ̲C̲O̲N̲S̲U̲M̲P̲T̲I̲O̲N̲ ̲G̲U̲A̲R̲A̲N̲T̲E̲E̲
If during the warrenty periode it can be proved that
the availability is less than required due to lack
of spares, CR will review the spare part calculation
and upgrade the spare part stock accordingly.
9.6 L̲O̲G̲I̲S̲T̲I̲C̲ ̲D̲E̲L̲A̲Y̲ ̲T̲I̲M̲E̲ ̲(̲L̲D̲T̲)̲
Due to the requested maintenance philosophy, where
HCAA perform the day to day maintenance, the LDT is
out of CR's control.
9.6.1 P̲r̲o̲c̲u̲r̲e̲m̲e̲n̲t̲ ̲o̲f̲ ̲S̲p̲a̲r̲e̲s̲
The LDT for procurement of spares will be typical nine
months. Spares will be availabel for max. 15 years
from date of the final acceptance.
9.7 D̲E̲L̲I̲V̲E̲R̲Y̲
Delivery of the spare parts according to the ASPL's
will take place simultaneously with the system installation.
9.8 F̲O̲R̲M̲A̲T̲ ̲F̲O̲R̲ ̲S̲P̲A̲R̲E̲ ̲M̲O̲D̲U̲L̲E̲S̲
9.8.1 L̲e̲v̲e̲l̲ ̲o̲f̲ ̲R̲e̲p̲a̲i̲r̲ ̲A̲n̲a̲l̲y̲s̲i̲s̲
The following level of repair analysis outlines CR's
recommended repair philasophy for CR modules.
9.8.2 E̲x̲p̲l̲a̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲t̲h̲e̲ ̲T̲a̲b̲l̲e̲
L̲I̲N̲E̲ ̲N̲U̲M̲B̲E̲R̲
Each replaceable item has an individual line No. The
CR80 modules are identified by the same line No as
indicated in the RSPL.
M̲A̲J̲O̲R̲ ̲I̲T̲E̲M̲
The headline above the table identifies the units (e.g.:
CENTRAL EQUIPMENT).
S̲U̲B̲-̲S̲Y̲S̲T̲E̲M̲
The headline above the table identifies sub-systems
within the unit (e.g.: Watchdog).
R̲E̲P̲L̲A̲C̲E̲A̲B̲L̲E̲ ̲S̲U̲B̲-̲A̲S̲S̲Y̲
This column identifies the replaceable sub-assemblies.
L̲E̲V̲E̲L̲ ̲O̲F̲ ̲R̲E̲P̲A̲I̲R̲
The following levels are identified:
S = Site
D = Depot
C = CR
V = Vendor
T̲Y̲P̲E̲ ̲O̲F̲ ̲R̲E̲P̲A̲I̲R̲
The following types are identified:
C = Component replacement
I = Depot or factory replaceable sub-module
W = Wiring
D = Discard
I̲T̲E̲M̲ ̲C̲O̲M̲P̲L̲E̲X̲I̲T̲Y̲
The following complexity is identified:
L = Large 50 ICs, or several LSI circuits
M = Medium 25-50 ICs
S = Small 0-25 ICs
Analoque circuit boards are categorized as a combination
of physical dimension and component density.
I̲T̲E̲M̲ ̲T̲Y̲P̲E̲S̲
The following item types are identified:
D = Digital - more than 75% are digital components
A = Analoque - more than 75% are analoque
components
M = Mechanical - more than 75% are mechanical
parts
E = Electromechanical - more than 75% are electromechanical
parts
H = Hybrid - less than 75% of each of the
above groups
R̲E̲P̲A̲I̲R̲ ̲M̲E̲T̲H̲O̲D̲S̲
The following repair methods are identified:
I = In-Circuit Tester - Zehntel Model 802
F = Functional Tester - GenRad
S = Standard - Traditional troubleshooting and repair
The In-Circuit Tester and Functional Tester are recommended
in lieu of traditional troubleshooting methods.
C̲E̲N̲T̲R̲A̲L̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ (CR80)
MTBF N
x Qty/ o
Line Repair Item Rep
1000 Mjr t
N̲o̲ ̲ ̲ ̲D̲e̲s̲c̲r̲i̲p̲t̲i̲o̲n̲ ̲&̲ ̲M̲f̲g̲.̲ ̲P̲a̲r̲t̲s̲ ̲N̲o̲ ̲ ̲ ̲ ̲L̲e̲v̲ ̲T̲y̲p̲ ̲C̲p̲x̲ ̲T̲y̲p̲ ̲M̲t̲d̲
̲ ̲h̲r̲s̲ ̲ ̲ ̲I̲t̲e̲m̲ ̲ ̲e̲
W̲a̲t̲c̲h̲d̲o̲g̲
11 CR8115M/005P-/00 W'dog
Crate D C M M S 26 16
12 CR8066M/010AB/00 LTU,
WD D C L D I 27 16
13 CR8076M/010--/00 WCA D C M D I 48 16
14 CR8089M/010--/00 CCA D C M D I 30 48
15 CR8091M/-----/00 CCBA D C S D F
700 16
16 CR8142M/-----/-- TSP D C S D S
600 48
17 CR8042M/010--/-- CUCP D C S D F
183 16
P̲r̲o̲c̲e̲s̲s̲o̲r̲
21 CR8003M/040PC/00 CPU/CACHE D C L D I 26 96
24 CR8016M/128PC/00 128K
RAM D C L D I 17 64
25 CR8020M/000PC/00 MAP/SCM/I0 D C L D I 19 32
26 CR8071M/010--/00 MIA D C L D I 86 32
27 CR8021M/010-C/00 STI D C L D I 33 32
28 CR8073M/010--/00 TIA D C M D I
118 64
C̲h̲a̲n̲ ̲U̲n̲i̲t̲
31 CR8081M/010A-/00 CIA-A D C L D I 71 16
32 CR8081M/010-B/00 CIA-B D C L D I 71 16
33 CR8044M/040AB/00 Disk
Ctl/32K D C L D I 32 48
34 CR8084M/010--/00 DCA D C M D F 47 48
35 CR8047M/040AB/00 St
Fd Ctlr D C L D I 60 16
36 CR8087M/010--/00 SFA D D S M S
10000 16 1
37 CR8066M/010AB/XX LTU,
Sync/16K D C L D I 28 55
38 CR8082M/010--/00 LIA-N D D S D S
10000 55 1
The table shown will be updated in accordance with
the hardware delivered.
9.8.3 R̲S̲P̲L̲ ̲F̲o̲r̲m̲a̲t̲
The lay-out of a typical RSPL is shown in figure 9.8.3.
Figure 9.8.3
Typical RSPL lay-out
THIS PAGE INTENTIONALLY LEFT BLANK
1̲0̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲ ̲T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲ ̲A̲N̲D̲ ̲C̲O̲N̲D̲I̲T̲I̲O̲N̲S̲
10.1 I̲N̲T̲R̲O̲D̲U̲C̲T̲I̲O̲N̲
This chapter discusses the General Mechanical and Electrical
interfaces and buses of the Processor Unit (PU) and
Channel Unit (CU) crate subsystems in CR80 Memory Mapped
Computer Systems.
Each unit (PU or CU) is a mechanical and electrical
entity, normally housed in a standard CR80, 25-slot
Crate (Card Cage). Each PU or CU Crate has its own
power supply (supplies), cooling system, and is galvanically
isolated from all extenal connections:
- S-NET
- X-NET (TDX-Bus)
- DATACHANNEL
- CONFIGURATION BUS
- MAINS LINES
The CR80 or PU, and CU are an electrically and physically
self-contained units, accomodating all address sourcing
devices of a PE. The PU or CU contains various modules.
It is capable of connecting into large multicomputer
configurations, with up to 15 other PE's via fast suprabuses
and to terminal networks via TDX-bus.
Physically, the CR80 modules constituting the PU are
housed in a 19" crate (card-cage) of height 443 mm
and depth 630 mm.
The PU or CU crate supports insertion of the following
CR80 standard modules in its 25 front and 19 rear positions.
As can be expected combination crates also exists,
which pack 2 small or medium size PU's into one 19"
Crate, or combine a PU and CU in one crate. In adddition
a smaller (15 front and 7 rear position) MINICRATE
exists. Since these are interface- and bus-compatible
with the large PU-crate, only the latter is treated
in the following.
The CR80 processing modules are housed in a standard
19" Module Magazine, the Processing Unit Crate (PU-Crate)
or the Channel Unit Crate (CU-Crate). Different types
of crates are available from the CR80 product line
as defined in the data sheets. The data sheets give
the specifications concerning module positions within
the PU-crate and the number of module slots available,
which the general interface specification for the PU-
or CU-crate are defined in this section.
The PU- or CU-crate consists basically of a front magazine
for the front modules (processing modules) and a rear
magazine for rear modules (adapter modules) placed
back to back.
The interface between the front modules and the rear
adapter modules is performed by means of 64p flat cable,
while the interface between the front module is established
by means of multilayer printed circuits boards, two
identical for the two data transfer buses P-bus and
C-bus and a third in the module interface connector
position.
The adapter module interfaces the PU external connections
on the Adapter module panel and by means of 64p flat
cable to the front module. Power and configuration
control signals to the Adapter Modules are distributed
via printed circuit board J3 backplane in upper connector
position of the rear crate.
10.2 M̲E̲C̲H̲A̲N̲I̲C̲A̲L̲ ̲C̲O̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲
The PU- and CU-crates constituting a CR80 Computer
is housed in a single or multiple standard 19" rack,
dependent of the actual system configuration. The specifications
given here are related to the integration of systems
while the datasheets give detailed specifications and
dimensions for the available standard racks.
The general construction of the racks is as shown in
figure 10.2-1. The width is standard 19", while the
height and depth will depend on the related type No.
Installation of the system units in rack is performed
as illustrated in the following figures:
10.2-2 CR80 Rack Front View
10.2-3 CR80 Rack Rear View
10.2-4 Installation of Units in CR80 RACK
The following comments to the figures should be noted:
Notes to figure 10.2-1, General Rack Construction:
1. The rack dimensions correspond to 19" standard.
2. The height, H, varies with the different types
and is selected in accordance with the actual system
requirement, i.e. number of system units to be
housed in the rack.
3. The depth, D, varies with the different standard
types and is selected in accordance with the actual
system requirement.
Figure 10.2-1
CR80 Cabinet and Installation of Supporting Brackets
Figure 10.2-2
Typical CR80 Front View
Figure 10.2-3
Typical CR80 Rear View
Figure 10.2-4
Crate Installation
4. The supporting brackets are inserted just below
the System Unit. One right and one left of each
unit.
Notes to figure 10.2-2, CR80 Rack Front View:
1. The system layout is an example and alternative
layouts are possible; the only restriction is that
a Fan unit be located just below the PU and the
CU.
2. The Mains filter is preferably located in the bottom
of the rack as shown, but it could alternatively
be located at the top.
3. The Mains filter has the front panel towards the
front of the rack, but it could as well be turned
around so the front panel is towords the rear of
the rack. If this solution is chosen, a blank panel
is mounted on the front instead of the filter.
Notes to figure 10.2-3, CR80 Rack Rear View:
1. Cables are not included in the figure as the number
of cables depends on the system configuration,
but is should be mentioned that cables should be
supported in accordance with good engineering practice.
2. The shown system configuration example includes
two power distribution panels located at the bottom
of the two fan units. No special requirements are
set on the location of the panels but they should
be located to allow access to the system, for example
opening of the adapter crates in the PU and CU's.
3. As mentioned in the notes to figure 10.2-2 the
mains filter can be turned around.
The FAN UNIT consists of a metal frame which is mounted
permanently in the 19" rack just below the crate. The
frame contains a upper side clearance allowing the
cooling air to dissipate vertically into front and
rear magazine of the crate. The frame contains a drawer
carrying electrical circuits, fan motors and filter
cushion.
The FAN UNIT applies two electrically independent systems
(A and B), each consisting of axial fan motors with
ball-bearings. Each system is capable of maintaining
sufficient cooling air to the associated crate. The
two systems are supplied from different mains phases,
in order that a mains failure will not stop removal
of dissipated heat from the crate.
For each system a POWER-ON lamp is located on front.
Power plug, ON-OFF switch and fuse are located on the
rear side of the unit.
In general the flexible and modular design of the CR80
computer ensures easy installation and maintenance.
High accessibility is achieved through the usage of
front and rear crates, where rear crates can be tilted
in order to provide easier access.
10.3 E̲L̲E̲C̲T̲R̲I̲C̲A̲L̲ ̲D̲E̲S̲I̲G̲N̲
The CR80 computer has been designed with use of the
best standards for commercial and military computer
systems. The aspect of investment protection and cost-effectiveness
has allways been a guideline for the design of CHRISTIAN
ROVSING Equipment.
The computer system offered for the ASC is standard
equipment, which has been proven and field tested in
accordance with current general electrical design requirements.
10.4 R̲E̲L̲I̲A̲B̲I̲L̲I̲T̲Y̲,̲ ̲A̲V̲A̲I̲L̲A̲B̲I̲L̲I̲T̲Y̲,̲ ̲M̲A̲I̲N̲T̲A̲I̲N̲A̲B̲I̲L̲I̲T̲Y̲ ̲(̲R̲A̲M̲)̲
The availability of the proposed equipment is very
high due to not only a high reliability of individual
system elements, but mainly due to the chosen CR80
computer configuration.
The actual availability will be very close to 100%,
due to the exceptional design of the CR80 configuration.
G̲e̲n̲e̲r̲a̲l̲ ̲C̲o̲n̲s̲i̲d̲e̲r̲a̲t̲i̲o̲n̲s̲
The high system availability has been achieved by the
use of highly reliable modules.
The reliability criteria imposed on the computer systems
have been evaluated and the proposed hardware/software
operational system analysed to determine the degree
of availability and data integrity provided. In this
chapter reliability is stated in numerical terms and
the detailed predictions derived from mathematical
models presented.
The availability predictions are made in accordance
with system reliability models and block diagrams corresponding
to the proposed configuration. This procedure involves
the use of module level and processor unit level failure
rates, or MTBF, (mean time between failures) and MTTR
(meantime to repair); these factors are used in conjunction
with a realistic modeling of the configuration to arrive
at system level MTBF and availability.
Tabulated results of the analysis are presented including
the reliability factors: system MTBF and repair time
MTTR.
The basic elements of the proposed system architecture
are constituted by standard CR80 units. Reliability
and maintainability engineering was a significant factor
in guiding the development of the CR80.
The CR80 architecture is designed with a capability
to achieve a highly reliable computer system in a cost-effective
way. It provides a reliable set of services to the
users of the system because it may be customized to
the actual availability requirements. The CR80 fault
tolerant computers are designed to avoid single point
errors of all critical system elements by provision
of multi-processor capabilities, mirrored disks and
dual power supplies.
The architecture reflects the fact that the reliability
of peripheral devices is lower than that of the associated
CR80 device controllers. This applies equally well
to communication lines where modems are used as part
of the transmision media. Thus, the peripheral devices,
modems, communication line, etc., impact the system
availability much more than the corresponding device
controllers.
To assure this very highly reliable product, several
criteria were also introduced on the module level:
- An extensive use of hi-rel, mil-spec components,
ICs are tested to the requirements of MIL-STD 883
level B or similar
- All hardware is designed in accordance with the
general CR80 H/W design principles. These include
derating specification, which greatly enhance the
reliability and reduce the sensibility to parameter
variations
- Critical modules feature a Built-In Test (BIT)
capability as well as a display of the main states
of the internal process by Light Emitting Diodes
on the module front plate. This greatly improves
module maintainability, as it provides debugging
and trouble shooting methods, which reduce the
repair time
- A high quality production line, which includes
high quality soldering, inspection, burn-in and
an extensive automatic functional test
- Software reliability is another aspect which will
be incorporated in achieving high over all availability
- Data has been replicated in order to increase system
availability
- Automatic and manual facilities are provided to
perform quick reconfiguration in case of errors
- Extensive M & D, maintenance and diagnostic software
can be used to minimize down times.
R̲e̲c̲o̲v̲e̲r̲y̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
Flexible variation in the size and structure of the
CR80 system used for the ASC are permitted by the unusual
degree of hardware and software modularity. The ASC
hardware essentially consists of fast transfer buses
joined to each other by adapters which allow units
on one bus to access those on another. Dualization
at the internal level regarding disks provides a CR80
hardware architecture which is exploited by the DAMOS
software operating system and programs to survive operational
failure of individual components.
Reliability, which is increasingly becoming of concern
in real-time and distributed network applications,
is achieved in the CR80 computer systems by applying
unique architectural concepts. The CR80 hardware/software
architecture treats all multiprocessors as equal elements
not absolutely dedicated to a specific role. Fault
tolerance and backup are achieved through a redundance
scheme without preassignment of system functions to
specific processors. This is in marked contrast to
the more common rigid dualized configurations often
encountered in dedicated applications with on-line
master/slave arrangements, or off-line backup with
switchover facility.
Performance degradation may result from the occurence
of a failure if it happens durings peak load, because
systems resources are used to recover from errors.
As an example, consider the mirrored disc. If a head
crash occurs on one of the discs, then a fresh blank
disc must be inserted, and all information must be
moved from the non-failed disc to the fresh disc. This
requires more disc activity than normal operational
use, so it might affect performance levels during peak
load situations. Of course the operator can choose
to wait with disc restoration till after peak load,
but this must be considered unrecommendable, because
the system is not able to recover from the next failure.
F̲a̲l̲l̲b̲a̲c̲k̲ ̲P̲r̲o̲c̲e̲d̲u̲r̲e̲s̲
As described earlier, the CR80 configuration for ASC
has been designed to provide maximum availability.
This means that several fallback procedures have been
implemented at the hardware and system software level.
Logical addressing is used throughout the system, which
make it possible to access the system from an alternative
terminal or print out on an alternative hardcopy device
subject to security constraints.
In excess of the standard fall back procedures implemented
in hardware and system software, like the mirrored
disc concept, procedural fall back procedures may be
implemented and enforced by the system. As an example
the parameterized distribution tables found in a similar
project and to be implemented in ASC, can provide a
copy of all messages to be printed on a specific terminal.
R̲e̲c̲o̲v̲e̲r̲y̲ ̲T̲i̲m̲e̲s̲
Recovery times are minimized throughout the system
by using automatic recovery wherever possible. This
approach eliminates all operator reaction time, which
is normally several magnitudes greater than automated
procedures. The actual recovery times depends very
much on the circumstances.
Reintroducing modules as part of restoring a failed
system under system operator control, will be dominated
by operator reaction time, but good procedural rules
and guidelines can minimize the time required.
The system operator can advise users of any planned
system facilities reduction.
O̲v̲e̲r̲a̲l̲l̲ ̲S̲y̲s̲t̲e̲m̲ ̲A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲
The ASC system has been designed with the objective
of providing an extremely high available system.
The computer system is partitioned into system elements
and the model used for reliability and availability
prediction shows how the proposed quipment provides
the high degree of reliability required.
Figure 2.3.5-1
Reliability Model for ASC
User Terminal Position
The reliability characteristics for the system are
stated in numerical terms by a mathematical model.
The supporting detailed prediction is presented in
this chapter. The system model is partitioned into
modular units and system elements that reflect the
redundancy of the configuration; it accounts for all
interconnections and switching points. The MTBF and
MTTR for the individual elements used in the calculations
were obtained from experience with similar equipment
on other programs.
The equipment has been partitioned and functions apportioned,
so that system elements can have only two states -
operable or failed. System elements are essentially
stand-alone and free of chain failures.
Careful attention has been paid in the design to eliminate
series risk elements. Redundant units are repairable
without interruption of service. Maintenance and reconfiguration
are possible without compromising system performance.
The primary source selected for authenticated reliability
data and predictions is the MIL-HDBK-217. The failure
rate data are primarily obtained from experience from
previous programs and continously revised as part of
the maintenance program on concurrent programs.
The reliability model which applies to the proposed
configurations is identified in the figure shown in
the following.
The model that has been calculated covers the basic
operational system. In order to improve availability
for the minimal system and the Communication Handling
system to an even higher degree, you can ensure higher
spare part availability on important modules, which
can be easily introduced as part of a fall back procedure.
M̲e̲a̲n̲-̲T̲i̲m̲e̲-̲B̲e̲t̲w̲e̲e̲n̲-̲F̲a̲i̲l̲u̲r̲e̲ ̲(̲M̲T̲B̲F̲)̲
The high reliability of the proposed equipment is achieved
through use of proven failure rate equipment similar
to that supplied for other programs.
Early in the design phase, a major objective for each
module is to achieve reliable performance. CR80 modules
make extensive use of carefully chosen components;
most of the IC…08…s are tested to the requirement of MIL-STD
883 level B.
The inverse of MTBF representing failure rate which
applies to system elements and modules is listed.
The MTBF data has been derived from reliability data
maintained on similar programs. Inherent MTBF values
are in general derived from the reliability predictions
accomplished in accordance with the U.S. MIL-HDBK-217
"Reliable Predictions of Electronic Equipment".
Failure rate data for terminal and peripheral equipment
is generally provided by the vendor in accordance with
the subcontract specifications:
…06…1 …02… …02… …02… …02… …02… …02… …02… …02… …02… …02…
Module Item Description MTBF FPMH MTTR
N̲o̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲h̲r̲s̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲m̲i̲n̲u̲t̲e̲s̲)̲
8002 CPU, SCM 36500 27.4 30
8003 CPU, CACHE 26100 38.3 30
8009 EPM
172400
5.8 30
8013 EPROM 91700 10.9 30
8016 RAM 128K/64K 17000/29600
58.8/33.8 30
8020 MAP 19400 51.6 30
8021 STI 32800 30.5 30
8037 UNIVAC I/F 33200 30.1 30
8039 IBM CH, I/F 32400 30.9 30
8044 DISC CTRL
DUAL/SINGLE 30200/39400
33.1/25.4 30
8045 TAPE CTRL 16K 35700 28.0 30
8046 DUAL PAR.CTRL 35700 28.0 30
8047 ST.FD.CTRL
DUAL/SINGLE 59500/84700
16.8/11.5 30
8050 POWER SUPPLY 26800 37.3 30
8055 MBT
285700
3.5 30
8059 MBE 10000000
0.1 30
8066 LTU DUAL/SINGLE 27600/45000
36.9/22.2 30
8070 CSA
769000
1.3 30
8071 MIA 85500 11.7 30
8072 SBA 90100 11.1 30
8073 TIA
117600
8
5 30
8074 EPA
256000
3.9 30
8078 IBA 21600 46.2 30
8079 UIA 15600 64.0 30
8081 CIA A & B 71400 14.0 30
8082 LIA-N 10000000
0.1 30
8083 LIA-S (Switch +
Common) 534759/3571428 1.87/0.28 30
8084 DCA 46900 21.3 30
8085 TCA
128200
7.8 30
Module Item Description MTBF FPMH MTTR
N̲o̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲h̲r̲s̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲m̲i̲n̲u̲t̲e̲s̲)̲
8086 PCA 185200 5.4 30
8087 SFA 10000000 0.1 30
8088 EIA A & B 113600 8.8 30
8106 MAINS FILTER
DISTRIBUTION 625000 1.6 30
8115 Minicrate 26300 38 60
8125/PC PU-CRATE 200000 5.0 60
8124/AB CU-CRATE 703630 1.4 60
Peripheral Item Description MTBF FPMH MTTR
N̲o̲.̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲h̲r̲s̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲m̲i̲n̲u̲t̲e̲s̲)̲
8300/--- DISC DRIVE,
SMD, 40-300MB 4000 250.0 90
8301/--- DISC DRIVE,
CMD (16-48)+16MB 4000 250.0 90
8302/--- DISC DRIVE, MMD,
12-80MB 8000 125.0 60
8307/--- FLOPPY DRIVE,
dual/single 8000 125.0 30
sided
8320/001 TAPE STATION,
Pertec FT 8000 8000 125.0 60
8320/002 TAPE STATION,
Pertec FT 9000 2500 400.0 60
M̲e̲a̲n̲-̲T̲i̲m̲e̲-̲T̲o̲ ̲R̲e̲p̲a̲i̲r̲ ̲(̲M̲T̲T̲R̲)̲
The proposed system is designed for ease of maintenance.
The system is built of modules each comprising a complete
well-defined function. Replacement of modular units
result in minimum repair time. Software and firmware
diagnostic routines rapidly isolate faulty modules;
repair can then be performed by semi-skilled maintenance
personnel and usually without special tools.
The proposed system, composed of redundant elements,
meets the objective of ease of maintenance. All units
and system elements are of a modular construction so
that any defective module can be isolated and replaced
in a minimum amount of time.
In the design of the System Elements, careful attention
was given to ease of maintenance without requiring
special tools, so that the maintenance could be performed
by semi-skilled maintenance personnel.
Fault detection and isolation to the system element,
in som cases module level, is inherent in the software
residing in the various processors. In peripheral devices,
the fault detection and isolation is accomplished by
a combination of on-line, software, built-in test,
and operator observations.
In case the correct function of the system is extremely
critical, the Processors will have built-in, on-line,
diagnostic programs. Even though the Processors are
highly reliable, failures can occur; usage of the off-line
diagnostics minimizes the downtime for a system.
An off-line diagnostics software package can be employed
to ease the diagnostics in case of error. Normally,
this software package is stored on disc. After initiation,
the program will test all modules forming the system
and print the name and address of the erronous module
on the operator…08…s console. Having replaced the erronious
module, the Processor is ready for operation again.
The operator might, if necessary, run the off-line
diagnostics program once more to verify that the system
is now working without errors.
The command interpreter module of the diagnostic package
enables the operator to initiate any or all of the
test programs for the specific subsystem off-line,
to assist in trouble shooting and to verify the repair.
Examples of modules tested are LTU…08…s, CPU and RAM modules,
etc.
The diagnostic package will also assist in fault isolation
of the peripherals. However, common and special test
equipment might have to be used to isolate the faulty
module.
The Mean-Time-To-Repair for the equipment is derived
from two sources. The first is actual experience data
on the equipment proposed for the system. The other
source is from predictions generated in accordance
with MIL-HDBK-472 or similar documents. As an example,
the MTTR for the Disk Storage Unit was derived from
repair times measured by the supplier. The repair times
of other units were derived by a time-line analysis
of the tasks associated with fault detection, isolation,
repair, and verification. These repair times were weighted
by the MTBF of each module to derive the unit MTTR.
The calculation of the Mean-Time-To-Repair (MTTR) is
done by weighting the individual module repair times
by the MTBF of the individual module. The MTTRs of
the major CR80 equipments are presented.
The predicted MTTR values are from experience with
modules of other programs. The predicted MTTR assumes
that all tools, repair parts, manpower, etc., required
for maintenance are continuously available.
The equivalent calculated overall availability will be above
99.9
====
For safety reasons MTTR figures used for a calculations
are very conservative, typically 30 minutes, but a
much better result can be obtained when operators and
maintenance people are carefully instructed and trained.
The following figure shows a typical fault isolation
and replacement sequence, when skilled people are used.
Figure 10.4
Typical Fault Isolation and…01…Replacement Sequence
10.5 A̲U̲D̲I̲B̲L̲E̲ ̲N̲O̲I̲S̲E̲ ̲L̲E̲V̲E̲L̲ ̲L̲I̲M̲I̲T̲S̲
The CR80 computer and all peripherals have been designed
with maximum considerations to ergonomics, including
noise levels. That means that the noise level will
generally be better than or equal to what can be expected
from similar equipment.
10.6 E̲N̲V̲I̲R̲O̲N̲M̲E̲N̲T̲A̲L̲ ̲C̲O̲N̲D̲I̲T̲I̲O̲N̲S̲ ̲A̲N̲D̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
The CR80 computer is used in many commercial and military
projects with strict requirements to environmental
conditions. Standard temperature ranges are 15-32…0e…o…0f…
but no problem is expected in operation within 10-40
degrees celcius. The version of the CR80 offered for
the ASC has not been designed for installation on ships
or similar, but for conditions normally found in land
situated installations.
10.7 E̲L̲E̲C̲T̲R̲O̲M̲A̲G̲N̲E̲T̲I̲C̲ ̲I̲N̲T̲E̲R̲F̲E̲R̲E̲N̲C̲E̲ ̲(̲I̲N̲T̲E̲R̲N̲A̲L̲L̲Y̲ ̲G̲E̲N̲E̲R̲A̲T̲E̲D̲)̲
The CR80 has been designed in accordance with VDE 871
class A and FCC class A.
10.8 G̲R̲O̲U̲N̲D̲I̲N̲G̲
The type of equipment, proposed for the ASC, has been
or will be installed in most West European countries,
e.g. the NATO financed CAMPS system is being installed
in Greece. Hence we are using the best installation
practises which are in accordance with the requirements.
1̲1̲ ̲ ̲C̲O̲N̲T̲R̲A̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲M̲E̲N̲T̲ ̲A̲N̲D̲ ̲E̲Q̲U̲I̲P̲M̲E̲N̲T̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲S̲
11.1 G̲E̲N̲E̲R̲A̲L̲
Christian Rovsing A/S (CR) agrees to comply with the
terms and conditions as outlined in chapter 11 of the
ASC RFP specification.
11.2 P̲R̲O̲J̲E̲C̲T̲ ̲M̲A̲N̲A̲G̲E̲R̲
As described in Section 3.2 of the Management Proposal,
CR will appoint a Project Manager, who will be the
intermediary between the contractor and the HCAA for
all decisions relating to the contract.
It is agreed that the Project Manager will be present
at all meetings arranged in connection with the contract,
and that temporary replacement of the Project Manager
will be in accordance with the conditions of RFP Section
11.2.
The Project Manager will be responsible for project
coordination and will take all necessary actions to
ensure that the project progresses normally. He will,
in addition, be responsible for all arrangements on
the part of the contractor with regard to meetings
and the personal contracts that have to be made, and
for the decisions to be taken in concert with the HCAA.
11.3 P̲R̲O̲G̲R̲E̲S̲S̲ ̲C̲H̲A̲R̲T̲
The contract will be executed in accordance with a
progress chart. This chart will be set out in the form
of a linear time-table (Pert Diagram). The unit of
time will be one working week, and the starting date
is to be the date of the signing of the contract between
the HCAA and the contractor.
The first progress chart will be included in the contract
Technical Specification.
The chart will specify the relative dates of all the
actions and decisions to be taken both by the HCAA
and the contractor. Any alterations to this chart will
be examined during the meetings held to discuss the
progress of the contract. The chart will be updated
by the contractor and forwarded to the HCAA within
a month after the decision to modify the chart was
made. Proposals concerning alterations will be made
by registered letter, the other party indicating his
approval also by registered letter.
11.4 P̲R̲O̲G̲R̲E̲S̲S̲ ̲M̲E̲E̲T̲I̲N̲G̲S̲
Progress meetings will be held at the times indicated
on the progress chart (at least every 3 months, unless
agreed otherwise), and will take place at Athens except
when there is prior agreement between the HCAA and
the contractor for the meeting to be held elsewhere.
In the latter event, the contractor would meet the
travel costs to the agreed place of the meeting for
the persons enumerated hereunder.
The following persons shall be present at progress
meetings.
- the contractor's representative (i.e. the project
manger)
- the HCAA representative
- any other persons which the above representatives
consider should be present in an assistant capacity.
After each meeting, a report will be prepared by the
supplier and submitted to the HCAA for its approval
within three weeks after the end of the meeting.
11.5 P̲R̲O̲J̲E̲C̲T̲ ̲E̲X̲E̲C̲U̲T̲I̲O̲N̲ ̲C̲H̲E̲C̲K̲S̲ ̲A̲N̲D̲ ̲F̲A̲C̲T̲O̲R̲Y̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲S̲
11.5.1 The HCAA will have the right to check that the execution
of the project is in accordance with the progress chart.
Such checks may be made by means of periodic visits
to the factories by the HCAA and/or its designated
representatives.
The contractor will provide all possible assistance
for facilitating these checks.
11.5.2 During the factory inspections the HCAA may request
the contractor to demonstrate any tests deemed necessary
to verify the proper execution of the project.
11.6 F̲I̲N̲A̲L̲ ̲F̲A̲C̲O̲T̲O̲R̲Y̲ ̲I̲N̲S̲P̲E̲C̲T̲I̲O̲N̲ ̲T̲E̲S̲T̲S̲ ̲(̲F̲F̲I̲-̲T̲E̲S̲T̲S̲)̲
11.6.1 Final tests in factory may be performed to verify that
the equipment complies technically with the requirements
of the specification. Equipment not complying will
be rejected.
11.6.2 The contractor will furnish a detailed description
of the proposed test techniques and procedures to verify
all equipment parameters and will provide a schedule
for such tests which will be submitted to the HCAA
8̲ ̲w̲e̲e̲k̲s̲ before the tests will start. Both documens
will be, if necessary, amended and be approved by both
parties within s̲i̲x̲ ̲w̲e̲e̲k̲s̲ of the receipt of these documents.
In particular, the operating conditions of the ASC
(see para. 5.5.4, 5.5.5 of the present specification)
and its operational and functional requirements (chapters
2 and 3 of the present specification) will be tested.
11.6.3 All equipment and sub-units will be fully intercon-
nected and built up into the system configuration.
Tests considered as impractical in the system configuration
may be performed using simulated inputs or on a test
bench when specifically approved by the HCAA.
11.6.4 The final factory inspection tests will be witnessed
by the HCAA and/or its designated representative. Those
HCAA representatives who will have to carry out the
factory inspections and to witness the tests but have
not received any previous training from the contractor
will be given, at his expense, a week's course of instruction
under the supervision of the engineer responsible for
the design of the equipment.
11.7 P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲(̲P̲A̲)̲
The provisional acceptance procedure is a series of
tests, carried out by the supplier and witnessed by
the HCAA, designed to verify the correct working of
the entire system, in accordance with the requirements
outlined in the Technical Specification.
The provisional acceptance will cover the entire delivery,
in particular the system, installed, fully tested and
in working order. It will also include the correct
working of the new equipment integrated into existing
systems (the performance parameters of these existing
systems having been clearly defined). An endurance
test and a load test on the equipment shall also be
included in the provisional acceptance tests.
Depending on the method adopted by the contractor to
install and integrate the complete system various subsystems
might be independently tested prior to the system provisional
acceptance tests. This would allow a reduction of the
PA period.
11.7.2 Declaration of PA of the system will be subject to
the satisfactory completion of the following activities
in agreement with the terms and conditions detailed
in the contractual Technical Specification:
a) agreement on the "Provisional Acceptance Schedule";
final factory inspection tess;
b) installation of the equipment to be supplied;
c) execution of the PA Schedule and successful presentation
of all tests defined therein;
d) training courses for the technical and programming
staff on all subjects required;
e) presentation, final agreement and delivery of the
technical and software documentation in the languages
specified;
f) delivery and acceptance of tools, components and
spare parts for maintenance;
g) delvery and acceptance of test systems and test
software.
11.7.3 The contractor will submit to the HCAA a document with
the specification and the schedule of the PA tests
to be carried out on the equipment at least eight weeks
prior to the start of the tests. This document will
be approved by the HCAA and, if necessary, modifications
and/or additions will be stipulated for incorporation
into the text, within four weeks after its receipt.
The aforesaid document will be prepared by the contractor
in cooperation with the Project Group of the HCAA and
concerns the site activities for PA.
It will contain in particular the following items:
a) the procedure to be observed for the good conduct
of the acceptance tests;
b) a plan of all actions to be taken for the testing
of various parts the system and the full system;
c) the specifications of all acceptance tests;
d) the form of documentation for the tests.
11.7.4 The acceptance test specifications are detailed descriptions
of all the tests and define for each test to be executed:
a) the objective of the test;
b) the state of the (sub)-system prior to the execution
of the test;
c) the correct execution of the test;
d) the measures to be taken to record the test results;
e) the predicted test results and/or the results of
preacceptance tests (see para. 11.7.5).
11.7.5 The contractor will, before submitting his equipment
for provisional acceptance, carry out all the tests
defined in the provisional acceptance schedule and
enter the figures for these tests into the provisional
acceptance document. These tests will be defined as
"pre-acceptance tests".
11.7.6 The provisional acceptance tests will be executed in
accordance with the PA schedule and will principally
comprise the following:
a) checking that the equipment is present and fully
installed;
b) partial testing of the different items of the system
and the interchange of data between them;
c) operating conditions (para. 5.6.3, 5.5.4, 5.5.3
of the present specification);
d) verification of the system performances by means
of live or simulated traffic (CHAPTERS 2 and 3
of the present specification);
e) testing of the system reactions on faults and/or
errors introduced into the system (degraded functioning);
f) continuous operation of the entire system for a
period of 72 hours under normal operational conditions
without intervention of maintenance staff.
11.7.7 Additional to the above tests, the HCAA may request
according to its judgement any further justifiable
tests in order to verify in a more detailed way the
conformity of the system with the technical specification.
11.7.8 Should any part of the system fail to pass the provisional
acceptance, i.e. it is "rejected", the contractor will
resubmit his equipment for provisional acceptance after
an agreed period. The contractor will be obliged to
supply a detailed report in which he describes the
reason for the failure or non-compliance of the equipment
and the corrective actions carried out.
11.8 F̲I̲N̲A̲L̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲
Final acceptance will normally be declared one year
after the provisional acceptance. Over this year the
system will be evaluated mainly where reliability is
concerned (CHAPTER 10 of the RFP specification).
In the event of a design failure arising in the equipment
during this period, the contractor will correct the
fault at his own expense. In addition, the contractor
will replace all the units or components which become
defective except where the defect has been due to gross
negligence on the part of the HCAA.
1̲2̲ ̲ ̲S̲Y̲S̲T̲E̲M̲ ̲C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲
12.1 G̲E̲N̲E̲R̲A̲L̲
The CHRISTIAN ROVSING A/S ASC will be a fully automatic
switching centre for messages and data. The centre
will be capable of handling conventional AFTN traffic
in phase 1, CBI data link control procedures and MET
chart traffic in phase 2, and CIDIN packet switching
traffic in phase 3.
12.2 I̲N̲F̲O̲R̲M̲A̲T̲I̲O̲N̲ ̲
The proposal consist of 4 parts in order to provide
all the required information on the operational, technical,
functional and financial issues.
Part I provides the management proposal with a description
of projects undertaken by CHRISTIAN ROVSING A/S and
related to this project. The part also describes the
managements approach planned for this project.
Part II provides a technical description of all the
operational, technical and functional requirements
of the ASC.
Part III provides a system description inclusive system
configuration , functions and hardware.
Part IV provides the detailed financial and contractual
information.
12.3 I̲M̲P̲L̲E̲M̲E̲N̲T̲A̲T̲I̲O̲N̲
Recognising the HCAA requirement for a 3 phase implementation
the offer is divided accordingly, with the CHRISTIAN
ROVSING A/S strong desire to implement all three phases
of the system based on our experience in message and
packet switching and processing.
The system configuration for the three phases is described
in part III chapter 1.
12.4 C̲O̲S̲T̲ ̲M̲O̲D̲E̲L̲
The cost model for the implementation of phase 2 and
3 is defined in part IV, Commercial Proposal.
A N N E X I
M&D USER REQUIREMENT SPECIFICATION
(GUIDELINE)
A N N E X II
DATA SHEETS