top - download
⟦dd472b61d⟧ Wang Wps File
Length: 71573 (0x11795)
Types: Wang Wps File
Notes: Spelunked
Names: »~ORPHAN34.00«
Derivation
└─⟦9bafbe04c⟧ Bits:30006092 8" Wang WCS floppy, CR 0144A
└─ ⟦this⟧ »~ORPHAN34.00«
WangText
…0b……00……00……00……00…"…02……00……00…"
…19……01……18……09……18……0f……18……05……17……0c……17……01……16……08……16……00……15……09……15……0f……15……01……15……07……14……0e……14……05……13……0c……13…
…13……07……86…1 …02… …02… …02…
…02…
…02…JPR/820319…02……02…
PROTOCOL CONVERTER
SYSTEM REQUIREMENTS SPECIFICATION…02……02…PC
4. A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲ ̲a̲n̲d̲ ̲M̲a̲i̲n̲t̲a̲i̲n̲a̲b̲i̲l̲i̲t̲y̲
4.1 G̲e̲n̲e̲r̲a̲l̲
Availability and maintainability requirements apply
to the equipment excluding environmental control equipment,
primary power spply to the equipment, and other purchaser
supplied equipment.
The equipment will meet the specified requirements:
a) When operating in a support environment which lies
within the limits of the specified operating requirements
of the equipmen.
b) When tools, repair parts, manuals, manpower, etc.
required for maintenance are available.
In designing the equipment to meet the specified requirements
no account need to be taken to catastrophic events
such as fire, flood, explosion, etc.which are beyond
the control of the equipment manufacturer.
The definitions of the terms used in this section are
given in section 4.2.
4.2 T̲e̲r̲m̲s̲
In interpreting specification and verification sections
in this paper on reliability and availaility the following
terms shall apply:
a) A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲. The probability of finding an item
(system, module, unit and part thereof) in a functioning
condition at a given time.
b) C̲o̲r̲r̲e̲c̲t̲i̲v̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲. The maintenance undertaken
to restore an iem to a specified condition after
a failure has occurred.
c) D̲o̲w̲n̲ ̲T̲i̲m̲e̲. The time during which any of the facilities
or functions to be provided by the item is not
available, for whatever reason.…86…1 …02… …02…
…02… …02…
d) F̲a̲i̲l̲u̲r̲e̲. The inability of any item to carry out
its specified function within the tolerance allowed
under its normal operating conditions.
Following failure situations shal be disregarded
in availability calculation:
1) The item is or has been exposed to conditions,
which are not within the tolerances allowed
under its normal operating conditions.
2) The item is or has been exposed to violence.
e) I̲t̲e̲m̲. An itm is defined as system, module, unit
and part thereof.
f) M̲e̲a̲n̲ ̲T̲i̲m̲e̲ ̲B̲e̲t̲w̲e̲e̲n̲ ̲F̲a̲i̲l̲u̲r̲e̲ ̲(̲M̲T̲B̲F̲)̲. The statistical
mean of the functioning time between failures.
For a given interval, the total measured functioning
time of the item divided by the totalnumber of
failures of that item during the interval. Agreed
scheduled preventive maintenance of modules of
the equipment shall not be counted when estimating
mean time between failure of such modules.
g) M̲e̲a̲n̲ ̲T̲i̲m̲e̲ ̲t̲o̲ ̲R̲e̲p̲a̲i̲r̲ ̲(̲M̲T̲T̲R̲)̲. The statisticl mean
of the distribution of times-to-repair. The summation
of active repair times during a given period of
time divided by the total number of malfunctions
during the same time interval. This repair time
shall include all actions required to deect, locate
and repair the fault.
h) P̲r̲e̲v̲e̲n̲t̲i̲v̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲. The maintenance undertaken
systematically with the intention of keeping an
item in a specified condition, reducing the occurrence
of failures, and prolonging the useful life of
the equiment.
i) R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲. The probability that an item will
perform a required function under stated conditions
for a stated period of time.
k) R̲e̲p̲a̲i̲r̲. A repair is the restoration of an item
to the state in which it can provide its specified
functins.
When the item is a replaceable module or includes
replaceable modules, the exchange operation is
considered as the repair operation.
l) E̲q̲u̲i̲p̲m̲e̲n̲t̲.̲ All the hardware constitutingthe protocol
converter.
m) M̲o̲d̲u̲l̲e̲. A collection of one or more units as defined
in this section which satisfy the following conditions:
1) It has a functional significance in the context
of R&M.
2) Individual failures can be localised to th
specific module.
3) The module is capable of removal and replacement.
4) The module operational condition has a simple
two state classification (operative or inoperative)
in the availability calculation.
n) U̲n̲i̲t̲. This has an exclusively fuctional significance
in this R&M context. The smallest hardware or
software element utilized in the Reliability and
Maintainability (R&M) models. The set of all units,
taken together make up the equipment. Each unit
shall satisfy the following cnditions:
1) It does not contain any portion of any other
unit.
2) The failure of the unit is independent of the
failure of any other unit.
3) The unit operational condition has a simple
two-state classification (operative or in-operative)in
the availability calculation.
4) Corrective maintenance on failed redundant
parts of a unit is performed only when the
unit containing these parts has failed.
4.3 R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲ ̲C̲h̲a̲r̲a̲c̲t̲e̲r̲i̲c̲t̲i̲c̲s̲
The reliability of the equipment is specified in terms
of its availability. The equipment is partitioned into
modules and units, which are used fo construction of
the R & M model and block diagram.
4.3.1 A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲ ̲C̲a̲l̲c̲u̲l̲a̲t̲i̲o̲n̲
The inherent availability of a module or unit shall
be measured in terms of two parameters:
- Mean time between failure (MTBF)
- Mean time to repair (MTTR)
The availability of a module or unit shall be determined
from the formula
Ai = ̲ ̲ ̲ ̲ ̲M̲T̲B̲F̲i̲ ̲ ̲ ̲ ̲ ̲
MTBFi + MTTRi
The availability value associated with each reliability
performance requirements, specified in succeeding paragraph
of this section, shall be determined from a R&M model
and block diagram by combining the availability co-efficients
for the modules and units affecting that availability
performance requirement. The availability co-efficient
for a series configuraion shall be calculated by:
elements ̲ ̲
A (system)= ll Ai
i=1
where Ai is the availability co-efficient of the i…09…th
element.
In the case of modules and units provided for the purpose
of redunancy (e.g. duplicated units) the availability
co-efficient shall be calculated by:
a) For (N-1) out of N redundancy is the availability
for (N-1) out of N being operative:
…0f…MTTR…0e…
A(N-1 out of N operative) = 1 - N * (N-1) * (------)…0e…2…0f…
…0e…MTBF…0f…
where MTTR MTBF.
) For other types of redundancy the availability
shall be calculated using the R&M model. Assumptions
made shall be justified.
4.4 A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲ ̲a̲n̲d̲ ̲R̲e̲l̲i̲a̲b̲i̲l̲i̲t̲y̲ ̲P̲e̲r̲f̲o̲r̲m̲a̲n̲c̲e̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
The equipment shall meet the following availability
requireents.
a) overall equipment availabiity P.99
4.5 R̲ ̲&̲ ̲M̲ ̲M̲o̲d̲e̲l̲
The R & M Block Diagram shall be defined in the Project
Implementation Plan, R and M Plan Section.
4.6 R̲ ̲&̲ ̲M̲ ̲T̲e̲s̲t̲i̲n̲g̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
The Protocol Converter equipment consists to avery
high extent of units and modules that are used in the
CAMPS program. The Protocol Converter R & M Plan will
therefore be tailored to take full advantage of the
Reliability and Maintainability Verification performed
in the CAMPS programme.
.6.1 A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
a) The availability and reliability performance characteristics
specified in section 4.4 shall be demonstrated
by performing availability measurements/calculations,
in which the values of the module/unit MTBFs and
MTRs are verified by:…86…1 …02… …02… …02… …02…
1) Testing/analysis in accordance with sections
4.6.1.1, 4.6.1.2 and 4.6.1.3 or,
2) Provision of acceptable evidence of conformity
to requirements, i.e. evidence supported byprior
observation of system or module performance
over a length of time sufficient to have the
same degree of confidence as the test procedure
that the required availability can be archived.
3) Provision of evidence that the unit or module
is pat of the CAMPS R and M programme.
b) The set of units and modules, taken together, shall
make up the equipment of the R&M model(s) used
for verification of system availability.
c) The R&M Characteristics shall be considered acceptable
if it is erified that the reliability performance
requirements specified in section 4.4. are met.
4.6.1.1 M̲T̲B̲F̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
4.6.1.1.1 M̲T̲B̲F̲s̲ ̲o̲f̲ ̲3̲5̲0̲0̲ ̲H̲o̲u̲r̲s̲ ̲o̲r̲ ̲L̲e̲s̲s̲
a) Tests shall be performed to measure the MTBF of
all units and modules having a predited MTBF value
of 3500 hours or less. The contractor need not
test all the individual units of a module being
tested unless the unit has a MTBF value less than
3500 hours and is part of another module which
is not being tested.
b) R&M testing shall be conducted in accordance with
an approved unit or module test plan. The overall
system test programme shall be planned so that
reliability data is obtained rom as many functional
tests as possible. In this manner the performance
of reliability testing, per se, will be reduced
to the minimum necessary for the demonstration
of system compliance with the R&M availability
requirements.
c) The R&M test pogramme shall make provisions for
the accumulation of sufficient testing time on
each type of module. The accumulated testing time
shall be equivalent to at least three multiples
of either:
1) the predicted MTBF value of the module with
an MTBF f 3500 hours or less, or
2) the largest predicted unit MTBF value for units
having a predicted MTBF value less than 3500
hours and forming part of a module with a MTBF
value greater than 3500 hours.
d) The R&M test programme shall provide for emonstrating
that unit and module MTBF values are equal to or
greater than the respective predicted values, to
a lower confidence limit value in accordance with
the following schedule:
80% lower confidence limit value at the time of
Final Accepance.
e) The lower confidence limit values of MTBF shall
be determined from the test data using the following
equation:
2T…0f…M…0e…
MTBF…0f…LCL…0e… …0f…=…0e… …0e… ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲…0f…
2
,f
where
T…0f…M…0e… = the total cumulative module
or
unit operating time obtained
from the test programme
2
,…0f…f…0e… = chi-square value wit
probability and f degrees
freedom
= (̲1̲0̲0̲-̲L̲C̲L̲)̲
100
LCL = Specified Lower Confidence
Level, expressed as a percentage
f = 2x(N…0f…p…0e… + 1)
N…0f…p…0e… = the actual numbe of va-
lid module or
unit failures observed
during the period T…0f…M…0e….
4.6.1.1.2 M̲T̲B̲F̲s̲ ̲G̲r̲e̲a̲t̲e̲r̲ ̲T̲h̲a̲n̲ ̲3̲5̲0̲0̲ ̲H̲o̲u̲r̲s̲
a) The contractor shall justify the use of MTBF values
greater than 3500 hours for individual units and
for modules, without redundant units, by means
of analytical calculations. Such calculations shalluse
values taken from actual test data on "like" or
similar equipment or from a component analysis,
utilizing values taken from recognized sources,
e.g. reliability and maintainability handbooks
maintained by National Government and by Industry.
) The Project Implementation Plan shall identify
those units and modules which have predicted MTBF
values greater than 3500 hours, and which will
have the MTBF values justified rather than tested.
The list shall include the predicted value of MTBF
or such units and modules. The list may be changed
as the programme progresses provided notification
is given at least 60 days in advance of starting
or cancelling any planned tests. The change process
contemplated for this list is the same as thatprovided
in the contract for all items (data) under Configuration
Control.
4.6.1.2 M̲T̲T̲R̲ ̲V̲e̲r̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
4.6.1.2.1 M̲T̲T̲R̲s̲ ̲o̲f̲ ̲4̲5̲ ̲M̲i̲n̲u̲t̲e̲s̲ ̲o̲r̲ ̲L̲e̲s̲s̲
a) Tests shall be performed to measure the MTTR of
all types of units and modules with a predicted
MTTR valueof 45 minutes or less.
The contractor need not test individual units of
a module that is being tested unless the unit is
also a part of another module that is not being
tested.
b) The MTTR measurements shall include corrective
and preventive mintenance actions, the time to
localise the failure to a particular module, time
to replace the failed module, verify the repair
action and restoring the system to operational
configuration exclusive of any software load requirements.
The MTTR doesnot include the repair time of the
failed module. The R&M test programme shall provide
for demonstrating that unit and module MTTR values
are less than or equal to the respective predicted
MTTR values to an upper confidence limit value
in accordanc with the following schedule:
1.80 % upper confidence limit value at the time
of Final Acceptance
c) The upper confidence limit values of MTTR shall
be determined from the test data by the following
equation:
̲
MTTR…0f…UCL…0e… = X + (t …0f…,f…0e…) . ̲S̲ ̲
…0e…N…0f…
where
̲
X = the observed statistical mean of
the measured maintenance action
periods:
̲
X
X = ̲ ̲i̲
N
Where X…0f…i…0e… are the individual observations and N is the
number of test measurements.
t …0f…,f = Students t-value with probability and
f degrees of freedom,
= (̲1̲0̲0̲-̲U̲L̲)̲
100
UCL = Specified Upper Confidence Limit expressed
as
a percentage.
f = (N-1),
S = Observed standard deviation of the measured
maintenance action periods:
̲
S…0e…2…0f… = (X…0f…i…0e… - X)…0e…2…0f…/(N - 1)
4.6.1.2.2 M̲T̲T̲R̲s̲ ̲G̲r̲e̲a̲t̲e̲r̲ ̲T̲h̲a̲n̲ ̲4̲5̲ ̲M̲i̲n̲u̲t̲e̲s̲
a) The Project Implementation Plan (PIP) shall identify
those units and modules that have MTTR values greater
tan 45 minutes, together with the predicted MTTR
values. Reasons for assigning a MTTR value in excess
of 45 minutes to a unit or module shall be given
and shall explain the maintenance procedures involved
in restoring such a unit or module to servic when
a malfunction occurs.
b) The list of units and modules having MTTR values
greater than 45 minutes may be changed as the programme
progresses provided notification is given at least
60 days in advance of starting any testing or cancelling
an planned tests. The change process contemplated
for this list is the same as that provided in the
contract for all items (data) under Configuration
Control.
4.6.1.3 R̲&̲M̲ ̲P̲l̲a̲n̲
The MTBF and MTTR for each unit and module shall be
part of a R&M plan which will specify how the MTBF
and/or MTTR is to be verified either by test, analysis,presentation
of evidence of conformity or through the CAMPS programme.
The R & M plan will be part of the PIP.
5. S̲o̲f̲t̲w̲a̲r̲e̲ ̲E̲n̲g̲i̲n̲e̲e̲r̲i̲n̲g̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
5.1 S̲y̲s̲t̲e̲m̲s̲ ̲P̲r̲i̲n̲c̲i̲p̲l̲e̲s̲
Fundamental properties of the software are its quality,
integrity and flexibility. The software shall meet
the oprational requirements together with the requirements
for ease of maintenance and modification. The software
shall be structured in a clearly identifiable hierarchical
way to ensure that the integrity and reliability requirements
of this specificatin are met. At the same time it shall
be readily expandable and must provide the facilities
specified below in such a way that the tasks of future
modification, error elimination and maintenance are
facilitated.
a) The software shall be provided a a complete, well
structured system consisting of three s̲u̲b̲-̲s̲y̲s̲t̲e̲m̲s̲:̲
1) The system software comprises all the software
(i.e. the program code, permanent data, pre-set
work space etc.) which is required to be resident
in or accessible to the system during its operation.
The system software shall provide the services
to the applications software.
2) The support software comprises all off-line
software required to supportthe testing and
maintenance of the operational system.
3) The applications software is defined as the
software providing the functional capabilities
called for in this specification.
b) The software, in conjunction with the hardware,
shall be designed to detect and limit the effect
of hardware faults which occur in the system. Upon
detection of the fault, actin should be taken to:
1) Report the fault.
2) Optimize the remaining system operational capabilities
while the fault persists.
c) The system design shall seek to maintain maximum
isolation and independence between units of all
types during rogram design and implementation and
during on-line operation of the system.
d) In the construction of program code, clarity of
meaning shall be a major consideration. When writing
the program code comments shall be inserted to
aid comprehension nd improve the readability.
e) It is mandatory that no instruction and constants
of the system software are modified during execution.
If it is done the circumstances must be well documented
and the program listing must contain complete cross-refrencing
comments. In the applications software the use
of this technique shall be unacceptable.
f) The data areas of a module shall be logically contiguous
and all exchange of data between different modules
shall take place either through well deined shared
data areas or by a parameter passing.
g) The software shall be carefully documented in parallel
to the design during the production phase. The
documentation shall form part of the deliverable
software package and conform to the softwae documentation
standards specified elsewhere in this document.
5.2 S̲y̲s̲t̲e̲m̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲
a) The system software facilities must allow the applications
software to be structured in terms of functional
modules.
b) The system software shall include the following
general facilities in some form:
1) Multi-programming and scheduling at run time,
i.e. the provision of a set of processes orequivalent
entities as the basic entities to which processor
time, store and other system resources are
allocated at run time.
2) Store management, i.e. facilites for permanently
or dynamically allocating areas of core store
to processes or thei equivalents for initializing
data areas securely when required; and for
obtaining permanent or dynamic access to such
areas when required.
3) Device control and interrupt response, i.e.
standardized interfaces between hardware devices
(includin traffic channels) and applications
software, such that the system software is
wholly responsible for the immediate control
of hardware device interfaces.
4) Inter-process interfaces, i.e. facilities for
passing activations and data between procsses
over standardized interfaces.
5) Fault handling, i.e. facilities for the detection,
location and containment of software and hardware
faults.
5.3 A̲p̲p̲l̲i̲c̲a̲t̲i̲o̲n̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲
The application software shall be provided as well-structured
module. The application software is to provide, in
conjunction with the system software, all the functional
capabilities called for in this specification. The
application software for each installation shall be
identical or, as a minimum, generated from common
library of program routines.
a) O̲v̲e̲r̲a̲l̲l̲ ̲S̲t̲r̲u̲c̲t̲u̲r̲e̲. The applications code and data
shall be structured in a hierarchical manner into
a well defined set of functional modules and units
at different functional lvels and with distinct
data areas for each transaction processed by the
system.
The ways in which the various applications software
modules are multi-programmed at run-time (i.e.
recursive/re-entry or "fresh copy", etc.) shall
be clearly defined
Communication between modules shall wherever practicable,
take place via standardised system facilities such
as interprocess calls and procedure calls. The
sharing of data areas between two or more units
or modules handling different transactios shall
be avoided and the situations in which such sharing
takes place shall be clearly defined. It shall
be a design aim to ensure that whenever data is
transmitted across an inter-module interface, the
data is in a compact, well defined form.
The process of integrating a module into the system
shall not require recompilation of the other elements
of the system.
b) M̲o̲d̲u̲l̲e̲s̲ ̲o̲f̲ ̲A̲p̲p̲l̲i̲c̲a̲t̲i̲o̲n̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲. It shall be a
design aim that each functional module of applications
software should satify the following criteria:
1) Provide a well defined function or group of
functions at some hierarchical level in the
software system, i.e. can be implemented as
self-contained programming task given a functional
specification, interface specifiations of any
external modules and data structures to which
it must refer.
2) Has well defined, compact input and output
interfaces.
3) Can be separately compiled/assembled.
4) Hides its decisions from other modules (e.g.
it allows access to internal data structures
only through one access mechanism provided
by the module).
5.4 S̲o̲f̲t̲w̲a̲r̲e̲ ̲I̲m̲p̲l̲e̲m̲e̲n̲t̲a̲i̲o̲n̲
a) U̲s̲e̲ ̲o̲f̲ ̲L̲a̲n̲g̲u̲a̲g̲e̲s̲
The software will be implemented in swell.
b) P̲r̲o̲g̲r̲a̲m̲s̲
It is mandatory that programme instructions shall
not be modified during run time and that within
each applications software module the programme
code and constnts should be segregated from the
modifiable data. The direct use of or access to
absolute store addresses by applications programmes
should be reduced to a minimum. Synchronization
processes shall take place at clearly defined points
in the programe. To maintain security and accountability,
reservation and release of shared resources, such
as data areas, must only take place at clearly
defined points in the applications programme.
c) M̲o̲d̲u̲l̲e̲ ̲S̲i̲z̲e̲ ̲C̲o̲n̲s̲t̲r̲a̲i̲n̲t̲s̲
The function of each module hould be readily understandable.
As a rule, no module shall contain more than 250
source statements unless approved by CR QA internally
and notification to SHAPE. It shall be a design
aim to limit the number of modules, exceeding the
250 line limitto 5% of the modules. Each module
must implement a function or function(s) as specified
in this document. Any requirement which would lead
to implementation of a module unable to satisfy
this constraint must be sub-divided into more manageable
unit. It is essential that any constraints imposed
on the module size by compilers, loading methods,
store management arrangements, etc., must be clearly
defined and adequate methods for dealing with these
constraints must be defined and implemented.
5.5 S̲o̲f̲t̲w̲a̲r̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲a̲n̲d̲ ̲M̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
a) The systems software shall be structured in a way
that will permit the addition or deletion of applications
units.
b) Software mintenance may take place on the CAMPS
software development system.
c) All software in the operational system will reside
in EPROMS.
5.6 S̲u̲p̲p̲o̲r̲t̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲
The support software includes all off-line software
required to support the implementatin, testing and
maintenance of the on-line system. All support software
may be made available at the CAMPS software support
installation (CSSI). .The software related to installation
of changes and assisting in fault finding is available
at all site
5.6.1 F̲a̲c̲t̲o̲r̲y̲ ̲T̲e̲s̲t̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲
At the CR factory a factory-test program shall be provided
to run the software under test.
5.7 S̲o̲f̲t̲w̲a̲r̲e̲ ̲I̲n̲t̲e̲g̲r̲i̲t̲y̲
Each module should contain credibility check to contain
the effects of corrupt or inaccurate data to the extent
this does not introduce redundant processin which will
decrease the system throughput.
5.8 P̲r̲o̲t̲e̲c̲t̲i̲o̲n̲ ̲o̲f̲ ̲S̲o̲f̲t̲w̲a̲r̲e̲ ̲a̲g̲a̲i̲n̲s̲t̲ ̲E̲M̲P̲
No protection against EMP shall be provided
6. G̲E̲N̲E̲R̲A̲L̲ ̲T̲E̲C̲H̲N̲I̲C̲A̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
6.1 G̲e̲n̲e̲r̲a̲l̲
The following section defines the general design and
construction requirements applicable to the Protocol
Converter.
6.1.1 E̲q̲u̲p̲m̲e̲n̲t̲ ̲P̲r̲o̲d̲u̲c̲e̲d̲ ̲b̲y̲ ̲C̲h̲r̲i̲s̲t̲i̲a̲n̲ ̲R̲o̲v̲s̲i̲n̲g̲ ̲A̲/̲S̲
a) The CR produced equipment is designed and produced
according to CR standard.
b) This standard is based on the following NATO standards:
1) NGTS 45 General Manufacturing Requirements.
2) NGTS 50 Design, Construction and Installation
Criteria for electrical and electronic
material.
3) NGTS 40 Environmental Test Methods.
c) CR standards are currently updated in order to
incorporate improvements in technology.…86…1
…02… …02… …02… …02…
d) Maintenance of CR standards are performed under
configuration management and supervised by CRs
Quality Assurance department.
e) All standards and their maintenance may be insected
by customers Quality Assurance Representative.
6.1.2 P̲r̲o̲d̲u̲c̲t̲s̲ ̲F̲r̲o̲m̲ ̲O̲t̲h̲e̲r̲ ̲S̲u̲p̲p̲l̲i̲e̲r̲s̲
a) Equipment supplied by other suppliers is chosen
in accordance with the requirements stated compared
to the specification given by the OEMs.
b) Qualit Assurance shall check and ensure that the
quality of such equipment fulfill all requirements
in respect of:
1) performance (in accordance with specifications
given by manufacturer)
2) durability
3) stability
4) maintainability
6.2 S̲e̲c̲i̲a̲l̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲ ̲f̲o̲r̲ ̲t̲h̲e̲ ̲P̲r̲o̲t̲o̲c̲o̲l̲ ̲C̲o̲n̲v̲e̲r̲t̲e̲r
a) In this section is mentioned a number of requirements
special for the Converter project.
b) In case of conflict with the standards mentioned
in 6.1.1 above, the following standards shall prevail.
6.2.1…02…E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲C̲o̲n̲d̲i̲t̲i̲o̲n̲s̲
In designing the equipment to meet the specified requirements
no account need be taken of catastrophic events such
as fire, flood, explosion, etc., which are beyond the
control of an equipment manufacturer.
The equipment will normally operate within accomodation
suitable for the operation of similar equipment produced
for commercial use.
After initial adjustments have been made, th equipment
shall maintain normal operation under all specified
environmental and power supply conditions.
6.2.1.1 …02…T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲ ̲a̲n̲d̲ ̲H̲u̲m̲i̲d̲i̲t̲y̲
The equipment shall continue to function when the humidity
and temperature of its environment are withi the ranges
and cycling specified below.
The equipment shall continue to operate in a fully
satisfactory manner even under the worst conditions
specified below.
…02…a) T̲e̲m̲p̲e̲r̲a̲t̲u̲r̲e̲
…02……02…Range : 10 to 40 deg.C
…02……02…Change : max 10deg. C per hour
…02…b) H̲u̲m̲i̲d̲i̲t̲y̲ ̲(̲R̲e̲l̲a̲t̲i̲v̲e̲ ̲H̲u̲m̲i̲d̲i̲t̲y̲ ̲=̲ ̲R̲H̲)̲
…02……02…Range : 40 to 90% RH, non-condensing
…02……02…Change : max. 6% RH per hour, non-condensing
…02…c) A̲l̲t̲i̲t̲u̲d̲e̲
…02……02…Range : Sea level to 2000 meter
The equipment shall be so designed that the loss o
site air conditioning or heating will not cause a catastrophic
failure within 15 minutes after the loss.
6.2.1.2 D̲u̲s̲t̲,̲ ̲F̲u̲m̲e̲s̲
The equipment shall be able to operate continuously
and with normal scheduled preventive maintenance in
the following ar environment:
a) Ai̲r̲ ̲c̲l̲e̲a̲n̲n̲e̲s̲s̲
Particle size Max. allowable number
(̲m̲i̲c̲r̲o̲n̲s̲)̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲(̲p̲a̲r̲t̲i̲c̲l̲e̲s̲/̲c̲u̲b̲i̲c̲m̲e̲t̲e̲r̲)̲
greater than 5 4* (10E5)
greater than 1.5 4* (10E6)
greater than 1 4* (10E7)
b) F̲u̲m̲e̲s̲
sulphur dioxide max. 14 ppm.
6.2.2 E̲n̲v̲i̲r̲o̲n̲m̲e̲n̲t̲a̲l̲ ̲T̲e̲s̲t̲i̲n̲g̲
No environmental testing shall be performed
6.2.3 U̲t̲i̲l̲i̲t̲y̲ ̲O̲u̲t̲l̲e̲t̲ ̲S̲o̲c̲k̲e̲t̲s̲
Utility outlet sockets for the operation of al equipment
shall be located in close proximity to all major racks
or cabinets. Installation of utility outlets will be
the responsibility of purchaser.
6.2.4 M̲a̲t̲e̲r̲i̲a̲l̲s̲
Materials used for encapsulation and embedment shall
be selected for theirelectrical, operational, environmental
and storage characteristics. Hard curing compounds
to hold replaceable parts are prohibited. (Parts soldered
to terminals, printed wiring boards etc. are not considered
replaceable in this context).
6.2.5 I̲t̲e̲r̲c̲h̲a̲n̲g̲e̲a̲b̲i̲l̲i̲t̲y̲
a) Modular hardware construction should be used wherever
feasible.
b) The items shall be designed to use the minimum
number practicable of the different types of electrical
cable, connectors, component and accessories.
c) Electrically identicalunits, assemblies, subassemblies
and replaceable parts shall be physically interchangeable
without modification of such items or of the equipment.
d) Interchangeable items shall be as defined in specifications,
drawings, and/or documentation to prmit their installation
as interchangeable units, assemblies, subassemblies,
and parts without regard to the source of manufacture
or supply.
e) Provision shall be made for design tolerances such
that items having the dimensions and characteristis
permitted by the item specification may be used
as replacement without selection or departure from
the specified equipment performance.
6.2.6 B̲e̲n̲c̲h̲ ̲H̲a̲n̲d̲l̲i̲n̲g̲
Smaller assemblies and sub-assemblies normally subject
to bench repair shall be capale of withstanding being
dropped onto a hard surface on all faces from a 30…0e…o…0f…
angle, using any one edge of the unit as a pivot, without
any physical, electrical or electronic damage.
6.2.7 C̲o̲v̲e̲r̲ ̲P̲l̲a̲t̲e̲s̲
Cover plates shall have a minimum of faseners consistent
with normal mechanical strength requirements. All such
fasteners should preferably be of the "captive" type.
6.2.8 C̲a̲b̲l̲i̲n̲g̲ ̲a̲n̲d̲ ̲F̲i̲t̲t̲i̲n̲g̲s̲
For wiring and cabling the following shall apply:
a) Where inter-connecting cabling between assemblies
is run in steel conduit or in shielded cables,
electrical continuity of the conduit or shielding,
as appropriate, shall be ensred to permit the correct
grounding.
b) Wiring shall be identified by colour coding, numbering,
or by other feasible means such as marking of terminals
at both ends of lead. All wires shall carry corresponding
identification numbers at each end. olour coding
for chassis wiring shall be comforming to good
engineering practice.
c) Where bus bars are used for interconnection between
assemblies and subassemblies they may be colour
coded to permit quick identification.
a) Cables and wires o similar connectors shall carry
a CR parts number. These numbers shall be the same
numbers as given in the as-built drawings and in
the maintenance and operating manuals.
6.2.9 F̲l̲u̲x̲ ̲a̲n̲d̲ ̲S̲o̲l̲d̲e̲r̲i̲n̲g̲
6.2.9.1 F̲l̲u̲x̲
Rosin fluxes conforming to recomended engineering practices
shall be used for making electrical electronic connections.
For fluxing purposes, a soldered joint the functions
of which are both a mechanical and an electrical connection
(for example in grounding applications througha chassis)
shall be considered an electrical connection.
6.2.9.2 S̲o̲l̲d̲e̲r̲i̲n̲g̲
All soldered connections shall be clean and smooth
in appearance. Sufficient solder shall be used to ensure
a continuous strong concave fillet feathered into th
base metals. Flux or other foreign residue must be
removed. The insulation of soldered wires shall not
show damage from the heat of the soldering operation.
Discolouration is permitted, but not charring, cracking,
decomposition and distortion.
.2.10 V̲e̲n̲t̲i̲l̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲C̲o̲o̲l̲i̲n̲g̲
a) Intake cooling air, if considered necessary, shall
be filtered such that the pressure within the associated
cabinet is higher than the ambient pressure outside.
The cooling air should preferably be exhausted
to th atmosphere at the top of the cabinet.
b) Resonance effects and vibrations because of the
ventilation and cooling shall not cause any deterioration
of equipment performance.
c) The distributed cooling systems in the CR produced
equipment may besupplied with air filters of a
nominal thickness of 2.5 cm.
6.2.11 E̲l̲e̲c̲t̲r̲o̲m̲a̲g̲n̲e̲t̲i̲c̲ ̲C̲o̲m̲p̲a̲t̲i̲b̲i̲l̲i̲t̲y̲
a) When installed the electromagnetic radiation of
the equipment shall comply with the COMSEC requirements
as described in AMSG 720 A and in para 6.2.18.3
of this specification.
b) When installed the different units, assemblies,
and subassemblies shall be able to perform as intended
in the presence of electromagnetic radiation from
other system within the limits specified in 6.2.11.a
abov.
6.2.12 T̲e̲s̲t̲ ̲a̲n̲d̲ ̲R̲e̲p̲a̲i̲r̲
6.2.12.1 A̲c̲c̲e̲s̲s̲i̲b̲i̲l̲i̲t̲y̲
a) Only chassis and assemblies contained within cabinets
or consoles shall be mounted on withdrawal slides
if they require remova or replacement during normal
maintenance and repair actions.
b) Plug-in boards and modules shall be provided with
a suitable removal tool, if they are not equipped
with build-in ejectors/extractors.
6.2.12.2 T̲e̲s̲t̲p̲o̲i̲n̲t̲s̲
a) Testjacks can be o the banana plug type.
b) Test points/tracing points for monitoring voltage/currents
and measuring/injecting signals/wave forms shall
only be provided to the extent they form part of
the maintenance/repair concept.
6.2.13 C̲o̲n̲s̲u̲m̲a̲b̲l̲e̲ ̲P̲a̲r̲t̲s̲ ̲
Al fluids, life limited parts, and any other comsumable
parts required for continuous operation of the equipment
shall be kept to a minimum both in number and quantities
required.
6.2.14 S̲a̲f̲e̲t̲y̲
All necessary safeguards shall be taken during thedesign,
development, production and installation of the equipment
to ensure safety of operating and maintenance personnel
from electrical and mechanical hazards.
6.2.14.1 R̲e̲g̲u̲l̲a̲t̲i̲o̲n̲s̲
a) The actual site installations in the different
host nations shall be made in accordance with the
appropriate National Safety Regulations of the
country cocerned according to installation drawings
as approved by the purchases.
b) The equipment itself and its associated power cabling
shall comply with the National Safety Regulations
of the country of origin for the equipment.
6.2.14.2 P̲e̲r̲s̲o̲n̲n̲e̲l̲ ̲S̲f̲e̲t̲y̲
a) Interlocks or key locks shall be incorporated where
appropriate to prevent any major assembly carrying
high tension voltages from being opened by unauthorised
personnel.
b) With the equipment assembled and set up for operation,
personne shall be protected from contact with potentials
in excess of 30 volts to ground, chassis or frame,
including potentials or charged capacitors.
c) Relevant notice and markings on equipment or documents
are to be provided to draw the attention of perating
and maintenance personnel to points where dangerous
voltages may be encountered.
d) Where a voltage of 50 or more volts is exposed
during the maintenance activities a suitable warning
shall be provided. It should be made according
to thefollowing principles:
1) "DANGER (xxx) VOLTS WHEN COVER REMOVED" (in
aluminium or white lettering l.5 cm high on
a red background) where (xxx) is the nominal
voltage.
2) "DANGER HIGH VOLTAGE (xxx) VOLTS" where (xxx)
is the nominal voltage.
3) "CAUTION (xxx) VOLTS. DISCONNECT POWER BEFORE
REMOVAL OF COVER" where (xxx) is the nominal
voltage.
6.2.14.3 E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲S̲a̲f̲e̲t̲y̲
a) Circuit breakers or switches which operat to make
or break AC power lines shall make or break all
conductors at the same time. The neutral wire in
three-phase circuits shall not pass through any
fuse.
b) Fuses and circuit breakers shall be provided within
the equipment as required for potection of the
equipment from damage due to overload. Each major
assembly shall be individually protected so that
a fault in one major assembly cannot damage any
other major assembly.
c) All fuses and circuit breakers should be located
such thatthey are readily accessible. Fuses shall
incorporate a visual system of failure indication.
6.2.14.4 G̲r̲o̲u̲n̲d̲i̲n̲g̲
a) The grounding system shall provide effective protection
for personnel and material against insulation defects.
It shall be arrangd so that there are three separate
and isolated ground circuits, namely:
1) AC power neutral
2) Equipment frame ground
3) Signalling and control ground
b) The AC power neutral shall provide a return for
the primary current so that the eqipment frame
ground is used only to establish a safety ground
and is not used as a normal current grounding element.
No place in the equipment or power filters shall
the AC power neutral be connected directly to equipment
frame ground.
c) All panels, drawers and other sub-assemblies, whether
fixed or removable, shall be fastened, or connected
to the associated frame, in a manner that ensures
they are securely grunded.
d) The signalling and control ground is to be routed
via the interconnecting wires and cables as appropriate.
6.2.15 N̲a̲m̲e̲p̲l̲a̲t̲e̲s̲ ̲a̲n̲d̲ ̲P̲r̲o̲d̲u̲c̲t̲ ̲M̲a̲r̲k̲i̲n̲g̲
A nameplate giving the serial number, SHAPE contract
number, date of manufacture, manuacturers name and
address and principal characteristics, where appropriate,
shall be attached in a prominent position on each major
assembly.
6.2.16 C̲o̲n̲t̲r̲o̲l̲s̲
The type and layout of controls shall be such as to
avoid an interruption of service r change of operational
mode as a result of accidental bumping, touching or
catching of clothing.
6.2.17 A̲c̲o̲u̲s̲t̲i̲c̲ ̲N̲o̲i̲s̲e̲
The maximum sound level due to noise emitted from the
equipment shall be less than 70 dB (A) when measured
under free fieldconditions by a precision sound level
meter located at a point 2 meters distant from the
noise source, and at the height at which the maximum
reading of the meter is obtained. The measuring instrument
shall be in accordance with IEC publication 179second
edition 1973.
6.2.18…02…P̲h̲y̲s̲i̲c̲a̲l̲ ̲C̲h̲a̲r̲a̲c̲t̲e̲r̲i̲s̲t̲i̲c̲s̲
6.2.18.1 S̲i̲z̲e̲,̲ ̲W̲e̲i̲g̲h̲t̲,̲ ̲P̲o̲w̲e̲r̲ ̲C̲o̲n̲s̲u̲m̲p̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲H̲e̲a̲t̲ ̲D̲i̲s̲s̲i̲p̲a̲t̲i̲o̲n̲
The site equipments consist of a terminal and one multi-bay
rack assembly.
The racks of each site equipment will b equipped with
subassemblies and modules according to the actual connectivity.
Detailed technical information will be supplied in
the Design Specification.
6.2.18.2 P̲o̲w̲e̲r̲ ̲I̲n̲p̲u̲t̲
The equipments shall be capable of satisfying the specified
perfrmance requirements when operating with following
power input:
a) Phases: Single- or 3-phase, and ground.
b) Voltage: Nominal value 380/220 V AC
Tolerances: +10%/-15%
c) Frequency: Nominal value: 50 Hz
Tolerances: +10/-10%
d) Harmonic
distortion: Max. 5%
e) Transients: Non-repetitive impulsive interference
with a magnitude not to exceed 500
volts, pulse rise and fall times
not faster than 0 microseconds and
a total duration of maximum 1 millisecond.
The available impulse energy at the
equipment power inlet shall not exceed
5J.
6.2.18.3 T̲e̲m̲p̲e̲s̲t̲ ̲R̲a̲c̲k̲s̲
The EMI racks are constructed of heavy gauge steel,
having all non-opening seams welded. The racks will
be of slightly greater size than equivalent non-EI
racks and will be significantly heavier. Cable entrance
for power and signals will be either through the top
or bottom of each rack. The racks are prepared for
both type of outlet.
a) R̲a̲c̲k̲ ̲C̲o̲n̲f̲i̲g̲u̲r̲a̲t̲i̲o̲n̲
The racks will be used as a single, free-standing
cabinet or assembled into bays of 2 racks in a
row forming a cabinet.
The individual racks will be transported separately
and joined with coupling accessories at site Thus,
3 rack types are defined.
1) L̲E̲F̲T̲ ̲E̲N̲D̲ ̲R̲A̲C̲K̲S̲, which includes one welded panelled
side and one open side with joiner frame, hardware,
and accessories.
2) R̲I̲G̲H̲T̲ ̲E̲N̲D̲ ̲R̲A̲C̲K̲, which includes one open side
without joiner frame and one welded paelled
side and accessories.
3) F̲R̲E̲E̲-̲S̲T̲A̲N̲D̲I̲N̲G̲ ̲R̲A̲C̲K̲, which includes both sides
welded panelled, and accessories.
The types of racks are non interchangeable, left cannot
be interchanged with right, a freestanding cannot be
changed to a right, etc
b) R̲a̲c̲k̲ ̲D̲o̲o̲r̲s̲
Each rack shall have a full size door in front
and rear. Doors will be operated with recessed
handles. The doors shall contain EMI gaskets.
c) R̲a̲c̲k̲ ̲V̲e̲n̲t̲i̲l̲a̲t̲i̲o̲n̲
To allow ventilation and EMI shielding, perforated
metal is use. The perforated areas are located
in the front doors and at the top.
d) A̲C̲ ̲P̲o̲w̲e̲r̲ ̲F̲i̲l̲t̲e̲r̲s̲
RF power filters shall be used, and they shall
be mounted directly to either the top or bottom
of racks.
e) V̲2̲4̲ ̲F̲i̲l̲t̲e̲r̲ ̲w̲i̲t̲h̲ ̲P̲a̲t̲c̲h̲i̲n̲g̲ ̲F̲a̲c̲i̲l̲i̲t̲y̲ ̲(̲P̲F̲)̲
The F shall be enclosed within one of the main
frame EMI racks. It provides access to all input
and output electrical signal connections to the
converter mainframe. Filtered connectors will be
installed in the PF as described below to meet
AMSG requireents.
The PF consists of a separately shielded box sealed
to the rack surface within an EMI rack into which
conduit or ducts from all external electrical signal
cables are passed. Upon removal of the PF cover,
banks of the necessary number of pi connectors
are accessible for user connection. Optical signal
cables if used are fed through a wavequide placed
separately or contained in the PF.
f) V̲2̲8̲(̲L̲)̲-̲A̲d̲a̲p̲t̲e̲r̲s̲ ̲f̲o̲r̲ ̲D̲r̲i̲v̲i̲n̲g̲ ̲E̲l̲e̲c̲t̲r̲i̲c̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲
The V28(L) shall provide 6-0-6 volts signal leels
and waveshaping.
It shall cover the range from 1200 to 9600 Bps.
7. S̲e̲c̲u̲r̲i̲t̲y̲
This section addresses or references all requirements
related to security.
In general: Transfer and transmission within the installation
means transfer and tansmission between the components.
7.1 T̲E̲M̲P̲E̲S̲T̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲
The components of the converter equipment are divided
in the following 2 categories.
1) A multi-bay EMI-rack assembly.
2) A terminal for maintenance an supervisory positions.
During short periods of corrective and preventive maintenance
e.g. open back doors, the emanation requirements below
are degraded.
It must be within the operational procedures, that
the supervisor is currently informed o activities concerning
corrective and preventive maintenance and thus is able
to decide whether it is acceptable to continue operation
or not.
a) To meet the NATO Security requirements, the equipment,
including ancillaries and peripherals, must b installed
in accordance with criteria laid down in AMSG 719B.
The production equipments shall be subject to inspection
and testing by ACE COMSEC Radiation Team at the
factory premises prior to despatch/distribution
to locations. After installation a final COMSEC
Radiation Survey will be carried out at each location
prior to operational approval being given. Rectification
of the equipment characteristics shortcomings shall
be the responsibility of the contractor.
b) Regarding the EMI-racks, ACE COMSEC shall be provided
with tangible evidence as to their effectiveness.
For this purpose detailed design and manufacturing
specification have been forwarded to SHAPE forevaluation
as part of the CAMPS programme. Also, laboratory
data on the shielding effectiveness of the rack
have been provided.
ACE COMSEC has measured the ambient noise at the
factory site at Ballerup and subject to provision
of customer supplied power filtering accepted its
suitability for TEMPEST tes (ref. CAMPS log 091
and CAMPS log 111). The actual TEMPEST test will
be perfomed as a qualification test by ACE COMSEC
at the factory site.
1) All equipment contained in multi-bay EMI-racks
assembly shall be TEMPEST cleared as a result
of the aove TEMPEST qualification test (equipment
of category 1 above). This shall include any
opto-electrical interfaces.
2) Equipment of category 2 (terminals) will be
delivered with a TEMPEST clearance certification
according to AMSG720A with the undrstanding
that the cerfification provided will apply
to the standard approved version of the equipment.
Where modifications are required, supplementary
test data will be provided, to confirm that
the EMI integrity has been maintained.
During thecontract phase, technical information
will be supplied to ACE COMSEC for evaluation and,
where required, a production model shall be delivered
for testing purposes.
c) S̲p̲e̲c̲i̲a̲l̲ ̲e̲a̲r̲t̲h̲i̲n̲g̲ ̲a̲r̲r̲a̲n̲g̲e̲m̲e̲n̲t̲s̲ with respect to 1)
AC power neutral, 2) safety grund, 3) Signalling
and control ground are necessary within the complete
system in order to comply with criteria laid down
in AMSG 719B. In the terminal equipments signal
common returns s̲h̲a̲l̲l̲ ̲b̲e̲ ̲s̲e̲p̲a̲r̲a̲t̲e̲ ̲a̲n̲d̲ ̲i̲n̲s̲u̲l̲a̲t̲e̲d̲
̲f̲r̲o̲m̲ ̲a̲l̲l̲ ̲o̲t̲h̲e̲r̲ ̲e̲a̲r̲t̲h̲s̲ or metal hassis (this includes
protective earth which is usually derived from
the station's main supply).
d) All electrical interconnections for data between
the equipments will use low level keying systems,
i.e. 6-0-6 volts at currents less than one mill-ampere.
All the remaining control lines should conform
to CCITT Recommendation V28.
e) All electrical wiring on the red side shall be
run in a screened cable, consisting of twisted
pairs and an overall continuous n̲o̲n̲-̲f̲e̲r̲r̲o̲u̲s̲ ̲s̲c̲r̲e̲e̲n̲.
All cables to and from the onverter to be supplied,
and installed by SHAPE.
f) Installation of any optical fibers shall be in
accordance with AMSG 719B.
g) As-built drawings and all circuit diagrams of the
first operational system, and similar material
for any variationsin subsequent system to be delivered,
showing all electrical interfaces and voltages,
shall be supplied to ACE COMSEC before factory
inspection.
h) To assist in the assessment of physical security
and guarding of classified information, a list
ofall items of equipment which will store, display
or record classified information shall be supplied
to ACE COMSEC by the contractor.From the list,
an assessment will be made for physical security
in accordance with AMSG 293D.
i) Installation workwill be witnessed by local COMSEC
staff to ensure that all installation conforms
to COMSEC requirements.
j) The central processor will be installed in an area
designated as a Red Area. Within the Red Area classified
information may be handled in lain language; the
transfer of information in an electrical form within
this area shall be subject to and comply with the
criteria laid down in AMSG 719B.
k) The crosstalk attenuation between any circuit carrying
classified information and any oher circuit within
the installation shall be not less than 100 dB.
l) The power supply to all the equipment in the Red
Area will enter via a filter or a group of filters
which will be supplied by the purchaser. The function
of these filters is toensure that no compromising
signals are able to reach a Black Area via the
power supply leads. The equipment shall function
satisfactorily with these filters present in the
power leads.
7.2 S̲y̲s̲t̲e̲m̲ ̲D̲e̲s̲i̲g̲n̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
In this section requirements with respect to hardware
and software aspects of equipment design are given.
a) H̲a̲r̲d̲w̲a̲r̲e̲
1) A clean architectual design where unassigned
codes must cause a trap.
2) Two classes of instructions, one for the privileged
use of the operating system and a user mode
used by both operating system and application
programs shall exist.
A set of privileged istructions exclusively
reserved for the operating system. These instructions
must control all I/O, the setting of memory
bounds mechanism, the setting of the system
state - privileged or user problem.
Sensitive instructions which could divert,
isrupt or inadvertently change the state of
the application software shall not be available
for execution unless the processor is in a
"privileged" state.
3) Every instruction code shall result in a prescribed
action. The occurence and/or attemped execution
of any illegal code or bit-pattern shall be
signalled and shall result in an abort procedure.
b) S̲o̲f̲t̲w̲a̲r̲e̲
The following software features shall be provided:
1) All programmes and data files loaded into the
system shall carry blck parity check sums to
allow the detection of corrupted data.
2) Recovery procedures after system failure shall
include checksumming of the operating system
software, reloading if this is necessary.
8. L̲O̲G̲I̲S̲T̲I̲C̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲
8.1 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
8.1.1 T̲r̲a̲n̲s̲p̲o̲r̲t̲a̲t̲i̲o̲n̲
8.1.1.1 S̲e̲c̲u̲r̲i̲t̲y̲
In the case of classified equipment and/or material,
special shippin shall be provided by the contractor
and confirmed/co-ordinated with the purchaser. NATO
Security manual C-M(55)15 Final, Volume 2 Enclosure
D, Section V defines special security requirements.
The contractor shall ensure that all classified materia
and/or equipment to be provided under the terms of
this contract will not be transported over or through
any non-NATO country, nor will any of the material
and/or equipment be handled by any non-NATO aligned
freight forwarder or shipping agency.
8.1.1.2 P̲a̲c̲k̲i̲n̲g̲
All equipment delivered under this contract will be
packed and crated in accordance with the best commercial
practices for the type of supplies involved, given
due consideration to climatic and shipping conditions
in order to ensre safe arrival to destination.
…02…a) Items returned for repair will be transported in the
original container used for transport to site. Contractor
will identify all items delivered in reusable containers.
…02…b) All delivered spares will be packed ndividually for
long term storage without performance or physical deterioration
with expected shelf life. Full details of the contents
and the shelf life shall be clearly indicated on the
package.
8.1.1.3 M̲a̲r̲k̲i̲n̲g̲
Items of supply and the packages or containers in which
supplies are transported shall in addition to normal
mercantile marking be marked with the following dat
on a separate nameplate (tranfers or stamping acceptable
if nameplate is not practical).
…02… Project title
…02… Purchaser Contract Number
…02… Contract Item Number
…02… Manufacturer's name and address
…02… Ship to address
8.1.1.4 P̲a̲c̲k̲i̲n̲g̲ ̲L̲i̲s̲t̲s̲
Packing liss shall accompany all shipments and two
copies each shall be provided to the purchaser. Each
packing list will contain the following information:
…02… Shipping Address
…02… Package Number
…02… Contract Number
…02… Contract Item Number
…02… Item Description
…02… Par Number
…02… NATO Stock Number (if available)
Serial Number
…02… Quantity shipped
…02… Date Shipped
8.1.1.5 N̲A̲T̲O̲ ̲S̲h̲i̲p̲p̲i̲n̲g̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲s̲
Whenever shipments under this contract requires NATO
Form 302 or other NATO shipping documents these shall
be made avalable to contractor without delay when requested
by contractor.
8.1.2 I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲
8.1.2.1…02…S̲e̲c̲u̲r̲i̲t̲y̲
…02…a) The protocol converter together with the maintenance
position will at each site be installed in a communications
security (red) area. The installation shalltherefore
conform with the relevant requirements to automatic
processing devices contained in the current issue of
AMSG 719B.
…02…b) Customers local COMSEC staff shall be entitled to monitor
the installation works. A final test and inspection
before ach installation becomes operative will be carried
out by an ACE-COMSEC team.
…02…c) The power supply to all equipment in the red area will
enter via a filter or a group of filters, which will
be provided by the customer.Detailed requirements will
bepart of the Civil Works Requirements data package
to be supplied by contractor.
8.1.2.2…02…S̲t̲a̲n̲d̲a̲r̲d̲s̲
a) The equipment shall operate from mains power installations
conforming to national regulations concerning power
and safety.
b) Contractor wil ensure that As-To-Be-Built drawings
submitted to SHAPE will conform to national safety
regulation.
c) Customer will approve the As-To-Be-Built drawings
for conformance to national regulations as well
as obtain approval of the completed installaton
from national authorities.
8.1.2.3…02…G̲r̲o̲u̲n̲d̲i̲n̲g̲
a) An efficient and comprehensive grounding system
shall be provided on each site by customer. The
grounding system shall comprise:
1) Secure ground
2) Safety ground (frame ground)
b) The safety ground will be part of the main power
system and conform to national regulations.
c) The secure ground shal conform to the requirements
of AMSG 719B. A suitable terminal for the secure
ground shall be provided as close as possible to
each major piece of equipment to be installed (VDU
or Rack).
8.1.2.4…02…M̲a̲i̲n̲s̲ ̲P̲o̲w̲e̲r̲ ̲S̲u̲p̲p̲l̲i̲e̲s̲
a) To be provided at eac site by customer.
…02…1) Three phase and single phase 380/220 volts 50 HZ
power supplies will be available at all sites.
…02…2) If consisting with national regulations the following
color coding shall apply:
…02… Line: Brown
…02… Neutral: Blue
…02… round: Yellow/green
b) In case of 3 phase installation, the lines can
be of any color, except blue and yellow/green.
c) In conformance with national regulations each end
of the neutral and ground wire shall be clearly
marked (coloured sleevesor coloured durable adhesive
tape).
…02…1) P̲r̲o̲t̲e̲c̲t̲i̲v̲e̲ ̲D̲e̲v̲i̲c̲e̲s̲
Protective devices for the mains power installation
shall be provided.
…02… Circuit breakers which operate to make or break
A.C. power lines shall make or break all conductors
at the sme time. The neutral wire shall not pass
through any fuse.
…02… All fuses and circuit breakers shall be so located
such that they are readily accessible.
…02… 2) U̲t̲i̲l̲i̲t̲y̲ ̲O̲u̲t̲l̲e̲t̲s̲ ̲S̲o̲c̲k̲e̲t̲s̲
…02… Utility outlets sockets for operation of each terminal
shall be provided as close as possible to the required
installation site of a terminal.
…02… The outlet sockets shall be of a uniform 220 V AC standard
type with ground and break of line only according to
the national standard for each installation. The socket
shall be of a type that only allows the plug to mate
in the correct orientation
…02… 3) Contractor shall deliver his requirements to the
power installation specifying the required number
of utilily as part of the Civil Works Requirements
Package.
8.1.2.5 E̲f̲f̲e̲c̲t̲ ̲o̲n̲ ̲M̲i̲l̲i̲t̲a̲r̲y̲ ̲A̲c̲t̲i̲v̲i̲t̲i̲e̲s̲
Installations in buildings shall be perormed in a manner
that avoids disruption of on-going military activities.
Contractor may be required under special circumstances
to stop work for military reasons. Under such circumstances,
the contractor shall furnish a report to SHAPE giving
detals of the time that the stop work order was enforced,
together with any other pertinent information.
8.1.2.6 S̲p̲a̲c̲e̲ ̲a̲n̲d̲ ̲A̲c̲c̲e̲s̲s̲ ̲D̲i̲m̲e̲n̲s̲i̲o̲n̲s̲
a) At each site an area of TBD meters by TBD meters
will be made available for the installation of
the Prtocol Converter and supervisory positions
with a minimum floor to ceiling height of 220 cm
without a raised floor, or 2 meters minimum if
a raised floor is provided.
…02…b) A̲c̲c̲e̲s̲s̲ ̲D̲i̲m̲e̲n̲s̲i̲o̲n̲s̲
All sites have access dimensions equal to or better
than
Height 1.70 meters
Width 0.65 meters
Length 3.70 meters
Above dimensions will be guaranteed as the minimum
envelope along the equipment access route of any
site.
8.1..7 S̲i̲t̲e̲ ̲S̲u̲r̲v̲e̲y̲s̲
…02…a) Following contract signature contractor shall perform
formal site surveys at each site.
b) Subject to coordination with contractor SHAPE will
arrange a visit to each site. The purpose of the
site surveys is to ensure that thecontractor can
perform the following tasks.
…02… 1) Verification of the site documentation specified
in d) below.
…02… 2) Preparation of the site civil works drawings/specifications
and the as-to-be-built drawings.
c) SHAPE representatives will assis contractor to
collect the relevant information to be used to
prepare the site for installation of the equipment.
At least one of SHAPE representatives on each site
survey team will be authorized to make decisions
and to sign a survey protocol on bhalf of SHAPE.
…02…d) S̲i̲t̲e̲ ̲D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲
Customer will deliver a data package to contractor
prior to site survey to permit him to conduct the
survey. Data not delivered prior to site survey
will be supplied during the survey. Additional
data will e supplied by customer in accordance
with minutes of meeting agreed to during the conclusion
of the site survey.
e) Drawings and specifications supplied by customer,
must contain sufficient information to permit contractor
to generate Civil WorksRequirements, As-to-be-built
drawings and As-built Drawings as described in
section TBD.
f) Customer shall without being requested so by contractor
submit all of the above data and subsequent updates
to ensure that contractor at all times has the
most current documetation package for the site
in question.
g) Above data shall be submitted to contractor no
later than 3 months prior to contractors scheduled
delivery of Civil Engineering requirements.
8.2 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲a̲n̲d̲ ̲S̲u̲p̲p̲o̲r̲t̲
8.2.1 M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲P̲l̲a̲n̲
Cntractor shall develope a maintenance plan as part
of the final PIP.
8.2.2 R̲e̲p̲o̲r̲t̲i̲n̲g̲ ̲S̲y̲s̲t̲e̲m̲
Contractor shall establish and manage a fault reporting
system to monitor system status and to analyze failures.
8.2.3 T̲o̲o̲l̲s̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
a)G̲e̲n̲e̲r̲a̲l̲.̲ As part of the Maintenance Plan the Contractor
shall submit a price list of all tools, test equipment,
test cables, test adapters, test programmes and other
items required at each site, to support the equipment
supplied.
b) Special type ools, test equipment and test programs
shall be clearly identified as well as the purpose
for which each tool and piece of test equipment
is required.
c) The list shall include, where applicable, associated
ancillaries such as signal sources, cable adapters,
matching devices, power sources and extension jigs
and cables.
d) Te test equipment and tools supplied under this
contract may be supplemented with other items which
will be listed in the maintenance plan.
8.2.3.1 P̲u̲r̲c̲h̲a̲s̲e̲
Test equipment and tools suggested by the Contractor
may be substituted or augmented bythe purchaser. Such
items will be deleted from or added to the contract
by an appropriate amendment. Test equipment supplied
with the site hardware and included in the basic contract
will be clearly identified.
8.2.3.2 U̲s̲e̲ ̲P̲r̲i̲o̲r̲ ̲t̲o̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲
) All test equipment and tools to be used by the
Contractor on site for the setting up, alignment
and measurement of performance shall be equipment
identical to that which is recommended by the Contractor.
b) Test equipment, facilities and tools or delivery
to the purchaser are not to be used by the Contractor
without prior approval from the purchaser. Approval
for the use of such items will be subject to:
1) All used items being in an "as new" state at
the time of on-site acceptance.
2) Re-calibration of test equipment where appropriate,
at the Contractor's expense.
8.2.4 C̲a̲l̲i̲b̲r̲a̲t̲i̲o̲n̲
The Contractor shall prepare a plan and procedures
for the calibration of each item of suggested special
test equipment. Calibration plans and procedures sall
also be provided for items of test equipment built
into the main equipment. A list of parameters to be
covered and recommended standards necessary for the
calibration of each item shall also be provided by
the Contractor. The calibration plan wll be part of
the Maintenance Plan.
8.3 S̲p̲a̲r̲e̲s̲ ̲a̲n̲d̲ ̲C̲o̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
a) G̲e̲n̲e̲r̲a̲l̲.̲ Contractor shall deliver to the Customer
the optimum range and level of spare parts, common
and special tools and test equipment required to
support the system.
b) Povisions to be supplied shall include the recommended
list of spares to be held on each site to cover
90 days operation without support from another
site and those to be held in a depot to cover 270
days operation. The parts selected and the quantiies
recommended shall be based on provision of adequate
support to meet the reliability and maintainability
requirements for the equipment at the lowest possible
cost.
The Protocol Converter may make use of spare parts
delivered with the CAMPS sytem.
8.3.1 S̲u̲p̲p̲l̲y̲ ̲o̲f̲ ̲P̲a̲r̲t̲s̲
8.3.1.1 R̲e̲c̲o̲m̲m̲e̲n̲d̲e̲d̲ ̲S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲L̲i̲s̲t̲ ̲(̲R̲S̲P̲L̲)̲
a) At contract signature, the Contractor shall submit
a Recommended Spare Parts List (RSPL). The RSPL
shallinclude all spare parts required to support
all equipment supplied by the Contractor.
b) The RSPL will include:
1) A 90 days stock for each site (80% confidence).
2) A 270 days stock for one supply depot (80%
confidence).
3) Insurance itms to be held on each site and
at the supply depot.
8.3.1.2 A̲p̲p̲r̲o̲v̲e̲d̲ ̲S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲L̲i̲s̲t̲ ̲(̲A̲S̲P̲L̲)̲
The Approved Spare Parts List (ASPL) will be derived
by using the RSPL, the equipment and documentation
and will be determined jointly by the Customerand the
Contractor during provisioning meetings to be held
by the Contractor. The ASPL shall be incorporated in
the contract by an appropriate amendment 60 days after
the receipt of the RSPL.
8.3.1.3 P̲r̲o̲v̲i̲s̲i̲o̲n̲ ̲o̲f̲ ̲S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲D̲u̲r̲i̲n̲g̲ ̲F̲i̲r̲s̲t̲ ̲Y̲e̲a̲r̲ ̲o̲f̲O̲p̲e̲r̲a̲t̲i̲o̲n̲
a) The Contractor shall provide all spare parts listed
in the ASPL prior to the site acceptance of each
site.
b) The Contractor shall replenish the spare parts
at each site for a period of one year after acceptance.
Follow-on procuremnt of spare parts as well as
spares needed for the replenishment described above
shall be covered by separate contracts.
c) Prior to Site Acceptance at any site the Contractor
shall provide his own spare parts to maintain the
equipment to the required performance level.
8.3.1.4 F̲o̲l̲l̲o̲w̲-̲o̲n̲ ̲S̲p̲a̲r̲e̲s̲
a) The Contractor agrees that follow-on spares in
support of items supplied under this contract shall
be available on order, for delivery within a reasonable
period, for a period of ten years from contract
signature. The contractor further agree that the
unit prices charged for such spares shall be fair
and reasonable and that spares will be sold to
SHAPE at the current catalog price for CR's most
favoured customer.
b) During the ten year period of guaranteed availability
of the follow-n spares the Customer may purchase
a fixed delivery time for follow-on spares.
8.3.1.5 S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲A̲v̲a̲i̲l̲a̲b̲i̲l̲i̲t̲y̲
The Contractor shall promptly notify the Customer upon
receipt of notice of any non-availability of spare
parts and will provide al data with respect to the
replacement and interchangeability of new parts.
8.3.1.6 I̲n̲v̲e̲n̲t̲o̲r̲y̲
The Contractor shall prepare a property inventory for
each site. The inventory will form part of the site
documentation.
8.3.1.7 D̲e̲f̲i̲n̲i̲t̲i̲o̲n̲s̲
a) I̲n̲s̲u̲r̲a̲n̲c̲e̲ ̲T̲y̲p̲e̲ ̲I̲t̲e̲m̲.̲ Item which is generally not
subject to periodic replacement or wear out but
is subject to infrequent replacement as the result
of acidents and other unexpected occurrences and
the stockage of which is considered to be necessary
for operational reasons and lead time considerations.
b) M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲F̲l̲o̲a̲t̲.̲ Pool of all, or of selected
end items comprised in a system which are keptin
storage and made available as rapid replacement
for like but unserviceable end items to allow for
maintenance processing. They can be used either
on an exchange or a rental basis.
c) M̲o̲d̲u̲l̲e̲/̲P̲r̲i̲n̲t̲e̲d̲ ̲C̲i̲r̲c̲u̲i̲t̲ ̲C̲a̲r̲d̲s̲.̲ Part of an assembly
replaceabl as a whole but also having some components
that may be replaceable individually; consisting
of a combination of components having a common
mounting or mounted on each other.
8.3.1.8 S̲p̲a̲r̲e̲ ̲P̲a̲r̲t̲s̲ ̲D̲e̲s̲i̲g̲n̲ ̲C̲h̲a̲n̲g̲e̲ ̲N̲o̲t̲i̲c̲e̲s̲
a) The Contractor will isse to the Customer Spare
Parts Design Change Notices (SPDCN) for each item
(fuse, resistor, capacitor, lamp, transistor, inductance
module, etc.) affected within:
1) Four weeks of the Customer's approval of the
Equipment Design Change Notice affeting the
spare parts change.
2) Not later than nine months before an item will
no longer be produced.
b) The SPDCN will refer to the assembly and the part
involved, the improvement achieved, the technical
manuals and the parts thereof to be amnded, the
impact on the provisioning actions already taken
and/or stocks of parts and components already delivered.
The SPDCN will also indicate the price of the new
part and provide recommendations as to the disposition
actions to be taken on the reviously recommended
part, as appropriate.
c) The above services are to be furnished at no additional
cost to the Customer, as long as the service is
rendered within the warranty period of the equipment.
d) Cost of issing SPDCNs subsequent to expiration
of warranty period will be negotiated separately
or be part of additional spares procurement.
8.3.1.9 P̲r̲o̲v̲i̲s̲i̲o̲n̲i̲n̲g̲ ̲C̲o̲n̲f̲e̲r̲e̲n̲c̲e̲s̲
The Contractor and purchaser will schedule and conduct
provisioning conferences ithin a mutually agreed and
suitable time frame to allow selection and timely delivery
of parts, tools and test equipment. Conference facilities,
documentation and equipment as required/ available
will be provided by the Contractor.
8.3.2 N̲A̲T̲O̲ ̲C̲d̲i̲f̲i̲c̲a̲t̲i̲o̲n̲
The Contractor shall make a quote for codification
of:
a) Items shown in the approved spare parts list (ASPL).
b) Major and minor sub-assemblies (if not included
in the ASPL).
9. T̲r̲a̲i̲n̲i̲n̲g̲
9.1 G̲e̲n̲e̲r̲a̲l̲ ̲R̲e̲q̲u̲i̲r̲e̲m̲e̲n̲t̲s̲
a) Contracor shall develop training programs and supply
associated course material for the following courses:
…02…1) Maintenance Training Course
…02…2) On-The-Job Training
b) …02…Contractor shall conduct the following training:
…02…1) A Hardware Maintenance Training Course to be conducted
at contractor's facility.
…02…2) On-the-job operator training.
c) L̲a̲n̲g̲u̲a̲g̲e̲. All courses shall be conducted in Englishand
all equipment handbooks and training material shall
be produced only in English.
d) C̲o̲u̲r̲s̲e̲ ̲L̲e̲n̲g̲t̲h̲. Formal Courses shall be designed
to be effective and efficient, but should be kept
as short as possible. The training plan is to be
based upon 6 hour day, 45 minute training period
and a 5 day week, and take account of NATO holidays
(approx. 1 day/month) and course administration
(1 day/course and 1 day/month).
e) C̲o̲u̲r̲s̲e̲ ̲S̲t̲r̲e̲n̲g̲t̲h̲. There shall be a maximum of 12
students per course. Forpractical work a course
shall be divided into 6 groups of 2 students if
possible, or individual "stands" if continuous
flow self-paced methods are selected for formal
courses.
9.2 T̲a̲r̲g̲e̲t̲ ̲P̲o̲p̲u̲l̲a̲t̲i̲o̲n̲
a) All students to be trained except RFT (seec. below)
will be military and civilian personnel from various
NATO countries, each having an English language
proficiency level of at least SLP 3232 (as described
in STANAG 6001 of 21. Oct. 76.).
…02…b) All technicians will have been trained in geneal
electronics but may not have extensive knowledge in
the electronic and digital techniques used in computer
equipment.
c) Personnel requirements applicable to customers
Resident Field Technician (RFT) are as follows:
1) The RFT shall have an English language proficiency
level of SLP 4443 as described in STANAG 6001
of 21 Oct 1976. The RFT must be graduate of
an accredited advanced communiction or electronics
technical school and have a minimum of 5 years'
experience in modern communication systems
using digital switching techniques. This experience
must include the maintenance of installation
testing of such equipment. He shall av a generel
knowledge of software to permit an initial
diagnosis and analysis of software faults in
order to furnish relevant data to the system
analysis and programming service.
2) He shall have participated in the CAMPS Maintenance
Courses
3 He shall have the necessary qualifications
to conduct extensive OJT courses attended by
operators and technicians.
9.3 D̲o̲c̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲a̲n̲d̲ ̲T̲r̲a̲i̲n̲i̲n̲g̲ ̲A̲i̲d̲s̲
a) The training documentation to be provided in support
of the training programme for the cntract shall
be written, compiled, published and delivered in
accordance with the contractual requirements for
documentation applicable for this contract.
b) The contractor shall prepare and provide all training
aids in the light of the maintenane requirements.
c) A̲p̲p̲r̲o̲v̲a̲l̲ ̲a̲n̲d̲ ̲D̲e̲l̲i̲v̲e̲r̲y̲. The contractor shall submit
a sample copy (preliminary version) of the training
documentation. Recommended changes shall then
be incorporated by the contractor and finalized
copies of the training documetation together with
training aids shall be delivered to purchaser.
d) S̲e̲c̲u̲r̲i̲t̲y̲ ̲C̲l̲a̲s̲s̲i̲f̲i̲c̲a̲t̲i̲o̲n̲. The contractor shall mark
the appropriate security classifications on all
documentation and training material following the
current ACE security direcives. The purchaser shall
approve the security grading before production
in quantity.
9.5 T̲r̲a̲i̲n̲i̲n̲g̲ ̲P̲r̲o̲g̲r̲a̲m̲ ̲P̲l̲a̲n̲
a) Contractor shall submit to purchaser a Training
Program Plan for his approval.
b) The plan shall give a detailed description of the
Training progam and the interrelationship between
the two types of training:
- training of customers Resident Field Technicians
in maintenance and fault finding.
- on-the-job training in operation of the equipment